This document provides details for a federal solicitation to construct an integrated health center in Murfreesboro, Tennessee. The solicitation number is 36C77623B0037 and is being issued by the Department of Veterans Affairs Technology Acquisition Center located in Austin, Texas. The project involves the construction of an integrated health center for veterans and has a description of "Project# 626-309 Construct Integrated Health Center (Minor)". No further details are provided on response dates, pricing terms, or other requirements. An attachment is referenced but its content is not disclosed.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
12 Cadillac Dr., Suite 150 Brentwood, TN 37027 P 615.297.4554
©Copyright 2020
TLC No.:
www.tlc-engineers.com
120483
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
214 Centerview Drive Suite 300 Brentwood, TN 37027
615.370.8500woldhfr.com
WOLD | HFR DESIGN
102 THIRD AVENUE NE
HICKORY, NC 28601
PHONE: 828.315.9962
FAX: 828.315.9966
NC ENGINEERING LICENSE NO: P-0214
NC ARCHITECTURE LICENSE NO: 51254
MURFREESBORO, TN
B
IM
/T
V H
S
A lv in C
Y o rk
V A
I n te g ra te d H e a lt h /2
A R
C H
P
R O
J E
C T
C E
N T
R A
L .r v t
/2
/2
:0
:5
P
M
GI 00.01
COVER SHEET TVHS - ALVIN C. YORK VAMC -
INTEGRATED HEALTH CENTER
AT05-20-2022
626-309
RA
PHONE: 615.370.8500
CITY/STATE/ZIP: BRENTWOOD, TN 37027
ADDRESS 214 CENTERVIEW W. DRIVE, STE 300
EMAIL: BCRUMP@WOLDHFR.COM
STRUCTRUAL
ENGINEER:
DESIGNER: BRIAN CRUMP
WEB: www.hfrdesign.com
FAX: 615.370.8530
PHONE: 615.370.8500
CITY/STATE/ZIP: BRENTWOOD, TN 37027
ADDRESS: 214 CENTERVIEW DRIVE, STE 300
EMAIL: GNEWMAN@WOLDHFR.COM
DESIGNER: GISELLE NEWMAN
INTERIOR
DESIGNER:
WOLD | HFR DESIGN
PROJECT NUMBER: 217040
WEB: www.woldhfrdesign.com
FAX: 615.370.8530
PHONE: 615.370.8500
CITY/STATE/ZIP: BRENTWOOD, TN 37027
ADDRESS: 214 CENTERVIEW DRIVE, STE 300
EMAIL: ATRAYLOR@WOLDHFR.COM
PROJ. MANAGER: ANTHONY TRAYLOR
EMAIL: RFRANKS@WOLDHFR.COM
PRINCIPAL: RON FRANKS
ARCHITECT: WOLD | HFR DESIGN
PHONE: (828) 315-9962
ADDRESS: 102 3RD AVE. NE, HICKORY, NC 28601
EMAIL: ED.HENSON@ATRIAXGROUP.COM
CONTACT: ED HENSON
ARCHITECT: ATRIAX GROUP
PROJECT NUMBER: 626-309
PHONE: 615.867.6000
CITY/STATE/ZIP: Murfreesboro, TN 37129
ADDRESS: 3400 Lebanon Road
EMAIL: HANS.JOHNSON2@VA.GOV
CONTACT PERSON: HANS JOHNSON
COR: VA
PROJECT CONTACT LIST
PHONE: (828) 315-9962
ADDRESS: 102 3RD AVE. NE, HICKORY, NC 28601
EMAIL: justing.keneer.atriaxgroup.com
CONTACT: JUSTIN KENEER
CIVIL: ATRIAX GROUP
WEB: www.tlc-engineers.com
FAX: 615.297.4554
PHONE: 615.297.4554
CITY/STATE/ZIP: BRENTWOOD, TN 37027
ADDRESS: 12 CADILLIAC DRIVE, SUITE 150
EMAIL: DERON.MCINTOSH@tlc-eng.com
ELECTRICAL: DERON MCINTOSH
EMAIL: STEVE.KEMP@tlc-eng.com
PLUMBING: STEVE KEMP
EMAIL: STEVE.KEMP@tlc-eng.com
MECHANICAL: STEVE KEMP
MECHANICAL,
PLUMBING, &
ELECTRICAL
ENGINEERS:
TLC ENGINEERING SOLUTIONS
PROJECT CONTACTS (CONT)
ARCHITECTS / STRUCTURAL
WOLD | HFR DESIGN ATRIAX GROUP
ARCHITECT / CIVIL
TLC ENGINEERING
MECHANICAL/ELECTRICAL/PLUMBING/TECHNOLOGY
DEPARTMENT OF VETERANS AFFAIRS
TVHS - ALVIN C. YORK VAMC - INTEGRATED HEALTH CENTER
3400 LEBANON PIKE
MURFREESBORO, TN 37130
PROJECT NO. 626-309
05-20-2022
100% CONSTRUCTION DOCUMENTS
W O
L D
H
F R
D E
S
IG
N
-2
-2
C O
N S
T R
U C
T
IO
N D
O C
U M
E N
T S
Revisions: Date:
WINDOW TAG
ELEVATION TAG
GYPSUM BOARD
CONCRETE
CONC. MASONRY UNITS
FINISH WOOD
BATT INSULATION
HANDICAP ACCESSIBLE
SECTION INDICATOR
SHEET NUMBER
ENLARGED PLAN NUMBER
NOTE: THE DIRECTION OF THE SECTION INDICATOR'S
FLAG MAY REFLECT AN "OPPOSITE HAND" OR
"MIRRORED VIEW" OF BUILDING AND WALL SECTIONS
EQUIPMENT TAG
A
CALLOUT TAG
# / A ##.##
# / A ##.##
# / A ##.##
0000-000
EXIST DEMO NEW
CONTINUOUS LINE
MEDIUM DASH LINE
0 4' 8' 12'
BREAK, ROUND (USER DEFINES SIZE)
BREAK, STRAIGHT
(SEE SECTION INDICATORS,
BUILDING, WITH BREAK STANDARDS)
DETAIL INDICATOR
DIMENSION LINE
DOOR OPENING/
BORROWED LIGHT IDENTIFIER
NORTH
DETAIL INDICATOR
FURNITURE, FIXTURE, &
EQUIPMENTS INDICATOR
GRAPHIC SCALE, 1/8" = 1'-0"
ROOM NAME AND NUMBER
COLUMN GRID
KEYNOTE
FIRE EXTINGUISHER CABINET
NORTH ARROW
WALL OR PARTITION TYPE
CORNER GUARD
EXISTING CONSTRUCTION
TO REMAIN
EXISTING CONSTRUCTION
TO BE REMOVED
NEW CONSTRUCTION
VV ITEM - VA SUPPLIED & INSTALLED
VC ITEM - VA SUPPLIED &
CONTRACTOR INSTALLED
CC ITEM - CONTRACTOR SUPPLIED &
INSTALLED
DETAIL NUMBER
SHEET WHERE REF.
SHEET WHERE DRAWN
FEC
AA
A
CG
CORRIDOR
C2
A3.1 A4.3
D2
A-512
101A
DOOR TAG
DRAWING BLOCK TITLE, TYPICALFLOOR PLAN1
RIGID INSULATION
EARTH
BASE COURSE
PROJECT LOCATION
PROJECT LOCATION
CONSTRUCTION TYPE: IIB, AUTOMATIC SPRINKLER SYSTEM, ALLOWED AREA:
OCCUPANCY GROUP: ALLOWED AREA
(1 STORY):
MAX
FRONTAGE
INCREASE
ALLOWED AREA
W/ INCREASE:
A-2 ASSEMBLY
A-3 ASSEMBLY
B - BUSINESS
M- MERCANTILE
7,125 SF =
7,125 SF =
17,250 SF =
9,375 SF =
38,000 SF +
38,000 SF +
92,000 SF +
50,000 SF +
45,125 SF - MOST
RESTRICTIVE
45,125 SF - MOST
RESTRICTIVE
109,250 SF
59,375 SF
CONSTRUCTION TYPE: II (0,0,0) AUTOMATIC SPRINKLER SYSTEM, ALLOWANCES/RESTRICTIONS:
2021 NFPA 101:
NEW AND EXISTING
ASSEMBLY
NEW AND EXISTING
BUSINESS
TABLE 12.1.6 AND
TABLE 13.1.6
SEC. 38.6.1 AND SEC.
39.6.1
- 1 STORY ALLOW FOR ANY OCCUPANT LOAD
2 STOIRES ALLOWED FOR AN OCCUPANY LOAD
OF 300 OR LESS.
NO MIN. CONSTRUCTION REQUIREMENTS
NEW AND EXISTING
MERCANTILE
SEC. 36.6.1 AND SEC.
37.6.1
NO MIN. CONSTRUCTION REQUIREMENTS
2021 IBC:
12 Cadillac Dr., Suite 150 Brentwood, TN 37027 P 615.297.4554
©Copyright 2020
TLC No.:
www.tlc-engineers.com
120483
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
214 Centerview Drive Suite 300 Brentwood, TN 37027
615.370.8500woldhfr.com
WOLD | HFR DESIGN
102 THIRD AVENUE NE
HICKORY, NC 28601
PHONE: 828.315.9962
FAX: 828.315.9966
NC ENGINEERING LICENSE NO: P-0214
NC ARCHITECTURE LICENSE NO: 51254
MURFREESBORO, TN
B
IM
/T
V H
S
A lv in C
Y o rk
V A
I n te g ra te d H e a lt h /2
A R
C H
P
R O
J E
C T
C E
N T
R A
L .r v t
/2
/2
:0
:5
P
M
GI 01.01
GENERAL DATA TVHS - ALVIN C. YORK VAMC -
INTEGRATED HEALTH CENTER
AT05-20-2022
626-309
RA
SYMBOL LEGEND
MECH. MECHANICAL
MED. MEDICAL
MED. CAB. MEDICAL CABINET
MFR. MANUFACTURER
MGMT. MANAGEMENT
MH MANHOLE
MIN. MINIMUM
MIR. MIRROR
MISC. MISCELLANEOUS
MR/S MIRROR WITH SHELF
MTD. MOUNTED
MTL. METAL
N.I.C. NOT IN CONTRACT
NOM. NOMINAL
O.C. ON CENTER
O.D. OVERFLOW DRAIN
O.F.O.I. OWNER FURNISHED / OWNER
INSTALLED
OPER. OPERATIONS
OPNG. OPENING
OPP. OPPOSITE
P.P.G. POLISHED PLATE GLASS
P.R.V. POWER ROOF VENTILATOR
P.T. PRESSURE TREATED
PART'N(S) PARTITION(S)
PLAS. PLASTER
PLAS. LAM. PLASTIC LAMINATE
PLYWD. PLYWOOD
PREP. PREPARATION
PREV. PREVENTIVE
PROF. PROFESSIONAL
PTD PAPER TOWEL DISPENSER
Q.T. QUARRY TILE
R. RADIUS
R.D. ROOF DRAIN
R.O. ROUGH OPENING
RECEPT. RECEPTION
RECOV. RECOVERY
REF. REFRIGERATOR
REF. REFER, REFERENCE
REINF. REINFORCING, REINFORCED
REQ'D REQUIRED
RM. ROOM
S SEALANT
S.&R. SHELF AND ROD
SAN. SANITARY
SB SPLASHBLOCK
SCHED. SCHEDULE
SD SOAP DISPENSER
SEC. SECTION, SECRETARY
SGNL. SIGNAL
SHLVG. SHELVING
SIM. SIMILAR
SPECS. SPECIFICATIONS
SS STAINLESS STEEL
STD. STANDARD
STL. STEEL
STO. STORAGE
STRUCT. STRUCTURAL
SYS. SYSTEM
T./TOIL./TL
T.
