Attachment D - Contractors Daily Report Form WI-452.pdf
PDF 108 KB Posted
- Attached to
- Wallops Flight Facility - Restoration of Main Base Electrical Infrastructure Federal contract opportunity
- Solicitation number
- 80GSFC21B0002
About this file
This daily construction report form and related federal contract opportunity involve electrical infrastructure restoration services at NASA's Wallops Flight Facility in Wallops Island, Virginia. The construction report form is Attachment D to solicitation 80GSFC21B0002, and will be used to document daily work, weather conditions, labor counts, equipment use, surveillance results, test results, instructions received, remarks, and safety inspections. The solicitation seeks bids to replace medium voltage direct burial cable and switches, create redundant feeders and looped circuits, replace transformers, and upgrade wiring at the main base. The contractor will be responsible for construction services in compliance with contract plans and specifications. The deadline to submit a bid response was not provided.
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT D
80GSFC21B0002
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
GODDARD SPACE FLIGHT CENTER
WALLOPS FLIGHT FACILITY
WALLOPS ISLAND, VA 23337
CONTRACTORS DAILY REPORT
FORM WI 452
FOR
Wallops Restoration of Main Base Electrical Infrastructure
LOCATED
AT
NASA GSFC/WALLOPS FLIGHT FACILITY
WALLOPS ISLAND, VIRGINIA
NASA WI-452
DAILY CONSTRUCTION REPORT
Contract No. ___________ Date: ______________ Report No. ____________
Description and Location of Work: ________________________________________________
Weather: (Clear) (P. Cloudy) (Cloudy) Temperature ______ Min: ______ Max: _______ Rainfall: __________ inches.
Contractor/Subcontractors and Area of Responsibility with Labor Count for Each:
a. __________________________________ d. __________________________________
b. __________________________________ e. __________________________________
c. __________________________________ f. __________________________________
Equipment Data: (Indicate items of construction equipment, other than hand tools, at the job site, and whether or not used.)
1. Work Performed Today: (Indicate location and description or work performed. Refer to work performed by prime and/or subcontractors by letter in Table above.)
NASA WI-452
2. Result of Surveillance: (Include satisfactory work completed, or deficiencies with action to be taken.)
3. Test Required by Plans and/or Specifications Performed and Results of Tests:
4. Verbal Instruction Received: (List any instructions given by Government personnel on construction deficiencies, retesting required, etc., with action to be taken.)
5. Remarks: (Cover any conflicts in plans, specifications, or instructions on any delay to the job attributable to weather conditions.)
6. Results of Safety Inspections: (Include safety violations and corrective actions taken.)
CONTRACTOR’S VERIFICATION: The above report is complete and correct and all material and equipment used and work performed during this reporting period are in compliance with the contract plans and specifications except as noted above.
(Contractor’s Approved Authorized Representative)
(NASA Inspector)