This solicitation is for the construction of Rapid Airfield Damage Recovery Storage Facilities at Aviano Air Base in Italy. The Naval Facilities Engineering Command is seeking bids for P-002 EDI, which involves building storage structures to house equipment for quickly repairing airfield runways and infrastructure after damage. Offerors must submit responses by the date specified in solicitation number N6247022R3000. The facilities will enable rapid recovery of airfield operations at the base through centralized storage of materials and vehicles for repairing runways, taxiways, and other airfield assets damaged by events such as weather or conflict. Construction is to be completed by the date outlined in the final contract to ensure the base's runways can be repaired swiftly following future disruption incidents.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WORK ORDER NO.
At the
PREPARED BY:
Architectural: Mechanical:
Civil: Electrical:
Structural:
APPROVED BY:
Specifications:
For Commander, NAVFAC:
Date:
Submitted By: Date:
10/10/2022
Help Note All fields can be edited. If you have trouble selecting a field, either use the tab key or click "highlight fields" in Acrobat 7. Fields that are not needed can be selected and deleted. Tool tips with "additional field" can be deleted or changed. The contract number can also be deleted or changed.
THIS PAGE INTENTIONALLY LEFT BLANK.
P-002 EDI: Rapid Airfield Damage Recovery Storage Facility 1659896 Aviano, Italy
HAVING PARTICIPATED IN THE DESIGN OF PROJECT No. 1659896, P-002 EDI-RADR
STORAGE, AVIANO AB, ITALY, AND HAVING THOROUGHLY REVIEWED THE COMPLETED
PROJECT DOCUMENTS, I DECLARE THAT THE FACILITY DESIGN INCLUDED HEREIN
COMPLIES WITH ALL APPLICABLE ITALIAN CODES AND LAWS.
DATE SIGNATURE (PROFESSIONAL SEAL)
10 October 2022 Registered Engineer
AVENDO PARTECIPATO ALLO SVILUPPO DEL PROGETTO N. 1659896, P-002 EDI-RADR
STORAGE, AVIANO AB, ITALIA, E AVENDO ESAMINATO ATTENTAMENTE LA DOCUMENTAZIONE
DI PROGETTO PRODOTTA, DICHIARO CHE IL PROGETTO ALLEGATO È CONFORME A TUTTE
LE NORME E LEGGI ITALIANE APPLICABILI.
DATA FIRMA (TIMBRO PROFESSIONALE)
10 October 2022 Registered Engineer
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 02/11, CHG 1: 08/14 LIST OF DRAWINGS
00 73 04 11/17 SUPPLEMENTARY CONDITIONS FOR PROJECTS
IN MEDITERRANEAN AREA
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK
01 14 00 11/11, CHG 13: 08/21 WORK RESTRICTIONS
01 20 00 11/20, CHG 2: 08/21 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 1: 08/21 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 05/17, CHG 6: 02/21 ELECTRONIC CONSTRUCTION AND FACILITY
SUPPORT CONTRACT MANAGEMENT SYSTEM
01 32 17.00 20 05/18, CHG 3: 08/20 COST-LOADED NETWORK ANALYSIS SCHEDULES
(NAS)
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 13 11/20 SPECIAL PROJECT PROCEDURES
01 35 26 11/20, CHG 1: 08/21 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
01 42 15 02/14 METRIC MEASUREMENTS
01 45 00.00 20 11/11, CHG 8: 02/21 QUALITY CONTROL
01 45 23.10 42 11/20 CERTIFICATIONS OF COMPLIANCE WITH
ITALIAN LAWS
01 45 35 11/20 SPECIAL INSPECTIONS
01 50 00 11/20, CHG 1: 08/21 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 11/15, CHG 5: 08/21 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 08/19, CHG 2: 11/20 PROJECT IDENTIFICATION
01 74 19 02/19, CHG 2: 08/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 78 23 08/15, CHG 2: 08/21 OPERATION AND MAINTENANCE DATA
01 78 23.33 08/18, CHG 1: 02/21 OPERATION AND MAINTENANCE MANUALS FOR
AVIATION FUEL SYSTEMS
01 78 24.00 20 02/15, CHG 3: 08/21 FACILITY ELECTRONIC OPERATION AND
MAINTENANCE SUPPORT INFORMATION (eOMSI)
01 91 00.15 20 02/21, CHG 1: 05/21 TOTAL BUILDING COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 05/10, CHG 2: 02/19 DEMOLITION
DIVISION 03 - CONCRETE
03 30 00 02/19, CHG 2: 05/21 CAST-IN-PLACE CONCRETE
03 30 53 05/14 MISCELLANEOUS CAST-IN-PLACE CONCRETE
DIVISION 05 - METALS
05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING
05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS
PROJECT TABLE OF CONTENTS Page 1
05 51 33 02/16, CHG 2: 02/18 METAL LADDERS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 11 13 08/11, CHG 1: 05/17 BITUMINOUS DAMPPROOFING
07 13 53 02/16, CHG 1: 08/17 ELASTOMERIC SHEET WATERPROOFING
07 19 00 05/11, CHG 1: 08/17 WATER REPELLENTS
07 21 13 02/16, CHG 2: 08/20 BOARD AND BLOCK INSULATION
07 21 16 11/11, CHG 4: 08/18 MINERAL FIBER BLANKET INSULATION
07 27 10.00 10 08/19, CHG 1: 02/20 BUILDING AIR BARRIER SYSTEM
07 27 19.01 05/17, CHG 2: 08/20 SELF-ADHERING AIR BARRIERS
07 27 26 05/17, CHG 2: 08/20 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 42 63 05/11, CHG 4: 08/20 FABRICATED WALL PANEL ASSEMBLIES
07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL
07 61 14.00 20 08/16, CHG 1: 08/18 STEEL STANDING SEAM ROOFING
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 33 23 08/20 OVERHEAD COILING DOORS
08 60 45 08/20 TRANSLUCENT PANELS
08 71 00 02/16, CHG 3: 08/20 DOOR HARDWARE
08 91 00 08/20 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR GYPSUM BOARD
09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD
09 30 10 08/20 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 67 23.16 02/21 FUEL RESISTIVE RESINOUS FLOORING,
5-COAT SYSTEM
09 90 00 02/21 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 53 02/15, CHG 1: 05/17 TRAFFIC SIGNAGE
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
DIVISION 13 - SPECIAL CONSTRUCTION
13 48 73 05/20, CHG 1: 08/20 SEISMIC CONTROL FOR MECHANICAL
EQUIPMENT
DIVISION 21 - FIRE SUPPRESSION
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
DIVISION 22 - PLUMBING
22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE
PROJECT TABLE OF CONTENTS Page 2
22 05 48.00 20 04/06, CHG 1: 05/15 MECHANICAL SOUND, VIBRATION, AND
SEISMIC CONTROL
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 03 00.00 20 08/10, CHG 3: 08/18 BASIC MECHANICAL MATERIALS AND METHODS