TOILET
T.O.S. TOP OF STEEL
T.O.W. TOP OF WALL
TB TOWEL BAR
TBL. TABLE
TECH. TECHNICIAN
TEL. TELEPHONE
THK. THICK
THKNS. THICKNESS
TPD TOILET PAPER DISPENSER
TRAIN. TRAINING
TRANS. TRANSFORMER
TREAT. TREATMENT
TYP. TYPICAL
U.N.O. UNLESS NOTED OTHERWISE
UNEXP. UNEXPOSED
VEST. VESTIBULE
W.H.F.E. WALL HUNG FIRE
EXTINGUISHER
W/ WITH
WC/W.C. WATER CLOSET
WD. WOOD
WP WATERPROOF(ING)
WP WALL PROTECTION
A.F.F. ABOVE FINISHED FLOOR
A.F.S. AT FINISHED SLAB
ACT ACOUSTICAL CEILING TILE
ADD'L ADDITIONAL
ADJ. ADJUSTABLE
ADMIN. ADMINISTRATION
ALUM. ALUMINUM
APPROX. APPROXIMATE
ASST. ASSISTANT
B.W. BOTTOM OF THE WALL
B/B BALLED & BURLAPPED
BR. BARE ROOT
BRKT. BRACKET
BRKTS. BRACKETS
C CALK
C'SNK. COUNTERSUNK
C.B. CATCH BASIN
C.F.C.I. CONTRACTOR FURNISHED /
CONTRACTOR INSTALLED
C.J. CONTROL JOINT
C.M.U. CONCRETE MASONRY UNIT
CAB. CABINET
CLG. CEILING
CLO. CLOSET
CNTR. COUNTER
COL. COLUMN
COMP. COMPUTER
CONC. CONCRETE
CONF. CONFERENCE
CONST. CONSTRUCTION
CONT. CONTINUOUS
CORR. CORRIDOR
DIA. DIAMETER
DIAG. DIAGONAL
DIM. DIMENSION
DIR. DIRECTOR
DISP. DISPENSER
DS DOWNSPOUT
DTL. DETAIL
DWGS. DRAWINGS
EA. EACH
ELEC. ELECTRICAL
ELEV. ELEVATION
ENCL. ENCLOSURE
EQ EQUAL
EQUIP. EQUIPMENT
EXIST. EXISTING
EXP. JT. EXPANSION JOINT
EXT. EXTERIOR
F.D. FLOOR DRAIN
F.E.C. FIRE EXTINGUISHER CABINET
F.F.E. FINISH FLOOR ELEVATION
FDS FOLD DOWN SEAT
FH FIRE HYDRANT
FIN. FINISH
FL. FLOOR
FOB FACE OF BRICK
FTG. FOOTING
FZR. FREEZER
G.B. GRAB BAR
GA. GAUGE
GAL. GALLON
GALV. GALVANIZED
GEN. GENERAL
GYP. GYPSUM
GYP. BD. GYPSUM BOARD
H.B. HOSE BIBB
H.M. HOLLOW METAL
HD. HEAD
HRDBD HARDBOARD
I.D. INSIDE DIAMETER
INFO. INFORMATION
INSUL. INSULATION
INT. INTERIOR
INV. INVERT
JT. JOINT
KIT. KITCHEN
LAB. LABORATORY
LAV. LAVATORY
LKR. LOCKER
M.O. MASONRY OPENING
MACH. MACHINE
MAINT. MAINTENANCE
MAT'L MATERIAL
MAX. MAXIMUM
GENERAL ABBREVIATIONS
● ALL OTHER NON-STRUCTURAL COMPONENTS WITHIN THE HVAC, MECHANICAL, PLUMBING, AND
ELECTRICAL SYSTEMS ARE ASSIGNED AN IMPORTANCE FACTOR OF 1.0 AND ARE ELIGIBLE FOR THE LATERAL BRACING EXEMPTIONS LISTED IN ASCE 7 SECTION 9.6. THE EXEMPTIONS APPLY TO SPECIFIC SMALLER SIZES OF PIPING AND DUCTWORK AND LESS HEAVY EQUIPMENT. NON-EXEMPT PORTIONS OF THESE SYSTEMS SHALL STILL BE LATERALLY BRACED. SYSTEMS WITH AN IMPORTANCE FACTOR OF 1.0
ARE CONSIDERED BY THE CODE TO BE NOT CRITICAL FOR THE CONTINUED OPERATION OF THE
FACILITY.
COMPONENTS WITH AN IMPORTANCE FACTOR OF 1.0:
● STORM SEWER SERVING CRITICAL CARE AREAS.
● SANITARY SEWER SERVING CRITICAL CARE AREAS.
● STEAM SYSTEM.
● HEATING HOT WATER SYSTEM.
● DOMESTIC HOT WATER SYSTEM.
● FIRE ALARM SYSTEM.
● EMERGENCY POWER DISTRIBUTION SYSTEMS INCLUDING ASSOCIATED GENERATOR, TRANSFER
SWITCHES, BUS DUCTS, SWITCHBOARDS, CONDUIT, AND TRANSFORMERS.
● GENERATOR ENGINE EXHAUST.
● DUCTWORK CARRYING RADIOACTIVE AGENTS AND INFECTIOUS ISOLATION AIR.
● MEDICAL GAS PIPING AND EQUIPMENT.
● FIRE SPRINKLERS AND EQUIPMENT.
● NATURAL GAS PIPING.
● FUEL OIL PIPING AND EQUIPMENT.
COMPONENTS WITH AN IMPORTANCE FACTOR OF 1.5:
3. ASSIGNED SEISMIC USE GROUP OR BUILDING DESIGN CATEGORY AS DEFINED IN THE IBC:
2. THE TERM "WITHSTAND" MEANS "THE SYSTEM WILL REMAIN IN PLACE WITHOUT SEPARATION OF ANY PARTS WHEN SUBJECTED TO THE SEISMIC FORCES SPECIFIED AND THE SYSTEM WILL BE FULLY OPERATIONAL
AFTER THE SEISMIC EVENT."
1. COMPONENTS SHALL WITHSTAND THE EFFECTS OF EARTHQUAKE MOTIONS DETERMINED ACCORDING TO
ASCE/SEI 7.
NON-STRUCTURAL SEISMIC NOTES
14. CONTRACTOR IS RESPONSIBLE FOR OBTAINING ALL LOCAL AND STATE CONSTRUCTION PERMITS.
13. CONTRACTOR SHALL NOT DISRUPT OR LIMIT THE FACILITY'S LIFE SAFETY PLAN AND SYSTEM.
12. SEISMIC: NON-STRUCTURAL COMPONENTS SHALL WITHSTAND THE EFFECTS OF EARTHQUAKE MOTIONS
DETERMINED ACCORDING TO ASCE/SEI 7. PROVIDE ENGINEERED SUPPORTS PER SEISMIC
CLASSIFICATION AND ASCE/SEI 7 REQUIRMENTS.
11. CODES: COMPLY WITH ALL APPLICABLE FEDERAL, STATE AND LOCAL CODES.
10. SUPPORT / BLOCKING: PROVIDE SUPPORT FOR NEW WORK. IF HANGERS, BACKERS, OR OTHER SUPPORTS ARE NOT DETAILED, NOTED, OR SPECIFIED, CONTRACTOR SHALL SUBMIT A VIABLE SUPPORT
DETAIL TO THE ARCHITECT FOR APPROVAL. ALL BLOCKING SHALL BE METAL (U.N.O.)
9. MAINTAIN RATINGS: MAINTAIN FIRE / SMOKE RATINGS OF EXISTING PARTITIONS AND BARRIERS.
8. SHUTDOWNS / DOWNTIME: CONTRACTOR SHALL MAKE EVERY EFFORT TO MINIMIZE DOWNTIME
ASSOCIATED WITH SCHEDULED SHUTDOWNS. COORDINATE WITH COR.
7. COORDINATE TRADES: GENERAL CONTRACTOR IS RESPONSIBLE FOR COORDINATION BETWEEN
TRADES. MECHANICAL DUCTWORK & EQUIPMENT SHALL HAVE PRIORITY OVER OTHER DISCIPLINES (FOR INSTALLATION & ROUTING). COORDINATE UTILITIES, SO THEY ARE INSTALLED IN AN ORDERLY AND
UNIFORM MANNER.
6. PROTECT / RESTORE: PROTECT EXISTING ITEMS, EQUIPMENT, FINISHES, ETC., TO REMAIN. REPAIR / REPLACE / RESTORE CONDITIONS THAT ARE DAMAGED OR DISTURBED AS A RESULT OF DEMOLITION OR
NEW WORK.
5. UTILITIES: UTILITIES AND SYSTEMS IN AREAS OUTSIDE THE CONSTRUCTION LIMITS SHALL REMAIN (U.N.O.).
4. COORDINATE NEW ITEMS: EXACT LOCATIONS OF ALL EQUIPMENT, DEVICES / OUTLETS, FIXTURES, CASEWORK, MOUNTS, AND ROUTING OF UTILITIES SHALL BE COORDINATED WITH AND APPROVED BY THE
COR.
3. DO NOT SCALE DRAWINGS.
2. VERIFY CONDITIONS: INVESTIGATE THE SITE AND VERIFY EXISTING CONDITIONS (BOTH EXPOSED AND
CONCEALED) PRIOR TO PRICING THE JOB.
1. DIAGRAMMATIC DRAWINGS: THE DRAWINGS ARE DIAGRAMMATIC IN NATURE. THE DRAWINGS
REPRESENT THE INTENT OF THE PROJECT WORK.
