- REQUEST FOR PROPOSAL (RFP) for Radiation Portal Monitor Program (RPMP) Deployment, Construction and Design
- Solicitation number
- 70RWMD20R00000012
About this file
This task order statement of work outlines design, engineering, and technical services required for the installation and relocation of radiation portal monitor systems at Pier J of the Port of Los Angeles/Long Beach. Key deliverables include site surveys, conceptual and final design packages, construction management and reports, procurement, installation, integration, commissioning, and training. The contractor must provide project management, design reviews at 30%, 60%, 90%, and 100% completion, a construction readiness review, and a final commissioning report. Services are to be completed by December 2021 in accordance with program guidance documents and requirements outlined in the task order. Pricing is to be provided using the contract line item numbers and table specified in Attachment J.7.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
70RWMD20R00000012 Attachment J.6
U.S. DEPARTMENT OF HOMELAND SECURITY
COUNTERING WEAPONS OF MASS DESTRUCTION
Contract No: 00-0000XXX Task Order No: 00-000000XXXX
Statement of Work November 2020
Task Order Title: Design, Engineering, and Technical Services for Installation/Relocation of Radiation Portal Monitor (RPM) Systems for Pier J, Port of Los Angeles/Long Beach (LA/LB), CA.
Scope: The Contractor shall conduct site survey, design, site management, construction and commissioning including fully integrating ancillary equipment for the RPMs with a command booth, and commission for Pier J, Port of LA/LB, CA:
· Main Gate
· Back Gate
· Rail Gate Table.1 Deliverables
| CLIN Name |
| SOW Reference/ |
CLIN #
| Deliverables |
| Due Date/NLT |
| Site Survey |
| IDIQ SOW 4.8 |
Scoping Meeting Summary
20 days after Site Survey
| Site Survey Report (includes Conceptual Design and background radiation effects) |
| 30 days after Site Survey |
| ICE |
| 30 days after Site Survey |
| Design and Construction Schedule |
| 30 days after Site Survey |
Design
IDIQ SOW 4.9, 4.11.3
| 30% Design Submittals |
| 30 days after SSR |
| 60% Design Submittals |
| 20 days after 30% |
| 90% Design Submittals |
| 30 days after 60% |
| 100% Design Submittals |
| 20 days after 90% |
| ICE with each design submittals |
| Per the design submittal |
| Updated Design and Construction Schedule with each Design Phase Submittal |
| Per the design submittal |
| Submittal Register |
| Per the design submittal |
| Approved Design Package |
| 5 days after 100% |
| Construction Readiness Review Checklist |
| A minimum of 7 days prior to the scheduled start of construction |
| Construction Readiness Checklist |
| At least 24 hours prior to the scheduled CRR |
IDIQ SOW 4.10
| Analysis reports of integration results and possible efficiencies |
| As required |
| Site Management |
| IDIQ SOW 4.12 |
| Quality Assurance/Control Site Plan |
| As required |
| Personnel Roster |
| 10 days after Notice to Proceed but prior to site work |
RFI Register
Project Schedule
| Meeting Minutes |
| 3 days after the meeting |
| Construction and Installation |
| IDIQ SOW 4.12.1, 4,12.2 |
| Daily Construction Report (includes both QA/QC sections) |
| Daily |
| Installed Equipment Lists and Site Configuration Baseline |
| As required |
Commissioning
IDIQ SOW 4.13, 4.15, 4.16
| Provide calibration scripts and reports as found settings, as left settings, and calibration results |
| As required |
Update Training Materials
Provide input to update local SOP
| Commissioning Package |
| 5 days before Go-live |
| Provide Training |
| Prior to or during 48- |
hour burn-in
| Commissioning Report |
| 2 days after 48-hour |
burn-in
Signed Acceptance Documents
| Decommissioning |
| IDIQ SOW 4.14 |
| Update equipment lists and calibration baselines |
| As required |
Requirements Documents: The following documents provide the project requirements, specifications, and other design standards for this task order. These documents include the IDIQ Contract SOW, DD-003, Ref Design Description-Seaports Design Requirements Document, Pier J_CDR, DD-065, RPM Deployment Process Document and other related Government Furnished Information (GFI).
Estimated Cost/Price: Please provide the estimated cost/pricing in Attachment J.7 CLIN Table to perform the scenario tasks in Paragraph 1.0.
1.0 Task Order Requirements:
1.1 Construction Site Management/Project Management: The Contractor shall provide Project Management services, including oversight of all construction and integration activities at all gates.
1.1.1 (IDIQ SOW 4.12) Personnel Roster: The Contractor shall provide a Personnel Roster including the name, title, company, phone number, and e-mail address for the following positions:
- Task Order Manager
- Construction Manager(s)/Field Representative(s)
- Communications Manager Any changes to this Personnel Roster at any time during the period of performance (POP) must be approved in advance by the Contracting Officer’s Representative (COR).