23 05 15 02/14 COMMON PIPING FOR HVAC
23 05 48.19 05/18, CHG 2: 08/20 SEISMIC BRACING FOR HVAC
23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 08 00.00 20 02/21, CHG 1: 05/21 COMMISSIONING OF MECHANICAL AND
PLUMBING SYSTEMS
23 09 00 02/19, CHG 3: 05/21 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC
AND OTHER BUILDING CONTROL SYSTEMS
23 21 23 08/17 HYDRONIC PUMPS
23 25 00 05/21 CHEMICAL TREATMENT OF WATER FOR
MECHANICAL SYSTEMS
23 30 00 05/20 HVAC AIR DISTRIBUTION
23 81 00 05/18, CHG 1: 02/21 DECENTRALIZED UNITARY HVAC EQUIPMENT
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.01 05/21 CYBERSECURITY FOR HVAC, BAS, CHILLED
WATER CONTROL SYSTEMS
25 05 11.02 05/21 CYBERSECURITY FOR FACILITY-RELATED
FIRE CONTROL MASS NOTIFICATION SYSTEMS
AND EMERGENCY RESPONSE RADIO SYSTEM
25 05 11.03 05/21 CYBERSECURITY FOR FACILITY-RELATED
LIGHTING CONTROL SYSTEMS
25 05 11.04 05/21 CYBERSECURITY FOR FACILITY-RELATED
MISCELLANEOUS CONTROL SYSTEMS
25 08 10 05/21 UTILITY MONITORING AND CONTROL SYSTEM
TESTING
25 10 10 02/19, CHG 1: 05/21 UTILITY MONITORING AND CONTROL SYSTEM
(UMCS) FRONT END AND INTEGRATION
DIVISION 26 - ELECTRICAL
26 05 48.00 10 10/07 SEISMIC PROTECTION FOR ELECTRICAL
EQUIPMENT
26 20 00 08/19, CHG 2: 05/21 INTERIOR DISTRIBUTION SYSTEM
26 27 14.00 20 02/21, CHG 1: 05/21 ELECTRICITY METERING
26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS
UNDER 600 VOLTS
26 31 00 05/15 SOLAR PHOTOVOLTAIC (PV) COMPONENTS
26 41 00 11/13 LIGHTNING PROTECTION SYSTEM
26 51 00 05/20, CHG 1: 05/21 INTERIOR LIGHTING
26 56 00 08/21 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
PROJECT TABLE OF CONTENTS Page 3
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 70 08/20 INTERIOR FIRE ALARM SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 11 00 11/18 CLEARING AND GRUBBING
31 23 00.00 20 02/11, CHG 2: 08/15 EXCAVATION AND FILL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT
32 05 33 08/17 LANDSCAPE ESTABLISHMENT
32 11 23 08/17 AGGREGATE BASE COURSES
32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS
32 13 14.13 08/19 CONCRETE PAVING FOR AIRFIELDS AND
OTHER HEAVY DUTY PAVEMENTS
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS
32 31 13 11/16, CHG 1: 05/17 CHAIN LINK FENCES AND GATES
32 92 19 08/17, CHG 1: 08/21 SEEDING
32 93 00 08/17, CHG 1: 08/21 EXTERIOR PLANTS
32 96 00 08/17, CHG 1: 08/21 TRANSPLANTING EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 11 00 02/18 WATER UTILITY DISTRIBUTION PIPING
33 30 00 05/18 SANITARY SEWERAGE
33 31 23.00 10 08/18 SANITARY SEWER FORCE MAIN PIPING
33 32 16 11/19 PACKAGED UTILITY WASTEWATER PUMPING
STATIONS
33 40 00 02/10, CHG 6: 02/19 STORM DRAINAGE UTILITIES
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 4
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/11, CHG 1: 08/14
PART 1 GENERAL
1.1 SUMMARY
1.2 CONTRACT DRAWINGS
1.3 SUPPLEMENTARY DRAWINGS
1.3.1 Reference Drawings
1.3.2 Boring Logs
1.3.3 Subsurface Data
-- End of Section Table of Contents --
DOCUMENT 00 01 15 Page 1
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/11, CHG 1: 08/14
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
DRAWING NO. NAVFAC DWG
NO.
TITLE
GI001 14121415 TITLE SHEET AND LOCATION MAPS
GI011 14121416 DRAWING INDEX
GI020 14121417 GENERAL AND SITE LEGEND
GI030 14121418 ABBREVIATIONS - SHEET 1
GI031 14121419 ABBREVIATIONS - SHEET 2
GI032 14121420 ABBREVIATIONS - SHEET 3
GI033 14121421 ABBREVIATIONS - SHEET 4
GI034 14121422 ABBREVIATIONS - SHEET 5
GI035 14121423 ABBREVIATIONS - SHEET 6
GI001A 14121424 LIFE SAFETY CODE NARRATIVE
GI002A 14121425 LIFE SAFETY CODE NARRATIVE
GI003A 14121426 LIFE SAFETY CODE NARRATIVE
GI004A 14121427 LIFE SAFETY CODE NARRATIVE
GI005A 14121428 LIFE SAFETY CODE NARRATIVE
GI101A 14121429 CODE COMPLIANCE SITE PLAN
GI102A 14121430 LIFE SAFETY OCCUPANCY CLASSIFICATION PLAN
GI103A 14121431 LIFE SAFETY FLOOR PLAN - AREA 'A'
GI104A 14121432 LIFE SAFETY FLOOR PLAN - AREA 'B'
C-001A 14121433 SITE 1 LEGEND
C-002A 14121434 SITE 1 GENERAL NOTES
C-003A 14121435 HAUL ROUTE
V-101A 14121436 TOPOGRAPHIC SURVEY MAP - SITE 1
VU101A 14121437 UNDERGROUND UTILITIES MAP - SITE 1
B-101A 14121438 SITE 1 - GEOTECHNICAL SURVEY PLAN
B-201A 14121439 BORING LOGS 1/5
B-202A 14121440 BORING LOGS 2/5
B-203A 14121441 BORING LOGS 3/5
B-204A 14121442 BORING LOGS 4/5
B-205A 14121443 BORING LOGS 5/5
CD101A 14121444 SITE 1 DEMOLITION PLAN
DOCUMENT 00 01 15 Page 2
CS101A 14121445 SITE 1 SITE PLAN
CG101A 14121446 SITE 1 GRADING PLAN
CP101A 14121447 SITE 1 PAVEMENT JOINT LAYOUT PLAN
CU101A 14121448 SITE 1 UTILITY PLAN
CK551 14121449 CIVIL DETAILS
CK552 14121450 CIVIL DETAILS
ES101A 14121451 P-002 RADR SITE 1 ELECTRICAL POWER SITE PLAN
ES102A 14121452 P-002 RADR SITE 1 ELECTRICAL LIGHTING SITE
ES103A 14121453 P-002 RADR SITE 1 - ELECTRICAL SITE
REFERENCE PHOTOS
TS101A 14121454 P-002 RADR SITE 1 TELECOM SITE PLAN
LD101A 14121455 EXISTING CONDITIONS AND DEMOLITIONS SITE PLAN
LS102A 14121456 DESIGN SITE AND PLANTING PLAN
LK501A 14121457 PLANT MATERIALS SCHEDULE AND DETAILS
S-001A 14121458 GENERAL NOTES 1/2
S-002A 14121459 GENERAL NOTES 2/2
SB101A 14121460 OVERALL FOUNDATION PLAN
SB102A 14121461 FOUNDATION PLAN - AREA A
SB103A 14121462 FOUNDATION PLAN - AREA B
SB104A 14121463 SLAB ON GRADE PLAN
SB201A 14121464 ELEVATION ON AXIS A AND E
SB202A 14121465 ELEVATION ON AXIS 1 AND 9
SF101A 14121466 OVERALL ROOF FRAMING PLAN
SF102A 14121467 ROOF FRAMING PLAN - AREA A
SF103A 14121468 ROOF FRAMING PLAN - AREA B
SF104A 14121469 STRUCTURAL SCHEME
SF301A 14121470 SECTIONS
SF401A 14121471 SERVICE AREA PLANS AND SECTIONS
SR301A 14121472 FOUNDATION REINFORCEMENT 1/2
SR302A 14121473 FOUNDATION REINFORCEMENT 2/2
SR303A 14121474 SERVICE AREA WALLS' REINFORCEMENT
SR304A 14121475 SERVICE AREA SLAB REINFORCEMENT
SK551 14121476 TYPICAL FOUNDATIONS REINFORCEMENT'S DETAILS
SK552 14121477 SLAB ON GRADE DETAILS
SK553 14121478 MISCELLANEOUS REINFORCEMENT DETAILS
SK554 14121479 TYPICAL PERIMETRAL DETAILS
SK555 14121480 BASE PLATE DETAIL