GENERAL PROJECT NOTES
ROOF CONSTRUCTION: 0 HR
FLOOR CONSTRUCTION: 0 HR
NON-BEARING WALLS & PARTITIONS (INTERIOR): 0 HR
NON-BEARING WALLS & PARTITIONS (EXTERIOR) 0 HR
BEARING WALLS (INTERIOR): 0 HR
BEARING WALLS (EXTERIOR): 0 HR
STRUCTURAL FRAME: 0 HR
H. FIRE PROTECTION REQUIREMENTS (IBC TABLE 601 & NFPA A.8.2.1.2):
DEAD ENDS GROUPS B, & M: 50 FEET MAX
DEAD ENDS GROUP A: 20 FEET MAX IBC/NFPA
CORR. FIRE RATING OCCUPANCY: 0 HRS (SPRINKLERED) IBC/NFPA
CORRIDORS: WIDTH: 96 IN IBC/NFPA
TRAVEL GROUPS B, & M: 100 FT
MAX COMMON PATH: TRAVEL GROUP A: 20 FT (75 FT IF NO
MORE THAN 50
OCCUPANTS)
IBC/NFPA
DISTANCE GROUP B: 300 FT (SPRINKLERED)
MAX EGRESS: DISTANCE GROUPS A, & M: 250 FT (SPRINKLERED) IBC/NFPA
EGRESS WIDTH: 0.2 PER OCCUPANT DOORS (OTHER) IBC/NFPA
G. EXIT REQUIREMENTS:
NOTE: REFRENCE TABLE ON SHEET GI 02.01
F. OCCUPANT LOAD:
PROPOSED HEIGHT: NO CHANGE
EXISTING HEIGHT: 49 FEET, VARIES
EXISTING SITE ADDITION AREA: 234 SF
PROPOSED MECH. EQUIP PLATFORM TOTAL AREA: 4,654 SF
PROPOSED MECH. EQUIP PLATFORM BUILDING
ADDITIONS AREA:
2,532 SF
PROPOSED MECH. EQUIP PLATFORM RENOVATION... 2,122 SF
EXISTING MECH. EQUIP PLATFORM AREA: 2,122 SF
PROPOSED GROUND FLOOR TOTAL AREA: 48,058 SF
PROPOSED GROUND FLOOR OUT OF SCOPE AREA: 11,243 SF
PROPOSED GROUND FLOOR BUILDING ADDITIONS AREA: 1,018 SF
PROPOSED GROUND FLOOR RENOVATION AREA: 35,797 SF
EXISTING GROUND FLOOR AREA: 47,040 SF
REFER TO THE CHART BELOW FOR SPECIFIC OCCUPANCY AREAS
ALLOWED AREA: 38,000 SF+ 7,125 SF FRONTAGE = 45,125 TOTAL (A-3 -
MOST RESTRICTIVE)
ALLOWED HEIGHT: 75' (A-3 - MOST RESTRICTIVE) IBC TABLE 504.3
E. BUILDING HEIGHT & AREA:
SEISMIC DESIGN CAT: B
SITE CLASSIFICATION: C
OCCUPANCY CAT: II
S1 = .124 Sd1 = .124
Ss = .246 Sds = .213
SITE CLASSIFICATION:
D. SEISMIC ZONE:
NFPA 220 - 2021: TYPE II (0,0,0) - FULLY SPRINKLERED NFPA 220,2021
IBC 2021: TYPE II-B - FULLY SPRINKLERED IBC TABLE 601
C. CONSTRUCTION TYPE:
NFPA 2021 : BUSINESS, ASSEMBLY, MERCANTILE
IBC 2021: MIXED OCCUPANCY - BUSINESS - B, ASSEMBLY - A3,
MERCANTILE - M
IBC 2021 SECTION 301
B. OCCUPANACY:
PH: 800-698-2411
WASHINGTON DC 20420
810 VERMONT AVE. NW
VETERANS ADMINISTRATION
A. AUTHORITIES HAVING JURISDICTION (AHJ):
DESCRIPTION: THIS PROJECT INCLUDES INTERIOR DEMOLITION AND RENOVATION OF
APPROXIMATELY 37,000 SF OF BUILDING 107 ON THE YORK VAMC CAMPUS.
RENOVATIONS INCLUDE CONVERTING A LARGE AUDITORIUM, RECREATION HALL,
AND INTERIOR SWIMMING POOL AREA AND A GYMNASIUM INTO THERAPY AREAS,
MULTIPURPOSE ROOMS, CLASSROOMS AND ADMINISTRATION AREAS. EXISTING
CAFETERIA, KITCHEN, MERCANTILE AREA, CHILLER PLAN AREA AND OTHER
MECHANICAL AND ELECTRICAL AREAS ARE TO REMIAN.
3400 LEBANON PIKE, MURFREESBORO,
TN 37130
LOCATION: TVHS - ALVIN C. YORK VAMC
PROJECT: TVHS - ALVIN C. YORK VAMC -
INTEGRATED HEALTH CENTER
PLAN REVIEW DATA DRAWING INDEX
SHEET # SHEET NAME
SUBMISSIONS
S D
D D
C D
C D
P-PP-0B1 UNDERGROUND - NEW WORK PLAN - GRAVITY - AREA B ● ●
P-PP-01 GROUND FLOOR - NEW WORK PLAN - GRAVITY - OVERALL ● ● ●
P-PP-01A GROUND FLOOR - NEW WORK PLAN - GRAVITY - AREA A ● ● ●
P-PP-01B GROUND FLOOR - NEW WORK PLAN - GRAVITY - AREA B ● ● ●
P-PP-11 GROUND FLOOR - NEW WORK PLAN - PRESSURE - OVERALL ● ● ●
P-PP-11A GROUND FLOOR - NEW WORK PLAN - PRESSURE - AREA A ● ● ●
P-PP-11B GROUND FLOOR - NEW WORK PLAN - PRESSURE - AREA B ● ● ●
P-PP-22A SECOND FLOOR - PLUMBING - AREA A ● ● ●
P-PP-22B SECOND FLOOR - PLUMBING - AREA B ● ● ●
P-PP-33 ROOF PLAN PLUMBGING OVERALL ● ●
P-PW-01 PLUMBING RISER - GRAVITY ●
P-PW-02 PLUMBING RISER - PRESSURE ●
10 - ELECTRICAL
E-EI-00 ELECTRICAL LEGEND, LIGHTING SCHEDULE, AND GENERAL NOTES ● ● ● ●
E-EI-02 PARTIAL ELECTRICAL ONELINE - NEW WORK ● ● ● ●
E-EI-03 ELECTRICAL PANEL SCHEDULES ● ● ●
E-EI-04 ELECTRICAL PANEL SCHEDULES ● ● ●
E-EI-05 ELECTRICAL PANEL SCHEDULES ● ● ● ●
E-EI-07 ELECTRICAL DETAILS ● ● ●
E-EI-08 ELECTRICAL DETAILS ● ● ●
E-EI-09 ELECTRICAL DETAILS ● ● ●
E-ES-01 ELECTRICAL SITE PLAN ●
E-ED-20 GROUND FLOOR - DEMO PLAN - ELECTRICAL - OVERALL ● ● ●
E-EL-00 GROUND FLOOR - NEW WORK PLAN - LIGHTING - OVERALL ● ● ●
E-EL-01 GROUND FLOOR - NEW WORK PLAN - LIGHTING - PART A ● ● ●
E-EL-02 GROUND FLOOR - NEW WORK PLAN - LIGHTING - PART B ● ● ●
E-EP-00 GROUND FLOOR - NEW WORK PLAN - POWER - OVERALL ● ● ● ●
E-EP-01 GROUND FLOOR - NEW WORK PLAN - POWER - PART A ● ● ●
E-EP-02 GROUND FLOOR - NEW WORK PLAN - POWER - PART B ● ● ●
E-EP-03 SECOND FLOOR - NEW WORK PLAN - POWER - OVERALL ● ● ●
E-EY-00 GROUND FLOOR - NEW WORK PLAN - SYSTEMS - OVERALL ● ● ●
E-EY-01 GROUND FLOOR - NEW WORK PLAN - SYSTEMS - PART A ● ● ●
E-EY-02 GROUND FLOOR - NEW WORK PLAN - SYSTEMS - PART B ● ● ●
11 - FIRE PROTECTION
F-FI-01 FIRE PROTECTION LEGENDS, DETAILS & NOTES ● ● ● ●
F-FD-01 BASEMENT - DEMOLITION PLAN - FIRE PROTECTION OVERALL ● ● ● ●
F-FD-02 GROUND FLOOR - DEMOLITION PLAN - FIRE PROTECTION OVERALL ● ● ● ●
F-FD-03 SECOND FLOOR - DEMOLITION - FIRE PROTECTION ● ● ● ●
F-FX-01A GROUND FLOOR - NEW WORK PLAN - FIRE PROTECTION - AREA A ● ●
F-FX-01B GROUND FLOOR - NEW WORK PLAN - FIRE PROTECTION - AREA B ● ●
F-FX-02A SECOND FLOOR - NEW WORK PLAN - FIRE PROTECTION - AREA A ● ●
F-FX-02B SECOND FLOOR - NEW WORK PLAN - FIRE PROTECTION - AREA B ● ●
12 - TECHNOLOGY
T-TJ-00 GENERAL TECHNOLOGY INFORMATION ● ● ● ●
T-TD-00 BASEMENT - DEMOLITION PLAN - OVERALL ● ● ● ●
T-TD-01 GROUND FLOOR - DEMOLITION PLAN - OVERALL ● ● ● ●
T-TJ-01 GROUND FLOOR - NEW WORK PLAN - TECHNOLOGY - OVERALL ● ● ● ●
T-TJ-01A GROUND FLOOR - NEW WORK PLAN - TECHNOLOGY - AREA A ● ● ●
T-TJ-01B GROUND FLOOR - NEW WORK PLAN - TECHNOLOGY - AREA B ● ● ●
T-TJ-04 TECHNOLOGY - ENLARGED ROOMS ● ● ●
T-TJ-05 TECHNOLOGY - ENLARGED ROOMS ● ● ● ●
T-TJ-06 TECHNOLOGY - ENLARGED ROOMS ● ● ● ●
T-TJ-07 TECHNOLOGY - DETAILS ● ● ● ●
T-TJ-08 TECHNOLOGY - DETAILS ● ● ● ●
T-TJ-09 TECHNOLOGY - RISER ● ● ● ●
T-TJ-10 TECHNOLOGY - A-V SCHEMATIC FUNCTIONAL DIAGRAM ● ● ●
DRAWING INDEX
SHEET # SHEET NAME
SUBMISSIONS
S D
D D
C D
C D
AC 11.02 CEILING DETAILS ● ● ●
AC 11.03 CEILING DETAILS ● ●
QH 12.01A GROUND FLOOR EQUIPMENT PLAN AREA A ● ● ●
QH 12.01B GROUND FLOOR EQUIPMENT PLAN AREA B ● ● ●
05 - INTERIOR DESIGN
IN 01.00 FINISH LEGEND & SCHEDULE ● ● ●
IN 01.01A GROUND FLOOR FINISH PLAN AREA A ● ● ●
IN 01.01B GROUND FLOOR FINISH PLAN AREA B ● ● ●
IN 02.01A GROUND FLOOR PATTERN PLAN AREA A ● ● ●
IN 02.01B GROUND FLOOR PATTERN PLAN AREA B ● ● ●
IN 03.00 SIGNAGE LEGEND ● ●
IN 03.01 SIGNAGE SCHEDULE ● ●
07 - STRUCTURAL
S 1.00 STRUCTURAL NOTES ● ● ●
S 1.01A FOUNDATION PLAN - AREA A ● ● ●
S 1.01B FOUNDATION PLAN - AREA B ● ● ●
S 1.02A LOW ROOF FRAMING PLAN - AREA A ● ● ●
S 1.02B SECOND FLOOR / LOW ROOF FRAMING PLAN - AREA B ● ● ●
