This site implementation plan template outlines requirements for the deployment of security screening equipment at airport checkpoints. It includes sections on roles and responsibilities of parties involved, a site validation report, tasks required at specific checkpoints, a schedule of preparatory work and daily activities, CCTV needs, special considerations, and appendices listing equipment to be installed and contact information for rigging operations. The Transportation Security Administration is soliciting proposals under solicitation number 70T04020R9AP4050 for checkpoint screening equipment deployment services to replace or install new technology at checkpoints nationwide on an indefinite delivery/indefinite quantity basis. Awards will be made to multiple vendors who will then prepare site-specific implementation plans using this template to complete task orders under the contract.

View the file

Other files

File Type Posted
CP RFP_Amendment 04_revised.pdf PDF
CP RFP_Amendment 04.pdf PDF
CP RFP_Amendment 04_SF30.pdf PDF
Solicitation Att2-Checkpoint Pricing Worksheet_Amendment 04.xlsx XLSX spreadsheet
Q_and_A amendment 4.pdf PDF
Solicitation Att2-Checkpoint Pricing Worksheet_Amendment 03 updated.xlsx XLSX spreadsheet
Solicitation Att2-Checkpoint Pricing Worksheet_Amendment 03.xlsx XLSX spreadsheet
CP RFP_Amendment 03_SF30.pdf PDF
CP RFP_Amendment 02.pdf PDF
CP RFP_Amendment 02_SF30.pdf PDF
Solicitation Att2-Checkpoint Pricing Worksheet_Amendment 02.xlsx XLSX spreadsheet
CP_SEDS QandA_Amendment 02.pdf PDF
CP RFP_Amendment 01.pdf PDF
CP RFP_Amendment 01_SF30.pdf PDF
Solicitation Att2-Checkpoint Pricing Worksheet_Amendment 01.xlsx XLSX spreadsheet
Solicitation Attachment 04-DHS Subcontracting Plan Review Checklist.pdf PDF
CP RFP QA_Amendment 01.pdf PDF
CP RFP 70T040R9AP4050 SEDS.pdf PDF
Contract Att07 - ETD - 500DT De-Installation Checklist.pdf PDF
Contract Att02 - BLS - CEIA EMA-MS Decommission Checklist.pdf PDF
Contract Att05 - WTMD - CEIA Decommission Checklist.pdf PDF
Contract Att06 - ETD - QSB220 De-Instal - Instal Checklist.pdf PDF
Solicitation Att3-Checkpoint PM Task Order.pdf PDF
Contract Att11 - Weekly Status Report.xlsx XLSX spreadsheet
SEDS Q and A Template.xls XLS spreadsheet
Contract Att04 - BLS - Responder Decomm Checklist.pdf PDF
Contract Att01 - AIT-1 and AIT-2 - L3 Decommission Checklist.pdf PDF
Solicitation Att2-Checkpoint Pricing Worksheet .xlsx XLSX spreadsheet
Contract Att09 - PSP Site Survey Template.xlsx XLSX spreadsheet
Contract Att03 - AT Decommission Checklist.pdf PDF
Solicitation Att1-SF1449 Checkpoint.pdf PDF
Contract Att10 - PSP Site Survey Report Template.pdf PDF
Contract Att12 - Daily Site Report.xlsx XLSX spreadsheet
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SITE IMPLEMENTATION PLAN

Site Implementation Plan – SIP IDIQ Contract Number Region:

Effort Name Task Order Number

Airport Name

Document Date:

CDRL 011 Purpose:
The purpose of the SIP is to outline and document contractor contingencies, site specific access requirements, operational timeliness, a communication process, and a general plan for installation. The SIP should contain all additional information and documentation as outlined in the SOW.

Airport Code:

Date:

System Integrator:

System Integrator POC:

Table of Contents

SECTION 1: PURPOSE4
SECTION 2: ROLES AND RESPONSIBILITIES5
SECTION 3: SITE VALIDATION6
3.1Results of the site validation6
3.2Shipping / Rigging Plan6
SECTION 4: SITE TASKS8
SECTION 5: SITE SCHEDULE9
5.1New Technology Installation Schedule9
5.2Preparatory Work9
5.3Daily Activities11
SECTION 6: CCTV13
6.1Checkpoint T2, T413
SECTION 7: SPECIAL SITE CONSIDERATIONS14
7.1General14
SECTION 8: APPENDICES15
Appendix A: Equipment List – Decommissioned / Relocated / Installed15
Appendix B: Rigging Report15
B.1 Overall Issues and concerns15
B.2 Checkpoint15
B.3 Checkpoint Additional as Needed16
Pictures of the site and rigging path are shown below16
Appendix C: Site Preparation Package16

SECTION 1: PURPOSE

Terminal
Checkpoints
# of Lanes
Airline(s)
Gates
International/ Domestic?

SECTION 2: ROLES AND RESPONSIBILITIES

The points of contact, including phone numbers, e-mail addresses, and roles and responsibilities, for this project are identified below.