1.1.2 (IDIQ SOW 4.12) The Contractor shall participate in project conference calls, video conferences, and meetings as requested.
1.1.3 (IDIQ SOW 4.12) The Contractor shall maintain schedule projections in MS Project format by site according to the standard CWMD WBS structure. The Contractor shall maintain the MS Project WBS for LA/LB work activities to the lane construction task level, in accordance with the WBS. The Contractor shall maintain a list of program milestones and test events, with critical path activities highlighted in red and visible from date of award through acceptance. Original start and end dates shall be included for each task. If estimated start and end dates change during any reporting period, the Contractor shall highlight them in blue for the next schedule iteration. The Contractor shall also highlight high-risk schedule items or potential schedule changes/delays in yellow. The Government may request an updated schedule in iterations at any time during the reporting period.
1.1.4 (IDIQ SOW 4.12.1) Daily Construction Execution Reports: The Contractor shall submit daily site reports for each day contractor or subcontractor personnel are on site. Daily reports shall be submitted via e-mail and shall include a Word version as an attachment. FOUO information shall not be transmitted in daily reports. If any discussion information is FOUO, the Contractor shall submit it, following all applicable CWMD program guidance on markings and transmission.
1.1.5 (IDIQ SOW 4.1) Weekly Reports: When there are no contractor or subcontractor personnel on site, the Contractor shall submit a weekly report, in contractor format, to include at a minimum: Work progress, including subcontractor work; Client stakeholder interface; Issues, to include possible cost/schedule or configuration management impacts; and Lessons Learned. Weekly reports shall be submitted via e-mail and shall include a Word version as an attachment FOUO information shall not be transmitted in daily reports. If any discussion information is FOUO, the Contractor shall submit it, following all applicable CWMD program guidance on markings and transmission.
1.1.6 (IDIQ SOW 4.22) Procurement/Logistics Services: The Contractor shall provide logistics services in support of this Task Order including, but not limited to: air/land travel arrangements; training efforts; permitting; procurement; and subcontracting. The Contractor shall arrange for any storage and provide delivery of equipment. These services shall include coordination and shipment of equipment purchased by other CWMD organizations upon request of the COR.
1.2 (IDIQ SOW 4.8) Site and Engineering Survey: The Contractor shall perform a combined site and engineering survey for each of the gates listed above. Enough information shall be gathered to write a Site Survey Report (SSR) and develop designs with appropriate certainty. The combined site and engineering survey shall include team members identified by the CWMD. The Contractor shall develop and submit an SSR that includes conceptual design and design requirements in accordance with agreements with CWMD agreed upon during the survey. Follow-up engineering surveys may be required.
1.3 (IDIQ SOW 4.8) Scoping Meeting: The Contractor shall schedule, host, and participate in a Scoping Meeting with CWMD team members within 20 days of completion of the site and engineering surveys. Secondary or follow-up scoping meetings may be required. The Contractor shall submit a Scoping Meeting Summary detailing, at a minimum, items discussed, issues raised, solutions agreed upon, and remaining open action items. The Scoping Meeting Summary shall also contain a listing of all current program guidance applicable to the Task Order.
1.4 (IDIQ SOW 4.8) Site Survey Report (SSR): The Contractor shall submit an SSR (including Conceptual design and background radiation effects). The SSR shall consist of integrated General Arrangement (GA) drawings and preliminary equipment lists. The SSR shall be in accordance with the CWMD/CBP agreements, and as determined in scoping meetings, in SSR and all other current program guidance and requirements.
1.5 (IDIQ SOW 4.8) SSR Review: The Contractor shall schedule, host, and participate in a Conceptual Design Review to review the GA Drawings and equipment lists with the Implementation team members identified by the CWMD at the contractor’s U.S. location, CWMD HQ, other site identified by the CWMD, or via a virtual meeting.
1.6 (IDIQ SOW 4.9) 30/60/90% Design Review: The Contractor shall provide an analysis and recommendation for design phase submissions i.e. for all design phases (30, 60, 90, 100 percent) required. Included in this analysis must be the critical features of work and the reasoning/justification for inclusion in each design phase. The Contractor shall provide an analysis and recommendation/justification for the project delivery method of design-bid-build. Included in this analysis must be the critical analysis factors such as size of the project and project level of difficulty. Identify key decision points in the process and when these decisions should be made. The Contractor shall update the Site Survey conceptual design in accordance with agreements reached during each the design phase review and with the concurrence of CWMD. The final drawing set shall be stamped by the architect/engineer of record. The phased design approach includes a 30% design, 60% design, 90% design, and 100% design.
1.7 (IDIQ SOW 4.9) Final Engineering Designs: The Contractor shall deliver final engineering designs that provide for a fully integrated, constructible, and fully functional system in accordance with the CWMD agreements with CBP, Pier J and other stakeholders as determined in scoping meetings, SSR, and all other current program guidance and requirements. The Final Engineering Designs will not be accepted until designs for all items to be installed or constructed are included in final version.