SK556 14121481 STEEL JOINTS DETAILS 1/3
SK557 14121482 STEEL JOINTS DETAILS 2/3
SK558 14121483 STEEL JOINTS DETAILS 3/3
SK559 14121484 CONNECTIONS DETAILS 1/2
SK560 14121485 CONNECTIONS DETAILS 2/2
SK561 14121486 FACADE FRAMING DETAILS 1/3
SK562 14121487 FACADE FRAMING DETAILS 2/3
SK563 14121488 FACADE FRAMING DETAILS 3/3
SK564 14121489 FACADE FRAMING BASE CONNECTION
SK565 14121490 FACADE FRAMING CONNECTIONS 1/2
SK566 14121491 FACADE FRAMING CONNECTIONS 2/2
DOCUMENT 00 01 15 Page 3
SK567 14121492 MISCELLANEOUS DETAILS
SK568 14121493 FALL PROTECTION SYSTEM CONNECTIONS 1/2
SK569 14121494 FALL PROTECTION SYSTEM CONNECTIONS 2/2
AE101A 14121495 OVERALL GROUND FLOOR PLAN
AE102A 14121496 GROUND FLOOR PLAN - AREA 'A'
AE103A 14121497 GROUND FLOOR PLAN - AREA 'B'
AE104A 14121498 FINISH PLAN AND SCHEDULE
AE111A 14121499 REFLECTED CEILING PLAN - AREA A
AE112A 14121500 REFLECTED CEILING PLAN - AREA B
AE121A 14121501 ROOF PLAN
AE131A 14121502 AIR BARRIER PLAN AND SECTION
AE201A 14121503 EXTERIOR ELEVATIONS
AE202A 14121504 EXTERIOR ELEVATIONS
AE301A 14121505 BUILDING SECTIONS
AE302A 14121506 WALL SECTIONS
AE401A 14121507 ENLARGED PLAN - RESTROOM
AE601A 14121508 DOOR SCHEDULE
AJ101A 14121509 ROOF PLAN - FALL PROTECTION SYSTEM
AK551 14121510 INTERIOR WALL TYPES
AK552 14121511 EXTERIOR WALL DETAILS
AK553 14121512 EXTERIOR WALL DETAILS
AK554 14121513 ROOF DETAILS
AK555 14121514 OPENING DETAILS
AK556 14121515 MISCELLANEOUS DETAILS
AK557 14121516 SIGNAGE DETAILS
FA001A 14121517 FIRE ALARM GENERAL NOTES, LEGEND, AND
FA101A 14121518 FIRE ALARM AUDIBILITY PLAN
FA102A 14121519 FIRE ALARM PLAN - AREA 'A'
FA103A 14121520 FIRE ALARM PLAN - AREA 'B'
FX001A 14121521 FIRE SUPPRESSION GENERAL NOTES
FX101A 14121522 FIRE SUPPRESSION HAZARD CLASSIFICATION PLAN
FX301A 14121523 FIRE SUPPRESSION SECTIONS
P-001 14121524 PIPING AND INSTRUMENTATION DIAGRAM LEGEND
PL101A 14121525 HEAVY FIRST FLOOR OVERALL PLUMBING PLAN
PL401A 14121526 HEAVY RESTROOM ENLARGED PLUMBING PLAN
PL501A 14121527 HEAVY PLUMBING DETAIL - SHEET 1
PL502A 14121528 HEAVY PLUMBING DETAIL - SHEET 2
PL601A 14121529 HEAVY REPAIR PLUMBING SCHEDULES
PL901A 14121530 HEAVY PLUMBING ISOMETRICS
M-001 14121531 MECHANICAL HVAC LEGEND
MH101A 14121532 HEAVY REPAIR HVAC ZONE PLAN
MH102A 14121533 HEAVY REPAIR HVAC PIPING PLAN
MH111A 14121534 HEAVY REPAIR HVAC DUCT PLAN
MH401A 14121535 HEAVY ENLARGED PLAN MECH ROOM
MH501A 14121536 MECHANICAL DETAILS - SHEET 1
MH502A 14121537 MECHANICAL DETAILS - SHEET 2
MH503A 14121538 MECHANICAL DETAILS - SHEET 3
MH504A 14121539 MECHANICAL DETAILS - SHEET 4
DOCUMENT 00 01 15 Page 4
MH505A 14121540 MECHANICAL DETAILS - SHEET 5
MH506A 14121541 MECHANICAL DETAILS - SHEET 6
MH507A 14121542 MECHANICAL DETAILS - SHEET 7
MH508A 14121543 MECHANICAL DETAILS - SHEET 8
MH509A 14121544 MECHANICAL DETAILS - SHEET 9
MH510A 14121545 MECHANICAL DETAILS - SHEET 10
MH511A 14121546 MECHANICAL DETAILS - SHEET 11
MH512A 14121547 MECHANICAL DETAILS - SHEET 12
MH601A 14121548 HEAVY REPAIR MECHANICAL SCHEDULES SHEET 1
MH602A 14121549 HEAVY REPAIR MECHANICAL SCHEDULES SHEET 2
MH603A 14121550 HEAVY REPAIR MECHANICAL SCHEDULES SHEET 3
MH604A 14121551 HEAVY REPAIR MECHANICAL SCHEDULES SHEET 4
MH605A 14121552 HEAVY REPAIR MECHANICAL SCHEDULES SHEET 5
MH606A 14121553 HEAVY REPAIR MECHANICAL SCHEDULES SHEET 6
MH607A 14121554 HEAVY REPAIR MECHANICAL SCHEDULES SHEET 7
MH701A 14121555 AHU CONTROL SCHEMATIC AND SEQUENCE OF
OPERATION
MH702A 14121556 AHU CONTROL SCHEMATIC AND SEQUENCE OF
OPERATION
MH703A 14121557 HEATING SYSTEM CONTROL SCHEMATIC AND
SEQUENCE OF CONTROL
MH704A 14121558 TYPCIAL MINI-SPLIT HEAT PUMP CONTROL
SCHEMATIC, POINTS LIST AND SEQUENCE OF
OPERATION
MH705A 14121559 MISC. CONTROL SCHEMATIC, POINTS LISTS AND
SEQUENCE OF OPERATION
MH706A 14121560 DDC ARCHITECTURAL DIAGRAM
MH901A 14121561 HEAVY HEATING WATER ISOMETRIC
E-001 14121562 ELECTRICAL LEGEND - SHEET 1
E-002 14121563 ELECTRICAL LEGEND - SHEET 2
EJ101A 14121564 GROUNDING PLAN - OVERALL
EJ102A 14121565 GROUNDING PLAN - AREA 'A'
EJ103A 14121566 GROUNDING PLAN - AREA 'B'
EJ110A 14121567 LIGHTNING PROTECTION PLAN
EL101A 14121568 LIGHTING PLAN - OVERALL
EL102A 14121569 LIGHTING PLAN - AREA 'A'
EL103A 14121570 LIGHTING PLAN - AREA 'B'
EL401A 14121571 ENLARGED LIGHTING PLANS
EP101A 14121572 POWER PLAN - OVERALL
EP102A 14121573 POWER PLAN - AREA 'A'
EP103A 14121574 POWER PLAN - AREA 'B'
EP110A 14121575 ROOF POWER PLAN
EP401A 14121576 ENLARGED POWER PLANS
EP601A 14121577 AC ONELINE DIAGRAM
EP602A 14121578 PANEL SCHEDULES - MDP
EP603A 14121579 PANEL SCHEDULES - PP1
DOCUMENT 00 01 15 Page 5
EP604A 14121580 PANEL SCHEDULES - PP2
EP605A 14121581 PANEL SCHEDULES - LP1
EP606A 14121582 PANEL SCHEDULES - RP1
EP607A 14121583 PANEL SCHEDULES - RP2
EP608A 14121584 DC ONELINE DIAGRAM
EK551 14121585 ELECTRICAL DETAILS - SHEET 1
EK552 14121586 ELECTRICAL DETAILS - SHEET 2
EK553 14121587 ELECTRICAL DETAILS - SHEET 3
EK554 14121588 ELECTRICAL DETAILS - SHEET 4
EK555 14121589 ELECTRICAL DETAILS - SHEET 5
EK556 14121590 ELECTRICAL DETAILS - SHEET 6
EK557 14121591 ELECTRICAL DETAILS - SHEET 7
EK558 14121592 ELECTRICAL DETAILS - SHEET 8
EK559 14121593 ELECTRICAL DETAILS - SHEET 9
EK570 14121594 ELECTRICAL LIGHTING DETAILS - SHEET 1
EK571 14121595 ELECTRICAL LIGHTING DETAILS - SHEET 2
EK572 14121596 ELECTRICAL LIGHTING DETAILS - SHEET 3
EK573 14121597 ELECTRICAL LIGHTING DETAILS - SHEET 4
EK574 14121598 ELECTRICAL LIGHTING DETAILS - SHEET 5
EK575 14121599 ELECTRICAL LIGHTING DETAILS - SHEET 6
EK576 14121600 ELECTRICAL LIGHTING DETAILS - SHEET 7
EK651 14121601 LIGHT FIXTURE SCHEDULE
T-001 14121602 TELECOMMUNICATIONS LEGEND
TP101A 14121603 TELECOM GROUND FLOOR PLAN
TP401A 14121604 ENLARGED TELECOM ROOM PLAN
TR601A 14121605 TELECOMMUNICATIONS OSP RISER DIAGRAM
TR602A 14121606 TELECOMMUNICATIONS RISER DIAGRAM
TK551 14121607 TELECOM DETAILS SHEET 1
TK552 14121608 TELECOM DETAILS SHEET 2
TK553 14121609 TELECOM DETAILS SHEET 3
TK554 14121610 TELECOM DETAILS SHEET 4
DRAWING NO. NAVFAC DWG
NO.
