Document Summary

This package of documents comprises Task Assignment Change Order (TACO) #3 for Contract HW550, an indefinite delivery contract between the Florida Department of Environmental Protection (FDEP) and Geosyntec Consultants. The contract covers environmental assessment and monitoring services at the Bellair Cleaners site in Orange Park, Clay County, Florida (FDEP ERIC ID ERIC_4257, Facility ID 109500594). The contract manager for FDEP is Killian Talley, and the contractor representative is Mike Lodato.

TACO #3 authorizes a cost reduction of $1,508.69 from the prior task amount, resulting in a final task cost of $41,434.82 with 190 labor hours. The work includes seven subtasks: project management; Year 2 Quarter 2 UIC groundwater monitoring; Year 2 Quarter 4 UIC and annual groundwater monitoring; reporting; Work Change Directive #1 related to a stolen waste drum incident; installation of five new monitoring wells (MW009-MW013) using direct push technology drilling; and groundwater sampling from the newly installed wells. Key deliverables include groundwater sampling field forms, monitoring well installation logs, an Annual Groundwater Monitoring Report, ADaPT files, and GIS data tables, with invoice amounts ranging from $4,181.08 to $22,507.36 and completion dates between September 28, 2018, and July 26, 2019. Subcontractors involved include Preferred Drilling Solutions, PermaFix Environmental Services, Southeastern Surveying, and Environmental Resource Solutions.

View the file

Other files

File Type Posted
CN-370000-HW550-DC39BCO4.pdf PDF
CN-370000-HW550-SL04LCO1.pdf PDF
CN-370000-HW550-BF02BCO1.pdf PDF
CN-370000-HW550-SW23CO4.pdf PDF
CN-370000-HW550-SL04WCO1.pdf PDF
CN-370000-HW550-SIS07B.pdf PDF
CN-370000-HW550-DC38CCO1.pdf PDF
CN-370000-HW550-BF3A.pdf PDF
CN-370000-HW550-HW028A.pdf PDF
CN-370000-HW550-DC30CCO2.pdf PDF
CN-370000-HW550-DC18C.pdf PDF
CN-370000-HW550-HW020G.pdf PDF
CN-370000-HW550-SIS9BCO1.pdf PDF
CN-370000-HW550-HW020B.pdf PDF
CN-370000-HW550-SA117.pdf PDF
CN-370000-HW550-DC03N.pdf PDF
CN-370000-HW550-A11.pdf PDF
CN-370000-HW550-BF504A.pdf PDF
CN-370000-HW550-SL13CCO1.pdf PDF
CN-370000-HW550-DC15ICO1.pdf PDF
CN-370000-HW550-DC37A.pdf PDF
CN-370000-HW550-FIL8.pdf PDF
CN-370000-HW550-FIL18.pdf PDF
CN-370000-HW550-DC17FCO1.pdf PDF
CN-370000-HW550-SA138.pdf PDF
CN-370000-HW550-DC21C.pdf PDF
CN-370000-HW550-SL10ACO1.pdf PDF
CN-370000-HW550-SIS9CCO1.pdf PDF
CN-370000-HW550-DC10ACO1.pdf PDF
CN-370000-HW550-SIS13A.pdf PDF
CN-370000-HW550-DC026i.pdf PDF
CN-370000-HW550-HW15J.pdf PDF
CN-370000-HW550-HW15ICO2.pdf PDF
CN-370000-HW550-HW09ECO3.pdf PDF
CN-370000-HW550-DC28B.pdf PDF
CN-370000-HW550-DC039D.pdf PDF
CN-370000-HW550-DC01H.pdf PDF
CN-370000-HW550-SLA60CO1.pdf PDF
CN-370000-HW550-HW20A.pdf PDF
CN-370000-HW550-DC025D.pdf PDF
CN-370000-HW550-SL004Y.pdf PDF
CN-370000-HW550-SA125.pdf PDF
CN-370000-HW550-SL13B.pdf PDF
CN-370000-HW550-SL04YCO1.pdf PDF
CN-370000-HW550-SLA92.pdf PDF
CN-370000-HW550-SIA063.pdf PDF
CN-370000-HW550-0A010CO1.pdf PDF
CN-370000-HW550-BF54B.pdf PDF
CN-370000-HW550-SA133.pdf PDF
CN-370000-HW550-DC21H.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

8/12/19

4/10/2019

Florida Department of Memorandum Environmental Protection

Printed on recycled paper.

