This document provides specifications for integrated door assemblies required for a construction project to build an integrated health center at the Alvin C. York VA Medical Center in Murfreesboro, Tennessee. The specifications include requirements for metal doors, metal frames, integrated hardware such as exit devices and continuous hinges, and finishes. Fire ratings and smoke ratings are also specified for some doors. The project is solicited under opportunity number 36C77623B0037 by the Department of Veterans Affairs Technology Acquisition Center in Austin, Texas. Integrated door assemblies must meet performance standards for cycles and be labeled if fire rated. Manufacturers are required to provide data and samples, and the installer must demonstrate experience.

View the file

Other files

File Type Posted
36C77623B0037 0008 - 8-29-23.pdf PDF
36C77623B0037 0007.pdf PDF
36C77623B0037 0006 - 8-22-23.pdf PDF
36C77623B0037 0005 - 8-18-23.pdf PDF
36C77623B0037 0004 - 08-15-2023.pdf PDF
Technical Questions Round 2 - 8-14-23.docx DOCX document
232113.13 FL - UNDERGROUND HYDRONIC PIPING.pdf PDF
2023-08-09 - IHC - Addendum 2.pdf PDF
IHC - Add 2 - Narrative.pdf PDF
36C77623B0037 0003 - 08-03-2023.pdf PDF
Technical Questions Tracking Spreadsheet - Murf IHC - 7-24-23.pdf PDF
VAMC - IHC - Addendum 1 - Dwgs.pdf PDF
36C77623B0037 0002.pdf PDF
Integrated Health Laydown Areas.pdf PDF
Attachment 17 - Construction Wage Rates - Rutherford County - 6-30-23.pdf PDF
Site Visit Sign In Sheet.pdf PDF
36C77623B0037 0001.docx DOCX document
Civil Binder.pdf PDF
Attachment 5 - CIVIL BINDER.pdf PDF
Attachment 11 - MECH BINDER-1.pdf PDF
Attachment 19 - Site Visit Instructions.pdf PDF
36C77623B0037_1.docx DOCX document
Attachment 9 - GENERAL BINDER.pdf PDF
Attachment 3 - ARCHITECTURAL BINDER-1.pdf PDF
Attachment 2 - IHC - SPEC - VOLUME 2.pdf PDF
Attachment 8 - FP BINDER.pdf PDF
Attachment 18 - Contractor Safety - Environmental Form.docx DOCX document
Attachment 7 - ELEC BINDER.pdf PDF
Attachment 1 - IHC - SPEC - VOLUME 1.pdf PDF
Attachment 13 - PLUMBING BINDER.pdf PDF
Attachment 15 - TECH BINDER.pdf PDF
Attachment 10 - INTERIORS BINDER.pdf PDF
Attachment 12 - MECH BINDER-2.pdf PDF
Attachment 17 - Construction Wage Rates.pdf PDF
Attachment 6 - DEMO BINDER1.pdf PDF
Attachment 4 - ARCHITECTURAL BINDER-2.pdf PDF
Attachment 14 - STRUCTURAL BINDER.pdf PDF
Attachment 16 - Limitations on Subcontracting - Construction Jan 2023 Deviation.docx DOCX document
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCT INTEGRATED HEALTH CENTER

TVHS ALVIN C YORK VAMC

Murfreesboro, TN

VA Project Number 626-309

08 17 10 - 1

SECTION 08 17 10 REV 2

INTEGRATED DOOR ASSEMBLIES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Integrated door assemblies including metal door frame, door, and hardware, unless specified in another Section, installed at cross-corridor locations.

