This document provides details for a federal solicitation to upgrade infrastructure at the Iron Mountain VA Medical Center. The solicitation number is 36C77622B0018 and is being issued by the Department of Veterans Affairs Technology Acquisition Center Austin. The scope of work involves upgrading electrical, IT, HVAC, communications, security, and fiber optic infrastructure to support a new Electronic Health Record Modernization system. Upgrades are needed for electrical systems, bonding and grounding, uninterruptible power supplies, building management system interfaces, HVAC configuration and capacity, communications closets, data and network cabling, and the campus fiber backbone. The solicitation describes necessary products and services to modernize critical building systems at the medical center in support of implementing a new VA health records platform.
View the file
Other files for this federal contract opportunity
Show all 28
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
+0
+0
+0
+0
1003+57
2000+00
2001+00
2002+00
2003+00
2003+73
NO P
ARKIN
G
NO PARKING
P P
P P
P P
P
S S
P P
P
P P P
S S
S
S
P P P P P P P P P
S S S S S S S S S S
P P
P P
P
P P P P P P P P P
S S
S S
S
S S S S S S S S
A3 0, A3
R K-
-2
P
P
MCR
RM 5281
P P
FIBER HUB
RM B105
S
S
CU0200
1"=60'-0"
30' 60' 120'
SCALE:
SECONDARY FIBER OPTICS CIVIL SITE PLAN
CIVIL - SECONDARY FIBER OPTICS
SITE PLAN
NORTH
A/E:
GDM OF OREGON
1584 McNeil St., Suite 200 Dupont, WA 98327 360-915-5128
PROJECT NO.
BUILDING NO.
DRAWING NO.
PROJECT TITLE
FLS
CHECKED BY DRAWN BY
APPROVED: PROJECT DIRECTOR
VA FORM 08 - 6231
A
Program Contracting Activity
Central (PCAC)
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PHASE
ARCHITECT/ENGINEER OF RECORDCONSULTANT
321 4 5 6 7 8 9 10
REVISIONS: DATE:
LOCATION
04.20.202110% BASIS OF DESIGN STAMP
DRAWING TITLE
ISSUE DATE
100% CONSTRUCTION
DOCUMENTS
ELECTRONIC HEALTH RECORDS
MODERNIZATION (EHRM)
INFRASTRUCTURE UPGRADES
585-21-700
35% SCHEMATIC DESIGN 06.01.2021
65% DESIGN DOCUMENTS 07.06.2021
10-29-2021OSCAR G. JOHNSON VA MEDICAL CENTER
325 E H ST.
IRON MOUNTAIN, MI 49801
95% DESIGN DOCUMENTS 08.09.2021
AJG RDR
100% CONSTRUCTION DOCUMENTS 10.29.2021
FOR OFFICIAL USE ONLY (FOUO)
EXPIRES 8-1-23
El ev at io n
El ev at io n
Station
999+75 1000+00 1000+25 1000+50 1000+75 1001+00 1001+25 1001+50 1001+75 1002+00 1002+25 1002+50 1002+75 1003+00 1003+25 1003+50 1003+75
STA:1001+74.09 ALIGN_1000
RIM= 1138.53
IE IN(4"S) = 1135.53
IE OUT(4"S) = 1135.53
EXISTING 8" STORM PIPEEXISTING 10" SANITARY SEWER PIPE
P P
P P
P P
P P
S S
S S
S S
S S
S
PPPPPPPPPPPPPPPPP
P P
P P
P P
SSSSSSSSSSSSSSSS
S S
S S
S
S
A3 0, A3
R K-
-2
P
P
1000+00 1001+00 1002+00 1003+00
+5
CU0201
CIVIL - SECONDARY FIBER OPTICS
PLAN AND PROFILE
H: 1"=20'-0" V:1"=5'-0"SCALE:
1"=20'-0"
10' 20' 40'
SCALE:
STA. 1000+00 - 1003+57
SECONDARY FIBER OPTICS PLAN
EXISTING GROUND
NORTH
SECONDARY FIBER OPTICS PROFILE
A/E:
GDM OF OREGON
1584 McNeil St., Suite 200 Dupont, WA 98327 360-915-5128
PROJECT NO.
BUILDING NO.
DRAWING NO.
PROJECT TITLE
FLS
CHECKED BY DRAWN BY
APPROVED: PROJECT DIRECTOR
VA FORM 08 - 6231
A
Program Contracting Activity
Central (PCAC)
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PHASE
ARCHITECT/ENGINEER OF RECORDCONSULTANT
321 4 5 6 7 8 9 10
REVISIONS: DATE:
LOCATION
04.20.202110% BASIS OF DESIGN STAMP
DRAWING TITLE
ISSUE DATE
100% CONSTRUCTION
DOCUMENTS
ELECTRONIC HEALTH RECORDS
MODERNIZATION (EHRM)
INFRASTRUCTURE UPGRADES
585-21-700
35% SCHEMATIC DESIGN 06.01.2021
65% DESIGN DOCUMENTS 07.06.2021
10-29-2021OSCAR G. JOHNSON VA MEDICAL CENTER
325 E H ST.
IRON MOUNTAIN, MI 49801
95% DESIGN DOCUMENTS 08.09.2021
AJG RDR
100% CONSTRUCTION DOCUMENTS 10.29.2021
FOR OFFICIAL USE ONLY (FOUO)
EXPIRES 8-1-23
STA. 1000+00 - 1003+57
PENETRATE INTO TUNNEL AND
WATERPROOF AS REQUIRED.