1.8 (IDIQ SOW 4.11.3) Construction Readiness Review (CRR): At a time approved by the CWMD, the Contractor shall schedule, host, and participate in a CRR a minimum of 7 days prior to the scheduled start of construction. The Contractor shall provide a construction readiness checklist at least 24 hours prior to the scheduled CRR. The construction readiness checklist shall include interfaces/activities assumed to be Pier J responsibility, schedule and implementation risks, and updated equipment lists. The CRR will not be considered successful until all listed items are completed, and all Final Designs have been accepted.
1.9 (IDIQ SOW 4.12.1) Construction and Integration: After successful Construction Readiness Review and written authorization by the COR, the Contractor shall install CBP Booth and integrate the RPM and ancillary equipment in accordance with the final approved designs and all current program guidance.
1.10 (IDIQ SOW 4.12.2) Procurement: The Contractor shall procure ancillary equipment and other materials necessary to meet the approved design and equipment requirements of each site. All equipment purchases shall be in accordance with CWMD/CBP requirements, specifications, and agreements with the project sponsor of Pier J.
1.11 (IDIQ SOW 4.13) RPM alignment and start-up: The Contractor shall arrange for the RPM manufacturer or another individual authorized by the CWMD to travel to perform RPM start-up and alignment and assess its functionality before Inspection, Testing and Commissioning.
1.12 (IDIQ SOW, 4.13, 4.16) Commissioning: The Contractor shall support Inspection, Testing, Training and Commissioning in accordance with the DD-065, RPM Deployment Process Document for all phases. The CWMD Inspection, Testing, Training and Commissioning Guide includes instructions and deliverables. Should site specific requirements necessitate changes to this checklist and the process or deliverables, the CWMD Program will provide updated checklists and instructions no later than 30 days prior to the scheduled Site Inspection and Testing Date. The Site Inspection and Testing reports shall be prepared in accordance with the DD-065, RPM Deployment Process Document
A Pier J Specific Standard Operating Procedure (SOP) is required and tailored to Pier J by local CBP. The SOP will be incorporated into the commissioning documentation; therefore, the site manager shall work collaboratively with local CBP to ensure that they complete and receive their approved SOP within two weeks of the scheduled go-live date. The site manager shall submit the SOP to the RPMP lifecycle documentation lead for incorporation into the commissioning or upgrade documentation package.
The site manager shall meet with the responsible local CBP representative (chief/supervisor/port director, as appropriate) to determine what training the CBP officers will need to operate the RPM-related systems.
1.13 (IDIQ SOW 4.13) Site Inspection and Commissioning Package: In addition to the deliverables defined in the DD-065, RPM Deployment Process Document, the Contractor shall provide the following documentation in preparation for transferring the system to CBP. One hard copy and one electronic copy shall be available for each site.
a) All system passwords, user IDs, and IP addresses (i.e. cameras, servers, workstations, software applications, etc.);
b) Provide As-Built Drawings [Updated Issued For Construction (IFC) based on final red-lined drawings];
c) System Administrator Manuals;
d) Operator/OEM Manuals for all equipment.
1.14 (IDIQ SOW 4.13) Final Commissioning Report: The Contractor shall submit a Final Commissioning Report which shall be provided electronically and hard copy (as noted) and shall include, at a minimum:
· Executive summary of construction, installation and integration activities;
· Final As-built drawings of the site
· Request for site acceptance
· Photos of the construction, installation, and integration activities
· Project Management data, including the final MS Project Schedule, resolution of project action or punch-list items, challenges and mitigations, and lessons learned
· Master Equipment List
· Spare Parts Inventory List
· Special Tools
· Warranty information to include expiration dates and explicit instructions for transferring the warranty to CBP
· List of vendors and subcontractors integral to the installation of the RPM and ancillary equipment, including their contact information
· Physical copies of software media (Vendor software and license information, Operating System CDs, Anti-virus, backup software, etc.)
· Back-up image copies of each server/workstation, clearly labeled with instructions on how to restore each system should they become corrupted backups for thumb drives, compact flash cards, or other media storage devices necessary for system operation shall also be provided
· Backup of configurations for all network equipment (routers, switch configuration files)
· Backup of configurations for all cameras and instructions for restoring or reloading saved configurations
· Screen shots for image quality settings for all video cameras
· Copies of shipping and export control documentation; and
· Any updates to the Acceptance Test Package, as required.
1.15 Warranty: The Contractor shall provide warranty and repair of all procured equipment and software it has installed prior to and after acceptance by CBP per the manufacturer’s warranty.
1.16 (IDIQ SOW 4.15) Final Inspection and Commissioning Site Visits: The Contractor shall provide technical support in the areas of construction, RPM installation and integration with ancillary equipment.