This is a Task Assignment Notification Form (DC039D) issued by the Florida Department of Environmental Protection (FDEP) Waste Cleanup Program to Geosyntec Consultants for conducting annual groundwater monitoring activities at the Scott's Northwood Cleaner facility (ERIC_5307) located at 2454 McMullen Booth Road, Clearwater, Pinellas County. The task assignment authorizes Geosyntec to perform work to satisfy the 270-day groundwater data requirement for FDEP's approval of a Remedial Alternatives Evaluation Report submitted on August 13, 2020. The contract is structured as a fixed-price task assignment under the broader HW550 indefinite delivery vehicle contract, with Crystal Posey serving as the FDEP Contract Manager and Todd Kafka as the Contractor Representative.
The scope of work comprises five subtasks: (1) Project Management; (2) LOE and Bidding Scope Preparation; (3) Groundwater Monitoring involving collection of 19 groundwater samples analyzed for volatile organic halocarbons (VOHs) using EPA Method 8260B; (4) Groundwater Monitoring Report including field forms, updated tables, figures, ADaPT/GIS data updates, and professional certification; and (5) IDW Management including disposal and transportation of investigation-derived waste through Erwin Remediation, Inc. The total fixed-price task assignment value is $12,125.86 with no retainage. Invoicing occurs upon FDEP receipt and approval of deliverables, with the final deliverable due date of January 7, 2022, and task completion date of May 31, 2022. Deliverables are scheduled for submittal on December 10, 2021, for the monitoring report and GIS data ($10,875.86) and January 7, 2022, for the final IDW manifest ($1,250.00).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW550
D000 N/ADC039D
Geosyntec
Todd Kafka
850-245-8851Crystal Posey
ERIC_5307
Scotts Northwood Cleaner
2454 McMullen Booth Road, Clearwater, Pinellas County
Monitoring
This Task Assignment (TA) authorizes Geosyntec Consultants to conduct annual groundwater monitoring to satisfy the the 270-day groundwater data requirement for the Department's approval of the Remedial Alternatives Evaluation Report submitted on August 13, 2020, as stated in the attached scope of work dated September 24, 2021.
Groundwater Monitoring Report, field forms, ADaPT/GIS, and IDW Manifests
01/07/2022
05/31/2022
$ 12,125.86 $ 0.00 $ 0.00 $ 0.00
$ 0.00
Crystal Posey Digitally signed by Crystal Posey Date: 2021.09.28 20:39:44 -04'00'
Crystal Posey Digitally signed by Crystal Posey Date: 2021.09.28 20:39:51 -04'00'
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2021.09.29 10:06:36 -04'00'
Todd Kafka, P.G. Digitally signed by Todd Kafka, P.G.
Date: 2021.09.29 14:23:33 -04'00'
$ 12,125.86
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 01-2018
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Subtask1-5: Groundwater Monitoring Report, ADaPT/GIS Update, and Final IDW Manifest 01/07/2022
FDEP receipt and approval of Groundwater Monitoring Report, ADaPT/GIS Update, and Final IDW Manifest - Subtask1-5 $ 12,125.86
$ 12,125.86
HW550
DC039D
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Interim Secretary
Memorandum
TO: HW550 Contract File FROM: Crystal Posey SUBJECT: Contemporary Cleaners
(ERIC_5307)
HW550 DC039D
2454 McMullen Booth Road, Suite 205 Clearwater, Pinellas County
DATE: September 28, 2021
Task Assignment HW550 DC039D is for Geosyntec Consultants to conduct annual groundwater monitoring activities to satisfy the 270-day groundwater data requirement for the Department's approval of the Remedial Alternatives Evaluation Report submitted on August 13, 2020, in accordance with the September 24, 2021 scope of work and cost estimate form.
Subtask 1: An automatic calculation based upon total direct labor hours determines the labor hours within this subtask.
Subtask 2: LOE Preparation Costs associated with preparation of this SOW and LOE are included in this subtask.
