ATTACHMENT 1 - Specifications VOL 1 of 2.pdf

PDF 6 MB Posted

Attached to
Y1AZ--EHRM Infrastructure Upgrades Construction - Iron Mountain Federal contract opportunity
Solicitation number
36C77622B0018
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This solicitation is for an Electronic Health Record Modernization (EHRM) Infrastructure Upgrades Construction project at the Oscar G. Johnson VA Medical Center in Iron Mountain, Michigan. The scope of work involves upgrades to the facility's electric and IT infrastructure to support a new EHRM system, including electrical upgrades, UPS improvements, HVAC reconfigurations, expanding and renovating closet spaces, upgrading the communication infrastructure with new data outlets and Cat6A cabling, physical security upgrades, and improving the fiber infrastructure campus-wide. The solicitation number is 36C77622B0018 and responses are due based on the posted schedule. The Department of Veterans Affairs Technology Acquisition Center in Austin, Texas is the contracting agency.

View the file

Other files for this federal contract opportunity

Other files attached to Y1AZ--EHRM Infrastructure Upgrades Construction - Iron Mountain, newest first.
File Type Posted
36C77622B0018 0003.pdf PDF
09 69 00 Access Flooring-Addenda 2.pdf PDF
Addendum 1.pdf PDF
ATTACHMENT 17 - Construction Wage Rates - Dickinson 6-17-22.pdf PDF
Technical Questions - FINAL - Iron Mtn. 6-27-22.pdf PDF
EHRM Asbestos Report.pdf PDF
36C77622B0018 0002.pdf PDF
Site Visit Sign-in Sheet - Iron Mtn. 5-18-22.pdf PDF
36C77622B0018 0001.pdf PDF
ATTACHMENT 2 - Specifications VOL 2 of 2.pdf PDF
ATTACHMENT 3 - Drawings VOL 1 - 1 of 5.pdf PDF
ATTACHMENT 15 - COVID-19 Safety Protocols 12-14-21.pdf PDF
ATTACHMENT 19 - Site Visit Instructions.pdf PDF
ATTACHMENT 8 - Drawings VOL 2 - 1 of 7.pdf PDF
ATTACHMENT 9 - Drawings VOL 2 - 2 of 7.pdf PDF
ATTACHMENT 12 - Drawings VOL 2 - 5 of 7.pdf PDF
ATTACHMENT 14 - Drawings VOL 2 - 7 of 7.pdf PDF
36C77622B0018 - 5-5-22.pdf PDF
ATTACHMENT 4 - Drawings VOL 1 - 2 of 5.pdf PDF
ATTACHMENT 5 - Drawings VOL 1 - 3 of 5.pdf PDF
ATTACHMENT 6 - Drawings VOL 1 - 4 of 5.pdf PDF
ATTACHMENT 7 - Drawings VOL 1 - 5 of 5.pdf PDF
ATTACHMENT 10 - Drawings VOL 2 - 3 of 7.pdf PDF
ATTACHMENT 11 - Drawings VOL 2 - 4 of 7.pdf PDF
ATTACHMENT 16 - Limitations on Subcontracting - Construction.docx DOCX document
ATTACHMENT 18 - Contractor Safety - Environmental Form.docx DOCX document
ATTACHMENT 13 - Drawings VOL 2 - 6 of 7.pdf PDF
ATTACHMENT 17 - Construction Wage Rates - Dickinson 2-25-22.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Electronic Health Record Modernization (EHRM) Infrastructure Upgrades Design Project Contract No. 36C77621C0029

VA 585-21-700 Iron Mountain

100% Technical Specifications

October 29, 2021

Volume 1-Divisions 00 thru 13

Oscar G. Johnson VA Medical Center

325 E H Street

Iron Mountain, Michigan For

US Department of Veterans Affairs

Program Contracting Activity Central (PCAC)

6150 Oak Tree Blvd., Suite 300

Independence, OH 44131

GDM OF OREGON

1584 McNeil St., Suite 200

Dupont, WA, 98327

360-915-5126

Dave Clem, Project Manager

OGJVAMC 100% CONSTRUCTION DOCUMENTS

IRON MOUNTAIN, MI 10/29/2021

OSCAR G. JOHNSON VA MEDICAL CENTER

ELECTRONIC HEALTH RECORDS

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 10 - 1 of 6

TABLE OF CONTENTS

SECTION 00 01 10

TABLE OF CONTENTS

Volume 1 of 2

THE SPECIFICATIONS LISTED BELOW FORM A PART OF THE CONTRACT.

