CN-370000-HW550-DC02HCO1.pdf
PDF 10 MB Posted
- Contract number
- HW550
- Issued by
- Florida
About this file
This is a Task Assignment Notification Change Order (Change Order No. 1) under DEP Contract No. HW550 between the Florida Department of Environmental Protection (FDEP) and Geosyntec Consultants. The contract pertains to environmental remediation and monitoring services at the Former Trophy Cleaners site (FDEP ID 529501416) in Florida, with Contractor Representative Mike Lodato and DEP Contract Manager Walsta Jean-Baptiste overseeing the work.
The change order reconciles costs related to Work Change Directive #1 executed on November 24, 2014, which authorized the collection of groundwater samples from monitoring wells MW001 and MW004. The net increase to the task amount is $1,846.52, bringing the total task cost from $48,464.35 to $50,310.87. The pricing structure consists of fixed price services ($37,110.87), cost reimbursement for utilities not to exceed $13,200.00, and a utilities handling fee of $120 per invoicing period. Work activities include Semi-Annual Operations & Maintenance and Groundwater Performance Monitoring Reports with deliverables due January 30, 2015, and October 30, 2015. Invoicing is structured across seven subtasks totaling $50,310.87, with specific deliverable requirements tied to FDEP approval of monitoring reports and utility invoices. The task completion date remains December 31, 2015, with no change in the original task period.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TASK ASSIGNMENT NOTIFICATION CHANGE ORDER FORM
DEP CONTRACT NO. HW550
Task Assignment #:
Contractor Name:
DC002H Change Order No.:
Geosyntec Consultants
Contractor Representative: Mike Lodato
DEP Contract Manager: Walsta Jean-Baptiste
Site Name: Former Trophy Cleaners
Site ID / Facility ID:: 529501416
Phone #: 850-245-8973
Description of Change [use additional pages if necessary]:
This Task Assignment Change Order reconciles costs related to WCD #1 in accordance with the Geosyntec scope of work and cost estimate forms.
The payment of utilities is the only part of this Task Assignment that is Cost Plus Fixed Fee.
The Deliverable and Invoice Schedule is attached.
Final Deliverable:
Semi-Annual O&M and Groundwater Performance
Monitoring Report and ADaPT/GIS update Final Deliverable Due Date: 10/30/2015
ASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
ITEM FIXED PRICE FEE SCHEDULE
COST PLUS FIXED FEE
TOTAL
Cost Reimbursement Fixed Fee
Original Task Amount $35,264.35 $0.00 $13,200.00 $0.00 $48,464.35
Task Amount Prior to this
Change Order $35,264.35 $0.00 $13,200.00 $0.00 $48,464.35
Net Increase/decrease in task amount $1,846.52 $0.00 $0.00 $0.00 $1,846.52
Task amount with all change orders
$37,110.87 $0.00 $13,200.00 $0.00 $50,310.87
CHANGE IN TASK TIME
Original Task Completion Date:
Completion Date Prior to this Change:
Net Increase/Decrease in Task Period:
Completion Date with all Change Orders:
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS#£) Section Representative
12/31/2015
12/31/2015
NA
12/31/2015
Date: \7J\lf/N
Date: XlAk/M Date: f^ll' lH
Date: lAJlhjzol1!
BWC TAFORM 03/03
Deliverables:
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number:
Task Assignment #:
Change Order #:
HW550
DC002H
Deliverable Deliverable Due Date
Semi-Annual O&M and Groundwater Performance
Monitoring Report for Year 1 Quarters 3 and 4 submitted electronicallyalong with one hardcopy; ADaPT/GIS update electronically
30-Jan-15
Semi-Annual O&M and Groundwater Performance
Monitoring Report for Year 2 Quarters 1, 2 and 3 submitted electronically along with one hardcopy; ADaPT/GIS update submitted electronically
30-Oct-15
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
Subtasks 2 and 3: FDEP approval of Semi-Annual O&M and Groundwater Performance Monitoring Report for Year 1 Quarters 3 and 4 submitted electronically along with one hardcopy; ADaPT/GIS update electronically
$13,222.35
Subtasks 1, 4, and 5: FDEP approval of Semi-Annual O&M and Groundwater Performance Monitoring Report for Year 2 Quarters 1, 2 and 3 submitted electronically along with one hardcopy; ADaPT/GIS update submitted electronically
$23,648.52
Subtask 6: FDEP approval of utility invoices for 6 months (September 2014 through February 2015); Utilities (Cost Plus Fixed Fee) = not to exceed $6,600; Utilities Handling Fee = $120
$6,720.00
Subtask 7: FDEP approval of utility invoices for 6 months (March through August 2015); Utilities (Cost Plus Fixed Fee) = not to exceed $6,600; Utilities Handling Fee = $120
$6,720.00
TOTAL COST $50,310.87
I3WC TAFORM 2/03