To: HW550 Contract Negotiation File

Bellair Cleaners Orange Park, Clay County

ERIC_4257

From: Killian Talley, Project Manager Date: August 6, 2019 Subject: Negotiation Summary

HW550 DC027G-3

This Task Assignment Change Order authorizes a reduction of costs related to subcontractor utilization and personnel utilized.

Subtask 1: Project Management An automatic calculation based upon total direct labor hours determines the labor hours within this subtask. The cost reduction related to this subtask is $95.52.

Subtask 2 – Subtask 5 No changes to these subtasks.

Subtask 6: Monitoring Well Installation This subtask reduces subcontractor costs and changes in personnel for field work. The cost reduction related to this subtask is $1,203.44.

Subtask 7: New Monitoring Well Groundwater Sampling This subtask reduces costs associated with changes in personnel who completed the field work.

The cost reduction related to this subtask is $209.73

The cost reduction related to this change order is $1,508.69.

The FDEP project manager agrees to the scope of work and final cost associated with this Task Assignment Change Order. The final cost for this Task Assignment Change Order is $41,434.82 with 190 labor hours.

Geosyntec Consultants may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment, which accompanies the Task Assignment Change Order Notification Form.

FDEP COST ESTI MATEContractor: Geosyntec Consultants

Date: 4/9/2019

Task #: DC027G SubTask 1 Project Management SubTask 6 Monitoring Well Installations

Site: Bellair Cleaners SubTask 2 Semi-Annual UIC Sampling SubTask 7 New Wells Groundwater Sampling

Activity/Phase: UIC and Annual Groundwater Sa SubTask 3 Annual Groundwater Sampling SubTask 8

Project Manager: R. Klinger SubTask 4 GMR SubTask 9

SubTask 5 WCD #1 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

Geosyntec Consultants $49.76 Project Manager Klinger 15 14.7

$1.00 Principal 0 0 0 0 0 0 0 0 0 0 $1.00 Principal 0 0 0 0 0 0 0 0 0 0 $1.00 Senior Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Senior Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Senior Professional 0 0 0 0 0 0 0 0 0 0

$49.76 Senior Professional Klinger 25 7 5 4 1 5 3 0 0 0 $1.00 Project Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Project Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Senior Staff Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Senior Staff Professional 0 0 0 0 0 0 0 0 0 0

$27.16 Senior Staff Professional Ahmed 36 0 0 0 0 36 0 0 0 0 $32.21 Senior Staff Professional Dawson 88 15 28 30 4 6 5 0 0 0 $26.92 Staff Professional Ramsey 13 0 0 0 0 0 13 0 0 0

$1.00 Staff Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Staff Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Staff Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Staff Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Tech Word Processor 0 0 0 0 0 0 0 0 0 0

$22.75 Admin Asst Hayes 1 0 0 1 0 0 0 0 0 0 $34.13 Professional Hensley 12 0 0 12 0 0 0 0 0 0

$1.00 Drafter/CADD 0 0 0 0 0 0 0 0 0 0 $1.00 Designer 0 0 0 0 0 0 0 0 0 0 $1.00 Site Manager 0 0 0 0 0 0 0 0 0 0 $1.00 Site Manager 0 0 0 0 0 0 0 0 0 0 $1.00 Senior Engineering Technician 0 0 0 0 0 0 0 0 0 0 $1.00 Engineering Technician 0 0 0 0 0 0 0 0 0 0

Total Hours 190.0 15 22 33 47 5 47 21 0 0 0

Direct Labor $6,568.32 $729.81 $831.47 $1,150.68 $1,597.65 $178.60 $1,419.82 $660.29 $0.00 $0.00 $0.00

Overhead 172.70% $11,343.48 $1,260.38 $1,435.95 $1,987.22 $2,759.14 $308.44 $2,452.03 $1,140.32 $0.00 $0.00 $0.00 Total Labor $17,911.80 $1,990.19 $2,267.42 $3,137.90 $4,356.79 $487.04 $3,871.85 $1,800.61 $0.00 $0.00 $0.00

Other Direct Costs $328.40 $36.49 $41.57 $57.53 $79.88 $8.93 $70.99 $33.01 $0.00 $0.00 $0.00

REV: 02/03 CEF_GEO.XLS Page 3

FDEP COST ESTI MATEContractor: Geosyntec Consultants

Task #: DC027G SubTask 1 Project Management SubTask 6 Monitoring Well Installations

Site: Bellair Cleaners SubTask 2 Semi-Annual UIC Sampling SubTask 7 New Wells Groundwater Sampling

Activity/Phase: UIC and Annual Groundwater Sa SubTask 3 Annual Groundwater Sampling SubTask 8