B. Smoke and draft control seals, unless specified in another Section.

1.2 RELATED REQUIREMENTS

A. Lock Cylinders: Section 08 71 00, DOOR HARDWARE.

B. Automatic Door Operators: Section 08 71 13, AUTOMATIC DOOR OPERATORS.

C. Electrical Power: DIVISION 26, ELECTRICAL.

1.3 APPLICABLE PUBLICATIONS

A. Comply with references to extent specified in this section.

B. Builders Hardware Manufacturers Association (BHMA):

1. A156.3-14 - Exit Devices.

2. A156.26-06 - Continuous Hinges.

3. A156.32-14 - Integrated Door Opening Assemblies.

C. ASTM International (ASTM):

1. A1011/A1011M-14 - Steel, Sheet and Strip, Hot-Rolled, Carbon, Structural, High-Strength Low-Alloy, High-Strength Low-Alloy with

Improved Formability, and Ultra-High Strength.

2. E2180-07(2012) - Determining the Activity of Incorporated

Antimicrobial Agents in Polymeric or Hydrophobic Materials.

D. Door and Hardware Institute (DHI):

1. Recommended Locations for Architectural Hardware for Standard Doors

& Frames (2004).

2. Recommended Locations for Builders' Hardware Custom Steel Doors &

Frames (1996).

E. National Fire Protection Association (NFPA):

1. 105-16 - Smoke Door Assemblies and Other Opening Protectives.

2. 252-12 - Fire Tests of Door Assemblies.

F. Steel Door Institute (SDI):

1. A250.3-11 - Test Procedure and Acceptance Criteria for Factory

Applied Finish Coatings for Steel Doors and Frames.

08 17 10 - 2

2. A250.8-14 - Specifications for Standard Steel Doors and Frames.

3. A250.10-11 - Test Procedure and Acceptance Criteria for Prime

Painted Steel Surfaces for Steel Doors and Frames.

G. UL LLC (UL):

1. 10C-09 - Positive Pressure Fire Tests of Door Assemblies.

2. 1784-15 - Air Leakage Tests of Door Assemblies and Other Opening

Protectives.

1.4 PREINSTALLATION MEETINGS

A. Conduct preinstallation meeting at project site minimum 30 days before beginning Work of this section.

1. Required Participants:

a. Contracting Officer's Representative.

b. Architect/Engineer.

c. Contractor.

d. Installer.

e. Other installers responsible for adjacent and intersecting work, including electrical.

2. Meeting Agenda: Distribute agenda to participants minimum 3 days before meeting.

a. Installation schedule.

b. Installation sequence.

c. Preparatory work.

d. Protection before, during, and after installation.

e. Installation.

f. Transitions and connections to other work.

g. Other items affecting successful completion.

3. Document and distribute meeting minutes to participants to record decisions affecting installation.

1.5 SUBMITTALS

A. Submittal Procedures: Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

B. Submittal Drawings:

1. Show size, configuration, and fabrication and installation details.

2. For each opening, list finish hardware items included in assembly, finish, degree of opening, and electrical rough-in requirements according to Door Schedule.

08 17 10 - 3

3. Submit templates to door and frame manufacturers to ensure proper size and location of hardware.

C. Manufacturer's Literature and Data:

1. Description of each product.

2. Installation instructions.

D. Sustainable Construction Submittals:

1. Recycled Content: Identify post-consumer and pre-consumer recycled content percentage by weight.

2. Low Pollutant-Emitting Materials:

a. Show volatile organic compound types and quantities.

E. Certificates: Indicate integrated door assemblies comply with specifications.

1. Show fire rated integrated door assembly is UL Listed for specified application.

F. Qualifications: Substantiate qualifications comply with specifications.

1. Installer.

G. Operation and Maintenance Data:

1. Care instructions for each exposed finish product.

2. Maintenance and adjustment instructions for integrated door assemblies.

1.6 QUALITY ASSURANCE

A. Installer Qualifications:

1. Regularly installs specified products.

2. Installed specified products with satisfactory service on five similar installations for minimum five years.

a. Provide contact names and addresses for completed projects when requested by Contracting Officer's Representative.