PROVIDE FALSEWORK AND SHORING
AS IS REQUIRED TO PERFORM
EXCAVATION IN A SAFE MANNER AND
PROTECT ALL EXISTING CONDITIONS.
WORK PERFORMED
BY OTHERS
WORK PERFORMED
BY OTHERS
NOTES:
1. THE CONTRACTOR IS TO PROVIDE LOCATES,
TEMPORARY SHORING, FALSEWORK, DEWATERING, AND
OTHER SERVICES, TOOLS, AND SUPPLIES AS IS
NECESSARY TO PERFORM THE CIVIL RELATED
PORTIONS OF THE WORK.
2. PROVIDE DEWATERING AS IS NEEDED FOR SURFACE
WATER RUN OFF INCLUDING RAIN AND SNOW MELT.
NO UNDERGROUND FLOW IS ANTICIPATED WITHIN
EXCAVATION ZONE OF THE WORK.
El ev at io n
Station
1999+75 2000+00 2000+25 2000+50 2000+75 2001+00 2001+25 2001+50 2001+75 2002+00 2002+25 2002+50 2002+75 2003+00 2003+25 2003+50 2003+75 2004+00
STA:2001+45.19 ALIGN_2000
RIM= 1138.90
IE IN(4"N) = 1135.57
IE OUT(4"N) = 1135.57
EXISTING 10" SANITARY SEWER PIPE EXISTING 8" STORM PIPE
P P
P P
P P
P P
S S
S S
S S
S S
S
PPPPPPPPPPPPPPPPP
P P
P P
P P
SSSSSSSSSSSSSSSS
S S
S S
S
S
A3 0, A3
R K-
-2
P
P
2000+00 2001+00 2002+00 2003+00
+7
CU0202
CIVIL - RESERVED FOR POWER PLAN
AND PROFILE
H: 1"=20'-0" V:1"=5'-0"SCALE:
1"=20'-0"
10' 20' 40'
SCALE:
STA. 2000+00 - 2003+73
RESERVED FOR POWER PLAN
EXISTING GROUND
NORTH
A/E:
GDM OF OREGON
1584 McNeil St., Suite 200 Dupont, WA 98327 360-915-5128
PROJECT NO.
BUILDING NO.
DRAWING NO.
PROJECT TITLE
FLS
CHECKED BY DRAWN BY
APPROVED: PROJECT DIRECTOR
VA FORM 08 - 6231
A
Program Contracting Activity
Central (PCAC)
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PHASE
ARCHITECT/ENGINEER OF RECORDCONSULTANT
321 4 5 6 7 8 9 10
REVISIONS: DATE:
LOCATION
04.20.202110% BASIS OF DESIGN STAMP
DRAWING TITLE
ISSUE DATE
100% CONSTRUCTION
DOCUMENTS
ELECTRONIC HEALTH RECORDS
MODERNIZATION (EHRM)
INFRASTRUCTURE UPGRADES
585-21-700
35% SCHEMATIC DESIGN 06.01.2021
65% DESIGN DOCUMENTS 07.06.2021
10-29-2021OSCAR G. JOHNSON VA MEDICAL CENTER
325 E H ST.
IRON MOUNTAIN, MI 49801
95% DESIGN DOCUMENTS 08.09.2021
AJG RDR
100% CONSTRUCTION DOCUMENTS 10.29.2021
FOR OFFICIAL USE ONLY (FOUO)
EXPIRES 8-1-23
PENETRATE INTO TUNNEL AND
WATERPROOF AS REQUIRED.
PROVIDE FALSEWORK AND SHORING
AS IS REQUIRED TO PERFORM
EXCAVATION IN A SAFE MANNER AND
PROTECT ALL EXISTING CONDITIONS.
STA. 2000+00 - 2003+73
RESERVED FOR POWER PLAN
PROPOSED
RESERVED FOR POWER
NOTES:
1. THE CONTRACTOR IS TO PROVIDE LOCATES,
TEMPORARY SHORING, FALSEWORK, DEWATERING, AND
OTHER SERVICES, TOOLS, AND SUPPLIES AS IS
NECESSARY TO PERFORM THE CIVIL RELATED
PORTIONS OF THE WORK.
2. PROVIDE DEWATERING AS IS NEEDED FOR SURFACE
WATER RUN OFF INCLUDING RAIN AND SNOW MELT.
NO UNDERGROUND FLOW IS ANTICIPATED WITHIN
EXCAVATION ZONE OF THE WORK.
6"
1' -0
M
IN
DRAIN ROCK UNDISTURBED EARTH
A/E:
GDM OF OREGON
1584 McNeil St., Suite 200 Dupont, WA 98327 360-915-5128
PROJECT NO.
BUILDING NO.
DRAWING NO.