DIVISION 00 - SPECIAL SECTIONS # of Pages

00 01 10 Table of Contents……………………………………………………………………………………………6

00 01 15 List of Drawing Sheets……………………………………………………………………………13

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements…………………………………………………………………………………28

00 01 15 List of Drawing Sheets………………………………………………………………………………6

01 11 00 Summary of Work…………………………………………………………………………………………………4

01 15 00 Green Environmental Management Systems Awareness

Training (GEMS)…………………………………………………………………………………………………6

01 32 16.15 Project Schedules…………………………………………………………………………………………10

01 33 23 Shop Drawings, Product Data, Samples and Log of

Submittals………………………………………………………………………………………………………………9

01 35 26 Safety Requirements……………………………………………………………………………………32

01 42 19 Reference Standards Codes and Regulations……………………………6

01 45 00 Quality Control………………………………………………………………………………………………13

01 45 29 Testing Laboratory Services………………………………………………………………10

01 45 35 Special Inspections………………………………………………………………………………………4

01 57 19 Temporary Environmental Controls……………………………………………………8

01 74 19 Construction Waste Management……………………………………………………………8

01 81 13 Sustainable Design Requirements………………………………………………………8

01 81.13.01 Sustainability Guiding Principles………………………………………………18

01 81 15 Infection Control Requirements………………………………………………………32

01 91 00 General Commissioning Requirements……………………………………………46

OSCAR G. JOHNSON VA MEDICAL CENTER

ELECTRONIC HEALTH RECORDS

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 10 - 2 of 6

TABLE OF CONTENTS

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Selective Demolition……………………………………………………………………………………3

02 82 11 Asbestos Abatement………………………………………………………………………………………72

02 83 33.13 Lead-Based Paint Removal and Disposal……………………………………13

DIVISION 03 – CONCRETE

03 30 00 Cast-in-Place Concrete……………………………………………………………………………35

DIVISION 04 – MASONRY

04 20 00 Brick Unit Masonry…………………………………………………………………………………………8

DIVISION 05 – METALS

05 40 00 Cold-Formed Metal Framing………………………………………………………………………8

05 50 00 Metal Fabrications…………………………………………………………………………………………8

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry………………………………………………………………………………………………10

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

07 16 16 Below Grade, Dry Side Waterproofing…………………………………………10

07 27 26 Fluid-Applied Membrane Air and Moisture Barrier……………6

07 53 23.15 Self-Adhering Ethylene-Propylene-Diene-Monomer Roof

Patching………………………………………………………………………………………………………………….8

07 77 00 Wall Accessories………………………………………………………………………………………………2

07 84 00 Firestopping…………………………………………………………………………………………………………7

07 92 00 Joint Sealants…………………………………………………………………………………………………10

DIVISION 08 – OPENINGS

08 11 10 Hollow Metal Doors and Frames……………………………………………………………8

08 14 16 Flush Wood Veneer Doors……………………………………………………………………………6

08 31 13 Access Doors and Frames……………………………………………………………………………6

08 51 13 Replacement of Aluminum Window in Building 1, Room

3167……………………………………………………………………………………………………………………………4

08 71 00 Door Hardware……………………………………………………………………………………………………14

OSCAR G. JOHNSON VA MEDICAL CENTER

ELECTRONIC HEALTH RECORDS

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 10 - 3 of 6

TABLE OF CONTENTS

DIVISION 09 – FINISHES

09 05 16 Surface Preparation for Floor Finishes……………………………………3

09 06 00 Schedule for Finishes………………………………………………………………………………18

(See Finish Schedule Included with Drawings)