1.7 DELIVERY

A. Deliver products in manufacturer's original sealed packaging.

B. Mark packaging, legibly. Indicate manufacturer's name.

C. Before installation, return or dispose of products within distorted, damaged, or opened packaging.

1.8 STORAGE AND HANDLING

A. Store products indoors in dry, weathertight facility.

B. Protect products from damage during handling and construction operations.

08 17 10 - 4

1.9 FIELD CONDITIONS

A. Field Measurements: Verify field conditions affecting integrated door assembly fabrication and installation. Show field measurements on

Submittal Drawings.

1. Coordinate field measurement and fabrication schedule to avoid delay.

2. Coordinate electrical work for electrified hardware installation.

1.10 WARRANTY

A. Construction Warranty: FAR clause 52.246-21, "Warranty of

Construction."

B. Manufacturer's Warranty: Warrant door closers and hinges against material and manufacturing defects.

1. Warranty Periods:

a. Door Closers: 10 years.

b. Steel Pinned Continuous Hinges: 10 years.

PART 2 - PRODUCTS

2.1 SYSTEM PERFORMANCE

A. Design integrated door assemblies complying with specified performance:

1. BHMA A156.32: Grade 1: 1,000,000 cycles.

B. Fire Rated Doors:

1. Fire Resistance Rating: As shown in Door Schedule.

2. Label: Comply with NFPA 252, UL 10C, and labeled by qualified testing and inspection agency showing fire resistance rating.

C. Smoke Rated Doors:

1. Smoke Resistance Rating: As shown in Door Schedule.

2. Label: Comply with NFPA 105, UL 1784, and labeled by qualified testing and inspection agency showing smoke resistance rating.

2.2 PRODUCTS - GENERAL

A. Basis of Design: Section 09 06 00, SCHEDULE FOR FINISHES.

B. Provide each integrated door assembly from one manufacturer.

C. Sustainable Construction Requirements:

1. Steel Recycled Content: 30 percent total recycled content, minimum.

2. Low Pollutant-Emitting Materials: Comply with VOC limits for the following products:

a. Non-flooring adhesives and sealants.

08 17 10 - 5

b. Paints and coatings.

2.3 INTEGRATED DOOR ASSEMBLY

A. Metal Doors: SDI A250.8; Level 2 and Physical Performance Level B, heavy duty; Model 2 seamless.

1. Face: ASTM A1011/A1011M; cold rolled steel, 1.0 mm (0.04 inches) thick, minimum.

a. Cladding: Wood veneer.

2. Core: Kraft paper honeycomb or polystyrene.

3. Thickness: 44 mm (1-3/4 inch).

4. Reinforce door for hardware installation.

B. Metal Frames: SDI A250.8 Level 2.

1. Metal: ASTM A1011/A1011M; cold rolled steel, 1.3 mm (0.05 inches) thick, minimum.

2. Construction: Continuously welded.

3. Reinforce frame for hardware.

a. Continuous Hinges: 2.3 mm (0.09 inches) thick.

b. Other Hardware: Comply with SDI A250.8.

4. Frame Anchors: Provide adjustable type anchors coordinated with wall construction, minimum 4 per jamb.

C. Integrated Hardware:

1. Exit Device: BHMA A156.3; Grade 1, passage function, inset in door face, clean and unobtrusive in design.

a. Push Bar End Caps: Metal, plated satin nickel (BHMA 619) finish.

b. Exit Device Trim: Lever matching door hardware specified in

Section 08 71 00, DOOR HARDWARE.

2. Continuous Hinges: BHMA A156.26.

a. Plastic Laminate Clad Doors: Wrap-around style hinge guards and provide stainless steel wrap-around edge guards at strike edge of door.

