About this file

This is a Questions and Answers document for GRCA 257282, Replace South Rim Wastewater Treatment Plant, Amendment 03, dated 09.02.2026, Contract No. 140P2026R0101.

The document contains four clarification questions and responses addressing structural and coating specifications for the wastewater treatment plant project. Question 1 seeks clarification on column dimensions (W12x45) located 10 feet north of Line 1 on the Process Tanks Structural Lower Level Plan, with the response referencing a callout on drawing 25S1020 attached to Addendum 3. Question 2 addresses constructability concerns regarding moment connections to column webs (detail 0512-020) that present installation conflicts due to 3/8" stiffeners; the response directs bidders to new connection details and callouts on drawings 25S1040 and 25S5001 in Addendum 3. Question 3 inquires about armor angle specifications and headed stud sizing and spacing, with the response directing reference to drawing 87S1030 for SST L3x3x¼ angle specifications. Question 4 addresses painting and coating system assumptions for structural steel, confirming that steel roof trusses and monorails receive System No. 4 Exposed Metal – Highly Corrosive shop primer, while all other structural steel receives a different system specification. The document serves as official clarification for contract bidders regarding technical specifications and design modifications.

View the file

Other files

File Type Posted
Sol_140P2026R0101_Amd_0006.pdf PDF
B09_Amendment_06_GRCA257282_FinalCD_Addendum_06_0006.pdf PDF
B09_Amendment_06_SF_30_0006.pdf PDF
B09_Amendment_06_B08_Att_13_Solit_PSP_Vol_II_SubKPlan_0006.docx DOCX document
B09_Amendment_06_GRCA_25782_Site_Visit_Sign_in_Sheet_0006.jpeg JPEG file
B09_Amendment_06_Answers_to_Questions_0006.pdf PDF
B09_Amendment_05_Answers_to_Questions_0005.pdf PDF
Sol_140P2026R0101_Amd_0005.pdf PDF
B09_Amendment_05_GRCA_Final_Individual_Specs_0005.zip ZIP file
B09_Amendment_05_GRCA257282_FinalCD_Addendum_02_SCADA_wSeal_0005.pdf PDF
B09_Amendment_05_GRCA257282_FinalCD_Addendum_04_0005.pdf PDF
B09_Amendment_05_GRCA257282_FinalCD_Addendum_05_0005.pdf PDF
B09_Amendment_05_SF_30_0005.pdf PDF
B09_Amendment_04_SF30_0004.pdf PDF
Sol_140P2026R0101_Amd_0004.pdf PDF
B09_Amendment_03_GRCA257282_FinalCD_Addendum_03_Compiled_wSeal_0003.pdf PDF
Sol_140P2026R0101_Amd_0003.pdf PDF
B09_Amendment_03_SF30_0003.pdf PDF
Sol_140P2026R0101_Amd_0002.pdf PDF
B09_Amendment_02_SF30_0002.pdf PDF
B09_Amendment_02_What_Evaluators_Will_Ask_for_Each_Factor_2_0002.pdf PDF
B09_Amendment_02_GRCA_257282_SR_WWTP_PreBid_Mtg_presentation_(8-11-26)_FINAL_0002.pdf PDF
B09_Amendment_02_GRCA_257282_Precon_SignIn_0002.pdf PDF
Sol_140P2026R0101_Amd_01.pdf PDF
B09_Amendment_01_GRCA257282_Access_Road_100P_Final_CD_DRAWINGS_01.pdf PDF
B09_Amendment_01_SF30_01.pdf PDF
B09_Amendment_01_RCA257282_Access_Road_100P_Final_CD_Specifications_01.pdf PDF
B09_Amendment_01_GRCA257282_CD_Specifications_June2025_01.pdf PDF
Sol_140P2026R0101.pdf PDF
B08_Att_11_Solit_PSP_Vol_II_Equals.pdf PDF
B08_Att_10_Solit_PSP_Vol_II_BidBond.pdf PDF
B08_Att_07_GRCA_257282_Price_Schedule.xlsx XLSX spreadsheet
B08_Att_01b_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part2.pdf PDF
B08_Att_03_GRCA257282_100P_FinalCD_Addendum_1.pdf PDF
B08_Att_01e_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part5_1.pdf PDF
B08_Att_12_Solit_PSP_Vol_II_GenRefs.pdf PDF
B08_Att_08_Solit_PSP_Vol_I_Exp_REQD.pdf PDF
B08_Att_09_Solit_PSP_Vol_I_PastPerf_REQD.pdf PDF
B08_Att_01c_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part3.pdf PDF
B08_Att_04_GRCA257282_Geotechnical_Recommendation_TM_May2025.pdf PDF
B08_Att_01d_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part4.pdf PDF
B08_Att_01a_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part1.pdf PDF
B08_Att_06_Wage_Determination_(1).pdf PDF
B08_Att_01e_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part5.pdf PDF
B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf PDF
B08_Att_05_Hazardous_Materials_Investigation_Report_South_Rim_WWTP.pdf PDF
B08_Att_13_Solit_PSP_Vol_II_SubKPlan_REQD_RELEASED_v2_Mar25.pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140P2026R0101 / Amendment 03/

09.02.2026

GRCA 257282, Replace South Rim Wastewater Treatment Plant

Question No. Sheet or Reference Question Response

Ref. 25S1020 Process Tanks Structural Lower Level Plan; What size are the (2) columns 10’- 0’ North of Line 1?

The columns are W12x45. Callout provided by markupon drawing 25S1020 (attached to Addendum 3).

Ref. 1/25S5001 Moment Connection; The perpendicular beam connections to the column web are called out as 0512-020. These beams are not erectable due to the presence of the 3/8” stiffeners above and below the beam connection. Please advise.

New connection detail and callouts provided for the beam to column web connection. Markups provided on drawings 25S1040 and 25S5001 (attached to Addendum 3).

Ref. 1/87S1030 “Armor Angles”; What size are the angles? Size and spacing of the headed studs?

Use SST L3x3x¼. Markup provided for drawing 87S1030 (attached to Addendum 3).

Ref. 09 90 00 Painting and Coatings; We assume all structural steel is to be shop primed with System No. 5 Exposed Metal – Mildly Corrosive other than the steel roof trusses which are to be shop primed with System No. 4 Exposed Metal – Highly Corrosive. Please confirm.

Steel roof trusses and monorails shall be shop primed with System No. 4 Exposed Metal – Highly Corrosive.

All other structural steel shall be shop primed with