Subtask 3: Groundwater Monitoring Costs associated with the collection of 19 groundwater samples to be analyzed for VOHs are included in this subtask.
Subtask 4: Groundwater Monitoring Report Costs associated with the preparation and submittal of a Groundwater Monitoring Report that will include field forms and updated tables and figures are included in this subtask.
Subtask 5: IDW Management Costs associated with the disposal and transportation for the IDW are included in this subtask. Erwin Remediation Inc is the lowest cost provider for the transportation and disposal services.
The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment (TA), total task amount is 12,125.86.
The final task completion date is May 31, 2022.
FDEP COST ESTIMATEContractor: Geosyntec Consultants
Date: 9/24/2021
Task #: HW550 SubTask 1 Project Management SubTask 6
Site: Scott's Custom Cleaners - ERIC_5307 SubTask 2 LOE and Bidding Scope Preparation SubTask 7
Activity/Phase: Annual Groundwater Monitoring SubTask 3 Groundwater Monitoring SubTask 8
Project Manager: James Mills SubTask 4 Groundwater Monitoring Report SubTask 9
SubTask 5 IDW Management SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
Geosyntec Consultants $34.13 Project Manager J. Mills 9 9.4 $68.75 Principal T. Kafka 2 0 0 2 0 0 0 0 0 0 $40.38 Project Professional M. Hensley 6 0 0 6 0 0 0 0 0 $34.13 Professional J. Mills 21 2 2 16 1 0 0 0 0 0 $31.25 Senior Staff Professional A. Langteau 7 0 0 7 0 0 0 0 0 0 $27.40 Staff Professional K. Gallagher 21 0 21 0 0 0 0 0 0 0 $29.45 Staff Professional E. Upton 22 0 22 0 0 0 0 0 0 0 $26.13 Admin Asst A. Acosta 1 0 0 1 0 0 0 0 0 0
Total Hours 89 9 2 45 32 1 0 0 0 0 0
Direct Labor $2,885.28 $320.59 $68.26 $1,291.56 $1,170.74 $34.13 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 172.70% $4,982.88 $553.66 $117.89 $2,230.52 $2,021.87 $58.94 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $7,868.16 $874.25 $186.15 $3,522.08 $3,192.61 $93.07 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $144.27 $16.03 $3.41 $64.58 $58.54 $1.71 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF_GEO.XLS Page 1
FDEP COST ESTIMATEContractor: Geosyntec Consultants
Date: 9/24/2021
Task #: HW550 SubTask 1 Project Management SubTask 6
Site: Scott's Custom Cleaners - ERIC_5307 SubTask 2 LOE and Bidding Scope Preparation SubTask 7
Activity/Phase: Annual Groundwater Monitoring SubTask 3 Groundwater Monitoring SubTask 8
Project Manager: James Mills SubTask 4 Groundwater Monitoring Report SubTask 9
SubTask 5 IDW Management SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $388.00 $0.00 $388.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $388.00 $0.00 $388.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $100.00 $0.00 $0.00 $0.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $100.00 $0.00 $0.00 $0.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $10.00 $0.00 $0.00 $0.00 $10.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $110.00 $0.00 $0.00 $0.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $1,386.00 $0.00 $1,386.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $104.00 $0.00 $104.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $1,490.00 $0.00 $1,490.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $65.00 $0.00 $65.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $1,215.40 $0.00 $1,215.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $58.20 $0.00 $0.00 $0.00 $58.20 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,338.60 $0.00 $1,280.40 $0.00 $58.20 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $11,339.03 $890.28 $189.56 $6,745.06 $3,251.15 $262.98 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $786.83 $87.43 $18.62 $352.21 $319.26 $9.31 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $12,125.86 $977.71 $208.18 $7,097.27 $3,570.41 $272.29 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF_GEO.XLS Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET (Haz. Waste Dept.)