Project Manager: R. Klinger SubTask 4 GMR SubTask 9

SubTask 5 WCD #1 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $905.00 $97.00 $194.00 $0.00 $97.00 $420.00 $97.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $905.00 $97.00 $194.00 $0.00 $97.00 $420.00 $97.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $5,590.00 $0.00 $0.00 $0.00 $0.00 $5,590.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $2,400.00 $0.00 $0.00 $0.00 $0.00 $2,400.00 $0.00 $0.00 $0.00 $0.00

IDW $766.00 $0.00 $0.00 $231.00 $0.00 $535.00 $0.00 $0.00 $0.00 $0.00

Utilities $750.00 $0.00 $0.00 $0.00 $0.00 $750.00 $0.00 $0.00 $0.00 $0.00

$2,785.00 $0.00 $0.00 $0.00 $0.00 $2,785.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $12,291.00 $0.00 $0.00 $231.00 $0.00 $12,060.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $1,229.10 $0.00 $0.00 $23.10 $0.00 $1,206.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $13,520.10 $0.00 $0.00 $254.10 $0.00 $13,266.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $4,750.00 $1,146.00 $2,342.00 $0.00 $0.00 $0.00 $1,262.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $375.00 $104.00 $167.00 $0.00 $0.00 $0.00 $104.00 $0.00 $0.00 $0.00 Total Laboratory $5,125.00 $1,250.00 $2,509.00 $0.00 $0.00 $0.00 $1,366.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $292.50 $32.50 $65.00 $0.00 $0.00 $162.50 $32.50 $0.00 $0.00 $0.00 Equipment (Drilling related) $552.90 $0.00 $0.00 $0.00 $0.00 $552.90 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $834.20 $208.55 $417.10 $0.00 $0.00 $0.00 $208.55 $0.00 $0.00 $0.00 Equipment (IDW related) $174.60 $58.20 $58.20 $0.00 $0.00 $0.00 $58.20 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,854.20 $299.25 $540.30 $0.00 $0.00 $715.40 $299.25 $0.00 $0.00 $0.00

Subtotal $39,644.50 $2,026.68 $3,955.24 $6,438.73 $4,690.77 $592.97 $18,344.24 $3,595.87 $0.00 $0.00 $0.00 Completion Fee $1,791.18 $199.02 $226.74 $313.79 $435.68 $48.70 $387.19 $180.06 $0.00 $0.00 $0.00

Total Estimated Cost $41,434.82 $2,225.72 $4,181.08 $6,752.53 $5,126.46 $641.67 $18,731.42 $3,775.94 $0.00 $0.00 $0.00

REV: 02/03 CEF_GEO.XLS Page 4

LEVEL OF EFFORT/EXPENSE WORKSHEET (Haz. Waste Dept.)

SITE : Geosyntec Consultants SUBTASK: Monitoring Well Installations

DATE: 4/9/19

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Professional (R.Klinger)

Senior Staff Professional (B.Dawson)

Senior Staff Professional (S. Ahmed)

TOTAL LABOR 47

TRAVEL

TYPE RATE UNIT USAGE TOTALS

Vehicle Rental Truck $420.00 week 1 $420.00 Truck $97.00 day 0 $0.00 Car $68.00 day 0 $0.00 subtotal $420.00

TOTAL TRAVEL $420.00

SUBCONTRACTOR (EQUIPMENT PROCUREMENT)

NAME PURPOSE RATE UNIT USAGE TOTALS

TOTAL SUBCONTRACTOR (EQUIPMENT) $0.00

SUBCONTRACTOR (SERVICES PROCUREMENT)

NAME PURPOSE RATE UNIT USAGE TOTALS

Drilling (Non-Conventional) Preferred Drilling $5,590.00 Lump Sum 1 $5,590.00

$0.00 Lump Sum 0 $0.00 subtotal $5,590.00

Surveying Southeastern Surveyors $1,400.00 Lump Sum 1 $1,400.00 Environmental Resource Solutions $1,000.00 Lump Sum 1 $1,000.00 subtotal $2,400.00

IDW

PermaFix $115.00 Per Drum 4 $460.00

$75.00 Transport Fee 1 $75.00 subtotal $535.00

Utilities GeoTek $750.00 Lump Sum 1 $750.00

$0.00 Month 0 $0.00 subtotal $750.00

Other ERS - Land Clearing $2,785.00 Lump Sum 1 $2,785.00 subtotal $2,785.00

TOTAL SUBCONTRACTOR (SERVICES) $12,060.00

LABORATORY COSTS

Rate # SAMPLES #QA/QC TOTALS

TOTAL LABORATORY $0.00

FIELD EXPENSES

ITEM RATE UNIT USAGE TOTALS

Drilling Related Monitoring Well Installation Kit $184.30 day 3 $552.90 Soil Assessment Kit $139.70 day 0 $0.00 Soil Sampling Kit (through concrete) $208.55 day 0 $0.00 subtotal $552.90

