Change Order Summary

This is a Task Assignment Change Order (Change Order No. 3) issued by the Florida Department of Environmental Protection (FDEP) under Statewide Contract CN202, Task Assignment 45, for the Wekiwa Springs State Park Erosion Control & Access project located in Orange County (Apopka), Florida. The contract is between FDEP and Michael Baker International, Inc., the prime consultant, with George F. Young, Inc. serving as the surveying subcontractor. The change order was executed on July 8-9, 2024, and approved by FDEP's Budget Representative, Project Manager, Contract Manager, and Contract Authority.

The change order adds two new subtasks to support Orange County Conservation Area Determination (CAD) and Conservation Area Impact (CAI) permitting for the project. Subtask 12 includes a boundary survey documenting wetland delineation boundaries, spring edge limits, and conservation area boundary corners, with deliverables consisting of a signed and sealed survey exhibit with legal description in PDF and hard copy formats (fixed price cost: $12,591.74). Subtask 13 encompasses five sub-components: preapplication meeting coordination ($534.05), supplemental wetland delineation ($1,174.91), Orange County field review ($1,068.10), CAD permit application preparation ($2,420.45 including $901.00 in reimbursable fees), and CAI permit application preparation ($5,617.73 including $1,273.00 in reimbursable fees). The total change order cost is $23,406.98, consisting of $21,232.98 in fixed price labor and $2,174.00 in reimbursable expenses, with an estimated project duration of 44 calendar days. The new task end date is February 25, 2025, representing a net increase of 284 days from the original task end date of May 17, 2024.

View the file

Other files

File Type Posted
CN-370000-CN202-CMC1.pdf PDF
CN-370000-CN202-T17.pdf PDF
CN-370000-CN202-T18.pdf PDF
CN-370000-CN202-T20CO5.pdf PDF
CN-370000-CN202-T27.pdf PDF
CN-370000-CN202-T29.pdf PDF
CN-370000-CN202-T2CO1.pdf PDF
CN-370000-CN202-T3.pdf PDF
CN-370000-CN202-T32.pdf PDF
CN-370000-CN202-T33CO3.pdf PDF
CN-370000-CN202-T36.pdf PDF
CN-370000-CN202-T44.pdf PDF
CN-370000-CN202-T45CO1.pdf PDF
CN-370000-CN202-T5CO1.pdf PDF
CN-370000-CN202-T5CO2.pdf PDF
CN-370000-CN202-T6CO2.pdf PDF
CN-370000-CN202-T6CO5.pdf PDF
CN-370000-CN202-T8CO1.pdf PDF
CN-370000-CN202-TA1.pdf PDF
CN-370000-CN202-TA34 CO2.pdf PDF
CN-370000-CN202-TA6.pdf PDF
CN-370000-CN202.pdf PDF
CN-370000-CN202-CMC2.pdf PDF
CN-370000-CN202-T10CO1.pdf PDF
CN-370000-CN202-T11.pdf PDF
CN-370000-CN202-T11.pdf.crdownload CRDOWNLOAD file
CN-370000-CN202-T13.pdf PDF
CN-370000-CN202-T14.pdf PDF
CN-370000-CN202-T14CO1.pdf PDF
CN-370000-CN202-T14CO2.pdf PDF
CN-370000-CN202-T17CO1.pdf PDF
CN-370000-CN202-T19.pdf PDF
CN-370000-CN202-T1CO1.pdf PDF
CN-370000-CN202-T20.pdf PDF
CN-370000-CN202-T20CO2.pdf PDF
CN-370000-CN202-T20CO4.pdf PDF
CN-370000-CN202-T26.pdf PDF
CN-370000-CN202-T28CO1.pdf PDF
CN-370000-CN202-T31CO1.pdf PDF
CN-370000-CN202-T32CO4.pdf PDF
CN-370000-CN202-T33.pdf PDF
CN-370000-CN202-T34.pdf PDF
CN-370000-CN202-T34CO1.pdf PDF
CN-370000-CN202-T35.pdf PDF
CN-370000-CN202-T38CO1.pdf PDF
CN-370000-CN202-T41.pdf PDF
CN-370000-CN202-T42.pdf PDF
CN-370000-CN202-T43.pdf PDF
CN-370000-CN202-T43CO1.pdf PDF
CN-370000-CN202-T43CO2.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

(Revised 9-26-2018) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN202 TA 45 3 61378C

Wekiwa Springs State Park Erosion Control & Access

Michael Baker International

Jeff Roberts, P.E., RSP1 (850) 701-2303 jeff.roberts@mbakerintl.com

Ralph Perkins, or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov

This Change Order is to include Orange County Conservation Area Determination (CAD) permitting and associated boundary survey for the referenced project per the attached Change Order dated 07/03/2024.