Name
Title
Office Number
Cell Number
Email

SECTION 3: SITE VALIDATION

The site validation should review the infrastructure of the relevant Airport building (electrical, floor loading, ceiling height, floor slopes, camera position views and duress alarms where required), the dimensions provided in the drawings, any hazardous material abatement requirements, and any other pertinent data. The site validation is an opportunity to make changes to the drawings in order that existing core drills can be reused or discuss any other proactive measures that could simplify the project, save money and/or provide a better design for the end users.

3.1 Results of the site validation

a. Validation Trip Date:

b. Validation Trip Attendees and Roles:

c. Drawing Set Used

d. RFC Status

e. Approved Deployment Concept Drawing Set

3.2 Shipping / Rigging Plan

a. Shipping

b. TSE Storage Location (Local warehouse address and POC)

c. Rigging

SECTION 4: SITE TASKS

4.1 Terminal 2 – Main Checkpoint

a. Hours of operation

b. Electrical / Data Cable Work Effort

c. Architectural Work Effort Tasks:

d. Equipment Deployment

e. Site Restoration Efforts Required

4.2 Terminal 4 – Main Checkpoint

a. Hours of operation

b. Electrical / Data Cable Work Effort

c. Architectural Work Effort Tasks:

d. Equipment Deployment

e. Site Restoration Efforts Required

SECTION 5: SITE SCHEDULE

Below is the day-by-day plan of activities to be completed during this project. Four (4) days of effort are required to complete activities at ONT.

5.1New Technology Installation Schedule
Installation Date
Technology Type
OEM
Checkpoint
Lane

Total

5.2 Preparatory Work

Checkpoint T2 & T4

CHECKPOINT T2 PREPATORY WORK

ACTIVITY #
ACTIVITY DESCRIPTION
RESPONSIBLE PARTY

Checkpoint T4

CHECKPOINT T4 PREPATORY WORK

ACTIVITY #
ACTIVITY DESCRIPTION
RESPONSIBLE PARTY

5.3 Daily Activities

T2 Main Checkpoint

DAY/NIGHT 1

ACTIVITY #
ACTIVITY DESCRIPTION
RESPONSIBLE PARTY

DAY/NIGHT 2

ACTIVITY #
ACTIVITY DESCRIPTION
RESPONSIBLE PARTY

T4 Main Checkpoint

DAY/NIGHT 3

ACTIVITY #
ACTIVITY DESCRIPTION
RESPONSIBLE PARTY

DAY/NIGHT 4 | Add More as Needed

ACTIVITY #
ACTIVITY DESCRIPTION
RESPONSIBLE PARTY

SECTION 6: CCTV

The following section provides a description of CCTV needs/requirements broken down by Checkpoint.

6.1Checkpoint T2, T4
a.General Description of CCTV Needs/Issues

b. Number of Cameras

c. Repositioning Needs

d. New Purchase Needs

e. Specific Airport Requirements

SECTION 7: SPECIAL SITE CONSIDERATIONS

7.1 General

a. TSA requirements

b. Airport/Vendor/Airline requirements

c. Specific airport concerns

SECTION 8: APPENDICES

Appendix A: Equipment List – Decommissioned / Relocated / Installed This section identifies the Transportation Security Equipment (TSE) and infrastructure by item type that will be decommissioned, relocated or installed at checkpoints.

Status (Decommission / Relocate / Install)

TSE Type
Vendor and Model #
Serial Number
TSA Barcode
Old Location (Term/ Ckpt/ Ln)
New Location

(Term/ Ckpt / Ln)

Appendix B: Rigging Report To coordinate delivery and storage of the TSE and ancillary equipment, shippers and riggers are to contact only the Site Lead.

B.1 Overall Issues and concerns

· Required Contacts

· Floor Protection Requirements

a. Floor protection requirements will be provided upon load calculation provided by the Leidos Architectural Team.

· Airport Requirements B.2 Checkpoint

· Delivery Route:

· Internal Points of Entry and Path:

B.3 Checkpoint Additional as Needed

· Delivery Route:

· Internal Points of Entry and Path:

Pictures of the site and rigging path are shown below

Appendix C: Site Preparation Package This section contains the Site Preparation Package.

The definition of the scope of work for this effort is described in the following Contractor Statements of Work (SOW), which are supplied as attachments inline below.

1. Equipment Movement/Rigger Contractor and SOW document

1. Electrical Contractor SOW document

1. General Contractor SOW document

Estimated Name of New IDIQ COntract Fixed Unit Price Scope Items:

Shipping
Rigging
Installation
De-Installation
Packaging
Crating
Temp

Storage Total TEDS Fixed Unit Pricing Estimate

Airport Code
$
$
$
$
$
$
$
$

Estimated Cost-Type Scope Items Note: Estimates derived using rates as of xx/xx/2017

Awarded Contractor
SOW Title
Date
Proposal Bid Estimate
Contracted Vendor Cost

OEM Install/De-install Kits and Consumables: OEM according to TSE type

Equipment Movement Contractor:

Beltmann

Electrical Contractor:

TBD

General Contractor:

Attachment 1: Airport Code Equipment Movement Statement of Work:

Attachment 2: Airport Code Electrical Statement of Work:

Attachment 3: Airport Code General Contractor Statement of Work:

Attachment 4: Airport Code Miscellaneous Other Statements of Work:

Document Date:

Document Number: Page 1 of 1 image1.jpeg

File details come from the government source that posted it. Updated .