B08_Att_07_GRCA_257282_Price_Schedule.xlsx
XLSX spreadsheet 27 KB Posted
- Solicitation number
- 140P2026R0101
About this file
This is a Price Schedule Template for the National Park Service (NPS) Denver Service Center for Solicitation Number 140P2026R0101, related to GRCA Project 257282 at Grand Canyon National Park. The template is a blank form used for design-bid-build (DBB), design-build (DB), and other project delivery methods, providing three sample price schedules with different work structures.
The primary project example addresses replacement of the wastewater plant at South Rim Village and includes four base contract line items: Replace South Rim WWTP (lump sum), South Rim WWTP Compost Facility (lump sum), South Rim WWTP Operations and Maintenance Support Services (lump sum), and South Rim WWTP Access Road Improvements (lump sum), with two optional line items for Radon Gas Testing and Active Radon Mitigation System. The template also includes sample schedules for a DBB project (Johnstonian Visitors Center at Yellowstone) with unit-priced items for water line, sanitary sewer line, and rock excavation, plus geothermal and photovoltaic options, and a DB project example for a structure at Yosemite Valley with design and construction lump-sum pricing. Offerors are required to submit pricing for all base and option line items; on lump-sum items, only total price is required, while unit-priced items require both unit price and extended total. In case of calculation errors, unit prices govern for individual items and corrected totals govern for summations. All measurement and payment information is contained in Division 01 Specifications Section 01 27 00.
View the file
Other files
Show all 47
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule Template
| Contract Price Schedule Template | |||||
| National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18 | |||||
| Solicitation Number: | 140P2026R0101 | ||||
| PARK - PMIS: | GRCA - 257282 | ||||
| (Project Management Information System) | |||||
| Developed Area: | Grand Canyon National Park | ||||
| Project Title: | Replace Wastewater Plant at South Rim Village | ||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | |||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | |||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | |||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | |||||
| govern. Round totals and extended prices to whole dollars. | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 1 | Replace South Rim WWTP | 1 | Lump Sum | $0.00 | $0.00 |
| 2 | South Tim WWTP Compost Facility | 1 | Lump Sum | $0.00 | $0.00 |
| 3 | South Rim WWTP Operations and Maintenance Support Services | 1 | Lump Sum | $0.00 | $0.00 |
| 4 | South Rim WWTP Access Road Improvements | 1 | Lump Sum | $0.00 | $0.00 |
| TOTAL BASE PRICE (Contract Line Item Number 01 through 04) | $0.00 | ||||
| 4 | OPTION B, (CLI Title) | - 0 | |||
| 5 | OPTION C, (CLI Title) | - 0 | |||
| 6 | OPTION D, (CLI Title) | - 0 | |||
| 5 | Option A: Radon Gas Testing | 1 | Lump Sum | $0.00 | $0.00 |
| 6 | Option B: Active Radon Mitigation System | 1 | Lump Sum | $0.00 | $0.00 |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Numbers5 through 6) ------------------------------------ | $0.00 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Numbers 1 through 6) ----------- | $0.00 | ||||
| All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items. |
Design-Bid-Build (DBB) Sample
| Contract Price Schedule - Design-Bid-Build (DBB) SAMPLE | |||||
| National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18 | |||||
| Solicitation Number: | N2011080811 | ||||
| PARK - PMIS: | YELL 012345 | ||||
| (Project Management Information System) | |||||
| Developed Area: | Old Faithful | ||||
| Project Title: | Johnstonian Visitors Center | ||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | |||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | |||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | |||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | |||||
| govern. Round totals and extended prices to whole dollars. | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 1 | Visitors Center | 1 | Lump Sum | $0.00 | |
| 2 | Water Line | 400 | Lineal Feet | - 0 | |
| 3 | Sanitary Sewer Line | 200 | Lineal Feet | - 0 | |
| 4 | Rock Excavation | 150 | Cubic Yards | - 0 | |
| TOTAL BASE PRICE (Contract Line Item Number 1 through 4) --------------------------------------------------------------------------------- | $0.00 | ||||
| 5 | OPTION A, Geothermal Wells | 1 | Lump Sum | - 0 | |
| 6 | OPTION B, Photovoltaic System | 1 | Lump Sum | - 0 | |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 5 and 6) ------------------------------------------------------------------- | $0.00 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 6) ---------------------------- | $0.00 | ||||
| All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items. |
Design-Build (DB) Sample
| Contract Price Schedule - Design-Build (DB) SAMPLE | |||||
| National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18 | |||||
| Solicitation Number: | N2011080811 | ||||
| PARK - PMIS: | YELL 012345 | ||||
| (Project Management Information System) | |||||
| Developed Area: | Yosemite Valley | ||||
| Project Title: | Design and Build a New Structure | ||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all | |||||
| option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced | |||||
| line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related | |||||
| item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts | |||||
| govern. Round totals and extended prices to whole dollars. | |||||
| Contract Line Item Number (CLIN) | Contract Line Item (CLI) Title | Quantity | Unit of Measure | Unit Price | Total Price |
| 1 | Design | 1 | Lump Sum | $0.00 | |
| 2 | Construction | 1 | Lump Sum | - 0 | |
| TOTAL BASE PRICE (Contract Line Item Number 1 and 2) --------------------------------------------------------------------------------------- | $0.00 | ||||
| 3 | OPTION A, Photovoltaic System | 1 | Lump Sum | - 0 | |
| TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 3) ---------------------------------------------------------------------------- | $0.00 | ||||
| TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 3) ---------------------------- | $0.00 | ||||
| All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items. |
File details come from the government source that posted it. Updated .