09 22 16 Non-Structural Metal Framing………………………………………………………………6

09 29 00 Gypsum Board…………………………………………………………………………………………………………6

09 65 13 Resilient Base……………………………………………………………………………………………………4

09 65 36 Static Dissipative Resilient Flooring………………………………………6

09 69 00 Access Flooring………………………………………………………………………………………………21

09 91 00 Painting………………………………………………………………………………………………………………….8

DIVISION 10 – SPECIALTIES

10 14 00 Signage………………………………………………………………………………………………………………………4

10 15 10 Miscellaneous Accessories………………………………………………………………………#

10 21 24 Cold Aisle Containment Curtains………………………………………………………4

10 44 13 Fire Extinguisher Cabinets……………………………………….…………………………2

DIVISION 11 – EQUIPMENT (NOT USED)

DIVISION 12 – FURNISHINGS (NOT USED)

DIVISION 13 - SPECIAL CONSTRUCTION

13 05 41 Seismic Restraint Requirements for Non-Structural

Components………………………………………………………………………………………………………………7

DIVISION 14– CONVEYING EQUIPMENT (NOT USED)

Volume 2 of 2

DIVISION 21- FIRE SUPPRESSION

21 13 13 Existing Pre-Action Sprinkler System Modification………8

21 13 45 Sprinkler Head Guards…………………………………………….…………………………………2

21 22 00 Clean Agent Fire Suppression System…………………………………………22

21 25 00 Condensed Aerosol Fire Extinguishing System……………………12

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 10 - 4 of 6

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing…………………………………………………32

22 05 23 General-Duty Valves for Plumbing Piping…………………………………7

22 07 11 Plumbing Insulation……………………………………………………………………………………10

22 08 00 Commissioning of Plumbing Systems…………………………………………………4

22 11 00 Facility Water Distribution…………………………………………………………………9

22 13 00 Facility Sanitary and Vent Piping………………………………………………13

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC……………………………………………………………35

23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment……………………………………………………………………………….10

23 05 41 Noise and Vibration Control for HVAC Piping and

Equipment…………………………………………………………………………………………………………………7

23 05 93 Testing, Adjusting, and Balancing for HVAC………………………10

23 07 11 HVAC and Boiler Plant Insulation…………………………………………………13

23 08 00 Commissioning of HVAC Systems………………………………………………………….5

23 09 23 Direct-Digital Control System for HVAC…………………………………29

23 22 13 Steam and Condensate Heating Piping…………………………………………12

23 23 00 Refrigerant Piping…………………………………………………………………………………………9

23 31 00 HVAC Ducts and Casings………………………………………………………………………………9

23 37 00 Air Outlets and Inlets………………………………………………………………………………4

23 81 00 Decentralized Unitary HVAC Equipment………………………………………12

23 81 23 Computer Room Air-Conditioners………………………………………………………77

DIVISION 25 – INTEGRATED AUTOMATION (NOT USED)

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations…………………………14

26 05 26 Grounding and Bonding for Electrical Systems…………………10

26 05 33 Raceway and Boxes for Electrical Systems……………………………18

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 10 - 5 of 6

26 05 41 Underground Electrical Construction…………………………………………12

26 05 73 Overcurrent Protective Device Coordination Study…………6

26 08 00 Commissioning of Electrical Systems……………………………………………4

26 24 16 Panelboards……………………………………………………………………………………………………………7

26 27 26 Wiring Devices…………………………………………………………………………………………………11

26 29 21 Enclosed Switches and Circuit Breakers……………………………………8

26 33 53 Static Uninterrupted Power Supply………………………………………………12

26 43 13 Surge Protective Devices…………………………………………………………………………3

26 51 00 Interior Lighting…………………………………………………………………………………………10

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications and Installations……53