TITLE
GI001 14121611 TITLE SHEET AND LOCATION MAPS
GI011 14121612 DRAWING INDEX
GI020 14121613 GENERAL AND SITE LEGEND
GI030 14121614 ABBREVIATIONS - SHEET 1
GI031 14121615 ABBREVIATIONS - SHEET 2
GI032 14121616 ABBREVIATIONS - SHEET 3
GI033 14121617 ABBREVIATIONS - SHEET 4
DOCUMENT 00 01 15 Page 6
GI034 14121618 ABBREVIATIONS - SHEET 5
GI035 14121619 ABBREVIATIONS - SHEET 6
GI001B 14121620 LIFE SAFETY CODE NARRATIVE
GI002B 14121621 LIFE SAFETY CODE NARRATIVE
GI003B 14121622 LIFE SAFETY CODE NARRATIVE
GI004B 14121623 LIFE SAFETY CODE NARRATIVE
GI005B 14121624 LIFE SAFETY CODE NARRATIVE
GI101B 14121625 CODE COMPLIANCE SITE PLAN
GI102B 14121626 LIFE SAFETY OCCUPANCY CLASSIFICATION PLAN
GI103B 14121627 LIFE SAFETY FLOOR PLAN - AREA 'A'
GI104B 14121628 LIFE SAFETY FLOOR PLAN - AREA 'B'
GI105B 14121629 LIFE SAFETY FLOOR PLAN - AREA 'C'
GI106B 14121630 LIFE SAFETY FLOOR PLAN - AREA 'D'
C-001B 14121631 SITE 2 LEGEND
C-002B 14121632 SITE 2 GENERAL NOTES
C-003B 14121633 HAUL ROUTE
V-101B 14121634 TOPOGRAPHIC SURVEY MAP - SITE 2
VU101B 14121635 UNDERGROUND UTILITIES MAP - SITE 2
B-101B 14121636 SITE 2 - GEOTECHNICAL SURVEY PLAN
B-201B 14121637 BORING LOGS 1/6
B-202B 14121638 BORING LOGS 2/6
B-203B 14121639 BORING LOGS 3/6
B-204B 14121640 BORING LOGS 4/6
B-205B 14121641 BORING LOGS 5/6
B-206B 14121642 BORING LOGS 6/6
CD101B 14121643 SITE 2 DEMOLITION PLAN (1 OF 2)
CD102B 14121644 SITE 2 DEMOLITION PLAN (2 OF 2)
CS101B 14121645 SITE 2 SITE PLAN (1 OF 2)
CS102B 14121646 SITE 2 SITE PLAN (2 OF 2)
CG101B 14121647 SITE 2 GRADING PLAN (1 OF 2)
CG102B 14121648 SITE 2 GRADING PLAN (2 OF 2)
CP101B 14121649 SITE 2 PAVEMENT JOINT LAYOUT
CU101B 14121650 SITE 2 UTILITY PLAN (1 OF 2)
CU102B 14121651 SITE 2 UTILITY PLAN (2 OF 2)
CK551 14121652 CIVIL DETAILS
CK552 14121653 CIVIL DETAILS
CK553B 14121654 SITE 2 PUMP STATION DETAILS (1 FOF 2)
CK554B 14121655 SITE 2 PUMP STATION DETAILS (2 FOF 2)
ES101B 14121656 P-002 RADR SITE 2 ELECTRICAL SITE DEMOLITION
PLAN
ES102B 14121657 ELECTRICAL POWER SITE PLAN
ES103B 14121658 ELECTRICAL LIGHTING SITE PLAN NORTH
ES104B 14121659 ELECTRICAL LIGHTING SITE PLAN SOUTH
ES105B 14121660 P-002 RADR SITE 2 - ELECTRICAL SITE
REFERENCE PHOTOS
TS101B 14121661 P-002 RADR SITE 2 TELECOM SITE DEMOLITION
TS102B 14121662 P-002 RADR SITE 2 TELECOM SITE PLAN
L-101B 14121663 OVERALL SITE PLAN
DOCUMENT 00 01 15 Page 7
LD102B 14121664 EXISTING CONDITIONS AND DEMOLITIONS SITE
PLAN - NORTH AREA
LD103B 14121665 EXISTING CONDITIONS AND DEMOLITIONS SITE
PLAN - SOUTH AREA
LS104B 14121666 DESIGN SITE AND PLANTING PLAN - NORTH AREA
LS105B 14121667 DESIGN SITE AND PLANTING PLAN - SOUTH AREA
LK501B 14121668 PLANT MATERIALS SCHEDULE AND DETAILS
S-001B 14121669 GENERAL NOTES 1/2
S-002B 14121670 GENERAL NOTES 2/2
SB101B 14121671 OVERALL FOUNDATION PLAN
SB102B 14121672 FOUNDATION PLAN - AREA A
SB103B 14121673 FOUNDATION PLAN - AREA B
SB104B 14121674 FOUNDATION PLAN - AREA C
SB105B 14121675 FOUNDATION PLAN - AREA D
SB106B 14121676 SLAB ON GRADE PLAN
SB201B 14121677 ELEVATION ON AXIS A AND G
SB202B 14121678 ELEVATION ON AXIS 1 AND 9
SF101B 14121679 OVERALL ROOF FRAMING PLAN
SF102B 14121680 ROOF FRAMING - AREA A
SF103B 14121681 ROOF FRAMING - AREA B
SF104B 14121682 ROOF FRAMING - AREA C
SF105B 14121683 ROOF FRAMING - AREA D
SF106B 14121684 STRUCTURAL SCHEME
SF301B 14121685 SECTIONS 1/2
SF302B 14121686 SECTIONS 2/2
SF401B 14121687 SERVICE AREA PLANS AND SECTIONS
SR301B 14121688 FOUNDATION REINFORCEMENT 1/3
SR302B 14121689 FOUNDATION REINFORCEMENT 2/3
SR303B 14121690 FOUNDATION REINFORCEMENT 3/3
SR304B 14121691 SERVICE AREA WALLS' REINFORCEMENT
SR305B 14121692 SERVICE AREA SLAB REINFORCEMENT
SK551 14121693 TYPICAL FOUNDATIONS REINFORCEMENT DETAILS
SK552 14121694 SLAB ON GRADE DETAILS
SK553 14121695 WALLS REINFORCEMENT SERVICE BLDG
SK554 14121696 TYPICAL PERIMETRAL DETAILS
SK555 14121697 BASE PLATE DETAILS
SK556 14121698 STEEL JOINTS DETAILS 1/3
SK557 14121699 STEEL JOINTS DETAILS 2/3
SK558 14121700 STEEL JOINTS DETAILS 3/3
SK559 14121701 CONNECTIONS DETAILS 1/2
SK560 14121702 CONNECTIONS DETAILS 2/2
SK561 14121703 FACADE FRAMING DETAILS 1/3
SK562 14121704 FACADE FRAMING DETAILS 2/3
SK563 14121705 FECADE FRAMING DETAILS 3/3
SK564 14121706 FACADE FRAMING BASE CONNECTIONS
SK565 14121707 FACADE FRAMING CONNECTIONS 1/2
DOCUMENT 00 01 15 Page 8
SK566 14121708 FACADE FRAMING CONNECTIONS 2/2
SK567 14121709 MISCELLANEOUS DETAILS
SK568 14121710 FALL PROTECTION SYSTEM CONNECTIONS 1/2
SK569 14121711 FALL PROTECTION SYSTEM CONNECTIONS 2/2