PROJECT TITLE
FLS
CHECKED BY DRAWN BY
APPROVED: PROJECT DIRECTOR
VA FORM 08 - 6231
A
Program Contracting Activity
Central (PCAC)
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PHASE
ARCHITECT/ENGINEER OF RECORDCONSULTANT
321 4 5 6 7 8 9 10
REVISIONS: DATE:
LOCATION
04.20.202110% BASIS OF DESIGN STAMP
DRAWING TITLE
ISSUE DATE
100% CONSTRUCTION
DOCUMENTS
ELECTRONIC HEALTH RECORDS
MODERNIZATION (EHRM)
INFRASTRUCTURE UPGRADES
585-21-700
35% SCHEMATIC DESIGN 06.01.2021
65% DESIGN DOCUMENTS 07.06.2021
10-29-2021OSCAR G. JOHNSON VA MEDICAL CENTER
325 E H ST.
IRON MOUNTAIN, MI 49801
95% DESIGN DOCUMENTS 08.09.2021
AJG RDR
100% CONSTRUCTION DOCUMENTS 10.29.2021
FOR OFFICIAL USE ONLY (FOUO)
EXPIRES 8-1-23
CU0300
CIVIL - DETAILS
SCALE: NTS
TRENCH DETAILS
DETECTABLE LOCATOR WARNING TAPE
NFS MATERIAL COMPACTED TO 95%
3000 PSI CONCRETE DYED ORANGE
CONDUIT/CONDUCTORS, SEE X/EX.X
NEW SOD TO MATCH EXISTING LAWNS
(NEW 4" CONCRETE OR ASPHALT PAVEMENT
TO MATCH EXISTING CONDITION
SEE DETAILS)
6"
4" MINIMUM CONCRETE ABOVE CONDUIT
TRENCH WIDTH AS REQUIRED
MINIMUM OF 24"
6" MINIMUM
M
IN
IM
U
M C
O
VE
R
6" 4"
COMPACTED,
APPROVED
SUBGRADE
COMPACTED
ROCK
BASE
PCC CONCRETE
PAVEMENT SECTION AS
SPECIFIED
3300 PSI @ 28 DAYS
SCALE: NTS
CONCRETE PAVEMENT DETAILS
SCALE: NTS
VAULT FOUNDATION DETAILS
6" COMPACTED
ROCK BASE
COMPACTED TRENCH
BACKFILL MATERIAL
FINISHED GRADE
NOTES:
1. DRAIN ROCK - 12" SQUARE BY MINIMUM 12" DEPTH
CENTERED UNDER THE VAULT SUMP DISCHARGE.
VAULT
BY OTHERS
01-GRADE LEVEL
0"
-01-T.O. FOOTING
-4'-0"
-02-B.O. FOOTING
-5'-0"
2'-0"
1' -0
M
IN 8"
8"
5' -0
#4 L-BAR ON 12" OC
#4 @ 12" OC
#4 @ 12" OC
#4 @ 12" OC
WITH HOOKS
6" COMPACTED ROCK
BASE (TYPICAL)
4' -0
6"
FINISHED GRADE
#4 @ 12" OC 2'-0" LONG
WITH 1'-0" HOOK
A/E:
GDM OF OREGON
1584 McNeil St., Suite 200 Dupont, WA 98327 360-915-5128
PROJECT NO.
BUILDING NO.
DRAWING NO.
PROJECT TITLE
FLS
CHECKED BY DRAWN BY
APPROVED: PROJECT DIRECTOR
VA FORM 08 - 6231
A
Program Contracting Activity
Central (PCAC)
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PHASE
ARCHITECT/ENGINEER OF RECORDCONSULTANT
321 4 5 6 7 8 9 10
REVISIONS: DATE:
LOCATION
04.20.202110% BASIS OF DESIGN STAMP
DRAWING TITLE
ISSUE DATE
100% CONSTRUCTION
DOCUMENTS
ELECTRONIC HEALTH RECORDS
MODERNIZATION (EHRM)
INFRASTRUCTURE UPGRADES
585-21-700
35% SCHEMATIC DESIGN 06.01.2021
65% DESIGN DOCUMENTS 07.06.2021
10-29-2021OSCAR G. JOHNSON VA MEDICAL CENTER
325 E H ST.
IRON MOUNTAIN, MI 49801
95% DESIGN DOCUMENTS 08.09.2021
AJG RDR
100% CONSTRUCTION DOCUMENTS 10.29.2021
FOR OFFICIAL USE ONLY (FOUO)
EXPIRES 8-1-23
CU0301
CIVIL - DETAILS
0.5% MINIMUM0.5% MINIMUM
SCALE: NTS
OUTDOOR MECHANICAL EQUIPMENT FOUNDATION DETAILS
2 NOTES:
1. PROVIDE FALSE WORK AND SHORING AS REQUIRED FOR
NEW AND EXISTING MATERIALS.
2. CRACK CONTROL JOINTS REQUIRED IF SURFACE IS
GREATER THAN 100 SQUARE FEET.
3. 5,000 POUNDS MAXIMUM ALLOWABLE EQUIPMENT
WEIGHT.
4. CONCRETE: 3300 PSI @ 28 DAYS.
5. MINIMUM CONCRETE COVER OF 2".
SCALE: NTS
OUTDOOR MECHANICAL EQUIPMENT FOUNDATION PLAN
MECHANICAL EQUIPMENT LENGTH + 1'-0"
M
EC
H
AN
IC
AL
E Q
U
IP
M
EN
T W
ID
TH
'-0
10/22/2021
EXP: 7/19/2023
A/E:
GDM OF OREGON
1584 McNeil St., Suite 200 Dupont, WA 98327 360-915-5128
PROJECT NO.