Expendables $32.50 day 5 $162.50

Other $0.00 0 $0.00 subtotal $0.00

TOTAL FIELD EXPENSES $715.40

Property owner and tenant notification (1); Technical support during well installation (2);

Review and submittal of well installation field notes (1); IDW waste manifest cordination and management (1)

TACO preparation (3); Field preparation (3)

5 days of mob/demob @ 1 hr/day (5); Oversight of brush clearing (6); Oversight of Utility locate (3); Oversight of monitoring well installation and development (2 days @ 10h/day) (20); IDW staging and field management (2);

HW550_DC027G-3_CEFLOE.xls 8/6/2019 Page 1 of 2 Subtask 6 TACO #3_Final

SUBTASK: New Wells Groundwater Sampling

DATE: 4/9/19

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Professional (R.Klinger)

Senior Staff Professional (B.Dawson)

Sr. Engineer

Staff Professional (A. Ramsey)

TOTAL LABOR 21

TRAVEL

TYPE RATE UNIT USAGE TOTALS

Vehicle Rental Truck $420.00 week 0 $0.00 Truck $97.00 day 1 $97.00 Car $68.00 day 0 $0.00 subtotal $97.00

TOTAL TRAVEL $97.00

SUBCONTRACTOR (EQUIPMENT PROCUREMENT)

NAME PURPOSE RATE UNIT USAGE TOTALS

TOTAL SUBCONTRACTOR (EQUIPMENT) $0.00

SUBCONTRACTOR (SERVICES PROCUREMENT)

NAME PURPOSE RATE UNIT USAGE TOTALS

TOTAL SUBCONTRACTOR (SERVICES) $0.00

LABORATORY COSTS

Rate # SAMPLES #QA/QC TOTALS Method - Matrix

EPA 8260 - GW $66.00 6 1 $462.00

Sodium - EPA 6020 $12.50 0 0 $0.00 TRPH - Fl PRO $84.00 0 0 $0.00

TDS - EPA160.1 $11.50 0 0 $0.00

RSK175-MEE $160.00 5 0 $800.00

TOC - EPA SM5310C/9060/415.1 $26.00 0 0 $0.00

subtotal $1,262.00 Shipping

Large cooler (25 to 50 lbs) $104.00 1 $104.00 Small cooler (0 to 25lbs) $63.00 0 $0.00 subtotal $104.00

TOTAL LABORATORY $1,366.00

FIELD EXPENSES

ITEM RATE UNIT USAGE TOTALS

Groundwater Sampling Kit $208.55 day 1 $208.55 Tubing (silicone) ft 0 $0.00 Tubing (polyethylene) ft 0 $0.00 subtotal $208.55 IDW Related Drum $58.20 drum 1 $58.20 subtotal $58.20

Expendables $32.50 day 1 $32.50

Other $0.00 0 $0.00 subtotal $0.00

TOTAL FIELD EXPENSES $299.25

Property owner and tenant notification (1); Technical support of sampling activities and review of groundwater results letter (1); Review and signature IDW manifest (1)

TACO Preparation (1); preparation of groundwater results letter with field forms and updated data tables (4)

Field Preparation (2); Mob @ 1 hr/day (1); DTW gauging (2); sample five monitoring wells @ 1.5 hr each (8)

8/6/2019 Page 2 of 2 Subtask 7 TACO #3_Final

FDEP COST ESTIMATEContractor: Geosyntec Consultants

Task #: DC027G SubTask 1 Project Management SubTask 6 Monitoring Well Installations

Site: Bellair Cleaners SubTask 2 Semi-Annual UIC Sampling SubTask 7 New Wells Groundwater Sampling

Activity/Phase: UIC and Annual Groundwater Sa SubTask 3 Annual Groundwater Sampling SubTask 8

Project Manager: R. Klinger SubTask 4 GMR SubTask 9

SubTask 5 WCD #1 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

Geosyntec Consultants $49.76 Project Manager Klinger -1 -0.6

$1.00 Principal 0 0 0 0 0 0 0 0 0 0 $1.00 Principal 0 0 0 0 0 0 0 0 0 0 $1.00 Senior Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Senior Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Senior Professional 0 0 0 0 0 0 0 0 0 0