S 1.03B ROOF FRAMING PLAN - AREA B ● ● ●
S 4.01 SECTIONS AND DETAILS ● ●
S 4.02 SECTIONS AND DETAILS ● ●
S 4.03 SECTIONS AND DETAILS ● ●
S 4.04 SECTIONS AND DETAILS ●
S 4.51 SECTIONS AND DETAILS ● ●
S 4.52 SECTIONS AND DETAILS ● ●
08 - MECHANICAL
M-MK-01 LEGENDS, NOTES, AND SYMBOLS ● ● ● ●
M-MK-02 SCHEDULES ● ● ●
M-MK-03 SCHEDULES ● ●
M-MK-04 SCHEDULES ●
M-MK-05 SCHEDULES (EXISTING EQUIPMENT) ●
M-MK-06 SCHEDULES ●
M-MD-01 BASEMENT OVERALL - HVAC DEMO ● ● ● ●
M-MD-02 GROUND FLOOR OVERALL - HVAC DEMO ● ● ●
M-MD-03 SECOND FLOOR OVERALL - HVAC DEMO ● ● ●
M-MD-04 ROOF OVERALL - HVAC DEMO ● ●
M-MD-05 AHU-34 & 35 EXISTING PLANS ● ●
M-MH-00 BASEMENT OVERALL - DUCTWORK ● ●
M-MH-01 GROUND FLOOR OVERALL - DUCTWORK ● ● ● ●
M-MH-01A GROUND FLOOR AREA A - DUCTWORK ● ● ●
M-MH-01B GROUND FLOOR AREA B - DUCTWORK ● ● ●
M-MH-02 SECOND FLOOR OVERALL - DUCTWORK ● ● ● ●
M-MH-02A SECOND FLOOR AREA A - DUCTWORK ● ● ●
M-MH-02B SECOND FLOOR AREA B - DUCTWORK ● ● ●
M-MH-03 ROOF PLAN OVERALL - DUCTWORK ● ● ●
M-MH-03-1 ROOF PLAN - OVERALL 3D ● ● ●
M-MH-03A ROOF PLAN - AREA A - DUCTWORK ● ● ●
M-MH-03B ROOF PLAN - AREA B - DUCTWORK ● ● ●
M-MH-04 SECTIONS ●
M-MP-00 BASEMENT OVERALL - PIPING ● ●
M-MP-00A BASEMENT AREA A - PIPING ● ●
M-MP-00B BASEMENT AREA B - PIPING ● ●
M-MP-01 GROUND FLOOR OVERALL - PIPING ● ● ●
M-MP-01A GROUND FLOOR AREA A - PIPING ● ●
M-MP-01B GROUND FLOOR AREA B - PIPING ● ●
M-MP-02 SECOND FLOOR OVERALL - PIPING ● ● ● ●
M-MP-02A SECOND FLOOR AREA A - PIPING ● ●
M-MP-02B SECOND FLOOR AREA B - PIPING ● ●
M-MJ-01 MECHANICAL DETAILS ● ● ● ●
M-MJ-02 MECHANICAL DETAILS ● ● ● ●
M-MJ-03 MECHANICAL DETAILS ● ● ● ●
M-MJ-04 MECHANICAL DETAILS ● ● ● ●
M-MJ-05 MECHANICAL DETAILS ● ●
M-MI-01 MECHANICAL CONTROLS ● ● ● ●
M-MI-02 MECHANICAL CONTROLS ● ● ● ●
M-MI-03 MECHANICAL CONTROLS ● ● ● ●
M-MI-04 MECHANICAL CONTROLS ●
M-MI-05 MECHANICAL CONTROLS ●
M-MI-06 MECHANICAL CONTROLS ●
M-MI-07 MECHANICAL CONTROLS ●
M-MI-08 MECHANICAL CONTROLS ●
09 - PLUMBING
P-PI-01 PLUMBING LEGENDS & NOTES ● ● ● ●
P-PI-02 PLUMBING SCHEDULES ● ● ● ●
P-PI-03 PLUMBING DETAILS ● ● ● ●
P-PI-04 PLUMBING DETAILS ● ● ● ●
P-PD-00 BASEMENT - DEMOLITION PLAN - PLUMBING OVERALL ● ● ● ●
P-PD-01 GROUND FLOOR - DEMOLITION PLAN - GRAVITY - AREA A ● ● ● ●
P-PD-02 SECOND FLOOR - DEMOLITION PLAN - GRAVITY - AREA B ● ● ● ●
P-PD-03 GROUND FLOOR DEMOLITION PLAN - PRESSURE - AREA A ● ●
P-PD-04 GROUND FLOOR DEMOLITION PLAN - PRESSURE - AREA B ● ●
P-PD-05 SECOND FLOOR - DEMOLITION PLAN - PLUMBING ● ●
P-PP-00 BASEMENT - NEW WORK PLAN - GRAVITY - OVERALL ● ●
P-PP-00B BASEMENT - NEW WORK PLAN - GRAVITY - AREA B ● ● ●
P-PP-0A1 UNDERGROUND - NEW WORK PLAN - GRAVITY - AREA A ● ●
DRAWING INDEX
SHEET # SHEET NAME
SUBMISSIONS
S D
D D
C D
C D
00 - GENERAL
GI 00.01 COVER SHEET ● ● ● ●
GI 01.01 GENERAL DATA ● ● ● ●
GI 01.02 WALL TYPE DETAILS ● ● ●
GI 01.03 ACCESSIBILITY DETAILS ● ● ● ●
GI 01.20 EXISTING PLAN/CAMPUS MAP ● ● ●
GI 01.21 OVERALL SCOPE ● ● ●
GI 01.30 SUGGESTED PHASING PLANS ● ● ●
GI 01.40 PHASE I ICRA PLAN ● ● ●
GI 01.41 PHASE II ICRA PLAN ● ●
GI 01.42 PHASE III ICRA PLAN ● ●
GI 01.43 PHASE IV ICRA PLAN ● ●
GI 01.44 PHASE V ICRA PLAN ● ●
GI 02.01 OVERALL LIFE SAFETY PLAN ● ● ● ●
GI 01.51 ASBESTOS AND LEAD SAMPLE LOCATION DRAWING ● ●
GI 01.52 ASBESTOS CONTAINING MATERIAL LOCATION DRAWING ● ●
GI 01.53 ASBESTOS CONTAINING MATERIAL LOCATION DRAWING ● ●
GI 01.54 ASBESTOS CONTAINING MATERIAL LOCATION DRAWING ● ●
GI 01.55 ASBESTOS SUMMARY KEYNOTES ● ●
01 - CIVIL
CG101 CIVIL COVER SHEET ●
V-101 EXISTING CONDITIONS PLAN ● ● ●
CD101 DEMOLITION PLAN ● ● ●
C-101 CIVIL SITE PLAN ● ● ●
C-102 GRADING PLAN ● ● ●
C-103 EROSION AND SEDIMENT CONTROL PLAN ● ●
C-104 GRADING AND DRAINAGE PLAN ●
C-201 GRADING AND DRAINAGE PLAN ●
C-501 CIVIL DETAILS 1 ● ● ●
C-502 CIVIL DETAILS 2 ● ● ●
C-503 CIVIL DETAILS 4 ● ● ●
C-504 CIVIL DETAILS 3 ● ●
C-505 CIVIL DETAILS 4 ●
03 - DEMOLITION
AD 01.01 PHASE I DEMO PLAN ● ●
AD 01.02 PHASE II DEMO PLAN ● ●
AD 01.03 PHASE III DEMOLITION PLAN ● ●
AD 01.04 PHASE IV DEMOLITION PLAN ● ● ● ●
AD 01.05 PHASE V DEMOLITION PLAN ● ●
AD 01.06 DEMO PHOTOS ● ● ● ●
04 - ARCHITECTURAL
AE 01.01 GROUND FLOOR OVERALL PLAN ● ● ● ●
AE 01.01A GROUND FLOOR PLAN AREA A ● ● ● ●
AE 01.01B GROUND FLOOR PLAN AREA B ● ● ● ●
AE 01.01C MECH EQUIP PLATFORMS/TRANSFORMER ● ● ●
AE 01.02 ROOF PLAN ● ● ● ●
AE 01.03 ALTERNATE PLANS ● ●
AE 01.10A GROUND FLOOR PLAN AREA A - DIMENSIONED ● ●
AE 01.10B GROUND FLOOR PLAN AREA B - DIMENSIONED ● ●
AE 02.02 ENLARGED PLANS - VESTIBULE/PMRS CONSULT ● ● ●
AE 02.03 ENLARGED PLANS - SIM LAB ● ● ●
AE 02.04 ENLARGED PLANS - KINESIO THERAPY ● ● ●
AE 02.05 ENLARGED PLANS - TOILETS ● ● ●
AE 02.06 ENLARGED PLANS - TOILETS ● ●
AE 03.01 DOOR ELEVATIONS, SCHEDULE, & NOTES ● ● ●
AE 03.02 DOOR DETAILS ● ● ●
AE 03.03 DOOR DETAILS ● ●
AE 03.04 WINDOW ELEVATIONS & NOTES ● ● ●
AE 03.05 WINDOW DETAILS - INTERIOR ● ●
AE 03.06 WINDOW DETAILS - EXTERIOR ● ● ●
AE 04.01 BUILDING ELEVATIONS ● ● ● ●
AE 04.02 BUILDING ELEVATIONS ● ● ●
AE 05.01 BUILDING SECTIONS AREA A ● ● ●
AE 05.02 BUILDING SECTIONS AREA B ● ● ●
AE 06.01 WALL SECTIONS ● ● ●
AE 06.02 WALL SECTIONS ● ● ●
AE 08.01 EXTERIOR DETAILS ● ● ●
AE 08.02 EXTERIOR DETAILS ● ● ●
AE 08.03 PLAN DETAILS ● ●
AE 08.04 PLAN DETAILS ● ●
AE 08.05 MISC. DETAILS ● ● ●
AE 08.06 MISC DETAILS ● ● ●
AE 08.07 RAMP DETAILS ● ●
AE 08.08 MISC. INTERIOR DETAILS ● ●
AE 08.09 MISC. INTERIOR DETAILS ● ●
AE 09.01 INTERIOR ELEVATIONS ● ● ●
AE 09.02 INTERIOR ELEVATIONS ● ● ●
AE 09.03 INTERIOR ELEVATIONS ● ● ●
AE 09.04 INTERIOR ELEVATIONS ● ● ●
AE 09.05 INTERIOR ELEVATIONS ● ● ●
AE 09.06 INTERIOR ELEVATIONS ● ● ●
AE 10.01 CASEWORK SECTIONS AND MISC DETAILS ● ● ●
AE 10.02 CASEWORK SECTIONS AND MISC DETAILS ● ● ●
AC 11.01 OVERALL REFLECTED CEILING PLAN ● ● ● ●
AC 11.01A GROUND FLOOR REFLECTED CEILING PLAN AREA A ● ● ● ●
AC 11.01B GROUND FLOOR REFLECTED CEILING PLAN AREA B ● ● ● ●
T. SAFETY STANDARD FOR REFRIGERATION SYSTEMS - ASHRAE STANDARD 15-2007.
S. VENTILATION FOR ACCEPTABLE INDOOR AIR QUALITY - ASHRAE STANDARD 62.1-2004.
R. THE PROVISIONS FOR CONSTRUCTION AND SAFETY SIGNS. STATED IN THE GENERAL
REQUIREMENTS SECTION 01010 OF THE VA MASTER CONSTRUCTION SPECIFICATION.
Q. EXECUTIVE ORDER 13423: STRENGTHENING FEDERAL ENVIRONMENTAL, ENERGY, AND
TRANSPORTATION MANAGEMENT.
P. FEDERAL LEADERSHIP IN HIGH PERFORMANCE AND SUSTAINABLE BUILDINGS: MEMORANDUM OF
UNDERSTANDING (MOU)
O. DOE INTERIM FINAL RULE: ENERGY CONSERVATION STANDARDS FOR NEW FEDERAL, COMMERCIAL
AND MULTI-FAMILY HIGH-RISE RESIDENTIAL BUILDINGS AND NEW LOW-RISE RESIDENTIAL
BUILDINGS, 10 CFR PARTS 433, 434, AND 435.