BUILDING NO.
DRAWING NO.
PROJECT TITLE
FLS
CHECKED BY DRAWN BY
APPROVED: PROJECT DIRECTOR
VA FORM 08 - 6231
A
Program Contracting Activity
Central (PCAC)
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PHASE
ARCHITECT/ENGINEER OF RECORDCONSULTANT
321 4 5 6 7 8 9 10
REVISIONS: DATE:
LOCATION
04.20.202110% BASIS OF DESIGN STAMP
DRAWING TITLE
ISSUE DATE
100% CONSTRUCTION
DOCUMENTS
ELECTRONIC HEALTH RECORDS
MODERNIZATION (EHRM)
INFRASTRUCTURE UPGRADES
585-21-700
35% SCHEMATIC DESIGN 06.01.2021
65% DESIGN DOCUMENTS 07.06.2021
10-29-2021OSCAR G. JOHNSON VA MEDICAL CENTER
325 E H ST.
IRON MOUNTAIN, MI 49801
95% DESIGN DOCUMENTS 08.09.2021
FOR OFFICIAL USE ONLY (FOUO)
100% CONSTRUCTION DOCUMENTS 10.29.2021
H:
\P ro jec t-F ile s\2
1\2
-0
0 - Ir on M ou nta in
VA
R em od el\
DR
AW
IN
GS
\A
CA
D\
-S N-
DA GM
400 COLUMBIA ST.
503-289-2661
Consulting Engineers Structural/Civil
SUITE 240
VANC. WA.
360-693-1621
SSOCIATES
98660-3117
STRUCTURAL NOTES
00-SN-002
STRUCTURAL STEEL
1. DETAIL, FABRICATE, ERECT, IDENTIFY AND PAINT STRUCTURAL STEEL ACCORDING TO AISC SPECIFICATIONS; EXCEPT CONTRACTOR SHALL USE THE
ARCHITECTURAL DRAWINGS IN CONJUNCTION WITH THE STRUCTURAL DRAWINGS FOR DIMENSIONS AND STRUCTURAL STEEL NOT SHOWN ON THE
STRUCTURAL DOCUMENTS.
2. MATERIAL:
A. W AND WT SHAPES: ASTM A992; FY = 50 KSI
B. M, MT, S, ST, HP, C, MC AND L SHAPES: ASTM A36; FY = 36 KSI.
C. STEEL HOLLOW STRUCTURAL SECTIONS (HSS):
ASTM A500 (COLD ROLLED):
GRADE B:
FY = 46 KSI (SQUARE, RECTANGULAR)
D. STEEL PLATES:
ASTM A36; FY = 36 KSI
3. CONNECT ALL MEMBERS WITH HIGH-STRENGTH BOLTS.
A. BEARING TYPE CONNECTIONS, TYPE N:
a. PROVIDE ASTM A325, TYPE N BOLTS AT ALL LOCATIONS NOT NOTED ON DRAWINGS AS TYPE SC.
b. PROVIDE HARDENED WASHERS CONFORMING TO ASTM F436 UNDER ELEMENTS TO BE TIGHTENED. PROVIDE NUTS CONFORMING TO ASTM
A563.
c. TIGHTEN TYPE N BEARING BOLTS TO A SNUG TIGHT CONDITION.
B. SLIP CRITICAL CONNECTIONS (TYPE SC), FOR USE ONLY WHERE NOTED ON DRAWINGS:
a. PROVIDE ASTM A325 LOAD-INDICATING BOLT ASSEMBLIES. INSTALL ACCORDING TO MANUFACTURER'S RECOMMENDATIONS.
b. IN LIEU OF LOAD-INDICATING BOLTS, PROVIDE STANDARD TYPE ASTM A325 SC BOLTS (CLASS A) WITH LOAD-INDICATING WASHERS. WASHERS
TO CONFORM WITH ASTM F959.
c. FULLY TENSION TYPE SC BOLTS.
d. REMOVE ALL PAINT AT SLIP-CRITICAL BOLT CONTACT SURFACES, OR PROVIDE CLASS A CONTACT SURFACE.
C. INSTALL HIGH-STRENGTH BOLTS ACCORDING TO ASTM STANDARDS.
D. DO NOT WELD TO HIGH-STRENGTH BOLTS.
4. GALVANIZED BOLTS (WHERE SHOWN ON DRAWINGS): HOT-DIPPED GALVANIZED ACCORDING TO ASTM A153, CLASS C.
5. ANCHOR RODS:
A. ASTM F1554, GR. 36; FY = 36 KSI
B. PROVIDE WITH STANDARD WASHERS AND NUTS.
C. GALVANIZE RODS (WHERE NOTED ON DRAWINGS) ACCORDING TO ASTM A153, CLASS C. OVER-TAP NUTS TO CLASS 2A FIT BEFORE GALVANIZING, ACCORDING TO ASTM A563.