SITE : Geosyntec Consultants SUBTASK 2: LOE and Bidding Scope Preparation
DATE: 9/24/21
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Professional J. Mills 2
TOTAL LABOR 2
TRAVEL
TOTAL TRAVEL $0.00
SUBCONTRACTOR (EQUIPMENT PROCUREMENT)
TOTAL SUBCONTRACTOR (EQUIPMENT) $0.00
SUBCONTRACTOR (SERVICES PROCUREMENT)
TOTAL SUBCONTRACTOR (SERVICES) $0.00
LABORATORY COSTS
TOTAL LABORATORY $0.00
FIELD EXPENSES
TOTAL FIELD EXPENSES $0.00
SOW/LOE preparation (2 hr)
Copy of Scotts Custom Cleaners (ERIC_5307)_DC039D_LOE_GW Sampling 9/28/2021 Page 3 of 7 Subtask 2
SUBTASK 3: Groundwater Monitoring
DATE: 9/24/21
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Professional J. Mills 2
Staff Professional K. Gallagher
Staff Professional E. Upton
TOTAL LABOR 45
TRAVEL
TYPE RATE UNIT USAGE TOTALS
Vehicle Rental Truck 1 truck per person for 2 days $97.00 days 4 $388.00 subtotal $388.00
TOTAL TRAVEL $388.00
SUBCONTRACTOR (EQUIPMENT PROCUREMENT)
TOTAL SUBCONTRACTOR (EQUIPMENT) $0.00
SUBCONTRACTOR (SERVICES PROCUREMENT)
TOTAL SUBCONTRACTOR (SERVICES) $0.00
LABORATORY COSTS
Rate # SAMPLES #QA/QC TOTALS Method - Matrix VOHs using 8260B $66.00 19 2 $1,386.00 subtotal $1,386.00 Shipping
Large cooler (25 to 50 lbs) $104.00 1 $104.00 subtotal $104.00
TOTAL LABORATORY $1,490.00
FIELD EXPENSES
ITEM RATE UNIT USAGE TOTALS
Analytical Related Shallow Groundwater Sampling K 2 sets of equipment, 2 days $208.55 day 4 $834.20 Deep Groundwater Sampling Kit 1 set of equipment, 1 day $349.20 day 1 $349.20 Tubing (silicon) 3/16 by 3/8 $2.00 ft 16 $32.00 subtotal $1,215.40 Expendables $32.50 day 2 $65.00
TOTAL FIELD EXPENSES $1,280.40
Field preparation (2 hr)
Field preparation (2 hr); mobe/demob (2 d @ 0.5 hr/d = 1 hr); collect 6 water levels from MWs not sampled (1 hr); sample 9 monitoring wells (9 @ 1.5 hr/well = 13.5 hr);
equipment calibration (2 d @ 0.5 hr/day = 1 hr), sample management (2 hr)
Field preparation (2 hr); mobe/demob (2 d @ 1 hr/d = 2 hr); collect 7 water levels from MWs not sampled (1 hr); sample 10 monitoring wells (10 @ 1.5 hr/well = 15 hr);
equipment calibration (2 d @ 0.5 hr/day = 1 hr); IDW management (1 hr)
9/28/2021 Page 4 of 7 Subtask 3
SUBTASK 4: Groundwater Monitoring Report
DATE: 9/24/21
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal T. Kafka 2
Project Professional M. Hensley 6
Professional J. Mills 16
Senior Staff Professional A. Langteau 7
Administrative Assistant A. Acosta 1
TOTAL LABOR 32
TRAVEL
TOTAL TRAVEL $0.00
SUBCONTRACTOR (EQUIPMENT PROCUREMENT)
TOTAL SUBCONTRACTOR (EQUIPMENT) $0.00
SUBCONTRACTOR (SERVICES PROCUREMENT)
TOTAL SUBCONTRACTOR (SERVICES) $0.00
LABORATORY COSTS
TOTAL LABORATORY $0.00
FIELD EXPENSES
TOTAL FIELD EXPENSES $0.00
Report assembly and PDF compilation (1 hr)
ADaPT & GIS table update (19 water levels, 21 samples = 40 data points @ 8 min/point = ~6 hr); GIS data table checker and submittal (1 hr)
Data evaluation/interpretation and PG certification on report (2 hr)
Prepare Annual Groundwater Monitoring Report (16 hr)
Prepare 6 report figures (6 hr)
9/28/2021 Page 5 of 7 Subtask 4