SK570 14121712 LIFT STATION FRAMING PLANS AND REINFORCEMENT
SK571 14121713 SECTIONS
SK572 14121714 REINFORCEMENT DETAILS
SK573 14121715 LASERPAD - PLAN, SECTION AND DETAILS
AE101B 14121716 OVERALL GROUND FLOOR PLAN
AE102B 14121717 GROUND FLOOR PLAN - AREA 'A'
AE103B 14121718 GROUND FLOOR PLAN - AREA 'B'
AE104B 14121719 GROUND FLOOR PLAN - AREA 'C'
AE105B 14121720 GROUND FLOOR PLAN - AREA 'D'
AE106B 14121721 FINISH PLAN AND SCHEDULE
AE111B 14121722 REFLECTED CEILING PLAN
AE121B 14121723 ROOF PLAN
AE131B 14121724 AIR BARRIER PLAN AND SECTION
AE201B 14121725 EXTERIOR BUILDING ELEVATIONS
AE202B 14121726 EXTERIOR BUILDING ELEVATIONS
AE301B 14121727 BUILDING SECTIONS
AE302B 14121728 WALL SECTIONS
AE401B 14121729 ENLARGED PLAN - RESTROOM
AE601B 14121730 DOOR SCHEDULE
AJ101B 14121731 ROOF PLAN - FALL PROTECTION SYSTEM
AK551 14121732 INTERIOR WALL TYPES
AK552 14121733 EXTERIOR WALL DETAILS
AK553 14121734 EXTERIOR WALL DETAILS
AK554 14121735 ROOF DETAILS
AK555 14121736 OPENING DETAILS
AK556 14121737 MISCELLANEOUS DETAILS
AK557 14121738 SIGNAGE DETAILS
FA001B 14121739 FIRE ALARM GENERAL NOTES, LEGEND, AND
FA101B 14121740 FIRE ALARM AUDIBILITY PLAN
FA102B 14121741 FIRE ALARM PLAN - AREA 'A'
FA103B 14121742 FIRE ALARM PLAN - AREA 'B'
FA104B 14121743 FIRE ALARM PLAN - AREA 'C'
FA105B 14121744 FIRE ALARM PLAN - AREA 'D'
FX001B 14121745 FIRE SUPPRESSION GENERAL NOTES
FX101B 14121746 FIRE SUPPRESSION HAZARD CLASSIFICATION PLAN
FX301B 14121747 FIRE SUPPRESSION SECTIONS
P-001 14121748 PIPING AND INSTRUMENTATION DIAGRAM LEGEND
PL101B 14121749 ZULU FIRST FLOOR OVERALL PLUMBING PLAN
PL401B 14121750 ZULU ENLARGED RESTROOM PLUMBING PLAN
PL501B 14121751 ZULU PLUMBING DETAIL - SHEET 1
PL502B 14121752 ZULU PLUMBING DETAIL - SHEET 2
PL601B 14121753 ZULU LOOP PLUMBING SCHEDULES
PL901B 14121754 ZULU PLUMBING ISOMETRICS
341 14121755 MECHANICAL HVAC LEGEND
DOCUMENT 00 01 15 Page 9
MH101B 14121756 ZULU HVAC ZONE PLAN
MH102B 14121757 ZULU HVAC PIPING PLAN
MH111B 14121758 ZULU HVAC DUCT PLAN
MH401B 14121759 ZULU ENLARGED PLAN MECH ROOM
MH501B 14121760 MECHANICAL DETAILS - SHEET 1
MH502B 14121761 MECHANICAL DETAILS - SHEET 2
MH503B 14121762 MECHANICAL DETAILS - SHEET 3
MH504B 14121763 MECHANICAL DETAILS - SHEET 4
MH505B 14121764 MECHANICAL DETAILS - SHEET 5
MH506B 14121765 MECHANICAL DETAILS - SHEET 6
MH507B 14121766 MECHANICAL DETAILS - SHEET 7
MH508B 14121767 MECHANICAL DETAILS - SHEET 8
MH509B 14121768 MECHANICAL DETAILS - SHEET 9
MH510B 14121769 MECHANICAL DETAILS - SHEET 10
MH511B 14121770 MECHANICAL DETAILS - SHEET 11
MH512B 14121771 MECHANICAL DETAILS - SHEET 12
MH601B 14121772 ZULU MECHANICAL SCHEDULES SHEET 1
MH602B 14121773 ZULU MECHANICAL SCHEDULES SHEET 2
MH603B 14121774 ZULU MECHANICAL SCHEDULES SHEET 3
MH604B 14121775 ZULU MECHANICAL SCHEDULES SHEET 4
MH605B 14121776 ZULU MECHANICAL SCHEDULES SHEET 5
MH606B 14121777 ZULU MECHANICAL SCHEDULES SHEET 6
MH607B 14121778 ZULU MECHANICAL SCHEDULES SHEET 7
MH701B 14121779 AHU CONTROL SCHEMATIC AND SEQUENCE OF
OPERATION
MH702B 14121780 AHU CONTROL SCHEMATIC AND SEQUENCE OF
OPERATION
MH703B 14121781 HEATING SYSTEM CONTROL SCHEMATIC AND
SEQUENCE OF CONTROL
MH704B 14121782 TYP. MINI-SPLIT HEAT PUMP CONTROL SCHEMATIC,
POINTS LIST AND SEQ. OF OPERATION
MH705B 14121783 MISC. CONTROL SCHEMATIC, POINTS LISTS AND
SEQUENCE OF OPERATION
MH706B 14121784 DDC ARCHITECTURAL DIAGRAM
MH901B 14121785 ZULU HEATING WATER ISOMETRIC
E-001 14121786 ELECTRICAL LEGEND - SHEET 1
E-002 14121787 ELECTRICAL LEGEND - SHEET 2
EJ101B 14121788 GROUNDING PLAN - OVERALL
EJ102B 14121789 GROUNDING PLAN - AREA 'A'
EJ103B 14121790 GROUNDING PLAN - AREA 'B'
EJ104B 14121791 GROUNDING PLAN - AREA 'C'
EJ105B 14121792 GROUNDING PLAN - AREA 'D'
EJ110B 14121793 LIGHTNING PROTECTION PLAN
EL101B 14121794 LIGHTING PLAN - OVERALL
EL102B 14121795 LIGHTING PLAN - AREA 'A'
DOCUMENT 00 01 15 Page 10
EL103B 14121796 LIGHTING PLAN - AREA 'B'
EL104B 14121797 LIGHTING PLAN - AREA 'C'
EL105B 14121798 LIGHTING PLAN - AREA 'D'
EL401B 14121799 ENLARGED LIGHTING PLANS
EP101B 14121800 POWER PLAN - OVERALL
EP102B 14121801 POWER PLAN - AREA 'A'
EP103B 14121802 POWER PLAN - AREA 'B'
EP104B 14121803 POWER PLAN - AREA 'C'
EP105B 14121804 POWER PLAN - AREA 'D'
EP110B 14121805 ROOF POWER PLAN
EP401B 14121806 ENLARGED POWER PLANS
EP601B 14121807 AC ONELINE DIAGRAM
EP602B 14121808 PANEL SCHEDULES - MDP
EP603B 14121809 PANEL SCHEDULES - PP1
EP604B 14121810 PANEL SCHEDULES - PP2
EP605B 14121811 PANEL SCHEDULES - LP1
