This document is a Task Assignment Change Order issued by the Florida Department of Environmental Protection (FDEP) for the HW550 indefinite delivery contract. The contracting parties are the State of Florida, Department of Environmental Protection, and Geosyntec Consultants. The task assignment pertains to the Colonial/Touch of Class site located in Greenacres, Palm Beach County, Florida (Site ID ERIC_5222). The contract manager is Killian Talley, and the contractor representative is Mike Lodato.
This Change Order (No. 1) extends the period of performance for Task Assignment DC038C from May 29, 2020 to June 30, 2020 to allow additional time for completion of final invoicing. The deliverable is an Interim Source Removal Work Plan, which was submitted on May 20, 2020 and approved by FDEP on the same date. The task involves 75 labor hours at a fixed price of $8,860.92, with no cost increase associated with this change order. The contractor may invoice upon FDEP receipt and approval of the work plan in accordance with the invoice schedule attached to the change order notification form.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Change Order No.:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
Site Name:
Site ID / Facility ID::
Description of Change [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverable:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
Cost Reimbursement Fixed Fee
Original Task Amount
Task Amount Prior to this Change Order Net Increase/decrease in task amount Task amount with all change orders $0.00 $0.00 $0.00 $0.00
Original Task Completion Date:
Completion Date Prior to this Change:
Net Increase/Decrease in Task Period:
Completion Date with all Change Orders:
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
FIXED PRICE
TASK ASSIGNMENT NOTIFICATION CHANGE ORDER FORM
ITEM
$0.00
$0.00
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
Final Deliverable Due Date:
$0.00
$0.00
CHANGE IN TASK TIME
FEE SCHEDULE
COST PLUS FIXED FEE
TOTAL
WCP TAFORM 01_18
HW550
1DC038C
Geosyntec Consultants
Mike Lodato
850-245-8928Killian Talley
Colonial/Touch of Class
ERIC_5222
This Task Assignment Change Order extends the task completion date to allow adequate time for final invoicing.
There is no change in the total cost related to this change order.
Interim Source Removal Work Plan 01/31/2020
$ 8,860.92 $ 0.00 $ 0.00 $ 0.00
$ 8,860.92 $ 0.00 $ 0.00 $ 0.00 $ 8,860.92
$ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00
$ 8,860.92
05/29/2020
05/29/2020
1 month
06/30/2020
Killian Talley Digitally signed by Killian Talley Date: 2020.05.28 00:59:51 -04'00'
Killian Talley Digitally signed by Killian Talley Date: 2020.05.28 01:00:00 -04'00'
Digitally signed by Jennifer Farrell Date: 2020.05.28 08:11:10 -04'00'
Michael N. Lodato Digitally signed by Michael N. Lodato Date: 2020.05.28 10:10:37 -04'00'
$ 8,860.92 $ 0.00 $ 0.00 $ 0.00
$ 8,860.92
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 01_18
Contract Number:
Task Assignment #:
Change Order #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
HW550
DC038C
$ 8,860.92
Subtask 1-2: Submittal of Interim Source Removal Work Plan (Complete)
Subtask 1-2: FDEP receipt and approval of Interim Source Removal Work Plan
01/31/2020
$ 8,860.92
10/17-2019
Florida Department of Memorandum Environmental Protection
Printed on recycled paper.
To: HW550 Contract Negotiation File Colonial/Touch of Class Greenacres, Palm Beach County
ERIC_5222
From: Killian Talley, Project Manager Date: May 28, 2020 Subject: Negotiation Summary
HW550 DC038C-1
This Task Assignment Change Order extends the period of performance for assignment DC038C to allow additional time for completion of final invoicing. The Department has finished review of the third revised report. The final deliverable was submitted on May 20, 2020 and approved by the Department on May 20, 2020.
There is no cost change related to this change order.
The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment Change Order. The final cost for this Task Assignment Change Order is $8,860.92 with 75 labor hours.
Geosyntec Consultants may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment, which accompanies the Task Assignment Change Order Notification Form.
| Task Assignment CHANGE ORDER |
| BWC Task Assignment Change Order Form (Rev 02-17).pdf |
| Task Assignment CHANGE ORDER |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |
File details come from the government source that posted it. Updated .