CN-370000-CN213-T7.pdf

PDF 2 MB Posted

Attached to
Master Agreement FL|CN213|b9c692f990a10778da60a76aaae4387a
Contract number
CN213
Issued by
Florida

About this file

This document is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (FDEP) under Contract No. CN213, Task Assignment No. 07. The contracting parties are the FDEP and Genesis (GGI, LLC, dba Genesis Group), a consulting firm headquartered in Tampa, Florida. The project involves design and permit services for the water tank replacement project at Rainbow Springs State Park located in Dunnellon, Florida. Genesis will utilize subcontractors including R.M. Barrineau for surveying, Nova Engineering and Environmental for geotechnical services, France Engineering, LLC for structural engineering, and Pinnacle Engineering Group for mechanical and electrical engineering.

The contract scope comprises eight subtasks: topographic survey, geotechnical investigation, 100% and final civil/structural/electrical construction documents, permit application and coordination, bid support services, and pre-construction and substantial completion services. The total contract value is $31,726.40, consisting of $31,226.40 in fixed price costs and $500.00 in reimbursable costs for the FDEP General Permit. Individual subtask costs range from $1,040.00 to $16,173.48, with payment contingent upon FDEP approval of deliverables. The project timeline spans multiple phases beginning upon Notice to Proceed, with subtasks scheduled sequentially based on completion of prior phases, extending through substantial completion and final certifications.

View the file

Other files

File Type Posted
CN-370000-CN213-CO1.pdf PDF
CN-370000-CN213-T1.pdf PDF
CN-370000-CN213-T10CO1.pdf PDF
CN-370000-CN213-T12.pdf PDF
CN-370000-CN213-T13.pdf PDF
CN-370000-CN213-T19.pdf PDF
CN-370000-CN213-T1CO1.pdf PDF
CN-370000-CN213-T24.pdf PDF
CN-370000-CN213-T25.pdf PDF
CN-370000-CN213-T27.pdf PDF
CN-370000-CN213-T2CO1.pdf PDF
CN-370000-CN213-T2CO2.pdf PDF
CN-370000-CN213-T4CO1.pdf PDF
CN-370000-CN213-TA3.pdf PDF
CN-370000-CN213.pdf PDF
CN-370000-CN213-CMC1.pdf PDF
CN-370000-CN213-T16CO2.pdf PDF
CN-370000-CN213-T16CO3.pdf PDF
CN-370000-CN213-T1CO3.pdf PDF
CN-370000-CN213-T2.pdf PDF
CN-370000-CN213-T20.pdf PDF
CN-370000-CN213-T20CO1.pdf PDF
CN-370000-CN213-T21.pdf PDF
CN-370000-CN213-T4CO2.pdf PDF
CN-370000-CN213-T9.pdf PDF
CN-370000-CN213-CMC3.pdf PDF
CN-370000-CN213-CO1.pdf.crdownload CRDOWNLOAD file
CN-370000-CN213-T10.pdf PDF
CN-370000-CN213-T10CO2.pdf PDF
CN-370000-CN213-T14.pdf PDF
CN-370000-CN213-T15.pdf PDF
CN-370000-CN213-T16.pdf PDF
CN-370000-CN213-T17.pdf PDF
CN-370000-CN213-T1CO2.pdf PDF
CN-370000-CN213-T22.pdf PDF
CN-370000-CN213-T22CO1.pdf PDF
CN-370000-CN213-T26.pdf PDF
CN-370000-CN213-T26CO1.pdf PDF
CN-370000-CN213-T27CO1.pdf PDF
CN-370000-CN213-T4CO3.pdf PDF
CN-370000-CN213-T5.pdf PDF
CN-370000-CN213-T5CO1.pdf PDF
CN-370000-CN213-T5CO2.pdf PDF
CN-370000-CN213-TA4.pdf PDF
CN-370000-CN213-A1.pdf PDF
CN-370000-CN213-CMC2.pdf PDF
CN-370000-CN213-T16CO1.pdf PDF
CN-370000-CN213-T18.pdf PDF
CN-370000-CN213-T22CO2.pdf PDF
CN-370000-CN213-T6.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: I Task Assignment No.: Owner's Name: I Project No.:

CN213 07 FDEP 61172

Project Location: Project Name:

Rainbow Springs State Park Water Tank Replacement Consultant Name:

Genesis Consultant Representative: Phone: Email:

Phillip Keys 813-620-4500 PKeyes@genesisgroup.com FDEP Contract Manager: Phone: Email:

Mae Roth 850-245-2781 Mae.Roth@dep.state.tl. us Description of Task:

Provide design and permit services for water tank replacement at Rainbow Springs State Park.