6. PROVIDE BEVELED WASHERS AT BOLT HEADS OR NUTS BEARING ON SLOPING SURFACES.
7. WELDING:
A. CONFORM WITH AWS SPECIFICATIONS.
B. WELDERS TO BE QUALIFIED UNDER AWS SPECIFICATIONS.
C. WELDS MATERIAL: 70 KSI FILLER METAL, UNLESS NOTED OTHERWISE.
D. WELDS TO METAL DECK, METAL STUDS OR OTHER COLD-FORMED METALS: CONFORM TO AWS D1.3.
E. WELDS TO GALVANIZED STEEL AND AREAS DAMAGED BY WELDING, FLAME CUTTING OR HANDLING: CLEAN, DRY AND REMOVE OIL, GREASE, SALT
AND CORROSIVE PRODUCTS. APPLY ORGANIC COLD GALVANIZING COMPOUND WITH A MINIMUM OF 94% ZINC DUST IN THE DRY FILM. APPLY IN
MULTIPLE COATS TO ACHIEVE AN 8 MIL THICKNESS.
8. CONTRACTOR TO DESIGN AND PROVIDE ERECTION AIDS (BOLTS, CLIPS, SHIMS, SEATS, ETC.) REQUIRED TO FACILITATE CONSTRUCTION.
9. INSTALL AND INSPECT HEADED STUDS AND SHEAR CONNECTORS ACCORDING TO CHAPTER 7 OF AWS D1.1 "STRUCTURAL WELDING CODE-STEEL".
10. EMBEDDED STEEL ASSEMBLIES: HOT-DIP GALVANIZE ACCORDING TO ASTM A123, WHERE NOTED ON DRAWINGS.
METAL ROOF OR FLOOR DECKING
1. CONFORM WITH THE PROVISIONS OF THE AMERICAN IRON AND STEEL INSTITUTE'S "SPECIFICATIONS FOR THE DESIGN OF COLD FORMED STEEL
STRUCTURAL MEMBERS".
2. METAL ROOF DECKING:
A. MATERIAL: VERCO TYPE PLB-36, 18 GA., 36" WIDE SHEETS, GALVANIZED DECK OR APPROVED EQUAL.
B. CONNECTIONS:
a. DECKING TO SUPPORTING MEMBERS:
3/4" DIAMETER FUSION WELDS AT 6" OC.
b. DECKING TO BEAMS OR WALLS (WHERE DECKING SPAN IS PARALLEL TO MEMBER):
3/4" DIAMETER FUSION WELDS AT 12" OC.
c. DECK TO DECK SIDE LAPS:
PUNCH-LOK AT 24" OC OR OTHER ICBO-APPROVED SHEAR TRANSFER MECHANISM WITH EQUAL OR GREATER STRENGTH CAPACITY
3. METAL FLOOR DECKING:
A. MATERIAL: VERCO TYPE PLN3, 18 GA., 32" WIDE SHEETS, GALVANIZED DECK OR APPROVED EQUAL.
B. CONNECTIONS:
a. DECKING TO SUPPORTING MEMBERS:
3/4" DIAMETER FUSION WELDS AT 12" OC.
b. DECKING TO BEAMS OR WALLS (WHERE DECKING SPAN IS PARALLEL TO MEMBER): 3/4" DIAMETER FUSION WELDS AT 12" OC.
c. DECK TO DECK SIDE LAPS:
BUTTON PUNCHING AT 24" OC. MAXIMUM.
4. PROVIDE DECKING CONTINUOUS OVER 3 OR MORE SPANS. WHERE 1 OR 2 SPAN CONDITIONS ARE REQUIRED, PROVIDE DECKING WITH SUFFICIENT
SECTION PROPERTIES TO EQUAL LOAD AND DEFLECTION CAPACITY OF A 3 SPAN CONDITION.
5. FURNISH ALL ACCESSORIES (OPENING REINFORCING ANGLES, CLOSURES, ETC.) TO PROVIDE A COMPLETE DIAPHRAGM.
6. QUALIFY ALL WELDERS UNDER AWS AND SPECIFICATIONS FOR COLD-FORMED METAL WELDING.
7. EXTEND DECKING A MINIMUM OF 2" ONTO SUPPORTS.
COLD-FORMED STEEL CONNECTIONS
1. ALL PLATES AND LEDGERS SHALL BE ANCHORED WITH A MINIMUM OF 3 ANCHORS PER PIECE.
2. ALL FRAMING CONNECTORS SHALL BE SIMPSON OR APPROVED. FILL ALL HOLES WITH SCREWS AS SPECIFIED BY THE HANGER MANUFACTURER, UNLESS NOTED OTHERWISE.
3. ALL SCREWS TO BE #10 SELF-DRILLING SHEET METAL (SDSM) SCREWS, UNLESS NOTED OTHERWISE.
COLD FORMED STEEL FRAMING
1. ALL FABRICATION, ERECTION AND IDENTIFICATION OF COLD FORMED STEEL FRAMING SHALL CONFORM WITH IBC SECTIONS 2209, 2210 AND 2211, AND A.I.S.I. "SPECIFICATION FOR THE DESIGN OF COLD-FORMED STEEL STRUCTURAL MEMBERS".