SUBTASK 5: IDW Management
DATE: 9/24/21
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Professional J. Mills 1
TOTAL LABOR 1
TRAVEL
TOTAL TRAVEL $0.00
SUBCONTRACTOR (EQUIPMENT PROCUREMENT)
TOTAL SUBCONTRACTOR (EQUIPMENT) $0.00
SUBCONTRACTOR (SERVICES PROCUREMENT)
IDW
T&D - Erwin 1 drum $100.00 Lump Sum 1 $100.00 subtotal $100.00
TOTAL SUBCONTRACTOR (SERVICES) $100.00
LABORATORY COSTS
TOTAL LABORATORY $0.00
FIELD EXPENSES
ITEM RATE UNIT USAGE TOTALS
IDW Related Drum $58.20 drum 1 $58.20 subtotal $58.20
TOTAL FIELD EXPENSES $58.20
Prepare IDW manifest (1 hr)
9/28/2021 Page 6 of 7 Subtask 5
12802 Tampa Oaks Blvd, Suite 151 Tampa, Florida 33637
PH 813.558.0990
FAX 813.558.9726
www.geosyntec.com
FR3305B/Scotts Custom Cleaners (ERIC_5307)_DC039D_SOW_GW Sampling_Final
24 September 2021
Ms. Crystal Posey Florida Department of Environmental Protection Waste Cleanup Program 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400
Subject: Annual Groundwater Monitoring SOW/LOE Scott’s Custom Cleaners, Inc.
2454 McMullen Booth Road, Suite 205 Clearwater Florida
FDEP ID ERIC_5307
FDEP Task Assignment No. DC039D (pending)
Dear Ms. Posey:
Geosyntec Consultants, Inc. (Geosyntec) has prepared the following scope of work (SOW) and proposed level of effort (LOE) to perform annual groundwater monitoring at the former Scott’s Custom Cleaners, Inc. facility (herein, the “Site”) located in Clearwater, Florida. Groundwater samples were last collected in April 2020 at the Site. Geosyntec prepared this proposal at the request of the Florida Department of Environmental Protection (FDEP) to update groundwater analytical results for evaluation of the Remedial Alternatives Evaluation Report submitted on 13 August 2020 since the existing data is over 270 days old.
Subtask 1 – Project Management
Subtask 2 – LOE Preparation
This subtask included the preparation of this SOW and LOE.
Subtask 3 – Groundwater Monitoring
Geosyntec will collect groundwater samples from 19 accessible groundwater monitoring wells.
Prior to groundwater sampling, Geosyntec will gauge and record the depth-to-water (DTW) from 19 Site monitoring wells within a 24-hour period, including from 13 wells that are not anticipated to be sampled on the first day of field activities. Geosyntec will collect a total of 19 groundwater samples from MW-1, MW002, MW-7 through MW-14, MW-16 through MW-21, and DMW-1 to DMW-3. Geosyntec assumes that a peristaltic pump will be used to collect groundwater from
MW-1, MW002, MW-7 through MW-14, and MW-16 through MW-21 and an electric submersible pump will be used to collect groundwater from DMW-1 to DMW-3, consistent with previous sampling events. Field activities will be conducted in accordance with the FDEP Standard Operating Procedures.
Groundwater samples will be submitted under chain of custody protocol for laboratory analysis of volatile organic halocarbons (VOHs) by Environmental Protection Agency Method 8260B. Two field duplicates will be collected for quality assurance and quality control purposes.