3. Other Hardware: As scheduled in this section.

2.4 FINISHES

A. Hardware Finish Symbols:

Table 1 Hardware Finish Symbols

US BHMA 156.18 Description

USP 600 Primed for field painting

08 17 10 - 6

US15 619 Dull Nickel Plated

US26D 626/652 Satin Chrome Plated

US28 628 Satin Aluminum

US32 629 Bright Stainless

US32D 630 Satin Stainless

N/A 689 Aluminum Painted

B. Finish Requirements:

1. Door Faces: Plastic Laminate .

2. Frames: Prime painted, SDI A250.10.

3. Door Hardware:

a. Continuous Hinges: BHMA 630.

b. Push Bar: BHMA 630 clad with BHMA 619 end caps.

c. Exit Device Trim: BHMA 630.

d. Push/Pull Trim: BHMA 626.

e. Door Closers: BHMA 689.

f. Miscellaneous: To match other finishes.

4. Anti-Microbial Coating: ASTM E2180; ionic silver coating.

5. Apply coating to hand-operated hardware including levers, pulls, push bars, push plates, and paddles.

PART 3 - EXECUTION

3.1 PREPARATION

A. Examine and verify substrate suitability for product installation.

B. Protect existing construction and completed work from damage.

3.2 INSTALLATION - INTEGRATED DOOR ASSEMBLIES

A. Install products according to manufacturer's instructions and approved submittal drawings .

B. Install door hardware at locations indicated in DHI Recommended

Locations for Architectural Hardware for Standard Steel Doors & Frames and DHI Recommended Locations for Builders' Hardware Custom Steel Doors

& Frames, unless otherwise indicated, or to comply with requirements of governing regulations, or if otherwise directed by Contracting

Officer's Representative.

C. Install door hardware in compliance with manufacturers' instructions, and templates. Comply with specified degree of opening for doors with automatic operators and overhead door closers. Securely fasten

08 17 10 - 7 hardware. Confirm operating parts move freely and smoothly without binding, sticking, and excessive clearance.

D. Coordinate installation and interface wiring with fire alarm and smoke detection systems. Provide auxiliary contacts, relays, and interface for fire alarm and security systems.

E. Remove or protect door hardware, before painting and finishing performed after integrated door assembly installation.

F. Adjust and check door assembly and each operating hardware item to ensure correct operation and function. Replace products which cannot be adjusted to operate as intended.

G. Final Adjustment: Perform final hardware check and adjustment maximum one month before building acceptance or partial building occupancy.

3.3 CLEANING

A. Clean exposed surfaces, including hardware. Do not use cleaners that will harm finishes.

3.4 PROTECTION

A. Protect integrated door assemblies from construction operations.

3.5 SCHEDULES

A. The following is a general listing of the Integrated Door Assembly requirements and is not intended for use as a final door submittal.

Provide hardware items required by established standards and practices, and to meet IBC and NFPA 101 whether specified or not in the following

LOCK CYLINDER BY SECTION 08 71 00, DOOR HARDWARE.

AUTO DOOR OPERATOR AND CONTROLS BY SECTION 08 71 13, AUTOMATIC DOOR

OPERATORS.

HW-8

Each [MHO] Pair Integrated Doors

(double egress) to Have:

RATED

1 Steel Frame

1 Integrated Pair Doors w/Auto

Flush Bolts & Push/Pull Trim

Q2241 x TYPE 25 LESS BOTTOM BOLT

AUTO

FLUSH BOLT (INACTIVE LEAF) x ACTIVE

CONCEALED VERTICAL LATCH (ACTIVE

LEAF)

08 17 10 - 8

2 Continuous Hinges A51031B x WIDE THROW AS REQUIRED TO

ACHIEVE FULL DOOR SWING

1 Coordinator TYPE 21A

1 Self-Adhesive Astragal R0Y_14

2 Closers C02011 (PT4D, PT4H) x 180° SWING

2 Magnetic Holders C00011 TRI-VOLTAGE

1 Set Self-Adhesive Seals R0E154

POWER, WIRING, CONDUIT, AND FIRE ALARM CONNECTION BY DIVISION 26.

- - E N D - -