$49.76 Senior Professional Klinger 0 0 0 0 0 0 0 0 0 0 $1.00 Project Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Project Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Senior Staff Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Senior Staff Professional 0 0 0 0 0 0 0 0 0 0

$27.16 Senior Staff Professional Ahmed 36 0 0 0 0 36 0 0 0 0 $32.21 Senior Staff Professional Dawson -49 0 0 0 0 -36 -13 0 0 0 $26.92 Staff Professional Ramsey 13 0 0 0 0 0 13 0 0 0

$1.00 Staff Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Staff Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Staff Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Staff Professional 0 0 0 0 0 0 0 0 0 0 $1.00 Tech Word Processor 0 0 0 0 0 0 0 0 0 0

$22.75 Admin Asst Hayes 0 0 0 0 0 0 0 0 0 0 $34.13 Professional Hensley 0 0 0 0 0 0 0 0 0 0

$1.00 Drafter/CADD 0 0 0 0 0 0 0 0 0 0 $1.00 Designer 0 0 0 0 0 0 0 0 0 0 $1.00 Site Manager 0 0 0 0 0 0 0 0 0 0 $1.00 Site Manager 0 0 0 0 0 0 0 0 0 0 $1.00 Senior Engineering Technician 0 0 0 0 0 0 0 0 0 0 $1.00 Engineering Technician 0 0 0 0 0 0 0 0 0 0

Total Hours -1.0 -1 0 0 0 0 0 0 0 0 0

Direct Labor ($281.89) ($31.32) $0.00 $0.00 $0.00 $0.00 ($181.80) ($68.77) $0.00 $0.00 $0.00

Overhead 172.70% ($486.83) ($54.09) $0.00 $0.00 $0.00 $0.00 ($313.97) ($118.77) $0.00 $0.00 $0.00 Total Labor ($768.72) ($85.41) $0.00 $0.00 $0.00 $0.00 ($495.77) ($187.54) $0.00 $0.00 $0.00

Other Direct Costs ($14.10) ($1.57) $0.00 $0.00 $0.00 $0.00 ($9.09) ($3.44) $0.00 $0.00 $0.00

REV: 02/03 CEF_GEO.XLS Page 1

FDEP COST ESTIMATEContractor: Geosyntec Consultants

Task #: DC027G SubTask 1 Project Management SubTask 6 Monitoring Well Installations

Site: Bellair Cleaners SubTask 2 Semi-Annual UIC Sampling SubTask 7 New Wells Groundwater Sampling

Activity/Phase: UIC and Annual Groundwater Sa SubTask 3 Annual Groundwater Sampling SubTask 8

Project Manager: R. Klinger SubTask 4 GMR SubTask 9

SubTask 5 WCD #1 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Travel

Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) ($475.00) $0.00 $0.00 $0.00 $0.00 ($475.00) $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW ($115.00) $0.00 $0.00 $0.00 $0.00 ($115.00) $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Land Clearing $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal ($590.00) $0.00 $0.00 $0.00 $0.00 ($590.00) $0.00 $0.00 $0.00 $0.00 Handling Fee ($59.00) $0.00 $0.00 $0.00 $0.00 ($59.00) $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost ($649.00) $0.00 $0.00 $0.00 $0.00 ($649.00) $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal ($1,431.82) ($86.98) $0.00 $0.00 $0.00 $0.00 ($1,153.86) ($190.98) $0.00 $0.00 $0.00 Completion Fee ($76.87) ($8.54) $0.00 $0.00 $0.00 $0.00 ($49.58) ($18.75) $0.00 $0.00 $0.00

Total Estimated Cost ($1,508.69) ($95.52) $0.00 $0.00 $0.00 $0.00 ($1,203.44) ($209.73) $0.00 $0.00 $0.00

REV: 02/03 CEF_GEO.XLS Page 2

SUBTASK: Monitoring Well Installations

DATE: 4/9/19

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Staff Professional (B.Dawson)

-36

Scientist/GIS

Senior Staff Professional

(S. Ahmed) 36

Staff Engineer

Admin

TOTAL LABOR 0

TRAVEL

TYPE RATE UNIT USAGE TOTALS

TOTAL TRAVEL $0.00

SUBCONTRACTOR (EQUIPMENT PROCUREMENT)

NAME PURPOSE RATE UNIT USAGE TOTALS

TOTAL SUBCONTRACTOR (EQUIPMENT) $0.00

SUBCONTRACTOR (SERVICES PROCUREMENT)

NAME PURPOSE RATE UNIT USAGE TOTALS

Drilling (Non-Conventional) Preferred Drilling $475.00 Lump Sum -1 ($475.00)