Subtask 4 – Groundwater Monitoring Report
Geosyntec will submit a Groundwater Monitoring Report that will be signed and sealed by a licensed Florida engineer or geologist and include field forms and updated tables and figures. The field forms will consist of groundwater sampling, calibration, DTW, and drum logs generated on- Site during the sampling activities. The tables will include (i) DTW measurements, (ii) groundwater analytical results for VOHs, and (iii) geochemical field parameters. The figures will include (i) Site map, (ii) groundwater elevation contours in the surficial aquifer, (iii) groundwater elevation contours in the Upper Floridan aquifer, (iv) groundwater analytical results in the surficial aquifer, and (v) groundwater analytical results in the Upper Floridan aquifer.
In addition, the ADaPT files and associated GIS data tables for the annual monitoring event will also be submitted.
Subtask 5 - IDW Management
Based on previous sampling events, it is estimated that purge water generated during sampling activities will be containerized in one, 55-gallon drum. Geosyntec also assumes the existing waste characterization analytical results can be used for disposal investigation-derived waste (IDW).
Erwin Remediation, Inc. is the lowest cost provider of transportation and disposal services (per drum). Geosyntec will review the generation of a waste characterization profile as well as prepare the IDW manifest. The IDW transportation and disposal quotes are provided in Attachment A.
Invoice and Deliverable Schedule
Please note the following schedule is contingent on FDEP review and approval of this SOW/LOE within two weeks of submittal. We have tentatively scheduled groundwater sampling for the week of 10/25/2021.
Subtask Deliverable Deliverable Date Invoice Amount
2, 3, 4 Submittal of Groundwater Monitoring Report, ADaPT Files, and GIS data tables 12/10/2021 $10,875.86
1, 5 Submittal of Final IDW manifest 1/7/2022 $1,250.00 Total $12,125.86
CLOSURE
As always, it is a pleasure to work with the FDEP. If you require any additional information or have any questions, please contact us at 813.558.0990.
Sincerely, James C. Mills Professional
Todd K. Kafka, P.G.
Senior Principal Hydrogeologist
Attachments Subcontractor Bids
LOE
ATTACHMENT A
SUBCONTRACTOR BIDS
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To:
Ms. Ann Sava
Geosyntec Consultants, Inc.
19321 US Highway 19 N
Building C, Suite 200
Clearwater, FL 33764
February 3, 2021
Re: Non-Hazardous Drum T&D Quote
Ms. Sava:
The price for the transportation and disposal (T&D) of drums of non-hazardous soil or water located the State of FL will be $100.00 per drum, for both transportation and disposal.
Pricing for locations in the Florida Keys will be handled on a case-by-case basis.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: ErwinRemediation@Gmail.com
Office: (850) 292-6511 mailto:Remediation@Gmail.com
BID PROPOSAL FORM
FDEP Drycleaner and Hazardous Waste Sites Investigation Derived Waste (IDW) Transportation and Disposal
Contractor Company Name: Capitol Environmental Services
Contact Name and Phone Number: Mike Anderson 813‐613‐0452
Region T&D of 1 Non‐Hazardous IDW Drum (solid or liquid)
T&D of 1 Hazardous IDW Drum (solid or liquid)
Northwest LQ 165.00 Solids 195.00 LQ 265.00 Solids 525.00
Northeast LQ 165.00 Solids 195.00 LQ 265.00 Solids 525.00
Central LQ 165.00 Solids 195.00 LQ 265.00 Solids 525.00
Southwest LQ 165.00 Solids 195.00 LQ 265.00 Solids 525.00
*Southeast LQ 165.00 Solids 195.00 LQ 265.00 Solids 525.00
* Excludes Monroe County (Case by case basis determined by volume of IDW)
Bid costs above should be inclusive of transportation fees, fuel fees, environmental recovery fees, etc.
No standby time should be included in the above bid costs.
Assume that the drums are accessible.
It is assumed that VOH totals results will be provided for profiling. If other analytical results are required, please indicated here:
| Task Assignment Notification |
| BWC Task Assignment Form (Rev 02_17).pdf |
| Task Assignment Notification |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |
Untitled
File details come from the government source that posted it. Updated .