This document comprises a Task Assignment Notification Form and supporting materials for contract HW550 between the Florida Department of Environmental Protection (FDEP) and Geosyntec Consultants. The task assignment (DC026i) authorizes work at the Art Craft Cleaners site (ERIC_4584) located at 1630 University Boulevard South, Jacksonville, Duval County, Florida. Crystal Posey serves as the FDEP Contract Manager, with Todd Kafka representing Geosyntec as the contractor representative. The work falls under the monitoring phase of the contract and is governed by contractual authority from William E. Burns, Jr.
The task assignment authorizes Geosyntec to conduct annual groundwater monitoring activities consisting of four subtasks: Project Management (Subtask 1), Annual Groundwater Sampling (Subtask 2), Annual Groundwater Monitoring Report (Subtask 3), and IDW Management (Subtask 4). Groundwater samples will be collected from 18 monitoring wells using conventional low-flow techniques and passive diffusion bags. The work is structured as a fixed-price contract with a total task value of $12,012.62, with no retainage. Deliverables include submittal of groundwater sampling field documentation due April 30, 2021 ($6,728.04), final IDW manifest due March 26, 2021 ($647.35), and FDEP receipt and approval of the Groundwater Monitoring Report with ADaPT/GIS update due June 4, 2021 ($5,284.58). The contract execution period extends through November 30, 2021. The cost estimate reflects labor costs of $8,346.99, travel expenses of $194.00, laboratory analytical costs of $1,490.00, field expenses of $828.87, subcontractor services for IDW disposal of $165.00, and a completion fee of $834.71.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW550
D000 N/ADC026i
Geosyntec
Todd Kafka
850-245-8851Crystal Posey
ERIC_4584
Art Craft Cleaners
1630 University Blvd S, Jacksonville, Duval County
Monitoring
This Task Assignment authorizes Geosyntec Consultants to conduct annual groundwater monitoring activities in accordance with the attached February 23, 2021 scope of work, cost estimate, and bid documentation.
Groundwater Monitoring Report, ADaPT/GIS update, and IDW Manifest
06/04/2021
11/30/2021
$ 12,012.62 $ 0.00 $ 0.00 $ 0.00
$ 0.00
Crystal Posey Digitally signed by Crystal Posey Date: 2021.02.23 17:44:53 -05'00'
Crystal Posey Digitally signed by Crystal Posey Date: 2021.02.23 17:44:58 -05'00'
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2021.02.24 07:25:07 -05'00'
Todd K. Kafka, PG Digitally signed by Todd K. Kafka, PG Date: 2021.02.24 09:30:42 -05'00'
$ 12,012.62
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 01-2018
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Subtask 2: Submittal of groundwater sampling field documentation 04/30/2021
Subtask 1, 3, & 4: Groundwater Monitoring Report, ADaPT/GIS update, and IDW Manifest 06/04/2021
FDEP approval of submittal of groundwater sampling field documentation - Subtask 2 $ 6,728.04
FDEP approval of Groundwater Monitoring Report, ADaPT/GIS update, and IDW Manifest - Subtask 1, 3, and 4 $ 5,284.58
$ 12,012.62
HW550
DC026i
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Noah Valenstein Secretary
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 3
2399-2400
Memorandum
TO:
FROM:
SUBJECT:
DATE:
HW550 Contract File
Crystal Posey, Project Manager
Art Craft Cleaners
ERIC_4584
HW550 DC026i
February 23, 2021
This Task Assignment authorizes Geosyntec to conduct annual groundwater sampling at the Art Craft Cleaners site. Groundwater samples will be collected from 18 monitoring wells in the monitoring well network to evaluate the current extent of the contaminant plume. Bid costs prepared by IDW haulers are included in the scope of work and exhibit the costs associated with the off-site disposal of the decontamination water generated during the sampling activities, all which is included in the attached scope of work dated February 23, 2021.
The deliverable due dates have been modified by the Contract Manager in the scope of work.
The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment (TA), total task amount is $12,012.62.
The final task completion date is November 30, 2021.