Project Manager: Gretchen Miller or successor

Start Date:

Completion Date:

I I 3/2/201 8 Upon execution

GregTurral

Budget Representative, FDEP Gretchen Miller

Project Manager, FDEP Mae Roth

Contract Manager, FDEP Phillip Keys. P.E.

Consultant Michale W Foster, P.E.

Contract Authority, FDEP

Pro_ject # Grant#

61172

29 dieit FLAIR Code:

Or2Code

37502000211

Schedule

Fixed Price Cost: $ 31.226.40 Cost Reimbursement not to exceed: $ 500.00

Total Task Amount: $31,726.40 Approval Signatures:

Greg Tu rra I Dlgllally signed by Greg Turral Date: 2017.08.0915:13:12 -04'00'

Signature Gretchen M"lller

Digitally signed by Gretchen Miller Date: 2017.08.0215:12:22-04'00'

Signature

Mae Roth

Signature

Signature

Signature

Digitally signed by Mee Roth Date: 2017.08.09 16:11:47 -04'00'

8-9-2017

Date

Date

Date 8-9-2017

Date

<jb;:7 Date •

Cat/Year Fund Module ObiectCode EO Amount

080039/18 675002 U3200 131500 XR $31,726.40

Total: $ 31,726.40

Page 1 ofl

3,Q Civil Engineering

Landscape Architecture Transpor tatiori

Urban Design Planning

CEI

August 1, 2017

Gretchen Z Miller, AIA, LEED AP Senior Architect Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399

RE: CN213, TA07

I 000 North Ashier Drive Suite 900

Tarnpa. Florida 33602-3718

RAINBOW SPRINGS STATE PARK NEUMATIC TANK, PIPING, AND ELECTRICAL BUILDING

REPLACEMENT PROJECT

Dear Gretchen:

Tel 813.620.4500 Fax 813.221.4980 www.Ge11esisGro1ip _c(>m

For your review, Genesis, has provided a proposal summary and man-hour documentation for the services tasks identified below:

Subtask 1 - Topographic Survey Subtask 2 - Geotechnical Investigation Subtask 3.1- 100% Civil, Structural, and Electrical Construction Documents Subtask 3.2 - Final Civil, Structural, and Electrical Construction Documents Subtask 4- Permit Application, Coordination, and Approval Subtask 5 - Bid Support Services Subtask 6.1- Pre-Construction Meeting and Shop Drawings Review Subtask 6.2 - Substantial Completion and Final Certifications

Sincerely, GENESIS

Phillip Keyes, P.E.

Associate Vice President, Public Infrastructure

TAMPA TALLAHASSEE PENSACOLA JACKSONVILLE MIRAMAR BEACH

8/1/17

PNEUMATIC TANK, PIPING, AND ELECTRICAL BUILDING REPLACEMENT

RAINBOW SPRINGS STATE PARK

CN213, TA07

The Florida Department of Environmental Protection (FDEP) has selected GGI, LLC, dba Genesis Group, dba Genesis (Consultant and/or Genesis) to provide professional services for the Rainbow Springs Hydro Pneumatic Tank and Pipe Replacement Project located on Southwest 81 st Place Road in Dunnellon, Florida. Consultant plans to use the following sub-contractors to complete some of the following Subtasks: 1) R.M. Barrineau - Survey, 2) Nova Engineering and Environmental - Geotechnical, 3) France Engineering, LLC - Structural, and 4) Pinnacle Engineering Group - Mechanical/Electrical.