2. MATERIAL:
A. ASTM A 653/653M, GRADE D (FY = 50 KSI) FOR 54 MIL AND THICKER STOCK.
B. ASTM A 653/653M, GRADE A (FY = 33 KSI) FOR 43 MIL AND THINNER STOCK.
3. FASTENING OF COMPONENTS SHALL BE WITH SELF-DRILLING SHEET METAL (SDSM) SCREWS, UNLESS NOTED OTHERWISE.
A. SCREW SPACING AND EDGE DISTANCE SHALL BE NOT LESS THAN 3X THE NOMINAL SCREW DIAMETER.
B. PENETRATIONS OF SCREWS THROUGH JOINED MATERIAL SHOULD NOT BE LESS THAN 3 EXPOSED THREADS.
C. WHERE FEASIBLE, INSTALL SCREWS FROM THINNER MATERIAL TO THICKER MATERIAL.
D. SCREWS SHALL BE INSTALLED AND TIGHTENED IN ACCORDANCE WITH SCREW MANUFACTURER'S RECOMMENDATIONS.
4. STEEL STUDS OR JOISTS SHALL HAVE STIFFENED LIPS, UNLESS NOTED OTHERWISE, AND MANUFACTURED BY MEMBERS OF THE STEEL STUD
MANUFACTURER'S ASSOCIATION. SIZES AND GAUGE ARE AS NOTED ON DRAWINGS.
5. PROVIDE ALL ACCESSORIES INCLUDING, BUT NOT NECESSARILY LIMITED TO, TRACKS, CLIPS, WEB STIFFENERS, ANCHORS, FASTENING DEVICES AND
OTHER ACCESSORIES REQUIRED FOR A COMPLETE AND PROPER INSTALLATION.
6. SPLICES IN AXIALLY LOADED STUDS SHALL NOT BE PERMITTED.
7. ALL STUDS, JAMBS, HEADERS, AND SILLS SHALL BE FULL LENGTH MEMBERS BETWEEN SUPPORTS.
8. EACH FLANGE OF STUDS SHALL BE SECURELY ATTACHED TO FLANGES OF BOTH UPPER AND LOWER TRACKS.
SPECIAL INSPECTION PROGRAM
INSPECTION TASK / TYPE OF WORK CONTINUOUS* PERIODIC* COMMENTS
SOILS
GRADING, EXCAVATION & FILL X REF. PROJECT
SPECIFICATION
CONCRETE
PLACEMENT OF REINFORCING STEEL X
PLACING OF REINFORCED CONCRETE X
TAKING OF TEST SPECIMENS X
STRUCTURAL WELDING
SINGLE PASS FILLET WELDS NOT EXCEEDING 5 16" X
FILLET WELDS EXCEEDING 5 16" X
GROOVE WELDS (FULL OR PARTIAL PENETRATION) X
FLOOR AND ROOF DECKING X
WELDED STAIR AND RAILING SYSTEMS X
HIGH STRENGTH (HS) BOLT INSTALLATION
TYPE N OR X HS BOLT X
COLD-FORMED STEEL FRAMING
VERIFY MEMBER SIZES, CONNECTIONS & DEFLECTION HEADS X
OTHER
POST-INSTALLED ANCHORS IN CONCRETE AND MASONRY PER ICC/ICBO
EVALUATION REPORTS
* FREQUENCY OF INSPECTION, WHICH MAY BE CONTINUOUS DURING THE TASK LISTED OR PERIODICALLY DURING THE TASK LISTED, AS DEFINED IN THE
TABLE.
SPECIAL INSPECTION PROGRAM FOOTNOTES:
1. PROVIDE SPECIAL INSPECTION, SPECIAL TESTING, REPORTING AND COMPLIANCE PROCEDURES ACCORDING TO CHAPTER 17 OF THE
INTERNATIONAL BUILDING CODE WITH THE OREGON STRUCTURAL SPECIALTY CODE INTERNATIONAL BUILDING CODE WITH THE WASHINGTON STATE
AMENDMENTS.
2. SPECIAL INSPECTOR QUALIFICATIONS: DEMONSTRATE COMPETENCE, TO THE SATISFACTION OF THE BUILDING OFFICIAL, FOR INSPECTION OF THE
PARTICULAR TYPE OF CONSTRUCTION OR OPERATION IN QUESTION.
3. PRIOR TO THE BEGINNING OF CONSTRUCTION, REVIEW THE SPECIAL INSPECTION REQUIREMENTS WITH THE ARCHITECT, ENGINEER, BUILDING
OFFICIAL, GENERAL CONTRACTOR AND SPECIAL INSPECTORS.
4. DUTIES OF THE SPECIAL INSPECTOR INCLUDE, BUT ARE NOT LIMITED TO:
A. OBSERVE THE WORK FOR CONFORMANCE WITH THE APPROVED PERMIT DRAWINGS AND SPECIFICATIONS. BRING DISCREPANCIES TO THE
IMMEDIATE ATTENTION OF THE GENERAL CONTRACTOR FOR CORRECTION, THEN, IF UNCORRECTED, TO THE ENGINEER AND TO THE BUILDING
OFFICIAL.
B. FURNISH INSPECTION REPORTS FOR EACH INSPECTION TO THE COR IN A TIMELY MANNER.
C. SUBMIT A FINAL REPORT STATING WHETHER THE WORK REQUIRING SPECIAL INSPECTION WAS INSPECTED, AND WHETHER THE WORK IS IN
CONFORMANCE WITH THE APPROVED PERMIT DRAWINGS AND SPECIFICATIONS.
5. DUTIES OF THE GENERAL CONTRACTOR INCLUDE, BUT ARE NOT LIMITED TO:
A. NOTIFY SPECIAL INSPECTOR THAT WORK IS READY FOR INSPECTION AT LEAST 24 HOURS BEFORE INSPECTION IS REQUIRED.
B. MAINTAIN ACCESS TO WORK REQUIRING SPECIAL INSPECTION UNTIL IT HAS BEEN OBSERVED AND INDICATED TO BE IN CONFORMANCE BY THE
SPECIAL INSPECTOR AND APPROVED BY THE COR.