FDEP COST ESTIMATEContractor: Geosyntec Consultants
Date: 12/22/2020
Task #: DC026I SubTask 1 Project Management SubTask 6
Site: Art Craft Cleaners SubTask 2 Annual Groundwater Sampling SubTask 7
Activity/Phase: Annual Groundwater Sampling SubTask 3 Annual Groundwater Monitoring Report SubTask 8
Project Manager: Crystal Posey SubTask 4 IDW Management SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
Geosyntec Consultants $34.13 Project Manager Johnson 10 10.0 $60.10 Principal Kafka 2 0 2 0 0 0 0 0 0 0 $34.13 Professional Dawson 1 1 0 0 0 0 0 0 0 0 $34.13 Professional Johnson 48 26 18 4 0 0 0 0 0 0 $28.37 Staff Professional Barnhart 17 17 0 0 0 0 0 0 0 0 $28.85 Staff Professional Langteau 6 0 6 0 0 0 0 0 0 0 $30.53 Admin Asst Gallagher 1 0 1 0 0 0 0 0 0 0 $40.38 Project Professional Hensley 6 0 6 0 0 0 0 0 0 0
Total Hours 91.0 10 44 33 4 0 0 0 0 0 0
Direct Labor $3,060.87 $340.10 $1,403.80 $1,180.45 $136.52 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 172.70% $5,286.12 $587.35 $2,424.36 $2,038.64 $235.77 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $8,346.99 $927.45 $3,828.16 $3,219.09 $372.29 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $153.05 $17.01 $70.19 $59.02 $6.83 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF_GEO.XLS Page 1
FDEP COST ESTIMATEContractor: Geosyntec Consultants
Date: 12/22/2020
Task #: DC026I SubTask 1 Project Management SubTask 6
Site: Art Craft Cleaners SubTask 2 Annual Groundwater Sampling SubTask 7
Activity/Phase: Annual Groundwater Sampling SubTask 3 Annual Groundwater Monitoring Report SubTask 8
Project Manager: Crystal Posey SubTask 4 IDW Management SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $194.00 $194.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $194.00 $194.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $150.00 $0.00 $0.00 $150.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $150.00 $0.00 $0.00 $150.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $15.00 $0.00 $0.00 $15.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $165.00 $0.00 $0.00 $165.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $1,386.00 $1,320.00 $0.00 $66.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $104.00 $104.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $1,490.00 $1,424.00 $0.00 $66.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $65.00 $65.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $705.67 $705.67 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $58.20 $58.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $828.87 $828.87 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $11,177.91 $944.46 $6,345.22 $3,278.11 $610.12 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $834.71 $92.75 $382.82 $321.91 $37.23 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $12,012.62 $1,037.21 $6,728.04 $3,600.02 $647.35 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF_GEO.XLS Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET (Haz. Waste Dept.)
SITE : Art Craft Cleaners SUBTASK: Annual Groundwater Sampling
DATE: 12/22/20
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Professional (B Dawson)
Professional (A. Johnson)
Staff Professional (J. Barnhart)
TOTAL LABOR 44
TRAVEL
TYPE RATE UNIT USAGE TOTALS
Vehicle Rental Truck $97.00 day 2 $194.00 subtotal $194.00
TOTAL TRAVEL $194.00
SUBCONTRACTOR (SERVICES PROCUREMENT)
TOTAL SUBCONTRACTOR (SERVICES) $0.00
LABORATORY COSTS
Rate # SAMPLES #QA/QC TOTALS Method - Matrix
EPA 8260 - GW $66.00 18 2 $1,320.00
subtotal $1,320.00 Shipping
Large cooler (25 to 50 lbs) $104.00 1 $104.00 Small cooler (0 to 25lbs) $63.00 0 $0.00 subtotal $104.00
TOTAL LABORATORY $1,424.00
FIELD EXPENSES
ITEM RATE UNIT USAGE TOTALS
