Rainbow Springs State Park Task Assignment Change Order Summary
This document is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for a consulting services contract with Halff Associates, Inc. The change order pertains to Task Assignment TA22 under FDEP Contract CN213 for the Rainbow Springs State Park project located in Florida. The consultant is represented by Bryant King, P.E., and the FDEP project manager is Ralph Perkins. The change order was executed on April 9, 2024, with all required signatures from FDEP budget, project management, and contract authority representatives, as well as the consultant.
This change order extends the task completion timeline by 313 days, moving the task end date from April 24, 2024, to March 3, 2025, to allow for completion of plans development. The extension was requested via email on April 8, 2024, by Austin Cushing of Halff Associates. No adjustment to the task amount is included in this change order; the total task amount remains $169,628.64, consisting of $500.00 in reimbursement and $169,128.64 in fixed fees. The FLAIR code allocation shows project 61462C with no additional EO amount associated with this time extension.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN213 TA22 CO1 61462C
Rainbow Springs State Park Repave Park Drive
Halff Associates, Inc.
Bryant King, P.E. 850-848-9436 bking@halff.com
Ralph Perkins or successor 850-245-2460 ralph.perkins@floridadep.gov
In order to complete plans development, this time extension has been requested per the email dated April 8, 2024.
$ 500.00 $ 169,128.64 $ 169,628.64 $ 500.00 $ 169,128.64 $ 169,628.64 $ 0.00 $ 0.00 $ 0.00
$ 500.00 $ 169,128.64 $ 169,628.64
06/02/2023
04/24/2024
04/24/2024
03/03/2025
Tamika Bass
Richard Marcil
Ralph Perkins
Bryant King, P.E.
Bryan Bradner
61462C
$ 0.00
From: Austin Cushing To: Marcil, Richard Subject: Rainbow Springs State Park Time Extension Date: Monday, April 8, 2024 8:08:19 AM
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Rene, We would like to request a time extension for the Rainbow Springs State Park project to March 3, 2025. Please let me know if you have any questions.
Regards, Austin
Austin Cushing, PE Civil Engineer
Halff O: 850.848.9426 E: acushing@halff.com
We improve lives and communities by turning ideas into reality.
File details come from the government source that posted it. Updated .