Background and Scope of Services Overview

The Rainbow Springs State Park existing potable water supply facilities include 1) 2 supply wells, 2) pumping, piping, and valves that supply the 5,000-gallon hydro pneumatic tank, 3) sodium hypochlorite disinfection and injection facilities, 4) distribution system throughout the park that includes flushing hydrants, 5) electrical and control facilities housed in a wooden building. The hydro pneumatic tank, electrical and control building and piping facilities have reached the end of their service life and need to be replaced. The scope of work provides for design, bidding and limited construction observation services for replacement of the existing on-site water supply system that includes the existing hydro pneumatic tank, valves, piping, modify well head elevations to meet regulatory requirements if required, electrical/controls, and electrical control building, and appurtenances associated with the water supply system. The scope of work also includes, review of existing supply demands, projections of future supply demands, review of regulatory and code requirements, development of opinion of probable construction cost (OPCC), development of permit applications, assistance during bidding, shop drawing review, evaluation of contractors pay request, develop change orders for approval, develop as-built drawings and process close out documents. The following provides a detailed Subtask break down of the scope of services, schedule and fee for the project. The scope of services does not include environmental services or work associated with the 2 existing on-site wells or pumps.

Reporting Requirements

The Consultant will submit monthly progress reports which indicate the work performed during the corresponding reporting period, work scheduled for the next reporting period, problems encountered and resolutions of the problems, and any schedule updates. The report will be provided with each monthly invoice submitted by the Consultant at no additional cost to the FDEP.

Project Construction Documents

The Consultant will prepare 100% and final plans, specifications, and OPCC illustrating all technical components and requirements for the construction of the improvements. An original copy of all final design documents, drawings, and other articles to meet all requirements of FDEP, including the FDEP BOC Contract with the Consultant, this Subtask Assignment, and any subsequent amendments, will be provided to the FDEP Project Manager (PM) upon completion of the work. These original articles will contain all original signatures and professional seals as necessary.

Subtask 1 - Topographic Survey

Description: Topographic Survey- The Consultant will complete a topographic survey of the existing land features at a vertical accuracy necessary to provide one (1) ft. contours for the limits of the fenced in area of the wellhead site.

• Topographic Survey of project area within fenced area of wellhead site

• Location of improvements, trees, visible utilities and underground marked by others

• NAO 83 (State Plane Coordinates)

• NAVD 88 (datum for elevation data)

• CAD DWG FILES with project data

• Two certified prints of topographic survey

• Topographic Survey of project area within fenced area of wellhead site

Surveys shall be performed under the direct supervision of a Licensed Florida Land Surveyor. Surveys shall meet or exceed the Standards of Practice per the Florida State Board of Surveyors.

Deliverables: The Consultant will provide to the FDEP PM two (2) copies of the signed and sealed Topographic Survey along with one (1) electronic copy of the Topographic Survey in PDF format.

Schedule: The Consultant will provide the Subtask 1 Deliverables to the FDEP PM four (4) weeks following the Notice to Proceed (NTP) which occurs upon execution of the Subtask Assignment.

Performance Measures: The Subtask 1 Deliverables will be reviewed by the FDEP PM to confirm they are complete, accurate and timely.

Fixed Price Costs:

Firm Description Unit Cost Hours Total Cost

Barrineau Surveyor and Maooer $115.00 4 $460.00 Barrineau Survey Tech $55.00 32 $1,760.00 Barrineau CAD Tech $50.00 16 $800.00 Barrineau Administration $30.00 2 $60.00 Genesis Sr. Professional Enoineer $120.00 2 $240.00 Genesis Engineer Intern $72.50 2 $145.00

TOTAL $3,465.00

Subtask 2- Geotechnical Investigation

Description: The Consultant will provide Geotechnical Services to complete the final design as follows:

• Field Investigation The Field investigation will be based on a total of two (2) Standard Penetration Test borings (SPT's). Within the proposed tank footprint, one (1) boring will be advanced to a depth of approximately 30 ft. below the existing grade and within the electrical building footprint one (1) boring will be advanced to a depth of approximately 20 ft. below the existing grade.

The SPT's will be drilled using a track-mounted drill and rotary wash drilling procedures, as deemed necessary by site/subsurface conditions. Maximum Standard Penetration Test drilling footage is anticipated to be on the order of 50 linear feet.

Soil samples will be collected at selected depth intervals via the Standard Penetration Test method (ASTM D-1586). Upon completion of the borings, the depth to groundwater will be measured. If practicable, the stabilized groundwater depths will be measured after completion of the borings. Soil cuttings from the drilling process will be used for backfilling the boreholes.

• Laboratory Testing The proposed laboratory-testing program will include visual classification of the soil samples collected during the drilling process in accordance with the Unified Soil Classification System (USCS) and ASTM standards.