Analytical Related Shallow GW Sampling Kit $208.55 day 2 $417.10 PDB Shipping $48.00 each 1 $48.00 PDBs (prefilled including 1 duplicate) $21.87 each 11 $240.57 subtotal $705.67 IDW Related Drum $58.20 drum 1 $58.20 other $0.00 0 $0.00 subtotal $58.20
Expendables $32.50 day 2 $65.00
TOTAL FIELD EXPENSES $828.87
Field prep (2); Mob/demob from site 2 days @ 1hr/day (2); Collect water levels (3);
Sample 10 MWs with pdbs and redeploy @ 1 hr/well (10)
Technical assistance with field staff (1)
SOW/LOE preparation (2); Property owner and tenant notification (1); Field prep (2);
Mob/demob from site 2 days @ 1hr/day (2); Collect water levels (3); Sample 8 MWs @ 1.5h/well (12); Sample management/shipping (1); IDW sampling and drum management (2); Review and submittal of groundwater sampling field notes (1)
Art Craft 2021 Annual GW Sampling_LOE 2/23/2021 Page 3 of 6 Subtask 2
SUBTASK: Annual Groundwater Monitoring Report
DATE: 12/22/20
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Principal (T. Kafka) 2
Professional (A. Johnson) 18
Staff Professional (A Langteau) 6
Project Professional (M. Hensley) 6
Admin Asst (Gallagher) 1
TOTAL LABOR 33
Technical review of GMR for professional certification
GMR preparation
GIS data tables: 19 water levels and 20 sample points @ 8min/point (5); GIS database data checker and submittal (1)
Figure preparation
Formatting and report production (1)
2/23/2021 Page 4 of 6 Subtask 3
SUBTASK: IDW Management
DATE: 12/22/20
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Professional (A. Johnson) 4
TOTAL LABOR 4
TRAVEL
TOTAL TRAVEL $0.00
SUBCONTRACTOR (SERVICES PROCUREMENT)
NAME PURPOSE RATE UNIT USAGE TOTALS
IDW
Hulls $150.00 Drum 1 $150.00 subtotal $150.00
TOTAL SUBCONTRACTOR (SERVICES) $150.00
Establish new waste profile (2 hr); Review and signature of IDW manifest and coordinate pickup (2 hr)
2/23/2021 Page 5 of 6 Subtask 4
SUBTASK: IDW Management
DATE: 12/22/20
LABORATORY COSTS
Rate # SAMPLES #QA/QC TOTALS
Method - Matrix
EPA 8260 - GW $66.00 1 0 $66.00
EPA 8260 - Soil $66.00 0 0 $0.00 TO-14 - Gas $200.00 0 0 $0.00 Other $0.00 0 0 $0.00 Other $0.00 0 0 $0.00 subtotal $66.00
TOTAL LABORATORY $66.00
FIELD EXPENSES
TOTAL FIELD EXPENSES $0.00
2/23/2021 Page 6 of 6 Subtask 4
Art Craft 2021 Annual GW Sampling_SOW
1200 Riverplace Boulevard, Suite 710 Jacksonville, Florida 32207
PH 904.858.1818
www.geosyntec.com
23 February 2021
Ms. Crystal Posey Florida Department of Environmental Protection 2600 Blair Stone Road Tallahassee, FL 32399-2400
Subject: SCOPE OF WORK and CEF/LOE Art Craft Cleaners 1630 University Boulevard South Jacksonville, Duval County, Florida
FDEP ERIC ID ERIC_4584
Dear Ms. Posey, Please find attached Geosyntec’s Scope of Work and Cost Estimate Form and proposed Level of Effort (CEF/LOE) for annual groundwater sampling activities at Art Craft Cleaners (Site) located in Jacksonville, Florida. A summary of the costs associated with the attached CEF/LOE is provided below.
Subtask 1 – Project Management
Subtask 2 – Annual Groundwater Sampling
Subtask 2 includes costs associated with annual groundwater monitoring at the Site which is planned for January 2021. As recommended in the April 2020 Annual Groundwater Monitoring Letter Report, groundwater samples will be collected from the 18 monitoring wells in the monitoring well network to evaluate the current extent of the contaminant plume. Prior to conducting groundwater sampling, depth to water measurements will be collected from the monitoring well network to evaluate groundwater flow direction and horizontal and vertical groundwater gradients. Groundwater sampling activities will be conducted in general accordance with FDEP SOPs, and samples will be collected from 8 shallow monitoring wells (PZ01 through PZ03, MW01, SM01 through SMW03, and SMW05) using conventional low flow techniques.