$ 150.00 $ 17,094.09 $ 17,244.09 $ 1,750.00 $ 52,340.64 $ 54,090.64 $ 2,174.00 $ 21,232.98 $ 23,406.98 $ 3,924.00 $ 73,573.62 $ 77,497.62

05/22/2023

05/17/2024

05/17/2024

02/25/2025

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2024.07.08 13:04:54 -04'00'

Del Cobb Del Cobb Digitally signed by Del Cobb Date: 2024.07.08 13:32:13 -04'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2024.07.08 13:58:34 -04'00'

Jeff Roberts, P.E., RSP1 Jeff Roberts Digitally signed by Jeff Roberts Date: 2024.07.08 14:13:53 -04'00'

Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2024.07.09 11:40:46 -04'00'

61378C 37503006080 080039/22 423001 U3200 131500 QK $ 23,406.98

$ 23,406.98

Cobb_DL Inserted Text

July 3, 2024

Mr. Del Cobb Project Manager Bureau of Design and Construction Division of Recreation and Parks 3900 Commonwealth Boulevard Tallahassee, FL 32399

RE: Statewide Contract: CN202, Task Assignment 45, Change Order 03 Wekiwa Springs Final Design

Wekiwa Springs Erosion Control & Access, Orange County (Apopka), FL

Dear Mr. Cobb:

For your review, Michael Baker International, Inc., is attaching a change order proposal summary and man-hour documentation for the subject task assignment to include Orange County Conservation Area Determination (CAD) permitting and associated boundary survey for the referenced project.

Please review the attached Change Order proposal and deliverables and let me know if there are any questions or comments.

Sincerely, Jeff Roberts, PE, RSP1 Vice President

Change Order 03

Wekiwa Springs State Park – Site Grading Improvements

Wekiwa Springs, Apopka, FL

Statewide Contract CN202, Task Assignment 45

Project Objective: Under TA #45, Michael Baker is completing the final Design Plans for grading improvements at the Wekiwa Springs State Park is in Orange County, Florida. Now that construction of the project is pending, this change order adds local agency permitting, post design and construction phase support services to support acquisition of required Orange County and Seminole County permits, preconstruction activities, review RFI’s, perform site reviews during construction, and support project closeout.

This Change Order adds the following new tasks to the project:

Subtask 12: Boundary Survey for CAD/CAI Application

George F. Young, Inc. (SURVEYOR) will document wetland delineation boundary flag locations by a registered land surveyor. The SURVEYOR will also survey the edge of water at the spring and the limits of sidewalk between the wetland boundary and the spring. The SURVEYOR will locate boundary corners of the Conservation Area Boundary which will be provided to the SURVEYOR by the CONSULTANT in KML or KMZ format. The SURVEYOR will prepare a legal description for the Conservation Area Boundary and will prepare two (2) hard copies and one electronic copy in Adobe portable document format (PDF) of a signed, sealed exhibit depicting the Conservation Area Boundary; the legal description for the

Conservation Area Boundary; and the delineated wetland limits, limits of the sidewalk between the wetland boundary and the spring, limits of the spring, and the Orange County-Seminole County

Boundary in the vicinity of the Conservation Area.

Deliverable: Signed and sealed survey figure depicting the Conservation Area Boundary, legal description, and wetland delineation in PDF and (2) hard copies (one for submittal to Orange County and one for the CLIENT).

Performance Measure: Final deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Company Classification Rate Hours Cost

MBI Project Manager $238.84 3 $716.52

GFY Inc. Prof. Surveyor/Mgr. $147.80 10 $1,478.00

GFY Inc. Prof. Surveyor $119.30 12 $1,431.60

GFY Inc. 2 Man Survey Crew $109.48 48 $5,255.04

GFY Inc. CADD Technician $74.06 48 $3,554.88

GFY Inc. Clerical $51.90 3 $155.70

Totals (Subtask 12) 193 $12,591.74

Subtask 13: Orange County CAD/CAI Permit Applications and Support

Subtask 13.1: Preapplication Meeting

The CONSULTANT will coordinate, schedule, and attend a virtual preapplication meeting with

Orange County’s environmental staff to discuss the county’s environmental permitting requirements. The meeting will be attended by CONSULTANT’s project manager, the

CONSULTANT’s environmental scientist, and the CONSULTANT’s project engineer.

Deliverable (Subtask 13.1): Preapplication meeting notes in electronic PDF format.

Subtask 13.2: Supplemental Wetland Delineation

Per coordination with Orange County, wetlands outside of the project impact area will require field delineation so that all wetlands in the limits of the area to be defined by the Conservation

Area Determination are delineated. The CONSULTANT will field delineate these additional wetland areas in accordance with the State of Florida’s wetland delineation methodology contained in Chapter 62-330.201 of the Florida Statutes (FS).

Deliverable (Subtask 13.2): Delineated wetlands will be shown on the survey performed under

Subtask 12.

Subtask 13.3: Orange County Field Review

The CONSULTANT will schedule and attend an on-site field review with Orange County staff to review the delineated wetland boundary. If adjustments to the wetland boundaries are necessary, they will be made at this time.

Deliverable (Subtask 13.3): Attendance at field review and electronic notes describing outcome of field review.