Laboratory testing will also include five (5) natural moisture content, five (5) percent fines, and two (2) Atterberg Limits tests of representative soils.

Note: Soil samples will be disposed of thirty (30) days after submittal of the final report, unless requested otherwise by the FDEP.

• Geotechnical Report The written geotechnical report (Geotechnical Report) will include the following:

- A description of the site, fieldwork, laboratory testing and general soil conditions encountered, as well as a Boring Location Plan, and individual Test Boring Records.

Site preparation considerations that include geotechnical discussions regarding site stripping and subgrade preparation, and engineered fill/backfill placement.

Recommendations for controlling groundwater and/or run-off during construction, and the need for a permanent dewatering system based on the anticipated post construction groundwater levels.

Measured apparent and estimated seasonal high groundwater levels at the boring locations.

Shallow and/or mat foundation system recommendations for the proposed tank and electrical building structures.

Suitability of on-site soils for re-use as structural fill and backfill. Additionally, the criteria for suitable fill materials will be provided.

Recommended quality control measures (i.e. sampling, testing, and inspection requirements) for site grading and foundation construction.

Note: If any obvious odors or contaminated materials seen during completion of the study, the FDEP PM will be notified immediately. However, the assessment of site environmental conditions, the detection of pollutants in the soil, rock or groundwater, or laboratory testing of samples, wetlands evaluation, or a site-specific seismic study are beyond the scope of this exploration. If authorized by FDEP, the Subtask Assignment with the Consultant will be amended to provide these services.

Deliverables: The Consultant will provide to the FDEP PM two (2) copies of the Geotechnical Report, signed and sealed by the responsible Florida Licensed Geotechnical Engineer, along with one (1) electronic copy of the report in PDF format.

Schedule: The Consultant will provide the Subtask 2 Deliverables to the FDEP PM four (4) weeks following Notice to Proceed.

Performance Measures: The Subtask 2 Deliverables will be reviewed by the FDEP PM to confirm they are complete, accurate and timely.

Fixed Price Costs:

Firm Description Unit Cost Hours Total Cost

Nova Senior Project Scientist $93.75 2 $187.50 Nova Project Scientist $69.24 10 $692.40 Nova Secretary $51.75 4 $207.00 Nova Drillino Services - Mobilization $500.00 EA 1 $500.00 Nova Drilling Services - Soil Test $12.00/FT 50 $600.00

Boring Nova Lab-% Fine/No. 200 sieve $55.00 EA 5 $275.00 Nova Lab-Natural Moisture Content $15.00EA 5 $75.00 Nova Lab-Atterbero Limits Test $65.00 EA 2 $130.00 Genesis Sr. Professional Engineer $120.00 2 $240.00 Genesis Enoineer Intern $72.50 4 $290.00

TOTAL $3,196.90

Subtask 3-Civil, Structural, and Electrical Construction Documents

Description: The Consultant will prepare design plans suitable for permitting and construction of the Project. Plans will be provided to the FDEP PM at 100% for review and comment. Review comments will be addressed and Final signed and sealed plans will be submitted to the FDEP PM. Plans will be prepared in AutoCAD (v. 2015) and produced on 22 x 34 sheets in accordance with FDEP CAD Standards where applicable.

The Consultant will provide an Opinion of Probable Construction Cost (OPCC) to the FDEP PM at the 100% and Final design submittal phases. The OPCC will be developed from the Project's estimated quantities, and prices will be generated from the use of the FOOT unit price averages, RS Means, recent bids from similar projects, and other sources as needed.

Subtask 3.1 -100% Civil, Structural, and Electrical Construction Documents

Description: Utilizing the information provided by the Topographic Survey and Geotechnical Report, the Consultant will prepare the 100% project construction documents for submittal to the FDEP PM. Consultant will coordinate with FDEP and SWFWMD in developing permit application documents for submittal along with the 100% design documents.

The Consultant will provide for the removal of the existing concrete foundation slab and replacement with new concrete tank foundation slab and a new pre-engineered (8'x10') electrical building and foundation.

The consultant will provide for new power supply equipment for existing pumps and associated controls as well as new electrical panels for the water supply system improvements. The proposal is based on the existing electrical service being adequate for the new electrical demand. Scope excludes Site Lighting.