Groundwater samples from the 6 intermediate monitoring wells (IMW01 through IMW06) and 4 deep monitoring wells (DMW01 through DMW04) will be collected from the passive diffusion bags (PDBs) deployed during the January 2020 sampling event. For quality assurance and quality control purposes, two duplicate groundwater samples will be collected during the 2021 sampling event. The 22 groundwater samples will be analyzed by a fixed-based lab for VOHs by EPA
Art Craft 2021 Annual GW Sampling_SOW
Method 8260. Upon completion of groundwater sampling, passive diffusion bags (PDBs) will be deployed in the 10 intermediate and deep monitoring wells, including one duplicate PDB, for the 2021 annual sampling event.
Subtask 3 – Annual Groundwater Monitoring Report
Subtask 3 includes costs associated with the preparation of an Annual Groundwater Monitoring Report (Report) in general accordance with Chapter 62-780, Florida Administrative Code (FAC).
The Report will document the results of the annual groundwater sampling and include the laboratory analytical results, chain of custody record, updated water level and analytical data tables, and updated site maps that illustrate the groundwater elevation contours and analytical results. The Report will include a recommendation for continued groundwater monitoring until the November 2015 Remedial Action Plan (RAP) is implemented.
The Report will be signed and sealed by the Florida Licensed Professional Engineer or Geologist responsible charge of the work. An electronic PDF version of the report will be uploaded to FDEP’s FTP site. ADaPT files and updated GIS Data Tables will be uploaded to the FDEP’s FTP site.
Subtask 4 – IDW Management Subtask 4 includes costs for IDW transport and disposal. Bid costs prepared by the IDW haulers are presented in Attachment A. Purge water and decontamination water generated during sampling activities will be placed in new 55-gallon drums and manifested for off-site disposal by Hulls Environmental Services. One sample will be collected from the IDW drum and analyzed for VOHs via EPA Method 8260B to establish a new waste profile with Hulls. IDW will be staged in the rear of the facility.
Art Craft 2021 Annual GW Sampling_SOW
Invoice and Deliverable Schedule:
Subtask Deliverable Deliverable Due Date Invoice Amount
2 Submittal of groundwater sampling field documentation
26 February 2021 $6,728.04
4 Submittal of final IDW manifest 26 March 2021 $647.35
1 & 3 FDEP receipt and approval of GMR Letter Report and ADaPT/GIS update 16 April 2021 $4,637.23
Total $12,012.62
As always, it is a pleasure to work with the FDEP. Please contact us if you have any questions or require additional information.
Sincerely, Blaine Dawson, P.G.
Project Geologist
Todd K. Kafka, P.G.
Principal Hydrogeologist
Copy: Mike Lodato, Geosyntec Alexis Johnson, Geosyntec
Attachments
30 April 2021
04 June 2021
04 June 2021
Posey_C Cross-Out
Posey_C Cross-Out
Posey_C Cross-Out
ATTACHMENT A
LEVEL OF EFFORT
PDB QUOTES PACKAGE
December 2019 – December 2020
Item Target PDB Depth Unit Cost ($)* Comments & Options 20 ft 77.25$ 50 ft 78.15$ 100 ft 79.65$ 250 ft 96.70$ Recommended Option for .75 inch wells: add 1 additional weight for wells 50‐100ft, ($20 ea, Not Included). add 1 wgt per add'l 100ft 20 ft 74.37$ 50 ft 75.27$ 100 ft 76.77$ 250 ft 93.82$ Recommended Option for 1 Inch wells: add 1 additional weight ($20 ea, Not Included) for wells 100‐200 ft depth 20 ft 72.00$ 50 ft 72.90$ 100 ft 74.40$ 250 ft 95.95$ Recommended Option for 2 & 4 Inch wells: add 1 additional weight ( $22 ea, Not Included) for wells>200 ft depth 20 ft 73.17$ 50 ft 74.07$ 100 ft 75.57$ 250 ft 97.12$ Recommended Option for 2 & 4 Inch wells: add 1 additional weight (Not Included) for wells>200 ft depth
0.75‐inch well 18.45$ GSD151, .75x 42in Prefilled 1‐inch well 18.45$ GSD151, .75x 42in Prefilled 2‐inch well 21.87$ GSD165, 1.33x24in Prefilled 4‐inch well 21.87$ GSD165, 1.33x24in Prefilled
Miscellaneous Tethers > 150 ft Require a Spool instead of H‐Frame. A spool is included in the 250ft price only. One Reel‐Handle is required separately and can be shared among all Spools. Use FSR109, $9.00ea
<20 lbs/2 Pgs $48 Zip Ties for attaching samplers to tether rings are sold in packages of 25 for $1.25 per pkg <50 lbs/2 Pgs $96 Shipping estimates are for Fedex GROUND Service. 1‐2 day delivery to Jacksonville FL from Atlanta Ga factory.
