This is a memorandum from the Utilities and Energy Management Branch Head of the Public Works Department at Naval Submarine Base New London establishing the contractor planned utility outage process effective December 5, 2025.

The memorandum defines the duties and responsibilities for six key organizational roles in coordinating planned utility outages. The ROICC Engineering Technician initiates the process by scheduling the outage date and time with the contractor, creating an Outage Notification Form, and submitting it to the UEM Engineering Technician at least 10 business days prior to execution. The UEM Engineering Technician verifies contractor employee information, assigns a work request number, and routes the form to the appropriate Supervisory Utilities Superintendent (either PRC322 for High Voltage or PRC323 for Steam/Water/Wastewater) within one business day. If the outage cannot be supported on requested dates, the UEM Engineering Technician coordinates alternate dates. The Supervisory Utilities Superintendent reviews time and manpower requirements and either approves or negotiates alternative dates. The Utilities Work Leader completes the Outage Notification Form specifying the method, devices to be operated, and affected facilities, then reviews the draft Switching Order Package within two business days and performs field verification. The UEM Engineer conducts a final review of the Switching Order Package within two business days, and the UEM Production Controller creates a work request in the Maximo system and assigns a work request number. The Assistant Public Works Officer serves as final approving authority and distributes notifications to the requester, customers, Fire Department, Safety, and Security via the group email NAVFAC_ML_PWD_NEWLONDON_OUTAGES@navy.mil. The process requires submission of a complete Switching Order Package no later than seven business days prior to the scheduled outage and final distribution of approved documents no later than two business days before execution. The memorandum explicitly notes this process applies only to planned outages; emergency outages require expedited handling outside this procedure.

View the file

Other files

File Type Posted
Solicitation Amendment N4008526R01730005.pdf PDF
Attachment 4 J-0200000-08 Boilers ELINS-Updated Amendment 0005.xlsx XLSX spreadsheet
Solicitation Amendment 004 N4008526R01730004.pdf PDF
Attachment 1 General Contract Information.docx DOCX document
Solicitation Amendment 003 N4008526R01730003.pdf PDF
Attachment 21 Corporate Experience.docx DOCX document
Solicitation Amendment002 N4008526R01730002.pdf PDF
Solicitation Amendment001 N4008526R01730001.pdf PDF
Solicitation -N4008526R0173.pdf PDF
Solicitation -N4008526R0173.pdf PDF
Attachment 1 General Contract Information.docx DOCX document
Attachment 9 0100000 C Boilers.pdf PDF
Attachment 11 0200000 F Boilers.pdf PDF
Solicitation - N4008526R0173.pdf PDF
Attachment 10 0200000 C Boilers.pdf PDF
Attachment 14 1502000 F Boilers.pdf PDF
Attachment 20 Past Performance Questionnaire (PPQ).docx DOCX document
Attachment 21 Corporate Experience.docx DOCX document
Attachment 4 J-0200000-08 Boilers ELINS.xlsx XLSX spreadsheet
Attachment 7 J020000006 Install Spill Control Plan.pdf PDF
Attachment 12 0200000 J Boilers.pdf PDF
Attachment 16 1502000 PAP Boilers.pdf PDF
Attachment 17 Solicitation Question Sheet.docx DOCX document
Attachment 2 J150200006 BLDG 29 Boiler Specifications.pdf PDF
Attachment 3 J150200003 Map.pdf PDF
Attachment 5 NEPA.pdf PDF
Attachment 6 J150200007 NLON Inventory.xlsx XLSX spreadsheet
Attachment 13 1502000 C Boilers.pdf PDF
Attachment 15 1502000 J Boilers.pdf PDF
Attachment 18 DBA WD CT20260024 Mod 2.pdf PDF
Attachment 19 SCA 2015-4111 Rev 35.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5 December 2025

MEMORANDUM

From: Utilities and Energy Management Branch Head, Public Works Department New London

Subj: Contractor Planned Utility Outage Process

1. The utility outage process is always challenging as it involves coordinating with a variety of customers and minimizing the impact that our operations have on their ability to meet their mission. We provide a critical service to our customers and therefore we need to have a clear and concise process for coordinating outages to ensure that all employees fully understand their duties and responsibilities. The Contractor Utility Outage Process is different than the In-House Process and therefore a separate memorandum is being issued to ensure clear understanding of the differences in procedure. This memorandum describes the Contractor Planned Utility Outage Process that is currently in effect.