EP606B 14121812 PANEL SCHEDULES - RP1
EP607B 14121813 PANEL SCHEDULES - RP2
EP608B 14121814 DC ONELINE DIAGRAM
EK551 14121815 ELECTRICAL DETAILS - SHEET 1
EK552 14121816 ELECTRICAL DETAILS - SHEET 2
EK553 14121817 ELECTRICAL DETAILS - SHEET 3
EK554 14121818 ELECTRICAL DETAILS - SHEET 4
EK555 14121819 ELECTRICAL DETAILS - SHEET 5
EK556 14121820 ELECTRICAL DETAILS - SHEET 6
EK557 14121821 ELECTRICAL DETAILS - SHEET 7
EK558 14121822 ELECTRICAL DETAILS - SHEET 8
EK559 14121823 ELECTRICAL DETAILS - SHEET 9
EK570 14121824 ELECTRICAL LIGHTING DETAILS - SHEET 1
EK571 14121825 ELECTRICAL LIGHTING DETAILS - SHEET 2
EK572 14121826 ELECTRICAL LIGHTING DETAILS - SHEET 3
EK573 14121827 ELECTRICAL LIGHTING DETAILS - SHEET 4
EK574 14121828 ELECTRICAL LIGHTING DETAILS - SHEET 5
EK575 14121829 ELECTRICAL LIGHTING DETAILS - SHEET 6
EK576 14121830 ELECTRICAL LIGHTING DETAILS - SHEET 7
EK651 14121831 LIGHT FIXTURE SCHEDULE
T-001 14121832 TELECOMMUNICATIONS LEGEND
TP101B 14121833 TELECOM GROUND FLOOR PLAN
TP401B 14121834 ENLARGED TELECOM ROOM PLAN
TR601B 14121835 TELECOMMUNICATIONS OSP RISER DIAGRAM
TR602B 14121836 TELECOMMUNICATIONS RISER DIAGRAM
TK501 14121837 CABLE SCHEDULES - SHEET 1
TK502 14121838 CABLE SCHEDULES - SHEET 2
TK551 14121839 TELECOM DETAILS SHEET 1
TK552 14121840 TELECOM DETAILS SHEET 2
TK553 14121841 TELECOM DETAILS SHEET 3
TK554 14121842 TELECOM DETAILS SHEET 4
DOCUMENT 00 01 15 Page 11
TK555 14121843 TELECOM DETAILS SHEET 5
1.3 SUPPLEMENTARY DRAWINGS
These supplementary drawings may not be a part of the contract but are included with the drawings for information.
1.3.1 Reference Drawings
The following reference drawings are intended only to show the original construction. Drawings are the property of the Government and shall not be used for any purpose other than that intended by the contract. Information on procuring these full-size drawings may be obtained from the Contracting Officer.
NAVFAC DWG NO. TITLE
NOT ASSIGNED SUBSTATION 23/1065 EQUIPMENT PLAN, GROUNDING PLAN
NOT ASSIGNED LOW VOLTAGE SWITCHGEAR SUBSTATION 23/1065 SWITCHBOARD
FRONT
NOT ASSIGNED LOW VOLTAGE SWITCHGEAR SUBSTATION 23/1065 SWITCHBOARD
FOUNDATION AND DETAILS OF FIXING TO THE FLOOR
NOT ASSIGNED LOW VOLTAGE SWITCHGEAR SUBSTATION 22/1064 230V SINGLE
LINE DIAGRAM
NOT ASSIGNED SUBSTATION 12A/78702 EQUIPMENT PLAN, GROUNDING PLAN
NOT ASSIGNED LOW VOLTAGE SWITCHBOARD SUBSTATION 12A/78702 SINGLE
LINE DIAGRAM
NOT ASSIGNED LOW VOLTAGE SWITCHBOARD SUBSTATION 12A/78702
SWITCHBOARD FRONT
NOT ASSIGNED LOW VOLTAGE SWITCHBOARD SUBSTATION 12A/78702
SWITCHBOARD FOUNDATION AND DETAILS OF FIXING TO THE
FLOOR
1.3.2 Boring Logs
The Government does not guarantee that borings indicate actual conditions, except for the exact locations and the time that they were made.
DOCUMENT 00 01 15 Page 12
1.3.3 Subsurface Data
Subsurface data, not specified or indicated, have been obtained by the Government at the station. The soils report is included as part of the solicitation.
-- End of Document --
DOCUMENT 00 01 15 Page 13
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
DOCUMENT 00 73 04
SUPPLEMENTARY CONDITIONS FOR PROJECTS IN MEDITERRANEAN AREA
11/17
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 LEGAL HOLIDAYS
1.4 ENGLISH SPEAKING REPRESENTATIVE
1.5 NORMS AND LAWS
1.6 INDUSTRY STANDARDS
1.7 PROPRIETARY NAMES
1.8 VALUE-ADDED TAX AND EXCISE TAX
1.9 ORAL MODIFICATION
1.10 NO WAIVER BY GOVERNMENT
1.11 PRODUCTS SPECIFIED USING USA STANDARDS
1.11.1 Local Products Specified Using United States of America (USA)
Standards
1.11.2 USA Manufactured Products Specified Using USA Standards
1.12 SECURITY REQUIREMENTS
1.12.1 Contractor Employee Base Access Pass:
1.12.2 Responsibility for Physical Security
1.12.3 Access to Operational Areas
1.12.4 Employment
1.12.5 Compliance
1.13 ANTI-MAFIA LAW
1.13.1 Pre-Award Effect of Anti-Mafia Procedures
1.13.2 Termination Under Italian Law No. 646 (Anti-Mafia)
1.13.3 Application of Italian Law No. 646 (Anti-Mafia) to
Subcontractors
1.13.4 Documentation Requirements
1.14 CERTIFICATION OF COMPLIANCE WITH ITALIAN LAWS
1.14.1 Certification
1.14.2 Static Load and Final Testing
1.14.3 Other Tests
1.15 CULTURAL RESOURCES
1.16 UNEXPLODED ORDNANCE
1.17 SECURITY REQUIREMENTS
PART 2 PRODUCTS
PART 3 EXECUTION
DOCUMENT 00 73 04 Page 1
DOCUMENT 00 73 04
SUPPLEMENTARY CONDITIONS FOR PROJECTS IN MEDITERRANEAN AREA
11/17
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ITALIAN LAWS AND DECREES (D.M.)
LAW No. 1086 (May 11, 1971) Norms for Works in Reinforced Concrete and Steel and Application Instructions
Law No. 373 (April 30, 1976) Norms for the containment of energy consumption for thermal uses in buildings.
Law No. 46 (March 5, 1990) Safety Norms for Technological Systems
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Request for Contractor Employee Base Access Pass; G
Chamber of Commerce Certificate of Membership; G
Family Status and Residency Certificate; G
SD-11 Closeout Submittals
Certified credentials of proposed testing personnel; G
Certification of the static load tests results; G
Certification of actual testing personnel; G
Certificate of conformity for electrical system; G
Certificate of compliance for heating system; G
Certificate of compliance for fire prevention system; G
Proof of IMD ordnance work authorization; G
DOCUMENT 00 73 04 Page 2
1.3 LEGAL HOLIDAYS
For information purpose, the following Italian holidays are observed:
January 1 New Year's Day January 6 Epiphany Variable Easter Variable Easter Monday (Monday after Easter Sunday) April 25 Liberation Day May 1 Labour Day June 2 Republic Day August 15 Feast of Assumption (Ferragosto) November 1 All Saints' Day December 8 Feast of Immaculate Conception December 25 Christmas Day December 26 Saint Stephen's Day
1.4 ENGLISH SPEAKING REPRESENTATIVE
At all times when any performance of the work at the site is being conducted by any employee of the Contractor or his subcontractors, the Contractor shall have a representative present on the site who is capable of explaining the work operations and receiving instructions in the English language. The Contracting Officer shall have the right to determine without appeal of such decision, whether the proposed representative has sufficient technical and lingual capabilities and the Contractor shall immediately replace any individual not acceptable to the Contracting Officer. The Construction Contractor's qualified Project Manager, on-site Superintendent, Quality Control Manager, and Quality Control Specialist shall be fluent (can read, speak, and write) in both English and Italian languages.
1.5 NORMS AND LAWS
In case of differences between project specifications or the accompanying drawings and referenced norms and laws, norms and laws shall govern. In case of differences between project specifications and the accompanying drawings, the specifications shall govern.
1.6 INDUSTRY STANDARDS
When both U.S. and European, or Italian, Industry Standards are applicable to this project and the standards are in conflict with each other, the most stringent of the industry shall govern.
1.7 PROPRIETARY NAMES
Manufacturer's proprietary names indicated for colors, textures and patterns of materials are for the purpose of color, texture and pattern selection only. Other manufacturers materials are acceptable and provided they closely approximate colors, textures and patterns indicated and provided they conform to all other requirements subject to Contracting Officer's approval.
1.8 VALUE-ADDED TAX AND EXCISE TAX
Where qualifications or experience requirements are set forth in the specifications with respect to equipment and equipment installers, written proof of such qualifications or experience must be provided within thirty
DOCUMENT 00 73 04 Page 3
(30) calendar days after Contract award, and before placing any order for such equipment or before dispatching equipment installers to the project site. Value-added tax for articles and services acquired by Contractors acting for or on behalf of the United States forces shall be reimbursed in accordance with Italy laws and regulations. Reimbursement of taxes paid shall be received by completing an Application for VAT reimbursement. Such form shall be validated by United States forces authorities and presented to an appropriate Italian fiscal authority, which shall certify it.
Excise tax for articles and services acquired by Contractors acting for or on behalf of the United States forces is either not to be collected or to be reimbursed by the appropriate Italian fiscal authority.
1.9 ORAL MODIFICATION
No oral statement of any person other than the Contracting Officer as provided in the clause in this Contract entitled FAR 52.243-4 "Changes" (AUG 1987), shall in any manner or degree modify or otherwise affect the terms of this Contract.
1.10 NO WAIVER BY GOVERNMENT
The failure of the Government, in any one or more instances, to insist upon the strict performance of any of the terms of this Contract or to exercise any option herein conferred shall not be construed as a waiver or relinquishment to any extent of the right to assert or rely upon such terms or option on any future occasion.
1.11 PRODUCTS SPECIFIED USING USA STANDARDS
1.11.1 Local Products Specified Using United States of America (USA) Standards
There are locally available products specified in this contract that meet USA standards. "Locally available products that meet USA standards" are defined as:
a. "Products that meet the referenced USA standards, and are manufactured and distributed in-country, or manufactured and distributed in the European Union, and are readily available locally from in-country sources or from the European Union sources"; or
b. "Products manufactured in the USA and distributed in-country or in the European Union or in the USA, and are readily available locally from in-country sources or from the European Union sources, or from USA sources."
The products are specified in the technical sections listed below:
1.11.2 USA Manufactured Products Specified Using USA Standards
There are products to be provided in this contract that are not readily available locally and must be manufactured in the United States of America (USA) and in compliance with USA standards. Products manufactured in another country are considered USA manufactured, if the manufacturers or suppliers are under license by USA manufacturers and the products meet the same applicable specifications and standards. The products are specified in the technical sections listed below:
DOCUMENT 00 73 04 Page 4
1.12 SECURITY REQUIREMENTS
Contractors and employees who require base access will be required to maintain a NATO Restricted security classification.
A Contractor or employee outside of the European Economic Area, of an EFTA-state or the Faeroe Islands, shall apply for and receive a work permit prior to the foreign national beginning work. Applications for work permits must be submitted, including necessary supporting documentation, to the Directorate of Immigration via MFA/KAB who then as applicable forwards the application to the Directorate of Labour if the conditions are met.
If a foreigner is a national of a state from within the European Economic Area, an EFTA-state or the Faeroe Islands, then it is not necessary to apply for a work permit.
The Contractor shall be responsible for furnishing each employee, and for requiring that each employee engaged in the project, display such identification as may be approved and directed by the Contracting Officer.
Every employee of the prime contractor, all subcontractor employees, and all material suppliers' employees, who require access to the base for any reason and for any length of time will be required to obtain a base access pass.
Procedures for obtaining base entry passes for construction/Contractors are provided as an attachment, VISITOR CONTROL CENTER, which is included at the end of this section.
1.12.1 Contractor Employee Base Access Pass:
The Contractor shall be responsible for furnishing and requiring that each person employed in connection with this contract or any subcontract hereunder, be provided with a valid/current Contractor Employee Base Access Pass.
Every 30 days, the Contractor shall submit a list of personnel who have badges. In order to obtain a base access pass, the Contractor shall complete a USAFE Form 79, REQUEST FOR BASE ENTRY IDENTIFICATION AND CONTRACTOR PERSONNEL IDENTIFICATION, available at the Office of the Contracting Officer, and present it to the Base Security Officer for approval. After approval, the Contractor can obtain a base badge.
The Contractor shall be responsible for obtaining permission for his personnel to enter the work site areas and for ensuring that such information is up-to-date and remains valid.
All prescribed identification shall be immediately delivered and/or surrendered to the Contracting Officer for cancellation upon: (1) termination or release of any employee; (2) termination or completion of contract.
1.12.2 Responsibility for Physical Security
The Contractor shall be responsible for physical security of all construction materials, supplies, and equipment of every description (including property which may be Government furnished or owned) provided and/or utilized in the execution of this contract.
DOCUMENT 00 73 04 Page 5
1.12.3 Access to Operational Areas
Contractor personnel are expressly prohibited and shall be restricted from entering operational buildings or areas without the specific authorization of the Contracting Officer. To perform work, where "security escorts" are required for access to a facility, the Contractor shall coordinate with the Contracting Officer for access to such facilities.