N ENERGY POLICY ACT OF 2005 (EPACT)
M. MANUAL OF STEEL CONSTRUCTION, LOAD AND RESISTANCE FACTOR DESIGN SPECIFICATIONS
FOR STRUCTURAL STEEL BUILDINGS, AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)
L. BUILDING CODE REQUIREMENTS FOR REINFORCED CONCRETE, AMERICAN CONCRETE INSTITUTE
AND COMMENTARY (ACI 318)
K. ARCHITECTURAL BARRIERS ACT ACCESSIBILITY STANDARDS (ABAAS) INCLUDING VA SUPPLEMENT, BARRIER FREE DESIGN GUIDE (PG-18-13)
J. ASME CODE FOR PRESSURE PIPING
I. ASME BOILER AND PRESSURE VESSEL CODE
H. SAFETY CODE FOR ELEVATORS AND ESCALATORS, AMERICAN SOCIETY OF MECHANICAL
ENGINEERS (ASME) A 17.1.
G. INTERNATIONAL PLUMBING CODE (IPC)
F. NATIONAL ELECTRICAL CODE (NEC)
E. VA SEISMIC DESIGN REQUIREMENTS, H-18-8
D. OCCUPATION, SAFETY AND HEALTH ADMINISTRATION (OSHA) STANDARDS.
C. NFPA NATIONAL FIRE CODES, WITH THE EXCEPTION OF NFPA 5000 AND NFPA 900
B. NFPA 101 - 2021 LIFE SAFETY CODE
A. INTERNATIONAL BUILDING CODE (IBC 2021) (ONLY WHEN SPECIFICALLY REFERENCED IN VA
DESIGN DOCUMENTS)
THE LATEST EDITIONS OF THE FOLLOW CODES SHALL BE FOLLOWED.
VA CODE LIST
VICINITY MAP
NON-RATED PARTITION
16" O.C.
SECTION
PLAN
1 3-5/8" STUD
DESCRIPTION:
2 43
UL DESIGN #:
STC RATING:
FIRE RATING:
SCALE:
45 - 49
N.T.S.
ABOVE CEILING ID (STENCIL):
PLAN DESIGNATION:
GENERAL NOTES:
1. ALL REQUIREMENTS OF LISTED UL
DESIGN # MUST BE MET.
WALL PRIORITY:
OPENINGS: --
V A R
IE
S
1. STEEL FLOOR AND CEILING CHANNELS - TOP AND BOTTOM CHANNELS OF WALL
ASSEMBLY SHALL BE MIN. 20 GA. GALV. STEEL SIZED TO FIT STUDS. TOP CHANNEL TO
HAVE 2" FLANGES (MIN). BOTTOM CHANNEL TO HAVE 1-1/4" FLANGES (MIN). SECURE
BOTTOM CHANNELS WITH STEEL FASTENERS AT 24" O.C. (MAX). SECURE TOP
CHANNELS TO VALLEYS OF STEEL FLOOR UNITS (OR STRUCTURE ABOVE) WITH STEEL
FASTENERS AT 12" O.C. (MAX).
2. STEEL STUDS - MIN. 3-5/8" WIDE (UNLESS NOTED OTHERWISE), 1-1/4" LEGS, 3/8" FOLDED
BACK RETURN. FORMED OF 20 GA.(MIN) GALV. STEEL. MAX. SPACING 16" O.C. CUT
STUDS 1" LESS IN LENGTH THAN ASSEMBLY HEIGHT WITH BOTTOM NESTING IN AND
SECURED TO FLOOR CHANNEL, AND WITH TOP NESTING IN CEILING CHANNEL WITHOUT
ATTACHMENT.
3. SOUND ATTENUATION BATT INSUL. - 3-1/2" (DEPENDING ON STUD SIZE) GLASS FIBER
BATTS IN STUD CAVITY. FILL ENTIRE CAVITY FULL HEIGHT.
4. GYPSUM WALLBOARD- 5/8" THICK TYPE "X", 4' WIDE, ATTACHED TO STEEL STUDS AND
FLOOR CHANNELS WITH 1" LONG TYPE S SELF-TAPPING STEEL SCREWS AT 8" O.C.
ALONG THE VERTICAL AND BOTTOM EDGES AND 12" O.C. IN THE FIELD OF THE BOARD.
INSTALL WALLBOARD WITH A MIN. 1/2" AND MAX. 3/4" GAP BETWEEN THE TOP OF THE
WALLBOARD AND THE BOTTOM OF THE FLOOR UNIT VALLEYS (OR STRUCTURE ABOVE).
NO SCREWS ARE TO BE INSTALLED WITHIN 4" OF THE STEEL FLOOR UNIT VALLEYS AT
THE TOP OF THE WALL. ORIENT JOINTS VERTICALLY AND STAGGER JOINTS ON
OPPOSITE SIDES OF THE ASSEMBLY.
5. JOINT TAPE AND COMPOUND - VINYL, DRY OR PRE-MIXED JOINT COMPOUND, APPLIED
IN TWO COATS TO JOINTS AND SCREW HEADS; PAPER TAPE 2" WIDE EMBEDDED IN
FIRST LAYER OF COMPOUND OVER ALL JOINTS. JOINTS REINFORCED.
6. ACOUSTICAL SEALANT.
1/ 4" M
IN
6 6" STUD
1HR FIRE BARRIER
UL DESIGN #:
STC RATING:
FIRE RATING:
SCALE:
16" O.C.
SECTION
PLAN
3-5/8" STUD1B
U465
45 - 49
1HR
N.T.S.
DESCRIPTION:
2 43
ABOVE CEILING ID (STENCIL):
"1HR FIRE BARRIER"
PLAN DESIGNATION:
GENERAL NOTES:
1. ALL REQUIREMENTS OF LISTED UL
DESIGN # MUST BE MET.
WALL PRIORITY:
1/ 4" M
IN
OPENINGS: 45 MIN
1. STEEL FLOOR AND CEILING CHANNELS - TOP AND BOTTOM CHANNELS OF WALL
ASSEMBLY SHALL BE MIN. 20 GA. GALV. STEEL SIZED TO FIT STUDS. TOP CHANNEL TO
HAVE 2" FLANGES (MIN). BOTTOM CHANNEL TO HAVE 1-1/4" FLANGES (MIN). SECURE
BOTTOM CHANNELS WITH STEEL FASTENERS AT 24" O.C. (MAX). SECURE TOP
CHANNELS TO VALLEYS OF STEEL FLOOR UNITS (OR STRUCTURE ABOVE) WITH STEEL
FASTENERS AT 12" O.C. (MAX).
2. STEEL STUDS - MIN. 3-5/8" WIDE, 1-1/4" LEGS, 3/8" FOLDED BACK RETURN. FORMED OF
20 GA.(MIN) GALV. STEEL. MAX. SPACING 16" O.C. CUT STUDS 1" LESS IN LENGTH THAN
ASSEMBLY HEIGHT WITH BOTTOM NESTING IN AND SECURED TO FLOOR CHANNEL, AND
WITH TOP NESTING IN CEILING CHANNEL WITHOUT ATTACHMENT.
3. SOUND ATTENUATION BATT INSUL. - 3-1/2" (DEPENDING ON STUD SIZE) GLASS FIBER
BATTS IN STUD CAVITY. FILL ENTIRE CAVITY FULL HEIGHT.
4. GYPSUM WALLBOARD- 5/8" THICK TYPE "X", 4' WIDE, ATTACHED TO STEEL STUDS AND
FLOOR CHANNELS WITH 1" LONG TYPE S SELF-TAPPING STEEL SCREWS AT 8" O.C.
ALONG THE VERTICAL AND BOTTOM EDGES AND 12" O.C. IN THE FIELD OF THE BOARD.
INSTALL WALLBOARD WITH A MIN. 1/2" AND MAX. 3/4" GAP BETWEEN THE TOP OF THE
WALLBOARD AND THE BOTTOM OF THE FLOOR UNIT VALLEYS (OR STRUCTURE ABOVE).
NO SCREWS ARE TO BE INSTALLED WITHIN 4" OF THE STEEL FLOOR UNIT VALLEYS AT
THE TOP OF THE WALL. ORIENT JOINTS VERTICALLY AND STAGGER JOINTS ON
OPPOSITE SIDES OF THE ASSEMBLY. WHEN ATTACHED TO FURRING CHANNELS,
WALLBOARD IS ATTACHED WITH 1" LONG TYPE S SCREWS AT 12" O.C.
5. JOINT TAPE AND COMPOUND - VINYL, DRY OR PRE-MIXED JOINT COMPOUND, APPLIED
IN TWO COATS TO JOINTS AND SCREW HEADS; PAPER TAPE 2" WIDE EMBEDDED IN
FIRST LAYER OF COMPOUND OVER ALL JOINTS. JOINTS REINFORCED.
6. FURRING CHANNELS (OPTIONAL NOT SHOWN) - RESILIENT 20 MSG GALV. STEEL
FURRING CHANNELS SPACED VERT. MAX. 24" O.C. ATTACH FLANGE TO EACH
INTERSECTING STUD WITH 1/2" LONG TYPE S-12 PANHEAD SCREWS.
7. ACOUSTICAL SEALANT.
8. PACKING MATERIAL - MIN. 4" TKNS. OF MIN. 4.0 PCF MINERAL WOOL BATT INSULATION
FIRMLY PACKED INTO FLUTES OF STEEL FLOOR UNITS AS A PERMANENT FORM.
PACKING MATERIAL TO BE RECESSED FROM BOTH SURFACES OF THE WALL AS
REQUIRED TO RECEIVE JOINT SEALANT.
9. JOINT TREATMENT MATERIAL - NON-SAG FIRE CAULK EACH SIDE MIN THICKNESS 1/2",
APPLIED WITHIN THE OPENING BETWEEN THE TOP OF THE WALLBOARD AND ALL
SURFACES OF THE STEEL FLOOR OR STRUCTURE, FLUSH WITH BOTH SURFACES OF
THE WALL ASSEMBLY.
7/ 8" M
IN
NO RATING - 3 5/8" MTL. STUD W/ 1 LAYER GYPSUM BOARD ON BOTH SIDES
1 HR FIRE RATED - 3 5/8" MTL. STUD W/ 1 LAYER GYPSUM BOARD ON BOTH SIDES
WALL LEGEND
1B
NO RATING - 2 1/2" MTL. STUD W/ 1 LAYER GYPSUM BOARD ON ONE SIDE
NO RATING - 3 5/8" MTL. STUD W/ 1 LAYER GYPSUM BOARD ON ONE SIDE
NO RATING - 7/8" HAT CHANNELS W/ 1 LAYER GYPSUM BOARD ON ONE SIDE
NO RATING - 3 5/8" MTL. STUD W/ 1 LAYER GYPSUM BOARD ON ONE SIDE AND 2" INSULATION5
NO RATING - 6" MTL. STUD W/ 1 LAYER GYPSUM BOARD ON EACH SIDE6
NO RATING - 3 5/8" MTL. STUD W/ 1 LAYER GYPSUM BOARD ON OUTSIDE OF THE ROOM AND
2 LAYERS OF GYPSUM BOARD ON INSIDE OF ROOM
8 NO RATING - 3 5/8" MTL. STUD W/ 2 LAYERS GYPSUM BOARD ON ONE SIDE
9 NO RATING - 3 5/8" MTL. STUD W/1 LAYER OF 5/8" GYP. BD AND 1 LAYER OF 5/16" BULLET
RESISTANT PANEL ON ONE SIDE AND 1 LAYER OF 5/8" GYP. PANEL ON THE OTHER
NON RATED SMOKE BARRIER- 3 5/8" MTL. STUD W/ 1 LAYER GYPSUM BOARD ON
BOTH SIDES
1A
NON RATED SMOKE BARRIER - 6" MTL. STUD W/ 1 LAYER GYPSUM BOARD ON EACH SIDE6A
SECTION
NON-RATED
FURRING WITH
INSULATION
ABOVE CEILING ID (STENCIL):
PLAN DESIGNATION:
GENERAL NOTES:
1. ALL REQUIREMENTS OF LISTED UL DESIGN
# MUST BE MET.
WALL PRIORITY:
ACOUSTICAL SEALANT
MTL. STUDS
AT 16" O.C. MAX.
