This Scope of Work document pertains to the Collins Street Complete Street - Phase I project issued by the City of Plant City, Florida, under Invitation for Bids (IFB) 25-014EN-FC-IFB. The project encompasses the reconstruction of Collins Street from just south of Alabama Street to Laura Street, spanning approximately 1,300 linear feet, with a substantial completion timeline of 365 calendar days from the Notice to Proceed. Work includes expanding sidewalk widths by relocating curbs inward and reducing roadway pavement width, milling and resurfacing, installing storm sewer systems, hardscape elements including decorative pavers, landscaping, irrigation, decorative street lighting, roadway signing, and pavement markings. Additional scope elements include complete removal and replacement of the existing traffic signal system at Collins Street and Alabama Street with a new mast arm configuration, pedestrian signals, and traffic controller, as well as relocation and replacement of the City of Plant City's potable water main within the roadway improvement limits. The bid was released on August 18, 2025, with questions due by September 8, 2025, and proposals due by October 9, 2025.
The contractor is responsible for obtaining the National Pollutant Discharge Elimination System (NPDES) permit and developing a Stormwater Pollution Prevention Plan (SWPPP) under the direction of a Florida Licensed professional engineer, which must be submitted to the City for review and approval. The contractor must coordinate directly with utility agencies including Tampa Electric Company (TECO), Charter Communications, Frontier Communications, and the City of Plant City regarding the relocation of overhead cables to underground facilities. The project area abuts properties with known soil and groundwater contamination; the contractor may encounter contaminated soil and groundwater during operations. Geotechnical reports prepared by Terracon Consultants, Inc., and permits including a Southwest Florida Water Management District ERP Project Exempt Permit are provided as exhibits. The contractor must comply with all Florida Department of Environmental Protection guidelines regarding Construction General Permit compliance and erosion control, with all costs associated with enforcement actions for non-compliance being the contractor's responsibility. The contractor must hold a State of Florida General Contractor's License and FDOT Prequalification.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Collins Street Complete Street Improvements-Phase I / 25-014EN-FC-IFB Scope of Work - Page 1 of 3
Scope of Work
Description of Work
Construction of improvements to Collins Street Complete Street Phase I Improvements which include, but are not limited to:
The reconstruction of Collins Street from just south of Alabama Street to Laura Street, approximately 1,300 linear feet. Improvements consist of expanding the sidewalk widths by relocating the curb inward and reducing the roadway pavement width, milling and resurfacing, installing storm sewer system, hardscape elements including decorative pavers, landscaping, irrigation, decorative street lighting, roadway signing, pavement markings, traffic control, and other ancillary items associated the improvements.
Traffic Signal at Collins Street and Alabama Street Intersection Includes the complete removal/replacement of the existing traffic signal system with the installation of a new mast arm traffic signal configuration, including pedestrian signals, signal interconnect, traffic controller, and maintenance of traffic signal control during construction.
Plant City Water Main Replacement Includes relocation / replacement of City of Plant City potable water within the limits of the roadway improvements.
Geotechnical Information Geotechnical information has been provided for the project as part of these Contract Documents. This information is being provided for the Bidder’s information only and is not intended to be a complete description of the subsurface conditions. The Bidder or the CONTRACTOR is not relieved of any duty as otherwise required in these Contract Documents to examine the site of the proposed work or to make any investigations or inquiries, including, but not limited to additional subsurface testing, because the CITY has provided this information. Any such examinations, investigations, inquiries or testing performed by the Bidder or CONTRACTOR shall be done at such Bidder's or CONTRACTOR’s own expense.
Any reports provided are for the CONTRACTOR’s general information. The CITY disclaims all responsibility for the findings and interpretations expressed in the reports by the testing laboratories. The CONTRACTOR shall make whatever subsurface and geotechnical investigations it deems necessary as to actual field conditions and to comply with the requirements of the Contract Documents.
Geotechnical Reports are included as an Exhibit and include:
1. “Geotechnical Engineering Report – South Collins Street Cores” dated July
25, 2019, by Terracon Consultants, Inc.
2. “Geotechnical Engineering Report – Collins Street Mast Arms” dated October
30, 2019, by Terracon Consultants, Inc.
Scope of Work - Page 2 of 3
Utility Coordination Utility Agency Owners (UAO) with existing overhead (aerial) cables attached to poles along Collins Street between Alabama Street and Laura Street are relocating their facilities to underground. Any conflicts between the WORK that the CONTRACTOR is to perform and the utility owner’s facilities shall be resolved by the CONTRACTOR and the utility owner with the CITY’S concurrence. Utility Relocation Schedules are included in the Contract Documents as an Exhibit. Utility Adjustment plans included in the construction plans are provided for information purposes only. Direct coordination by the CONTRACTOR and Utilities is required during the course of the project.
Soil and Groundwater Management The project area abuts properties with known soil and groundwater contamination.
Contractor’s operations may encounter contaminated soil and groundwater. See General Requirements.
Permits A. The CITY has obtained the following permit exemption:
1. Southwest Florida Water Management District, ERP Project Evaluation- Project
Exempt Permit, File Number 823413, May 13, 2021.
B. The CONTRACTOR is responsible to apply and obtain NPDES permit and shall meet the following requirements:
1. CONTRACTOR shall be responsible for meeting the requirements of the National
Pollutant Discharge Elimination System (NPDES) permitting program in the State of Florida, found in DEP Document No. 62-621.300(4)(a). This includes: submittal of a Notice of Intent to the Florida Department of Environmental Protection Stormwater Notices Center and posting of Notice of Intent (NOI) or acknowledgement letter from DEP at the site: construction and documenting inspections for erosion control measures and Stormwater Management: the development and implementation of a Stormwater Pollution Prevention Plan (SWPPP): and, filing Notice of Termination (NOT) within fourteen days of final stabilization of the site and retention of reports for three (3) years after final stabilization. The SWPPP must be prepared under the direction of a Florida Licensed professional engineer. Prior to implementation, the SWPPP is to be submitted to the CITY for review and approval.
2. The CONTRACTOR shall review and understand the project construction limits, areas specified for clearing and grubbing, wetland delineations, and areas specified per the project permits for temporary and permanent impacts against their means and methods of construction prior to bidding on the Contract. If the CONTRACTOR’s means and methods of construction require permit modifications, the CONTRACTOR shall be responsible for all impacts, including project costs and delays associated with pursuing the modifications to the permits.
3. Since erosion control on the project site is performance based, simply installing
Scope of Work - Page 3 of 3 erosion control devices shown on the SWPPP may not be sufficient in certain cases. If inspections by the CONTRACTOR or the CITY reveal that controls are insufficient, the CONTRACTOR is to install additional erosion control devices as necessary to prevent off-site discharge of sediment and other possible sources of pollution, such as stormwater runoff.
4. All Construction General Permit (CGP) compliance violations and/or SWPPP deficiencies identified through site inspections shall be resolved in a timely manner, dependent upon the severity of the violation. Failure to resolve all compliance violations in a timeframe agreeable to the CITY shall result in requisite enforcement actions. All costs associated with enforcement actions shall be the responsibility of the CONTRACTOR.
5. CONTRACTOR shall adhere to all Florida Department of Environmental
Protection guidelines regarding CGP compliance and SWPPP implementation.
Additional resources can be found on FDEP’s website:
https://floridadep.gov/water/stormwater/content/construction-activity-cgp https://floridadep.gov/water/stormwater/content/construction-activity-cgp
| Scope of Work |
| Description of Work |
| Plant City Water Main Replacement |
| Geotechnical Information |
| Utility Coordination |
| Soil and Groundwater Management |