Subtask 13.4: Conservation Area Determination (CAD)

The CONSULTANT will prepare an application for a Conservation Area Determination for submittal to Orange County. The application package will include an aerial photograph exhibit with parcel boundaries, a soils map exhibit, a U.S. Geological Survey topographic map exhibit, a land cover mapping exhibit, a property boundary exhibit, and the Conservation Area Boundary Exhibit that will be prepared by the surveyor under Subtask 4.

Deliverable (Subtask 13.4): Orange County Conservation Area Determination Application in PDF.

Subtask 13.5: Conservation Area Impact (CAI) Permit

The CONSULTANT will prepare a Conservation Area Impact Permit application. The application will include an aerial photograph exhibit, Uniform Mitigation Assessment Method forms for the areas of wetland buffer impact and secondary wetland impact from the project, and the plan set for the project with the Wekiva Riparian Habitat Protection Zone (WRHPZ) Buffer depicted and the impact area acreages called out.

Due to impacts to the WRHPZ and secondary impacts to wetlands, the CLIENT will likely be required to provide some compensatory mitigation for the impact. The CONSULTANT will work with the CLIENT to identify a potential source of mitigation for the project based on existing land management activities at Wekiva Springs State Park, such as removal of exotic plant species. The success of this effort will be determined by whether such activities can be identified and well documented. If no suitable mitigation can be identified from existing park land management activities, it is anticipated that the CLIENT would be required to purchase wetland mitigation credits from a wetland mitigation bank located in Orange County with a service area that includes the project area.

The CONSULTANT will prepare a mitigation narrative that describes the proposed mitigation for the project. It will describe either an ongoing or proposed land management activity at Wekiva

Springs/Rock Springs or it will describe the purchase of wetland mitigation credits from a mitigation bank with a service area that includes the project site. This narrative will be submitted as part of the Conservation Area Impact Permit application. If mitigation credit purchase is selected as the source for mitigation, the CONSULTANT will coordinate with the mitigation banks to help arrange for the CLIENT’s purchase of the required credits.

Deliverable (Subtask 13.5): Orange County Conservation Area Impact Permit Application in PDF.

Assumptions:

1. Protected species surveys, species permitting, consultation, or mitigation is not included.

2. Mitigation credits are available from a mitigation bank in Orange County with a service area that includes the area of the project.

3. Purchase price of any required wetland mitigation bank credits would be paid for by the CLIENT.

4. If development of a wetland mitigation plan is required, this will be provided under a separate agreement.

5. Coordination with the State Historic Preservation Office is not included.

Performance Measure: Final deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 13.1 Preapplication Meeting

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Michael Baker Environmental Scientist $106.81 5 $534.05

Subtask 13.1 Total Cost $534.05

Subtask 13.2 Supplemental Wetland Delineation

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Michael Baker Environmental Scientist $106.81 11 $1,174.91

Subtask 13.2 Total Cost $1,174.91

Subtask 13.3 Orange County Field Review

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Michael Baker Environmental Scientist $106.81 10 $1,068.10

Subtask 13.3 Total Cost $1,068.10

Subtask 13.4 Conservation Area Determination (CAD) Permit

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Michael Baker Sr. Environmental Scientist $172.27 2 $344.54

Michael Baker Environmental Scientist $106.81 11 $1,174.91

Subtask 13.4 Labor Cost $1,519.45

Subtask 13.4 Reimbursable Cost (fees) $901.00

Subtask 13.4 Total Cost $2,420.45

Subtask 13.5 Conservation Area Impact (CAI) Permit

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Michael Baker Sr. Environmental Scientist $172.27 6 $1,033.62

Michael Baker Environmental Scientist $106.81 31 $3,311.11

Subtask 13.5 Labor Cost $4,344.73

Subtask 13.5 Reimbursable Cost (fees) $1,273.00

Subtask 13.5 Total Cost $5,617.73

Subtask 13 LABOR $8,641.24

Subtask 13 Reimbursable Expenses $2,174.00

Total Subtask 13 Costs $10,815.24

Summary of Fees:

Subtask Subtask Fixed

Price Cost Subtask

Reimbursable

New Subtasks (This Change Order)

Subtask 12: Supplemental Boundary Survey $12,591.74

Subtask 13.1: Preapplication Meeting $534.05

Subtask 13.2: Supplemental Wetland Delineation $1,174.91

Subtask 13.3: Orange County Field Review $1,068.10

Subtask 13.4: Conservation Area Determination $1,519.45 $901.00

Subtask 13.5: Conservation Area Impact $4,344.73 $1,273.00

New SubTotal Fixed Price Cost (This Change Order) $21,232.98 --

New Total Reimbursable Cost (This Change Order) -- $2,174.00

New Total Cost (This Change Order Only) $23,406.98

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.

Project Schedule:

Project Schedule is based on estimated duration of calendar days to complete each subtask. Schedule dates will be established after approved and executed contract has been received. Where most practical, subtasks will be worked on concurrently.

Subtask Subtask Duration (Calendar Days)

Subtask 12: Supplemental Survey 14

Subtask 13: Orange County CAD/CAI Permit Applications and Support

BLANK TA CO FORM.pdf
TA45_CO3_Wekiwa Springs Runoff_OrangeCo_CAD-CAI_070324.pdf