$0.00 Lump Sum 0 $0.00 subtotal ($475.00)

IDW

PermaFix $115.00 Per Drum -1 ($115.00)

$75.00 Transport Fee 0 $0.00 subtotal ($115.00)

TOTAL SUBCONTRACTOR (SERVICES) ($590.00)

LABORATORY COSTS

Rate # SAMPLES #QA/QC TOTALS

TOTAL LABORATORY $0.00

FIELD EXPENSES

ITEM RATE UNIT USAGE TOTALS

TOTAL FIELD EXPENSES $0.00

TACO preparation (3); Field preparation (3); 5 days of mob/demob @ 1 hr/day (5);

Oversight of brush clearing (6); Oversight of Utility locate (3); Oversight of monitoring well installation and development (2 days @ 10h/day) (20); IDW staging and field management (2);

5 days of mob/demob @ 1 hr/day (5); Oversight of brush clearing (6); Oversight of Utility locate (3); Oversight of monitoring well installation and development (2 days @ 10h/day) (20); IDW staging and field management (2);

8/6/2019 Page 1 of 2 Subtask 6_TACO #3

SUBTASK: New Wells Groundwater Sampling

DATE: 4/9/19

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Staff Professional (B.Dawson)

-13

Sr. Engineer

Staff Professional (A. Ramsey)

TOTAL LABOR 0

TRAVEL

TYPE RATE UNIT USAGE TOTALS

TOTAL TRAVEL $0.00

SUBCONTRACTOR (EQUIPMENT PROCUREMENT)

NAME PURPOSE RATE UNIT USAGE TOTALS

TOTAL SUBCONTRACTOR (EQUIPMENT) $0.00

SUBCONTRACTOR (SERVICES PROCUREMENT)

NAME PURPOSE RATE UNIT USAGE TOTALS

TOTAL SUBCONTRACTOR (SERVICES) $0.00

LABORATORY COSTS

Rate # SAMPLES #QA/QC TOTALS

TOTAL LABORATORY $0.00

FIELD EXPENSES

ITEM RATE UNIT USAGE TOTALS

Personal Protection

TOTAL FIELD EXPENSES $0.00

TACO Preparation (1); preparation of groundwater results letter with field forms and updated data tables (4); Field Preparation (2); Mob @ 1 hr/day (2); DTW gauging (2);

sample five monitoring wells @ 1.5 hr each (8)

Field Preparation (2); Mob @ 1 hr/day (1); DTW gauging (2); sample five monitoring wells @ 1.5 hr each (8)

8/6/2019 Page 2 of 2 Subtask 7_TACO #3

1200 Riverplace Boulevard, Suite 710 Jacksonville, Florida 32207

PH 904.858.1818

FAX 904.396.1143

www.geosyntec.com

29 July 2019

Mr. Killian Talley Florida Department of Environmental Protection 2600 Blair Stone Road Tallahassee, FL 32399-2400

Subject: Year 2 UIC & Annual Groundwater Monitoring Scope of Work/Level of Effort Bellair Cleaners – TACO #3 1101-123 Blanding Boulevard Orange Park, Clay, Florida

FDEP ERIC ID ERIC_4257

FDEP Facility ID No. 109500594

Dear Mr. Talley, Please find attached Geosyntec’s Task Assignment Change Order (TACO) #3 for the Year 2 Underground Injection Control (UIC) and annual groundwater monitoring activities, outlined below, for the Former Bellair Cleaners (Facility ID 109500594) located in Orange Park, Florida.

A summary of the scope of work and costs associated with TACO #1 is provided below in red text.

Subtask 1 – Project Management

Subtask 2 – Year 2, Quarter 2 UIC Groundwater Monitoring: UIC groundwater samples will be collected semi-annually from upgradient monitoring well MW002, source area monitoring well MW001, and downgradient monitoring well MW004. The UIC groundwater samples will be submitted to a fixed-base laboratory and analyzed for sodium, total dissolved solids (TDS), and total recoverable petroleum hydrocarbons (TRPH). Chlorinated volatile organic compounds (CVOC), total organic carbon (TOC), ethane, and ethene will also be analyzed for during the semi-annual events to monitor reductive dechlorination following placement of the amendment. The samples will be stored on ice and shipped to the analytical laboratory under chain of custody for analysis under standard turnaround times. Geosyntec will containerize groundwater IDW in one 55-gallon steel drum. Based on historical monitoring well contaminant concentrations, the IDW drum will be sampled for CVOCs to confirm compliance with the existing non-hazardous waste profile with PermaFix. IDW T&D costs have been included in Subtask 4. Groundwater sampling logs will be submitted to FDEP to document the field work for invoicing. ADaPT and GIS datatables from Year 2, Quarter 2 will be compiled after one year of monitoring and submitted with the annual report, discussed in Subtask 4.

