CN-370000-HW550-BF04CCO3.pdf
PDF 73 KB Posted
- Contract number
- HW550
- Issued by
- Florida
About this file
This is a Task Assignment Notification Change Order Form for DEP Contract No. HW550, issued by the Florida Department of Environmental Protection (DEP). The contractor is Geosyntec Consultants, represented by Mike Ladato, with the DEP Contract Manager being Carrie L. Kruchell, P.G. The task assignment pertains to work at Bob Lee's Auto Repair facility (Facility ID: BF04C).
Change Order No. 3 extends the task completion date by 21 days due to delays in the final review of the Interim Source Removal (ISR) Work Plan and Bid Package. The original task completion date of July 13, 2017 was previously extended to July 28, 2017, and is now further extended to August 31, 2017. The task maintains a fixed price of $6,663.66 with no cost reimbursement or additional fees. The final deliverable, the Interim Source Removal (ISR) Work Plan with Bid Package, is due by July 21, 2017 for DEP approval. Invoicing is contingent upon DEP approval of the ISR Work Plan and Bid Package (Subtasks 1-3), at which point the full contract amount of $6,663.66 will be payable. No cost increase is associated with this change order.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO. HW550
Task Assignment #: Change Order No.: 3 Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #: 850.245.8968 Ste ID / Facility ID::
Description of Change [use additional pages if necessary]:
Final Deliverables: Final Deliverable Due Date: 7/21/2017
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
Cost Reimbursement Fixed Fee
Original Task Amount $6,663.66 $0.00 $0.00 $0.00
Task Amount Prior to this Change Order $6,663.66 $0.00 $0.00 $0.00 Net Increase/decrease in task amount $0.00 $0.00 $0.00 $0.00 Task amount with all change orders $6,663.66 $0.00 $0.00 $0.00
Original Task Completion Date: 7/13/2017
Completion Date Prior to this Change: 7/28/2017
Net Increase/Decrease in Task Period: 21 days
Completion Date with all Change Orders: 8/31/2017
DEP Task Manager: Date: 8/18/2017
DEP Contract Manager: Date: 8/18/2017
Contractual Authority: Date: 8/18/2017
Contractor Representative: Date:
Section Representative ________
Due to the delays with the final review for the Interim Source Removal (ISR) Work Plan & Bid Package, the DEP is issuing this Change Order (#3) to extend the final Task Completion Date to 8/31/17. We expect to finalize our review
FIXED PRICE
TASK ASSIGNMENT NOTIFICATION CHANGE ORDER FORM
Geosyntec Consultants Mike Ladato Phone #: (813) 558-0990 Carrie L. Kruchell, P.G.
Bob Lee's Auto Repair
BF04C
sooner, but have extended the date to the end of the month to be sure.
Interim Source Removal (ISR) Work Plan
ITEM
$6,663.66
$6,663.66
$0.00
$6,663.66
CHANGE IN TASK TIME
FEE SCHEDULE
COST PLUS FIXED FEE
TOTAL
BWC TAFORM 03/03
8/18/2017
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number: HW550 Task Assignment #: BF04C
Change Order #: 3
Deliverables:
Deliverable Deliverable Due Date Draft Bid Package 14-Jul-17
Interim Source Removal (ISR) Work Plan w/ Bid Package 21-Jul-17
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
FDEP Approval of Interim Source Removal (ISR) Work Plan w/ Bid Package (Subtasks 1-3) $6,663.66
TOTAL COST $6,663.66
BWC TAFORM 2/03
| Task Assignment CHANGE ORDER |
| Deliverable & Invoice Schedule |
File details come from the government source that posted it. Updated .