1.12.4 Employment
Should the continued employment of any person in connection with this contract, or any subcontract thereunder, be deemed by the Contracting Officer to be prejudicial to the interests of the Government, that person shall immediately be removed from the work. In this connection the Contractor agrees that:
a. Cases which may involve disciplinary action against such persons, or the necessity of reassignment or termination of their services, shall be investigated, processed, reported and disposed of, as directed by the Contracting Officer.
b. Employment contracts of all persons employed in connection with this contract, or any subcontract thereunder shall include clauses containing the substance of this clause.
1.12.5 Compliance
Compliance with the foregoing provisions of this clause by subcontractors shall be the responsibility of the Contractor.
1.13 ANTI-MAFIA LAW
1.13.1 Pre-Award Effect of Anti-Mafia Procedures
Inasmuch as the work of this solicitation is to be performed on land owned by the Italian State, the prospective contractor will be subject to Italian Law No. 646, of 13 September 1982, and subsequent integrations and amendments. The solicitation data will be made available only to firms that meet the related submittal requirements below in paragraph "Submittals".
As such, in the event that prior to award any disciplinary actions or proceedings for Mafia related matters exist against the apparent low bidder, no award will be made to said low bidder.
1.13.2 Termination Under Italian Law No. 646 (Anti-Mafia)
If during the life of this contract, any proceeding or disciplinary actions contemplated by Italian Law No. 646 of 13 September 1982 (and subsequent amendments and integrations) is undertaken against any component of the Contractor or any Subcontractor, the Government can consider this a failure to execute the work and terminate the contractor's right to proceed with the work under the "Default" clause of this contract.
1.13.3 Application of Italian Law No. 646 (Anti-Mafia) to Subcontractors
In addition to the requirement in the FAR Clause 52.244-1, SUBCONTRACTS, of this contract, before the Contracting Officer can consent to any subcontractors, the Contractor will be required to certify to the Contracting Officer that no disciplinary actions or proceedings for Mafia related matters exist against such Subcontractors.
DOCUMENT 00 73 04 Page 6
1.13.4 Documentation Requirements
Contractor shall submit the following:
a. An original, unexpired and not older than 10 months at the time of the bid opening, of the Chamber of Commerce Certificate of Membership (Certificato di iscrizione alla Camera di Commercio).
b. Originals, unexpired and not older than one month at the time of the bid opening, of the Family Status and Residency Certificate of each member of the firm, as listed in the Chamber of Commerce Certificate of Membership (Per Decreto Legislativo n. 490 of 8 Aug 94, published in the Gazzetta Ufficiale n. 186 of 10 Aug 1994).
1.14 CERTIFICATION OF COMPLIANCE WITH ITALIAN LAWS
1.14.1 Certification
As a condition of final acceptance of the work, the Contractor shall submit to the Contracting Officer a certificate of compliance for all contract work certifying that the work complies with Italian Law No. 46 and that the provided work is adequate and safe for the designated use.
All work shall comply with Italian norms and standards as a minimum.
Follow all applicable Italian and European standards and codes for each product and installation required for the project. All applicable norms and standards shall be met, whether or not a specific Italian or European norm standard is indicated for a product or installation. If there is a conflict between Italian norms and standards and the United States Federal Mandates, the more stringent shall apply.
The certification shall be made by the responsible technician of the installation firm who shall have been regularly registered on the Installation National Professional Rolls of Italy for at least the last three years.
1.14.2 Static Load and Final Testing
The Contractor shall comply with the pertinent articles of Italian LAW No. 1086. Because this construction will be performed on property owned by the Italian State, the LAW No. 1086 Articles pertaining to notification and participation by civil authorities are not applicable.
The Contractor shall be fully responsible for construction, supervision, static load tests, and final testing, and for all costs associated with this procedure and specifically follow Article 7 of Italian LAW No. 1086 in performing the test. Any fees for these tests shall be in accordance with Italian Professional Law No. 143 of 2 March 1949 as amended.
Article 2 of Italian LAW No. 1086 requires the static load tests to be performed under the supervision of an engineer or architect registered on the National Professional Verifier Rolls of Italy.
Since GENIODIFE intends to participate in static load and final testing, the Contractor shall notify the Contracting Officer at least 21 calendar days prior to any static load or final test to enable the Contracting Officer to notify GENIODIFE.
DOCUMENT 00 73 04 Page 7
Prior to performing the tests, submit to the Contracting Officer the names and certified credentials of proposed testing personnel, engineer(s) or architects(s) they propose to perform the static load testing.
Upon completion of the tests, the Contractor shall submit to the Contracting Officer two original certification of the static load tests results of the static load tests together with a certification of actual testing personnel stating that each test was performed by the same engineer(s) or architects(s) whose certified credentials were previously submitted. The Contracting Officer will submit one original certification to GENIODIFE.
1.14.3 Other Tests
In addition to the certifications listed above, the Contractor shall provide with all other certifications and testing required by Italian Law.
The Contractor is also responsible for all permits required by Italian Law (See Contract Clause FAR 52.236-7, "Permits and Responsibilities". The Contractor shall submit to the Contracting Officer two originals of each certification required by Italian Law. Such certifications may include but not be limited by the following as applicable to the project:
a. Certificate of conformity for electrical system in accordance with Italian Law No. 46. Include a separate specific certificate of compliance for each electrical panel in accordance with Italian Law No. 46.
b. Certificate of compliance for heating system above 100,000 Kal/hr in accordance with Italian Law No. 373.
c. Certificate of compliance for fire prevention system in accordance with DM 16 February 1982 and UFC 3-600-01.
1.15 CULTURAL RESOURCES
Cultural resources such as archaeological remains or villa remains may be uncovered during construction excavation operations on and off Aviano Air Base. If during excavations, suspected cultural remains are found, excavation operations shall immediately cease and contractor shall notify the Contracting Officer. The Contracting Officer shall contact 31 CES/CEV, Environmental Flight, at telephone number 632-4322.
1.16 UNEXPLODED ORDNANCE
The Contractor is advised that unexploded ordnance may exist in areas where excavation work is required.
During the entire life of this Contract, the Contractor shall be responsible for performing both visual and electronic inspection of the work areas to prevent danger to personnel and loss of equipment from inadvertently exploding old ordnance.
During excavation work the Contractor shall use caution when unknown objects are encountered and thoroughly identify the object prior to removal.
Upon discovery of any suspected unexploded ordnance in the course of contract work, the Contractor shall clear the area and contact the Base Operations Officer and the Contracting Officer. Resultant exploratory and removal work shall be subject to negotiations for a contract change in
DOCUMENT 00 73 04 Page 8 accordance with the Contract Clauses.
Contractor shall upon issuance of the notice to proceed by the Contracting Officer shall provide the exploratory excavation and removal of suspected unexploded ordnance. This work shall be conducted only by a firm authorized by the Italian Ministry of Defense (IMD) to perform such work, and approved by the Contracting Officer. Submit proof of IMD ordnance work authorization to the Contracting Officer for review and approval prior to conducting ordnance work.
The Contractor shall have the approved ordnance removal firm committed to an on-call basis in the event that suspected unexploded ordnance is encountered during contract work.
1.17 SECURITY REQUIREMENTS
The Contractor shall be responsible for furnishing each employee, and for requiring that each employee engaged in the work display, such identification as may be approved and directed by the Contracting Officer.
All prescribed identification shall immediately be delivered to the Contracting Officer for cancellation upon release of any employee.
Contractor personnel shall be restricted from entering operational buildings or areas without the specific authorization of the Contracting Officer.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
DOCUMENT 00 73 04 Page 9
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
08/15, CHG 2: 08/21
PART 1 GENERAL
1.1 SUBMITTALS
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.2 Location
1.3 ON-SITE PERMITS
1.3.1 Utility Outage Requests and Utility Connection Requests
1.4 LOCATION OF UNDERGROUND UTILITIES
1.4.1 Notification Prior to Excavation
1.5 NAVY…