Mr. Killian Talley 29 July 2019

Subtask 3 – Year 2, Quarter 4 UIC and Annual Groundwater Monitoring: UIC groundwater samples will be collected semi-annually from upgradient monitoring well MW002, source area monitoring well MW001, and downgradient monitoring well MW004. The UIC groundwater samples will be submitted to a fixed-base laboratory and analyzed for sodium, TDS, and TRPH.

TOC will also be analyzed during the semi-annual event to monitor amendment distribution following injection activities. In addition, Geosyntec personnel will collect samples from MW001, MW002, MW003, MW004, MW005, MW006, MW007, and MW008 for CVOCs, ethane, and ethene during the annual groundwater monitoring event to evaluate the dechlorination progression within the surficial aquifer. Prior to groundwater sampling, Geosyntec will gauge and record the depth to water from site monitoring wells to document groundwater flow conditions. The samples will be stored on ice and shipped to the analytical laboratory under chain of custody for analysis under standard turnaround times. Geosyntec will containerize groundwater IDW in a 55-gallon steel drum. The IDW drum will be sampled for CVOCs to confirm compliance with the existing non-hazardous waste profile with PermaFix. IDW T&D costs have been included in Subtask 4.

WCD #2: As was discussed with the FDEP during the path forward teleconference in March 2019, Geosytnec collected an additional groundwater sample from just above the hardpan in monitoring well MW004 to be analyzed for CVOCs. The additional costs associated with the additional groundwater sample collection are reflected in TACO 2.

The costs associated with WCD #2 are below the authorized amount.

Subtask 4 – Reporting: Year 2 of UIC monitoring and the annual groundwater sampling event will be documented in an Annual Groundwater Monitoring Report which will be signed and sealed by a licensed Florida engineer or geologist in charge of the project. Copies of final manifests will be included in the report. In addition, the ADaPT files and associated GIS datatables for Year 2 of UIC monitoring and the annual monitoring event will also be submitted.

The FDEP is being reimbursed for the costs associated with the disposal of the IDW purge water drum from the semi-annual groundwater sampling event conducted in September 2018 that was stolen.

The Annual Groundwater Monitoring Report will also document the additional monitoring well installation and groundwater sampling activities discussed in Subtasks 6 and 7. The ADaPT files and associated GIS datatables for the additional groundwater sampling activities associated with the newly installed monitoring wells will also be submitted.

Subtask 5 – Work Change Directive #1: Following the collection of the semi-annual groundwater samples in September 2018, Geosyntec subcontracted PermaFix to manifest and dispose of the IDW purge water drum. When PermaFix arrived at the site on 17 October 2018, they informed Geosyntec that the IDW purge water drum was no longer in the staging area and was unable to be located. Geosyntec contacted the Clay County Sheriff’s office on 19 October 2018 to report the missing drum and were informed that a statement would need to be given at the site and a police report would need to be prepared. The additional costs associated with the site visit to file the police report for the stolen IDW drum on 19 October 2018 are reflected in TACO 1.

The costs associated with WCD#1 are below the authorized amount.

Subtask 6 – Monitoring Well Installations: Subtask 6 includes costs associated with the installation of five monitoring wells located in the driveway and wooded area south of the Site.

Prior to conducting field activities associated with the well installation, a site boundary survey and wetland survey of the wooded area behind will be conducted. The proposed monitoring well locations will be cleared and surveyed for underground utilities by the appropriate subcontractors prior to drilling activities.

As was discussed with the FDEP during the January 2019 meeting and subsequent path forward teleconference in March 2019, the proposed monitoring wells will be installed south of the Site building in the alleyway and in the wooded area along the southern property boundary at the locations presented on Figure 1. Three shallow monitoring wells (MW009, MW010, and MW011) will be installed in the alley and two monitoring wells (one shallow [MW012] and one deep [MW013]) will be installed south of MW006 along the property boundary. Each well will be installed using the direct push technology (DPT) drilling method and constructed of 1-inch (in) diameter Schedule-40 polyvinyl chloride (PVC) pipe with 5-feet (ft) of 0.010-in. pre-packed standard factory-slotted screen. Monitoring wells MW009, MW010, MW011, and MW012 will be screened above the hard pan layer noted in the rear of the former dry cleaning facility (approximately 16-ft below land surface (BLS)). The proposed vertical extent well (MW013) will be installed using the direct push DPT drilling method and constructed of 1-in diameter Schedule- 40 PVC pipe with 5-ft of 0.010-in. pre-packed standard factory-slotted screen in the same geologic unit as MW003 (screened beneath a second hard pan unit observed at approximately 40-ft BLS to a total depth of approximately 51-ft BLS). The final monitoring well depths may be adjusted based on observed lithology and confirmed with FDEP. Monitoring wells MW009, MW010, and MW011 will be completed at land surface with flush-mount manholes, 2-ft by 2-ft by 4-in. thick concrete pads, and locking monitoring well caps. Monitoring wells MW012 and MW013 will be completed at land surface with 4-ft aluminum stick-up protective casings set in 2-ft by 2-ft by 4-in thick concrete pads. The monitoring wells will be developed until the discharge is relatively sediment-free. Monitoring well locations and top of casing elevations will be surveyed by a licensed Florida surveyor.

