Restoration of Main Base Electrical Infrastructure Industry RFIs 7 - 05182021.pdf
PDF 151 KB Posted
- Solicitation number
- 80GSFC21B0002
About this file
This document contains responses to industry questions regarding a solicitation from the National Aeronautics and Space Administration Goddard Space Flight Center for the restoration of main base electrical infrastructure at Wallops Flight Facility. The responses clarify that certain buildings may be able to have restoration work performed during normal business hours though this cannot be guaranteed. Additionally, it is acceptable to arc tape medium voltage cables as a group rather than individually wrapping each conductor. The solicitation seeks construction services including replacement of medium voltage direct burial cable and switches, creation of redundant feeders and looped circuits, transformer replacement, and wiring upgrades at the main base location.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Restoration of Main Base Electrical Infrastructure Response to Industry Questions #7
5/18/21
1. Will all buildings be required to be done after hours or weekends? If not please clarify which buildings can be during normal business hours.
The following buildings may be able to be done during normal business hours, but can’t be guaranteed.
A-1 A-2-1 A-41 A-131 B-30
CG-6
C-094 D-4 D-8 D-137 E-6 E-7 E-10 E-110 E-134 F-8 F-9 F-10-3 F-10-4 F-11 F-16-1 F-16-2 F-19 F-20 F-14 F-19 F-21 F-23 F-24 F-25 F-26 F-27 F-44 F-168 H-30 M-1 N-116
Restoration of Main Base Electrical Infrastructure Response to Industry Questions #7
5/18/21
N-117 N-133 N-157 N-159B N-159C N-159-Ramp N-161C N-163A-W N-165—1 N-169-W N-159D-W Cap Bank #1-W N-174-A&B N-175-W N-179-W N-181-2 N-185 N-181-3-W N-181-4-W N-181-1-W N-222 H-30
MLS PAD-3
TR-HOT-PAD
TR-A-2-1
M-1
2. General note 23 drawing E-002 “Single phase fault indicators shall be provided on all incoming and outgoing conductors located within the medium voltage equipment enclosures. This includes all pad mounted enclosures for medium voltage equipment, such as transformers, sectionalizing cabinets, medium voltage switches, etc.
Fault indicators are not required.
3. Second part of note 23. Please confirm if it is acceptable to arc tape the medium voltage cables as a group instead of individually wrapping each conductor.
Yes, its acceptable to arc tape the medium voltage cables as a group instead of individually wrapping each conductor.