2. Duties and Responsibilities

A. ROICC Engineering Technician

1. Work with the contractor to schedule the date and time for an outage

2. Input all necessary information into the tracking spreadsheet on the shared drive so that an outage number can be assigned

3. Complete an Outage Notification Form (see Attachment 1) with as much information as possible

4. Submit the Outage Notification Form to the UEM Engineering Technician no later than 10 business days prior to the execution date of the outage

B. UEM Engineering Technician

1. Upon receiving the Outage Notification Form from the ROICC Engineering Technician, perform the following actions within one business day:

i. Verify that all necessary contractor employee information is on the Outage Notification Form (supplied by the ROICC Engineering Technician) so that the administrative portion of the switching order can be completed solely based upon the information on the sheet

ii. Submit the Outage Notification Form to the UEM Production Controller so that a work request number can be assigned

iii. Submit the Outage Notification Form to the appropriate Supervisory Utilities Superintendent (PRC322 - High Voltage or PRC323 – Steam/Water/Wastewater) to ensure the outage can be supported

iv. If the outage cannot be supported on the requested dates, coordinate with the ROICC Engineering Technician and the appropriate Supervisory Utilities Superintendent to select another date

2. If the outage can be supported, the respective Utilities Work Leader (High Voltage Electrician or Maintenance Mechanic) will identify the affected facilities and devices to operate and return the Outage Notification Form. Upon receiving the completed Outage Notification Form, submit the form to all Facilities Operations Specialists, Fire, Security, NMCI, the UEM Production Controller, outage requestor and all concerned parties within two business days

3. Draft a complete Switching Order Package as necessary and submit to the Utilities Work Leader for field verification no later than seven business days prior to the scheduled outage date

4. Upon receiving the Switching Order Package from the Utilities Work Leader after field verification has been performed, make any changes that are required and submit to the UEM Engineer for Final Review

5. After the UEM Engineer has completed the final review, submit the approved Outage Notification Form and Switching Order Package to the appropriate Utilities Work Leader and all other parties concerned no later than two business days prior to execution

6. Maintain copies of all Switching Order Packages for one year

7. In the absence of the UEM Engineering Technician, the UEM Engineer will complete their respective duties

C. Supervisory Utilities Superintendent

1. Upon receiving the Outage Notification Form from the UEM Engineering Technician, review the time requirements and projected manpower forecast to ensure the outage can be supported

i. If the outage cannot be supported, coordinate directly with the ROICC Engineering Technician to select a different date and time. When a new date and time have been negotiated, modify the Outage Notification Form and submit to the UEM Engineering Technician for processing

ii. If the outage can be supported, pass the Outage Notification Form to the appropriate Utilities Work Leader so that facilities affected and devices to operate can be identified

D. Utilities Work Leader

1. Receive the Outage Notification Form from the Utilities Distribution Supervisor

i. Complete the Outage Notification Form (see Attachment 1) in its entirety (excluding the outage number).

ii. The method for accomplishing the outage needs to be clearly thought out and all devices that need to be operated need to be indicated on the appropriate location on the Outage Notification Form. Facilities affected also need to be clearly identified on this form. Field verification is not necessary at this time.

2. Submit the Outage Notification Form to the UEM Engineering within 1 business day

3. Review the draft Switching Order Package provided by the UEM Engineering Technician and field verify all steps of the Switching Order Package within 2 business days. Sign as the UEM Field Verifier at the appropriate location on the form.

4. Execute the outage on the required date and time when an approved Outage Notification Form and a complete Switching Order Package are sent by the UEM Engineering Technician

5. The Utilities Distribution Work Leader or Utilities Distribution Supervisor may delegate some or all of the tasks in this section to a High Voltage Electrician or Pipefitter as necessary to fulfill mission requirements.

E. UEM Engineer

1. Upon receiving a Switching Order Package from the UEM Engineering Technician that has been field verified, perform one final review on the Switching Order Package and sign as the UEM Final Reviewer in the appropriate location.

Return the Switching Order Package to the UEM Engineering Technician within two business days.

F. UEM Production Controller

1. Upon receiving the Outage Notification Form from the UEM Engineering Technician, create a work request in Maximo and input the outage information

2. Modify the Outage Notification Form to include the new number

3. Resend to the UEM Engineering Technician

4. It is important to note that this process is for planned utility outages. This memorandum does not apply to emergency outages as they will need to be expedited.

5. Send the finalized request to the Assistant Public Works Officer (APWO) as the approving authority. The APWO shall maintain documentation of all approved, pending, and completed outages. The APWO will distribute notifications of approved outages to the requester, customers, Fire Department, Safety, and Security which are included in a group email for SUBASE outages:

NAVFAC_ML_PWD_NEWLONDON_OUTAGES@navy.mil

6. Attachment 2 summarizes the key components of the process. If there are any questions or concerns regarding this procedure, please contact the Maintenance Office Director at 860-694-4484 or Michael.W.Gabiga.civ@us.navy.mil.

MICHAEL W. GABIGA

Maintenance Office Director Acting Utilities and Energy Management Branch Head Public Works Department New London

Attachments:

1. Outage Notification Form

2. Flow Chart for Contractor Utility Outage Process Distribution: