Attachment I - HAZMAT Report Summary.pdf

PDF 768 KB Posted

Attached to
P-002 EDI: Rapid Airfield Damage Recovery Storage Facilities, Aviano Air Base, Italy
Solicitation number
N6247022R3000
Issued by

About this file

This hazardous materials report summary provides the results of an environmental survey conducted for the construction of Rapid Airfield Damage Recovery Storage Facilities at Aviano Air Base in Italy. Soil samples were taken from test borings between 0.5 and 3.0 meters below ground to test for various pollutants including arsenic, cadmium, cobalt, chromium, mercury, nickel, lead, copper, zinc, hydrocarbons, benzene, ethylbenzene, styrene, toluene, xylene, total aromatic compounds, polycyclic aromatic hydrocarbons, and asbestos. The report also analyzed soil aggressiveness to concrete. With one exception of hydrocarbon levels above residential but within industrial limits in one area, all pollutant concentrations were found to be below the more conservative Italian residential limits as well as the less stringent industrial limits set by national environmental law. Given the industrial nature of the project sites, the facilities are in compliance. As the buildings will be uninhabited and occupied less than four hours per day, radon mitigation is not required.

View the file

Other files

File Type Posted
Amendment 0009.pdf PDF
Amendment 0008.pdf PDF
Amendment 0007.pdf PDF
Attachment S - Revised Drawing CU101A.pdf PDF
Attachment O - Site Visit Sign In.pdf PDF
Attachment T - Revised Drawing CU101B.pdf PDF
Attachment R - Revised Drawing CS102B.pdf PDF
Attachment U - Revised Specification 01 50 00.pdf PDF
Amendment 0006.pdf PDF
Attachment P - Site 2 Access Road Aerial.pdf PDF
Attachment Q - Revised Drawing CD101A.pdf PDF
Amendment 0005.pdf PDF
Amendment 0004.pdf PDF
Amendment 0003.pdf PDF
Attachment N - Gas Line Trench Detail.pdf PDF
Amendment 0002.pdf PDF
Attachment M - Installation Access Request Form.pdf PDF
Amendment 0001.pdf PDF
Attachment L - Installation Access Request Checklist.pdf PDF
Attachment E - Price Proposal Form.pdf PDF
Attachment F - LRA Commercial Vehicle Inspection Procedures.pdf PDF
Attachment K - Italian Safety Plan_Combined.pdf PDF
Attachment H 1659896dwgVOL1_3of3.pdf PDF
Attachment H 1659896dwgVOL1_1of3.pdf PDF
Attachment H 1659896dwgVOL1_2of3.pdf PDF
Attachment C - Construction Experience Project Data Sheet.pdf PDF
Attachment G - Specifications.pdf PDF
Attachment D - Past Performance Questionnaire (PPQ).pdf PDF
Attachment B - SEC-NAV_5512_1_11787 Form.pdf PDF
Attachment H 1659896dwgVOL2_1of4.pdf PDF
Attachment H 1659896dwgVOL2_3of4.pdf PDF
Attachment A - Pre-Proposal Inquiry Form.xls XLS spreadsheet
Attachment H 1659896dwgVOL2_2of4.pdf PDF
Attachment J - Host Nation Code Compliance Certification.pdf PDF
N62470-22-R-3000.pdf PDF
Attachment H 1659896dwgVOL2_4of4.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DS1:NAVFAC:29314.09:07:07 2-3 Stanley Consultants

The buildings under design will be located on the plain, where alluvial deposits outcrop; here the groundwater is between 50 to 110 m below topographic surface. The average hydraulic gradient is 0.8‰. This aquifer recharge is underground.

Infiltration Tests Results No permanent ground water table has been found during the drilling of borings. Three variable head infiltration tests have been performed on site, as detailed in the geological report.

This method allows to determine the permeability of a test pit above the groundwater level.

The process involves digging a pit (with either a squared or rounded footprint) and filling it with water. The pit size depends on the ground particle diameters, with the pit volume to be larger as the particle size increases.

Based on the correlation table provided by Colombo (Elementi di geotecnica, 1977), resulting permeability coefficient per each test are as follows:

Site 1 (I1) – K = 6.40E(-6) m/s

Site 2 (I2) – K = 1.77E(-5) m/s

Site 2 (I3) – K = 2.33E(-6) m/s

Hazardous Materials Report Summary General Parameters Stanley Consultants was commissioned by NAVFAC ATLANTIC to conduct a hazardous materials and soil environmental survey at construction areas of “Rapid Airfield Damage Recovery Storage Facilities for a Medium Rapid Airfield Damage Recovery kit”. Buildings will be in Aviano Air Force Base, Italy.

A site investigation was performed in June 2021 by local firm “Palladio”, and a comprehensive report has been provided for reference.

Code Requirements Italian Codes

• Italian DPR 120/2017 - Management of excavated earth and rocks

• Italian Legislative Decree No. 152 of 2006 and related NTA - Environmental standard

• Regional regulations

Other References

• Aviano Air Base Design Guide 2017.

• Aviano Air Base Design Guide – Annexes revision 2011.

2-35

DS1:NAVFAC:29314.09:07:07 2-4 Stanley Consultants

Environmental Sampling Each boring performed corresponds to an environmental sampling between 0.5 and 3.0 m below ground, to detect the concentration of the following pollutants in accordance with national environmental law:

Arsenic, Cadmium, Cobalt, Chrome IV, Chrome, Mercury, Nickel, Lead, Copper, Zinc, Hydrocarbons C, Benzene, Ethylbenzene, Styrene, Toluene, Xylene, Total aromatic compounds, Polycyclic aromatic hydrocarbons, Asbestos.

Furthermore, additional analysis has been performed to include n. 4 aggressiveness of the soil to concrete.

Results Italian regulation (DL 152/06) sets two category of limits, one more severe for residential occupancy and one less severe for industrial occupancy.

The concentration determined in all the tests is always less than the most conservative value, with the only exception of the hydrocarbons C in the site 1 area, where the concentrations are above the residential limits but always well within the industrial limits. The area at issue shall be clearly classified within the industrial occupancy sites, therefore the less severe limits apply.

Given the above, pollutant concentrations are always below the limits.

With respect to Radon mitigation, it does not apply to uninhabited spaces, or any room or building occupied less than 4 hours per day by one individual, therefore the buildings are exempted from the application of any mitigation measure.

2-36