C. PROVIDE THE SPECIAL INSPECTOR WITH ACCESS TO APPROVED PERMIT DRAWINGS AND SPECIFICATIONS AT THE JOB SITE.
D. MAINTAIN JOB-SITE COPIES OF ALL REPORTS SUBMITTED BY THE SPECIAL INSPECTOR.
6. DEFINITIONS:
A. CONTINUOUS INSPECTION: THE SPECIAL INSPECTOR IS OBSERVING THE WORK REQUIRING SPECIAL INSPECTION AT ALL TIMES.
B. PERIODIC INSPECTION: THE SPECIAL INSPECTOR IS ON SITE AS REQUIRED TO CONFIRM THAT THE WORK REQUIRING SPECIAL INSPECTION IS IN
CONFORMANCE.
C. SPECIAL INSPECTION: THE INSPECTION OF CONSTRUCTION REQUIRING THE EXPERTISE OF AN APPROVED SPECIAL INSPECTOR TO ENSURE
COMPLIANCE WITH CODE AND THE APPROVED CONSTRUCTION DOCUMENTS.
SPECIAL TESTING REQUIREMENTS
1. STRUCTURAL FILL OR BACK-FILL: VERIFY COMPACTION WITH RANDOM FIELD DENSITY TESTS.
2. STRUCTURAL CONCRETE: SAMPLE AND TEST ACCORDING TO STRUCTURAL NOTES.
3. STRUCTURAL STEEL:
A. NON-DESTRUCTIVE METHOD TESTING: CONFORM WITH AWS D1.1.
BRICK AND MASONRY ANCHORED VENEER
1. ALL LEDGER ANGLES WHICH SUPPORT BRICK AND MASONRY SHALL BE HOT-DIPPED GALVANIZED, IN ACCORDANCE WITH ASTM A123.
2. PROVIDE APPROVED VENEER ANCHORS IN COMPLIANCE WITH IBC CHAPTER 14, AT NOT LESS THAN 1 PER EACH 2 SQUARE FEET OF WALL AREA
AND AT NOT OVER 24" ON CENTER HORIZONTAL SPACING. PROVIDE ADDITIONAL TIES AS REQUIRED, SPACED NOT OVER 3'-0" APART, WITHIN 12" OF THE EDGE AROUND ALL OPENINGS AND AT EACH THIRD COURSE AT JAMBS. INSTALL ANCHORS IN SECOND COURSE ABOVE AND BELOW LEDGER
ANGLES.
3. VENEER ANCHORS ARE TO BE HOT-DIPPED GALVANIZED, TWO-PIECE ADJUSTABLE TIE AND ANCHOR SYSTEMS. ANCHORS SHALL BE 12 GAUGE (97 MIL) BENT STEEL SHEET. TIES SHALL BE 3/16" DIAMETER STEEL WIRE EXTENDING TO WITHIN 3/4" OF THE OUTSIDE FACE OF VENEER. VENEER TIES SHALL ENGAGE OR ENCLOSE A 3/16” DIAMETER HORIZONTAL JOINT REINFORCEMENT WIRE IN THE VENEER. THE VENEER JOINT REINFORCEMENT SHALL BE CONTINUOUS, WITH BUTT SPLICES BETWEEN THE TIES PERMITTED. WIRE OR PLATE PINTLE SYSTEMS REQUIRE SPECIAL INSPECTION
PER THE STRUCTURAL NOTES.
4. VENEER TIE MANUFACTURER: HOHMANN AND BARNARD, INC.
A. METAL STUD BACKING: X-SEAL S.I.S. WITH SEISMICLIP OR HB-213 S.I.S. WITH SEISMICLIP. ATTACH TO METAL STUDS WITH 2 NO. 10
SELF-DRILLING SHEET METAL (SDSM) SCREWS. SCREWS SHALL HAVE SUFFICIENT LENGTH TO FULLY PENETRATE THE STUD FLANGE.
B. CONCRETE BACKING: 2-SEAL WITH SEISMICLIP OR 315-BT WITH SEISMICLIP. ATTACH 2-SEAL TO CONCRETE BACKING WITH
PROPRIETARY ANCHORS PER MANUFACTURER’S RECOMMENDATIONS. ATTACH 315-BT TO CONCRETE BACKING WITH 305-DOVETAIL
SLOT ANCHOR.
C. STRUCTURAL STEEL BACKING: 359-FH WELD-ON TIE WITH VEE BYNA-TIE AND SEISMICLIP. ATTACH TO STEEL WITH 1/8” X 1” FILLET WELDS
TOP AND BOTTOM.