EON Products December 2019- December 2020 PDB Rates
Shipping Charge
*All unit costs must include applicable service costs
Prefilled Diffusion Sampler (<250mL) with ASTM Type 1 Deionized Water for 0.75‐inch well with complete hanger kit (locking cap, stainless steel reusable weight, suspension tether,PDB connection rings, tether holding frame, etc.)
Prefilled Diffusion Sampler (<250mL) with ASTM Type 1 Deionized Water for 1‐inch well with complete hanger kit (locking cap, stainless steel reusable weight, suspension tether,PDB connection rings, tether holding frame, etc.)
Prefilled Diffusion Sampler (<250mL) with ASTM Type 1 Deionized Water for 2‐inch well with complete hanger kit (locking cap, stainless steel reusable weight, suspension tether,PDB connection rings, tether holding frame, etc.)
Prefilled Diffusion Sampler (<250mL) with ASTM Type 1 Deionized Water for 4‐inch well with complete hanger kit (locking cap, stainless steel reusable weight, suspension tether,PDB connection rings, tether holding frame, etc.)
Cost for additional PDB (<250 mL)
AJohnson Rectangle
AJohnson Rectangle
AJohnson Rectangle
Alexis Johnson
From: Alexis Johnson Sent: Tuesday, November 26, 2019 9:24 AM To: 'Brian Bendis'; lynn@eonpro.com; donna.jackson@alsglobal.com Subject: PDB Quotes Attachments: PDB Quotes Package 2018.pdf
Hi All, Could you please send over revised quotes for passive diffusion samplers good for the next year in the format attached?
Thanks, Alexis I. Johnson, E.I.(FL) Senior Staff Engineer
1200 Riverplace Boulevard Suite 710 Jacksonville, FL 32207 Direct: 904-450-4262 Mobile: 609-658-0914 www.Geosyntec.com
This electronic mail message contains information that (a) is or may be LEGALLY PRIVILEGED, CONFIDENTIAL, PROPRIETARY IN NATURE, OR OTHERWISE PROTECTED BY LAW FROM DISCLOSURE, and (b) is intended only for the use of the Addressee(s) named herein. If you are not the intended recipient, an addressee, or the person responsible for delivering this to an addressee, you are hereby notified that reading, using, copying, or distributing any part of this message is strictly prohibited. If you have received this electronic mail message in error, please contact us immediately and take the steps necessary to delete the message completely from your computer system.
AJohnson Callout no bid provided by ALS
| Task Assignment Notification |
| BWC Task Assignment Form (Rev 02_17).pdf |
| Task Assignment Notification |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |
| Art Craft 2021 Annual GW Sampling_LOE.pdf |
| Cost Estimate |
| Subtask 2 |
| Subtask 3 |
| Subtask 4 |
| PDB Quotes Package 2020.pdf |
| ALS PDB Quotes.pdf |
| Sheet1 |
| Pine PDB Quotes.pdf |
| Sheet1 |
| PDB Quotes Package 2018.pdf |
| ALS PDB Quotes.pdf |
| Sheet1 |
| Pine PDB Quotes.pdf |
| Sheet1 |