The 100% Civil, Structural, and Electrical Construction Documents will include the following:

• Cover Sheet

• Key Sheet

• General Notes

• Existing Conditions Plan

• Demolition Plan

• Site Plan

• Grading Plan

• Water supply piping and valve improvements plan, profile and cross-sections

• Hydro Pneumatic Plan and Elevation

• Structural Plans and Details

• Electrical Plans and Details

• Miscellaneous Construction Details

Deliverables: The Consultant will provide to the FDEP PM:

• One (1) paper copy of 100% Civil, Structural, and Electrical Construction Documents

• One (1) paper copy of OPCC on the 100% Civil, Structural, and Electrical Construction Documents

• One (1) CD containing:

o PDF of 100% Civil, Structural, and Electrical Construction Documents o PDF of OPCC on the 100% Civil, Structural, and Electrical Construction Documents

Schedule: The Consultant will provide to the FDEP PM the Subtask 3.1 Deliverables 12 weeks after review and acceptance of Topographic Survey and Geotechnical Report by the FDEP PM.

Perlormance Measures: The Subtask 3.1 Deliverables will be reviewed by the FDEP PM to confirm they are complete, accurate and timely.

Fixed Price Costs:

I Firm I Description : Unit Cost ! Hours Total Cost '

Genesis ! Principal i $180.00 ! 2 $360.00 I Genesis I Sr. Professional Engineer I $120.00 ' 24 $2880.00 ' i Genesis Engineer Intern $72.50 48 $3,480.00 Genesis Administrative Assistant $45.00 4 $180.00 France Principal Engineer $114.99 7 $804.93 France Draftsman $30.42 19 ' $577.98 Pinnacle Engineering Sr. Engineer (Elect) $143.01 13 i $1,859.13 Pinnacle Enqineerinq Sr. Desiqner $108.29 36 ' $3,898.44 '

Pinnacle Engineering CAD Designer $63.10 30 ! $1,893.00 : Pinnacle Engineering Administrative Assistant $40.00 6 $240.00

TOTAL $16,173.48

Subtask 3.2 - Final Civil, Structural, and Electrical Construction Documents

Description: The Final submittal of the Civil, Structural, and Electrical Construction Documents will incorporate final review comments from the 100% Construction Documents submittal and any specific conditions required by the permitting agencies. At a minimum, the Final Construction Documents will include a set of drawings and specifications with pertinent information required to bid and construct the Project. An adjusted engineer's OPCC will be provided if changes have occurred from the review of the 100% Construction Documents or due to permit conditions that could affect the Project costs.

Deliverables: The Consultant shall provide to the FDEP PM:

• Three (3) paper copy sets of Final signed and sealed Civil, Structural, and Electrical Construction Documents

• One (1) paper copy of Final OPCC

• One (1) CD containing:

- PDF of the Final Civil, Structural, and Electrical Construction Documents

- PDF of Final OPCC

- Design files in AutoCAD 2015 of the Final Civil, Structural, and Electrical Construction Documents

' I I

I I

I

Schedule: The Consultant will provide to the FDEP PM the final plans 2 weeks after receipt of permit approvals from regulatory agencies.

Perlormance Measures: The subtask 3.2 Deliverables will be reviewed by the FDEP PM to confirm they are complete, accurate and timely.

Fixed Price Costs:

Firm Descriotion Unit Cost Hours Total Cost

Genesis Principal $180.00 2 $360.00 Genesis Sr. Professional Enqineer $120.00 4 $480.00 Genesis Enoineer Intern $72.50 4 $290.00 Genesis Administrative Assistant $45.00 4 $180.00 France Principal Engineer $114.99 1 $114.99 France Draftsman $30.42 1 $30.42 Pinnacle Enqineerinq Sr. Enqineer (Elect) $143.01 2 $286.02 Pinnacle Enoineerinq Sr. Desiqner $108.29 4 $433.16 Pinnacle Engineerina CAD Desianer $63.10 4 $252.40 Pinnacle Enqineerinq Administrative Assistant $40.00 2 $80.00

TOTAL $2,506.99

Subtask 4- Permit Application, Coordination, and Approval

Description: During the development of the 100% Construction Documents, the Consultant will coordinate with the FDEP regulatory staff and SWFWMD for preparation of the required permit submittal documents. Permit applications will be submitted along with the 100% design submittal package. Following the permit application submittal, if necessary, the Consultant will provide one (1) response to comments from the FDEP regulatory staff within (1) week after comments are received. The following permit is anticipated:

• FDEP Notice of Intent to Use the General Permit for Construction of Water Main Extensions for Public Water Supply (Rule 62-555.405, F.A.C.) - It is anticipated that FDEP will permit the project through the General Permit because it is an in-kind replacement project with minimal impact to stormwater run-off quantity or quality. Therefore, an exemption to stormwater requirements will also be requested from FDEP as well as from SWFWMD. As there are no environmental/biological services provided as part of this Scope of Services, additional services will be required if insufficiencies in the environmental documents are identified by the regulatory agencies.

• Additional services will also be required if a General Permit for Construction is not approved by FDEP.

• No other permitting is anticipated or included in the scope of services.

Deliverables: The Consultant will provide to the FDEP PM one (1) paper copy and one (1) digital copy of all permit documentation including permit submittals, correspondence memos, Requests for Additional Information (RAl's), responses to RAl's, and the final permit documents.

Schedule: The Consultant will provide to the FDEP PM the Subtask 4 Deliverables within one (1) week of correspondence associated with FDEP permitting.

Perlormance Measures: The Subtask 4 Deliverables will be reviewed by the FDEP PM to confirm they are complete, accurate and timely.

Fixed Price Costs:

! Firm Description I Unit Cost I Hours Total Cost i Genesis Principal I $180.00 1 $180.00 / Genesis Sr. Professional Enqineer I Genesis Enqineer Intern : Genesis Administrative Assistant

I TOTAL

Reimbursable Cost:

I Permit Fee: - FDEP General $500.00 ! Permit for Construction of Water ! Main Extensions for Public Water i Suoolv I Reimbursable Total Cost $500.00

Total for Subtask 4: $1,540.00

Subtask 5- Bid Support Services

I $120.00 4 $480.00 i $72.50 4 $290.00 I $45.00 I 2 $90,00 i

$1,040.00

Description: The Consultant will attend a mandatory pre-bid meeting that will be held on site. The Consultant will take notes, including an attendance record. Consultant will provide written responses to RFls noted at the pre-bid meeting and throughout the bidding process. A deadline for questions will be established in the Invitation to Bid Advertisement and all questions submitted prior to that deadline will be responded to prior to the bid opening date in accordance with the State purchasing requirements. If necessary, the Consultant will provide revised Construction Documents to the FDEP PM.

Deliverables: The Consultant will provide to the FDEP PM pre-bid meeting notes, written responses to RFls through the bidding period, and any revised Construction Documents.

Schedule: The Consultant will provide to the FDEP PM the Subtask 5 Deliverables within one (1) week of the FDEP receiving bid packages from construction contractors.

Performance Measures: The Subtask 5 Deliverables will be reviewed by the FDEP PM to confirm that they are complete, accurate and timely.

Fixed Price Costs:

Firm I Description Unit Cost i Hours I Total Cost

Genesis I Sr. Professional Enqineer $120.00 8 I $960.00 Genesis i Engineer Intern $72.50 ! 2 I $145.00 Genesis i Administrative Assistant 1 $45.00 ! 2 I $90.00 Pinnacle I Sr. Engineer ! $143.01 1 I $143.01 I

TOTAL I $1,338.01

Subtask 6 - Construction Support Services

Description: The Consultant will provide Post Design Services and Construction Support to FDEP throughout the duration of construction of the Project.

I

I l i ' I

Subtask 6.1- Pre-Construction Meeting and Shop Drawings Review

Description: Services will include, but not be limited to:

• Attendance at the pre-construction meeting

• Respond to RAl's (Maximum of 2 responses)

• Review of shop drawing submittals and testing results

• As necessary, any revisions to the Construction Documents

Deliverables: The Consultant will provide to the FDEP PM Subtask 6.1 Deliverables as follows:

• One (1) copy of the pre-construction meeting notes in PDF format

• One (1) copy of responses to RFl's in PDF format

• Three (3) paper copies of any revised Construction Documents and one (1) electronic copy of any revised

Civil Construction Documents, and

• Three (3) paper copies of reviewed shop drawings and one (1) electronic copy of the reviewed shop drawings.