Bid costs prepared by the land clearing subcontractors, private utility locaters, DPT drillers, and surveyor are attached and summarized in the following table. Based on the bids, Geosyntec recommends selecting ERS for the land clearing, GeoTek to complete the utility locate and Preferred Drilling Solutions (PDS) to complete the monitoring well installation activities. Multiple bids were not obtained for the survey activities as it is considered a professional service.

Geosyntec has selected Southeastern Surveying and Environmental Resource Solutions to complete the survey activities.

Land Clearing Moran $3,335

FECC $4,073

ERS $2,785

Utility Locate GeoTek Services $750

Geoview $800

GPRS $800

Monitoring Well Installation

Partridge $7,595 Preferred Drilling $6,065

EDS $7,370

Surveyor

Southeastern Surveying $1,400 Environmental Resource Solutions $1,000

Soil, purge water, and decontamination water generated during monitoring well installation activities will be placed in labeled, 55-gallon steel drums and manifested for off-Site disposal under the existing non-hazardous waste profile. It is estimated that five non-hazardous drums will be generated. IDW will be staged along the edge of the alleyway in the rear of the former dry cleaning facility and transported off-Site by PermaFix Environmental Services.

Upon completion of the monitoring well installation activities, Geosyntec will submit a field package consisting of field notes, boring logs, and monitoring well construction logs.

The items for the costs reduction associated with the reduction in IDW generated during the monitoring well installation activities. Due to scheduling conflicts, the monitoring well installation activities were completed by different Geosyntec personnel. The costs associated with the staffing adjustment is reflected in TACO 3.

Subtask 7 – New Monitoring Well Groundwater Sampling: Following the installation of the five new site monitoring wells, Geosyntec personnel will collect samples from MW009, MW010, MW011, MW012, and MW013 for CVOCs, ethane, and ethene to evaluate the dechlorination progression within the surficial aquifer and refine the limits of the current groundwater contaminant plume. Prior to groundwater sampling, Geosyntec will gauge and record the depth to water from site monitoring wells to document groundwater flow conditions. The samples will be stored on ice and shipped to the analytical laboratory under chain of custody for analysis under standard turnaround times. Geosyntec will containerize groundwater IDW in one 55-gallon steel drum. Based on historical monitoring well contaminant concentrations, the IDW drum will be sampled for CVOCs to confirm compliance with the existing non-hazardous waste profile with PermaFix. IDW T&D costs have been included in Subtask 4. Groundwater sampling logs will be submitted to FDEP to document the field work for invoicing.

Due to scheduling conflicts, the groundwater sampling activities were completed by different Geosyntec personnel. Additionally, as the groundwater sampling event was conducted in one day, the FDEP is having costs reduced for the second day’s mobilization time. The costs associated with the staffing adjustment and reduction in mobilization time are reflected in TACO 3.

Invoice and Deliverable Schedule:

Subtask Deliverable Invoice Amount Deliverable Date

Submittal of groundwater sampling field forms associated with Year 2, Quarter 2 Semi-Annual UIC monitoring

$4,181.08 28 September 2018

Submittal of groundwater sampling field forms associated with Year 2, Quarter 4 Semi-Annual UIC monitoring and annual groundwater monitoring

$6,752.53 29 March 2019

6, 7 Submittal of monitoring well installation and groundwater sampling field forms $22,507.36 31 May 2019

1, 4, 5 Submittal of GMR, ADaPT files, GIS data tables, and IDW manifests $7,993.85 26 July 2019

Total $41,434.82

As always, it is a pleasure to work with the FDEP. If you require any additional information or have any questions, please don’t hesitate to ask.

Rachel Klinger

Principal

Blaine Dawson

Professional