5. ALL HOT-DIPPED GALVANIZING OF VENEER ANCHORS, AND ALL OTHER HARDWARE WHICH SUPPORTS VENEER, SHALL HAVE A MINIMUM COATING OF 1.5 OUNCES OF ZINC PER SQUARE FOOT OF SURFACE AREA, IN ACCORDANCE WITH ASTM A153, CLASS B2
1 2
A
B
C
9'-0"
'-5
1/ 4"
1'- 6 3
/4"
HSS 4x4x3/8
HSS 4x4x3/8
02-SD-100
(E) 5" MIN
CONC SOG
1 2
A
B
C
9'-0"
'-5
1/ 4"
1'- 6 3
/4"
3" CONCRETE OVER
1 1/2" 18 GA METAL
DECK
02-SD-100
W8x21
W8x21
C8 x1
8.7
C8 x1
8.7
C8 x1
8.7
C8 x1
8.7
C8 x1
8.7
02-SD-100
A/E:
GDM OF OREGON
1584 McNeil St., Suite 200 Dupont, WA 98327 360-915-5128
PROJECT NO.
BUILDING NO.
DRAWING NO.
PROJECT TITLE
FLS
CHECKED BY DRAWN BY
APPROVED: PROJECT DIRECTOR
VA FORM 08 - 6231
A
Program Contracting Activity
Central (PCAC)
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PHASE
ARCHITECT/ENGINEER OF RECORDCONSULTANT
321 4 5 6 7 8 9 10
REVISIONS: DATE:
LOCATION
04.20.202110% BASIS OF DESIGN STAMP
DRAWING TITLE
ISSUE DATE
100% CONSTRUCTION
DOCUMENTS
ELECTRONIC HEALTH RECORDS
MODERNIZATION (EHRM)
INFRASTRUCTURE UPGRADES
585-21-700
35% SCHEMATIC DESIGN 06.01.2021
65% DESIGN DOCUMENTS 07.06.2021
10-29-2021OSCAR G. JOHNSON VA MEDICAL CENTER
325 E H ST.
IRON MOUNTAIN, MI 49801
95% DESIGN DOCUMENTS 08.09.2021
FOR OFFICIAL USE ONLY (FOUO)
100% CONSTRUCTION DOCUMENTS 10.29.2021
H:
\P ro jec t-F ile s\2
1\2
-0
0 - Ir on M ou nta in
VA
R em od el\
DR
AW
IN
GS
\A
CA
D\
-S F-
DA GM
400 COLUMBIA ST.
503-289-2661
Consulting Engineers Structural/Civil
SUITE 240
VANC. WA.
360-693-1621
SSOCIATES
98660-3117
BUILDING 2 PLANS
02-SF-100
4" =1'-0"
BASEMENT PLAN
02-SF-100
A
4" =1'-0"
LEVEL 2 PLAN
02-SF-100
B
PLAN NOTES:
1. SEE SHEET 00-SN-001 AND 00-SN-002 FOR STRUCTURAL NOTES
2 3
A
B
10'-10 3/4"
'-2
3/ 4"
(E) BLDG 11
6" CONC SOG W/ #4 @ 12"oc
CENTERED EA WAY OVER 6"
COMPACTED CRUSHED ROCK
11-SD-100
11-SD-100
11-SD-100
11-SD-100
SIM
11-SD-100
11-SD-100
11-SD-100
11-SD-1002 3
A
B
10'-10 3/4"
'-2
3/ 4"
1 1/2" 20 GA
METAL DECK
600S162-68 @ 16"oc
A/E:
GDM OF OREGON
1584 McNeil St., Suite 200 Dupont, WA 98327 360-915-5128
PROJECT NO.
BUILDING NO.
DRAWING NO.
PROJECT TITLE
FLS
CHECKED BY DRAWN BY
APPROVED: PROJECT DIRECTOR
VA FORM 08 - 6231
A
Program Contracting Activity
Central (PCAC)
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PHASE
ARCHITECT/ENGINEER OF RECORDCONSULTANT
321 4 5 6 7 8 9 10
REVISIONS: DATE:
LOCATION
04.20.202110% BASIS OF DESIGN STAMP
DRAWING TITLE
ISSUE DATE
100% CONSTRUCTION
DOCUMENTS
ELECTRONIC HEALTH RECORDS
MODERNIZATION (EHRM)
INFRASTRUCTURE UPGRADES
585-21-700
35% SCHEMATIC DESIGN 06.01.2021
65% DESIGN DOCUMENTS 07.06.2021
10-29-2021OSCAR G. JOHNSON VA MEDICAL CENTER
325 E H ST.
IRON MOUNTAIN, MI 49801
95% DESIGN DOCUMENTS 08.09.2021
FOR OFFICIAL USE ONLY (FOUO)
100% CONSTRUCTION DOCUMENTS 10.29.2021
H:
\P ro jec t-F ile s\2
1\2
-0
0 - Ir on M ou nta in
VA
R em od el\
DR
AW
IN
GS
\A
CA
D\
-S F-
DA GM
400 COLUMBIA ST.
503-289-2661
Consulting Engineers Structural/Civil
SUITE 240
VANC. WA.
360-693-1621
SSOCIATES
98660-3117
BUILDING 11 PLANS
11-SF-100
4" =1'-0"
FOUNDATION PLAN
11-SF-100
A
4" =1'-0"
ROOF FRAMING PLAN
11-SF-100
B
PLAN NOTES:
1. SEE SHEET 00-SN-001 AND 00-SN-002 FOR STRUCTURAL NOTES
2. SHEATH ALL EXTERIOR WALL STUDS W/ 5/8" TYPE X GYPSUM BOARD
SHEATHING. SEE DETAILS 5&6 /11-SD-100 FOR FASTENING INFORMATION
3. SEE ARCH FOR EXTERIOR WALL ASSEMBLY