GYPSUM WALLBOARD - 5/8"
THICK TYPE "X"
JOINT TAPE AND COMPOUND
ACOUSTICAL SEALANT
UL DESIGN #:
FIRE RATING:
GA FILE #:
STC RATING: --
OPENINGS: --
DAMPERS: --
CEILING ASSEMBLY
GYPSUM BOARD CUT TO FIT
1/ 4" M
IN
1/ 4" M
IN
3 5/8" STUD5 SCALE:
N.T.S.
2" RIGID INSULATION
SECTION
NON-RATED FURRING
ABOVE CEILING ID (STENCIL):
PLAN DESIGNATION:
GENERAL NOTES:
1. ALL REQUIREMENTS OF LISTED UL DESIGN
# MUST BE MET.
WALL PRIORITY:
ACOUSTICAL SEALANT
HAT CHANNEL- 7/8" MIN
MTL STUD - 2 1/2"
AT 16" O.C. MAX.
GYPSUM WALLBOARD - 5/8"
THICK TYPE "X"
JOINT TAPE AND COMPOUND
ACOUSTICAL SEALANT
UL DESIGN #:
FIRE RATING:
GA FILE #:
STC RATING: --
OPENINGS: --
DAMPERS: --
CEILING ASSEMBLY
GYPSUM BOARD CUT TO FIT DECK
CONFIGURATION
1/ 4" M
IN
1/ 4" M
IN
7/8" HAT CHANNEL3
SCALE:
N.T.S.
2 1/2" STUD4
3 5/8" STUD2
HIGHER PRIORITY
PRIORITY 1 (HIGHEST)
PRIORITY 2
PRIORITY 3
PRIORITY 4
PRIORITY 5 (LOWEST)NON-RATED WALL
ONE HOUR FIRE WALL
ONE HOUR FIRE AND SMOKE WALL
TWO HOUR SHAFTWALL
TWO HOUR FIRE WALL
TWO HOUR FIRE AND SMOKE WALL
WALL PRIORITY LEGEND
LOWER PRIORITY
PLAN
PRIORITY 2
0 6" 1' 2'3"
TEST REF
WP 1711
WP 1200
GAGOLD BOND
OSU T-1770
FM W1A-1HR.
UL U411
OSU T-1771
PARTITIONRATED WALL
HOLLOW METAL FRAME
JAMB STUDS
TAPE & JT. COMP.-TYP.
ONE HOUR
CONSTRUCTION
2 HR.
CONSTRUCTION
METAL
STUDS
HIGHER PRIORITY WALL
1 LAYER AT 1 HOUR
FIRE &/OR SMOKE
PARTITIONS
(NON-RATED)
3 5/8"
GYPSUM WALLBOARD
5/8" TYPE "X"
NON-RATED HIGH STC PARTITION
16" O.C.
SECTION
PLAN
7 3-5/8" STUD
DESCRIPTION:
2 43
UL DESIGN #:
STC RATING:
FIRE RATING:
SCALE:
N.T.S.
ABOVE CEILING ID (STENCIL):
PLAN DESIGNATION:
GENERAL NOTES:
1. ALL REQUIREMENTS OF LISTED UL
DESIGN # MUST BE MET.
WALL PRIORITY:
OPENINGS:
1/ 2"
1. STEEL FLOOR AND CEILING CHANNELS - TOP AND BOTTOM CHANNELS OF WALL
ASSEMBLY SHALL BE MIN. 20 GA. GALV. STEEL SIZED TO FIT STUDS. TOP CHANNEL TO
HAVE 2" FLANGES (MIN). BOTTOM CHANNEL TO HAVE 1-1/4" FLANGES (MIN). SECURE
BOTTOM CHANNELS WITH STEEL FASTENERS AT 24" O.C. (MAX). SECURE TOP
CHANNELS TO VALLEYS OF STEEL FLOOR UNITS (OR STRUCTURE ABOVE) WITH STEEL
FASTENERS AT 12" O.C. (MAX).
2. STEEL STUDS - MIN. 3-5/8" WIDE (UNLESS NOTED OTHERWISE), 1-1/4" LEGS, 3/8" FOLDED
BACK RETURN. FORMED OF 20 GA.(MIN) GALV. STEEL. MAX. SPACING 16" O.C. CUT
STUDS 1" LESS IN LENGTH THAN ASSEMBLY HEIGHT WITH BOTTOM NESTING IN AND
SECURED TO FLOOR CHANNEL, AND WITH TOP NESTING IN CEILING CHANNEL WITHOUT
ATTACHMENT.
3. SOUND ATTENUATION BATT INSUL. - 3-1/2" (DEPENDING ON STUD SIZE) GLASS FIBER
BATTS IN STUD CAVITY. FILL ENTIRE CAVITY FULL HEIGHT.
4. GYPSUM WALLBOARD- 5/8" THICK TYPE "X", 4' WIDE, ATTACHED TO STEEL STUDS AND
FLOOR CHANNELS WITH 1" LONG TYPE S SELF-TAPPING STEEL SCREWS AT 8" O.C.
ALONG THE VERTICAL AND BOTTOM EDGES AND 12" O.C. IN THE FIELD OF THE BOARD.
INSTALL WALLBOARD WITH A MIN. 1/2" AND MAX. 3/4" GAP BETWEEN THE TOP OF THE
WALLBOARD AND THE BOTTOM OF THE FLOOR UNIT VALLEYS (OR STRUCTURE ABOVE).
NO SCREWS ARE TO BE INSTALLED WITHIN 4" OF THE STEEL FLOOR UNIT VALLEYS AT
THE TOP OF THE WALL. ORIENT JOINTS VERTICALLY AND STAGGER JOINTS ON
OPPOSITE SIDES OF THE ASSEMBLY.
5. JOINT TAPE AND COMPOUND - VINYL, DRY OR PRE-MIXED JOINT COMPOUND, APPLIED
IN TWO COATS TO JOINTS AND SCREW HEADS; PAPER TAPE 2" WIDE EMBEDDED IN
FIRST LAYER OF COMPOUND OVER ALL JOINTS. JOINTS REINFORCED.
6. ACOUSTICAL SEALANT.
1/ 4" M
IN
BULLET RESISTANT PARTITION
16" O.C.
SECTION
PLAN
9 3-5/8" STUD
DESCRIPTION:
2 43
UL DESIGN #:
STC RATING:
FIRE RATING:
SCALE:
45 - 49
N.T.S.
ABOVE CEILING ID (STENCIL):
PLAN DESIGNATION:
GENERAL NOTES:
1. ALL REQUIREMENTS OF LISTED UL
DESIGN # MUST BE MET.
WALL PRIORITY:
OPENINGS: --
V A R
IE
S
1. STEEL FLOOR AND CEILING CHANNELS - TOP AND BOTTOM CHANNELS OF WALL
ASSEMBLY SHALL BE MIN. 20 GA. GALV. STEEL SIZED TO FIT STUDS. TOP CHANNEL TO
HAVE 2" FLANGES (MIN). BOTTOM CHANNEL TO HAVE 1-1/4" FLANGES (MIN). SECURE
BOTTOM CHANNELS WITH STEEL FASTENERS AT 24" O.C. (MAX). SECURE TOP
CHANNELS TO VALLEYS OF STEEL FLOOR UNITS (OR STRUCTURE ABOVE) WITH STEEL
FASTENERS AT 12" O.C. (MAX).
2. STEEL STUDS - MIN. 3-5/8" WIDE (UNLESS NOTED OTHERWISE), 1-1/4" LEGS, 3/8" FOLDED
BACK RETURN. FORMED OF 20 GA.(MIN) GALV. STEEL. MAX. SPACING 16" O.C. CUT
STUDS 1" LESS IN LENGTH THAN ASSEMBLY HEIGHT WITH BOTTOM NESTING IN AND
SECURED TO FLOOR CHANNEL, AND WITH TOP NESTING IN CEILING CHANNEL WITHOUT
ATTACHMENT.
3. SOUND ATTENUATION BATT INSUL. - 3-1/2" (DEPENDING ON STUD SIZE) GLASS FIBER
BATTS IN STUD CAVITY. FILL ENTIRE CAVITY FULL HEIGHT.
4. GYPSUM WALLBOARD- 5/8" THICK TYPE "X", 4' WIDE, ATTACHED TO STEEL STUDS AND
FLOOR CHANNELS WITH 1" LONG TYPE S SELF-TAPPING STEEL SCREWS AT 8" O.C.
ALONG THE VERTICAL AND BOTTOM EDGES AND 12" O.C. IN THE FIELD OF THE BOARD.
INSTALL WALLBOARD WITH A MIN. 1/2" AND MAX. 3/4" GAP BETWEEN THE TOP OF THE
WALLBOARD AND THE BOTTOM OF THE FLOOR UNIT VALLEYS (OR STRUCTURE ABOVE).
NO SCREWS ARE TO BE INSTALLED WITHIN 4" OF THE STEEL FLOOR UNIT VALLEYS AT
THE TOP OF THE WALL. ORIENT JOINTS VERTICALLY AND STAGGER JOINTS ON
OPPOSITE SIDES OF THE ASSEMBLY.
5. JOINT TAPE AND COMPOUND - VINYL, DRY OR PRE-MIXED JOINT COMPOUND, APPLIED
IN TWO COATS TO JOINTS AND SCREW HEADS; PAPER TAPE 2" WIDE EMBEDDED IN
FIRST LAYER OF COMPOUND OVER ALL JOINTS. JOINTS REINFORCED.
6. ACOUSTICAL SEALANT.
7. 5/16" BULLET RESISTANT PANEL. PANEL TO BE ON SECURE SIDE OF THE ROOM AND
SHOULD STOP JUST ABOVE THE FINISHED CEILING LINE
1/ 4" M
IN
12 Cadillac Dr., Suite 150 Brentwood, TN 37027 P 615.297.4554
©Copyright 2020
TLC No.:
www.tlc-engineers.com
120483
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
214 Centerview Drive Suite 300 Brentwood, TN 37027
615.370.8500woldhfr.com
WOLD | HFR DESIGN
102 THIRD AVENUE NE
HICKORY, NC 28601
PHONE: 828.315.9962
FAX: 828.315.9966
NC ENGINEERING LICENSE NO: P-0214
NC ARCHITECTURE LICENSE NO: 51254
MURFREESBORO, TN
B
IM
/T
V H
S
A lv in C
Y o rk
V A
I n te g ra te d H e a lt h /2
A R
C H
P
R O
J E
C T
C E
N T
R A
L .r v t
/2
/2
:0
:0
P
M
GI 01.02
WALL TYPE DETAILS TVHS - ALVIN C. YORK VAMC -
INTEGRATED HEALTH CENTER
AT05-20-2022
626-309
RA
● USE SEMI-GLOSS PAINT.
● LOCATE NOT MORE THAN 12'-0" O.C. ON CORRIDOR SIDES OF PARTITIONS, AND WITH A LEAST ONE MESSAGE PER ROOM ON ROOM SIDE OF PARTITION, AND WITHIN 15'-0" OF THE END OF EACH WALL.
● STENCIL MESSAGE SIMILAR TO: "SMOKE PARTITION" OR "1-HR FIRE BARRIER."
● IDENTIFY PARTITIONS ABOVE CEILINGS ON BOTH SIDES OF PARTITIONS EXCEPT WITHIN SHAFTS IN RED
LETTERS NOT LESS THAN 4" HIGH WITH AT LEAST A 3/8" STROKE.
12. FIRE AND SMOKE PARTITION / BARRIER IDENTIFICATION:
11. PENETRATIONS IN WALLS SHALL BE SEALED AS REQUIRED BY THE WALL RATING PER AN APPROVED UL
DESIGN.
10. GYPBOARD PANELS SHALL BE PLACED A MINIMUM OF 1/4" ABOVE FLOOR AND SHALL BE CUT WITHIN 1/4" MAX TOLERANCE TO SHAPE OF DECK OR STRUCTURE ABOVE. GAPS BETWEEN PANELS SHALL BE <1/4".
● PROVIDE DEFLECTION AND BRIDGING CLIPS.
● MAINTAIN CLEARANCE UNDER STRUCTURAL BUILDING MEMBERS TO AVOID DEFLECTION TRANSFER TO
STUDS. PROVIDE EXTENDED LEG CEILING RUNNERS.
9. DO NOT TRANSFER DEFLECTION FROM STRUCTURAL BUILDING MEMBERS TO STUDS. CONTRACTOR'S
OPTION, PROVIDE EITHER OF THE FOLLOWING:
8. EXTEND ALL WALL CONSTRUCTION TO THE DECK ABOVE AND SEAL U.N.O.
7. INSTALL ACOUSTICAL GASKETS AT FLOOR AND CEILING TRACK LOCATIONS.
6. PROVIDE ACOUSTICAL INSULATION FULL HEIGHT IN ALL WALLS U.N.O.
5. STAGGER JOINTS ON OPPOSITE SIDES OF PARTITIONS.
4. ALL FRAMING SHALL BE 20 GA U.N.O.
● PROVIDE FIRE RATED IMPACT RESISTANT GYPBOARD 4'-0"H ON ALL WALLS NOT SCHEDULED TO RECEIVE RIGID WALL PROTECTION, AND ADDITIONAL LOCATIONS AS NOTED ON DRAWINGS. (IMPACT RESISTANT GYPBOARD SHALL TAKE PRIORITY AT LOCATIONS INDICATED TO RECEIVE GLASS FIBER
FACED GYPSUM PANELS.)
● PROVIDE FIRE RATED GLASS FIBER FACED GYPSUM PANELS ON INTERIOR SURFACE OF EXTERIOR WALLS, TOILET ROOMS, JANITOR'S CLOSETS, MECHANICAL SPACES, AND WITHIN 4'-0" OF WATER...
● ALL GYPBOARD SHALL BE 5/8" TYPE 'X' U.N.O.
3. GYPBOARD REQUIREMENTS:
1. ALL WALLS SHALL BE 3-5/8" METAL STUD AT 16"0.C. MAX U.N.O.
REFERENCE WALL TYPE DETAILS, PLANS, AND SPECIFICATIONS.
GENERAL WALL NOTES
INTERSECTION OF RATED WALLS
GENERAL NOTES
1. THIS IS DIAGRAMMATIC IN NATURE AND SHOWS GENERIC
CONDITIONS. SEE FLOOR PLANS FOR ACTUAL CONDITIONS.
2. MAINTAIN NOTED CLEARANCES AT ALL DOORS.
MIN
18"
M
IN
(A)
FRONT APPROACH, PULL SIDE
M
IN
(B)
FRONT APPROACH, PUSH SIDE
M
IN
(C)
FRONT APPROACH, PUSH SIDE,
DOOR PROVIDED WITH BOTH
CLOSER AND LATCH
MIN
12" MIN
36"
M
IN
(D)
HINGE APPROACH, PULL SIDE
M
IN
(F)
HINGE APPROACH, PUSH SIDE
MIN
42"
M
IN
(E)
HINGE APPROACH, PULL SIDE
MIN
22" 48 M
IN
(G)
HINGE APPROACH, PUSH SIDE,
DOOR PROVIDED WITH BOTH
CLOSER AND LATCH
MIN
22"
MIN
24"
M
IN
(H)
LATCH APPROACH, PULL SIDE
MIN
24"
M
IN
(I)
LATCH APPROACH, PULL SIDE,
DOOR PROVIDED WITH
CLOSER
M
IN
(J)
LATCH APPROACH, PUSH SIDE
MIN
24" 48 M
IN
(K)
LATCH APPROACH, PUSH SIDE,
DOOR PROVIDED WITH CLOSER
MIN
24"
MIN
18"
M
IN
(A)
PULL SIDE
X > 8"
MANEUVERING CLEARANCES AT RECESSED
DOORS AND GATES
MANEUVERING CLEARANCES AT MANUAL
SWINGING DOORS AND GATES
(B)
PUSH SIDE
M
IN
X > 8"
(C)
PUSH SIDE, DOOR PROVIDED
WITH BOTH CLOSER AND
LATCH
M
IN
X > 8"
MIN
12"
DOORS IN SERIES AND GATES IN SERIES
(A)
48" MIN
(B)
48" MIN
(C)
48" MIN
(BACK)(SIDE CONTROL WALL) (SIDE)
T .O . S
E A T
SOME ITEMS MAY NOT BE APPLICABLE
HCWV
GB/U GB/U
GB-42
MIRROR
TPD
TB-18
FPDL
BCS
PTD-WR
C L P U
LL
H A N D
LE
C L F
LU
S H C O N T R O L
GB-18 INSULATED
SUPPLY AND
DRAIN LINES
TPD
M A X
M A X
M A X
M A X
M A X
M
IN
S U R F A C E
M A X T O
R E F
LE
C T
IV
E
25"MAX
17"MIN
MIN
30"
MIN
60"
S U R F A C E
T .O
G R
IP
P
IN
G
M A X
6" MAX
MIN
30" 36" 36"
1"
1"
18"
36"
18"
S U R F A C E
T .O
G R
IP
P
IN
G
6" M A X
1"
M
IN
T O O U T
LE
T
M
IN
M A X
G R
IP
S U R F A C E
T .O
1"
42" MIN
MAX
12"
40" ±1"
S U R F A C E
M A X T O
R E F
LE
C T
IV
E
18" OR 24"
(FRONT) (SIDE)
M A X
M
IN
1"
4" MAX
(BACK) (CONTROL WALL)
GB/L
CURTAIN
ROD
CONTRO
L AREA
M
IN
M A X
FLUSH
VALVE
M A X
6" MAX
36" MIN
60" MIN±1"
17"
GB-36
CLEAR
15" MIN
CLEAR
15" MIN
8" (±1")
M A X
C O N T R O
LS
H C A C C E S S
IB
LE
"54
MIN
15"
M A X
CONTROL
AREA
MAX
15"
M
IN
CONTROL
AREA, IF
SEAT
PROVIDED
PROVIDED
27" MAX
IF SEAT
M A X
M
IN6" MAX
PTD
M A X
M A X
C O N T R O
LS
M A X
SD
M A X
5" MAX 42
M A X
C O N T R O
LS
EHD EHD-HF
C O N T R O
LS
C O N T R O
LS
C O N T R O
LS
UNOBSTRUCTED ITEMS
MAX
24". 44 M A X
C O N T R O
LS
PAPER TOWEL
DISPENSER & WASTE
RECEPTACLE (PTD-WR)
C O N T R O
LSFPDR
PAPER
TOWEL
DISPENSER
(PTD)
ELECTRIC
HAND DRYER
(EHD)
ELECTRIC
HAND DRYER -
HANDS FREE
(EHD-HF)
SOAP
DISPENSER
(SD)
FEMININE
PRODUCT
DISPENSER
(FNDR)
M A X
FEMININE
PRODUCT
DISPOSAL UNIT
(FNDL)
SD (ONLY) SD, PTD, EHD
OR EHD-HF
BACK WALL
MOUNTED
OBSTRUCTED ITEMS
SIDE WALL
MOUNTED
TOILET PAPER
DISPENSER
(TPD)
TOWEL BAR
18" MIN
(TB-18)
BABY CHANGING STATION
(BCS)
MIN
12".
MIN
24".
G R
IP
S U R F A C E
T .O
HC WATER CLOSET
(HCWC)
GRAB BAR
42" (GB-42)
(SIDE) (FRONT)
GRAB BAR
18" (GB-18)
GRAB BAR
36" (GB-36)
M
IN
54" MIN
HC LAVATORY
(SIDE) (FRONT)
COAT HOOK
(CH)
(FRONT)
MIRROR WITH OR
WITHOUT SHELF
(MIR/S-18X36)
(MIR-18X36)
(MIR/S-24X36)
(MIR-24X36)
ROLL IN SHOWER
(RS)
CONT. "U" SHAPED GRAB
BAR (GB/U)
MAX
6"
MAX
6"
GB/L
CONT. "L" SHAPED GRAB BAR
(GB/L)
TRANSFER SHOWER
(TS)
(SIDE)
(CONTROLS ON ANY WALL
IF NO SEAT IS PROVIDED)
12 Cadillac Dr., Suite 150 Brentwood, TN 37027 P 615.297.4554
©Copyright 2020
TLC No.:
www.tlc-engineers.com
120483
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
214 Centerview Drive Suite 300 Brentwood, TN 37027
615.370.8500woldhfr.com
WOLD | HFR DESIGN
102 THIRD AVENUE NE
HICKORY, NC 28601
PHONE: 828.315.9962
FAX: 828.315.9966
NC ENGINEERING LICENSE NO: P-0214
NC ARCHITECTURE LICENSE NO: 51254
MURFREESBORO, TN
B
IM
/T
V H
S
A lv in C
Y o rk
V A
I n te g ra te d H e a lt h /2
A R
C H
P
R O
J E
C T
C E
N T
R A
L .r v t
/2
/2
:0
:0
P
M
GI 01.03
ACCESSIBILITY DETAILS TVHS - ALVIN C. YORK VAMC -
INTEGRATED HEALTH CENTER
AT05-20-2022
626-309
RA
NOT TO SCALE
ACCESSIBLE DOOR CLEARANCES
NOT TO SCALE
TYPICAL TOILET FIXTURE AND ACCESSORY MOUNTING REQUIREMENTS
UP
WORK DRESS DRESS
STAGE
AUDITORIUM
STOR. MALE TLT. FEMALE TLT.
BARBER SHOP VENDING STORAGE
CANTEEN CANTEEN RETAIL STOR. MALE TLT. FEMALE TLT.
WOMENS
LOUNGE
REC. THERAPY
STORAGE
TLT.
REC.
THERAPY
CHIEF
REC.
THERAPY
OFFICE
ELEC. SHOWER
POOL
LOCKER
TLT.
HAC
STAIR ACCESS
HAC STORAGE OFFICEREC.
LOCKER
EXERCISE/GYM.
REC. HALL
KITCHEN
MECH.
ELEC.
ELEC.
HAC
STORAGE
RETAIL STOR.
RETAIL STOR.
TLT.TLT.
STOCK ROOM
CANTEEN
DISH WASH
MECH.
FOOD STOR.
RECEIVING
MECH.
KITCHEN
CHILLER PLANT
UP
RAMP DN
DN
R A M
P D
N
R A M
P D
N
BUILDING 107 (LOCATION
OF PROJECT)
EXISTING PIPE TUNNEL
EXISTING PIPE TUNNEL
EXISTING PIPE TUNNEL
EXISTING POOL
12 Cadillac Dr., Suite 150 Brentwood, TN 37027 P 615.297.4554
©Copyright 2020
TLC No.:
www.tlc-engineers.com
120483
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
214 Centerview Drive Suite 300 Brentwood, TN 37027
615.370.8500woldhfr.com
WOLD | HFR DESIGN
102 THIRD AVENUE NE
HICKORY, NC 28601
PHONE: 828.315.9962
FAX: 828.315.9966
NC ENGINEERING LICENSE NO: P-0214
NC ARCHITECTURE LICENSE NO: 51254
MURFREESBORO, TN
B
IM
/T
V H
S
A lv in C
Y o rk
V A
I n te g ra te d H e a lt h /2
A R
C H
P
R O
J E
C T
C E
N T
R A
L .r v t
/2
/2
:0
:0
P
M
GI 01.20
EXISTING PLAN/CAMPUS MAP TVHS - ALVIN C. YORK VAMC -
INTEGRATED HEALTH CENTER
AT05-20-2022
626-309
RA
1/16" = 1'-0"
1 EXISTING FLOOR PLAN
0 8' 16' 32'4'
4 CAMPUS MAP
2 FIRST FLOOR
0 8' 16' 32'4'
3 BASEMENT
0 8' 16' 32'4'
HOLDOPEN
UP
UP
72.0'
.0
CORRIDOR TO BLDG 7
AREA B
AREA A
A R
E A
B
A R
E A
A
ELECTRICAL
STAIRS
SIM MAINTENANCE
G30G
PROCEDURE SIM LAB
G30FCONTROL ROOM
G30E
WAITING
G39
MULTI-PURPOSE
G20J
MULTI-PURPOSE
G20F
MULTI-PURPOSE
G20D
MULTI-PURPOSE
G20B
MULTI-PURPOSE
G20
MULTI-PURPOSE
G20H
STOR.
G20C
MED/SURG SIM LAB
G30D KITCHEN/SERVING
G21
EDUC CHIEF
G17A
MUSIC THERAPY CLINIC
G13
WC STORAGE
G12B
REC. THERAPY CLINIC
G08
COMPUTER LAB
G16
STOR.
G20A
STOR.
G20E
STOR
G20G
STOR.
G20I
BARBER CART
G02FOOD SERVICE CHIEF
G03
FOOD SERVICE VEND SUPPLY
G04
CORRIDOR
G54
CORRIDOR
G52
MUSIC THER. 1
G43
MUSIC THER. 2
G42
CORRIDOR
G45
WORK AREA
G15
ENTRY
G01
CORRIDOR
G46
COURTYARD
G10
CORRIDOR
G48
CORRIDOR
G48A
CORRIDOR
G49
CORRIDOR
G50
CORRIDOR
G51
STORAGE
G20K
PRACTICE ROOM
G13B
MUSIC STORAGE
G13A
ALS CLASSROOM
TRNG EQUIP STOR
G30C
STAFF LOUNGE
G33
CREATIVE ARTS GROUP
G34
LOBBY
G36
PMRS STORAGE
G31
ACCESS STAIR
G26
FEMALE
G24
MALE
G25
LACTATION
G27
HAC
G30I
MALE
G37
FEMALE
G38
MEDIA COORD.
G17B
WORK
G17
PAT. RESOURCE
G40
RT SPVR.
G15A
PMRS CONSULT
G14
HAC
G07
RECREATION
STORAGE
G08B
MALE
G09A
FEMALE
G09C
VENDING
G32
KINESIO GROUP THERAPY
G12
WORK
G12A
KITCHENETTE
G08A
VESTIBULE
G35
SECURITY
G35A
STORAGE
G34A
CORRIDOR
G55
STORAGE
G30K
STORAGE
G30H
DE-BRIEF
G30A
CORRIDOR
G30 CORRIDOR
G30
CONNECTOR
G47
FEMALE SHOWER
G09D
MALE SHOWER
G09B
ENTRY
G44
CORRIDOR
G53
CHARGING CART STOR.
G19WHOLE HEALTH
STORAGE
G18
IT
G23
CHASE
G26A
CLO.
G30B
C O
R R
ID
O
R T
O B
LD
G
OUTLINE SHOWS
MECH EQUIP
PLATFORM ABOVE,
REF. 3/AE 01.21
OUTLINE SHOWS MECH EQUIP
PLATFORM ABOVE, REF. 2/AE
01.21
REFERENCE MECHANICAL
SHEETS FOR SCOPE OF
WORK REQUIRED IN THE
MEZZANINE LEVEL. ANY
WORK THAT IS DISTURBED
DURING MECHANICAL WORK
SHOULD BE REPAIRED TO
ORIGINAL CONSTRUCTION.
ROOF BELOW
ROOF BELOW
ROOF BELOW
REC THERAPY BELOW
STAIR
SCOPE LEGEND
IN SCOPE RENOVATION
IN SCOPE ADDITION
AHU - 1
AHU - 2
MULTIPURPOSE ROOM BELOW
WALKING PATH
SIM LAB AREA BELOWROOF BELOW
MECH EQUIP PLATFORM 2
12 Cadillac Dr., Suite 150 Brentwood, TN 37027 P 615.297.4554
©Copyright 2020
TLC No.:
www.tlc-engineers.com
120483
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
214 Centerview Drive Suite 300 Brentwood, TN 37027
615.370.8500woldhfr.com
WOLD | HFR DESIGN
102 THIRD AVENUE NE
HICKORY, NC 28601
PHONE: 828.315.9962
FAX: 828.315.9966
NC ENGINEERING LICENSE NO: P-0214
NC ARCHITECTURE LICENSE NO: 51254
MURFREESBORO, TN
KEYPLAN
AREA A
AREA B
OUT OF
SCOPE
B
IM
/T
V H
S
A lv in C
Y o rk
V A
I n te g ra te d H e a lt h /2
A R
C H
P
R O
J E
C T
C E
N T
R A
L .r v t
/2
/2
:1
:0
P
M
GI 01.21
OVERALL SCOPE TVHS - ALVIN C. YORK VAMC -
INTEGRATED HEALTH CENTER
AT05-20-2022
626-309
RA
GENERAL NOTE:
ALL WORK SCHEDULED TO BE COMPLETED BASED ON MEP OR ANY
OTHER WORK OUTSIDE THE SCOPE OF WORK SHOULD BE COORDINATED
WITH THE FACILITY.
ANY WORK THAT RESULTS IN THE NEED TO REMOVE OR ALTER EXISTING
CONDITIONS OUTSIDE THE SCOPE OF WORK SHOULD BE REPLACED OR
REPAIRED TO MATCH THE EXISTING FINISH AND CONSTRUCTION
CONDITIONS BEING REMOVED AT NO COST TO THE FACILITY.
THIS INCLUDES, BUT IS NOT LIMITED TO THE FOLLOWING:
GYPSUM BOARD AND FINISHES
DOORS INCLUDING FRAMES/HARDWARE OR OTHER ACCESSORIES
WINDOWS AND FRAMES
CEILING TILES AND GRIDS
FLOORING INCLUDING FINISHES
1/16" = 1'-0"
1 GROUND FLOOR OVERALL SCOPE PLAN
1/16" = 1'-0"
2 MECH EQUIP PLATFORM 1
0 8' 16' 32'4'
0 8' 16' 32'4'
1/16" = 1'-0"
3 MECH EQUIP PLATFORM 2 SCOPE PLAN
C O R R
ID
O R T O B
LD
G
CORRIDOR TO BUILDING 7
MECH EQUIP PLATFORMS
INCLUDED AS PART OF PHASE IIB
PHASING LEGEND
PHASE I
PHASE III
PHASE IV
PHASE V
PHASE II
PATIENT PATH
FOR PHASE II
PATIENT PATH
FOR PHASE III
PHASE IA OF THE PROJECT WILL INCLUDE DEMOLITION OF
THE ENTIRE GYM AREA INCLUDING ALL FINISHES/CEILINGS
WALLS AND THE BRICK THAT IS ALONG THE INSIDE OF THE
GYM. REF. DEMO PLANS FOR FULL EXTENT OF DEMOLITION.
THIS PHASE SHALL ALSO INCLUDE THE BUILD BACK OF ALL
NEW COMPONENTS AND WALLS WITHIN THE EXISTING GYM
AREA. REF AE 01.01 FOR LIMITS OF PHASE 1A CONSTRUCTION
THE IT/COMM ROOMS WILL NEED TO COMPLETELY FINISHED
OUT FIRST.
PHASE IIA SHALL CONSIST OF THE DEMOLITION AND
COMPLETION OF A PORTION OF THE PASS THRU CORRRIDOR
TO BUILDING 7 AND BUILDING 116. THIS WORK SHALL BE
COMPLETELY CLOSED OFF WITH TEMPORARY PARTITIONS TO
CONCEAL DUST FROM ESCAPING. DURING PHASE IIA,
PATIENTS WILL PASS THRU THE WORK THAT WAS DEMOED
DURING PHASE IB. THIS AREA SHALL BE LEFT OPEN, CLEANED
AND CLEAR OF ANY HAZARDS FOR PATIENTS TO PASS THRU.
PHASE I PHASE III
ONCE PHASE IIA IS COMPLETE, THE CORRIDOR SHALL BE
OPENED UP TO ALLOW PATIENTS TO PASS THRU.
TEMPORARY PARTITIONS SHALL BE PLACED TO SEPERATE
DEMOLITION THAT WILL BEGIN AS PART OF PHASE IIB. REF. GI.
01.41B FOR THE LOCATION OF THOSE PARTITIONS. IN
ADDITION TO THIS, THE TEMPORARY PARTITIONS SHALL
REMAIN UP THAT SEPERATE PHASE IB AND THAT PHASE
SHALL NOW BE FINISHED OUT AS DESIGNED. PHASE IIB CAN
ALSO NOW BE FINISHED AS DESIGNED.
PHASE IV
PHASE IB SHALL CONSIST OF THE DEMOLITION OF THE
OFFICES, TOILETS ETC. THAT ARE SOUTH OF THE EXISTING
PASS THRU CORRIDOR. IN ORDER TO KEEP THE CORRIDOR IN
OPERATION DURING CONSTRUCTION, A TEMPORARY
PARTITION WILL NEED TO BE CONSTRUCTED TO CLOSE OFF
THE CORRIDOR FROM ANY CONSTRUCTION DEBRIS, REF. GI.
01.40 FOR MORE INFORMATION ON LOCATION OF TEMPORARY
BARRIER. ONCE THE…