Schedule: The Consultant will provide to the FDEP PM the Subtask 6.1 Deliverables within four {4) weeks after the pre-construction meeting.

Performance Measures: The Subtask 6.1 Deliverables will be reviewed by the FDEP PM to confirm that they are complete, accurate and timely.

Fixed Price Costs:

Firm Description Unit Cost Hours

Genesis Sr. Professional Enaineer Genesis Engineer Intern Genesis Administrative Assistance Pinnacle Sr. Engineer

TOTAL

Subtask 6.2 - Substantial Completion and Final Certifications

Description: Services will include, but not be limited to:

$120.00 $72.50 $45.00

$143.01

• One (1) site visit to attend the Substantial Completion of Construction inspection

• Development of Punch List items

• Complete and sign the FDEP Certification of Substantial Completion

Total Cost $240.00

$1,160.00 $90.00

$286.02 $1,776.02

• One (1) site visit to review the Contractor's as-built survey and verify Final Completion of Construction

Note: Preparation of record drawings/as-built survey will be required of the construction contractor prior to the final inspection.

Deliverables: The Consultant shall provide to the FDEP PM Subtask 6.2 Deliverables as follows:

• Certification of Substantial Completion of Construction including Punch List items

• Verification of Final Completion of Construction on Consultant's letterhead

• Review, including comments for corrections or recommendation for approval, of construction contractor as-built survey

• Two (2) paper copies of Final Certification of FDEP Permit and one (1) PDF copy

Schedule: The Consultant will provide to the FDEP PM the Subtask 6.2 Deliverables as follows:

• The Certification of Substantial Completion of Construction, including the Punch List, within one (1) week following the completion of the Substantial Completion inspection.

• The Verification of Final Completion of Construction within one (1) week following the completion of the Final Completion inspection.

• Review and recommendation for the construction contractor's as-built survey within two (2) weeks of the Consultant's receipt of the construction contractor's as-built survey.

• The Final Certification of the FDEP Permit within one (1) week of receipt of the Final Certification from FDEP regulatory staff.

Performance Measures: The Subtask 6.2 Deliverables will be reviewed by the FDEP PM to confirm that they are complete, accurate and timely.

Fixed Price Costs:

i Firm I

Genesis ' Genesis

Genesis

TOTAL

Proiect Schedule:

! Description Unit Cost

Sr. Professional Engineer $120.00 Engineer Intern $72.50 Administrative Assistant i $45.00

! Activity

I Duration (Calendar Days} ' Subtask 1: Topographic Survey i 28

Subtask 2: Geotechnical 128 Investigation

Hours Total Cost 4 $480.00

' 16 $1,160.00 2 $90.00

$1,730.00

Subtask 3.1: 100% Civil, 84 After acceptance of the Topographic Survey and Geotechnical Structural, and Electrical Report Construction Documents Subtask 3.2:_Final Civil, Structural, 14 After receipt after receipt of permit approvals and Electrical Construction i Documents i

Subtask 4: Permit Pre-Application 17 After receipt of RAI comments from regulatory agencies and Aoolication Submittals I

Subtask 5: Bid Support Services I 7 After receiving bid packages from construction contractors Subtask 6.1: Pre-Construction I 28 After the pre - construction meeting Meeting and Shop Drawings Review Subtask 6.2: Substantial 7 After receipt of Final Certification from regulatory approvals Comoletion and Final Certifications

8/1/1 7

Summarv of Fees:

Subtask Subtask Fixed Price Cost Subtask Reimbursable

Subtask 1: Topographic Survey $3,465.00

Subtask 2: Geotechnical $3,196.90 Investigation

Subtask 3.1: 100% Civil, Structural, $16,173.48 and Electrical Construction Documents Subtask 3.2:_Final Civil, Structural, $2,506.99 and Electrical Construction Documents Subtask 4: Permit Application, $1,040.00 Coordination, and Approval Subtask 5: Bid Support Services $1,338.01

Subtask 6.1: Pre-Construction $1,776.02 Meeting and Shop Drawings Review Subtask 6.2: Substantial $1,730.00 Com!!letion and Final Certifications

Total Fixed Price Cost: $31,226.40

Total Reimbursable Cost: FDEP $500.00 General Permit for Construction of Water Main Extensions for Public Water Supply

Overall Total Cost: $31,726.40

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.

$500

File details come from the government source that posted it. Updated .