27 05 26 Grounding and Bonding for Communication Systems…………10

27 05 33 Raceways and Boxes for Communications Systems………………17

27 08 00 Commissioning of Communications Systems…………………………………4

27 11 00 Communications Equipment Room Fittings…………………………………18

27 15 00 Communications Structured Cabling………………………………………………17

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and

Security…………………………………………………………………………………………………………………31

28 05 13 Conductors and Cables for Electronic Safety and

Security…………………………………………………………………………………………………………………14

28 05 26 Grounding and Bonding for Electronic Safety and

Security……………………………………………………………………………………………………………………6

28 05 28.33 Conduits and Backboxes for Electronic Safety and

Security……………………………………………………………………………………………………………… 17

28 08 00 Commissioning of Electronic Safety and Security

Systems………………………………………………………………………………………………………………………5

28 13 00 Access Control……………………………………………………………………………………………………4

28 31 00 Fire Detection and Alarm ……………………………………………………………………14

DIVISION 31 – EARTHWORK

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 10 - 6 of 6

31 20 00 Earthwork……………………………………………………………………………………………………………22

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Concrete for Exterior Improvements……………………………………………20

32 12 16 Asphalt Paving…………………………………………………………………………………………………8

32 17 23 Pavement Markings.………………………………………………………………………………………8

32 90 05 Turfgrass Sodding…………………………………………………………………………………………5

DIVISION 33 – UTILITIES (NOT USED)

DIVISION 34 – TRANSPORTATION (NOT USED)

DIVISION 48 – ELECTRICAL POWER GENERATION (NOT USED)

- - - E N D - - -

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 15 - 1 of 13

LIST OF DRAWING SHEETS

SECTION 00 01 15

The drawings listed below accompanying this specification form a part of the contract.

VOL 1

Drawing No. Title

GENERAL

GI001 COVER SHEET-VOLUME 1

GI002 SHEET INDEX

GI003 ABBREVIATIONS

GI004 LEGEND AND SYMBOLS

GI005 INFECTION CONTROL PLAN-TYPICAL

GI006 LIFE SAFETY-BLDG 1-SUB-BASEMENT

GI007 LIFE SAFETY-BLDG 1-BASEMENT-NORTHWEST

GI008 LIFE SAFETY BLDG 1-BASEMENT-WEST

GI009 LIFE SAFETY BLDG 1-BASEMENT-EAST

GI010 LIFE SAFETY BLDG 1-1ST FLOOR-NORTHWEST

GI011 LIFE SAFETY BLDG 1-1ST FLOOR-WEST

GI012 LIFE SAFETY-BLDG 1-1ST FLOOR-EAST

GI013 LIFE SAFETY BLDG 1-2ND FLOOR

GI014 LIFE SAFETY BLDG 1-3RD FLOOR

GI015 LIFE SAFETY BLDG 1-4TH FLOOR

GI016 LIFE SAFETY BLDG 1-5TH FLOOR

GI017 LIFE SAFETY BLDG 1- 6TH FLOOR

GI018 LIFE SAFETY BLDG 1-7TH FLOOR

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 15 - 2 of 13

GI019 LIFE SAFETY BLDG 1-8TH FLOOR

GI020 LIFE SAFETY-BLDG 2

GI021 LIFE SAFETY-BLDG 4

GI022 LIFE SAFETY-BLDG 6

GI023 LIFE SAFETY-BLDG 11

ARCHITECTURAL

AE-SB1 ARCH FLOOR PLAN-BLDG 1 SUB-BASEMENT

AE-0B1 ARCH FLOOR PLAN-BLDG 1 BASEMENT

AE-0B2 ARCH FLOOR PLAN BLDG 1 BASEMENT

AE-011 ACAD FLOOR PLAN-BLDG 1 FIRST FLOOR

AE-012 ARCH FLOOR PLAN-BLDG 1 FIRST FLOOR

AE-021 ARCH FLOOR PLAN-BLDG 1 SECOND FLOOR

AE-022 ARCH FLOOR PLAN-BLDG 1 SECOND FLOOR

AE-031 ARCH FLOOR PLAN-BLDG 1 THIRD FLOOR

AE-032 ARCH FLOOR PLAN-BLDG 1 THIRD FLOOR

AE-041 ARCH FLOOR PLAN-BLDG 1 FOURTH FLOOR

AE-042 ARCH FLOOR PLAN-BLDG 1 FOURTH FLOOR

AE-051 ARCH FLOOR PLAN-BLDG 1 FIFTH FLOOR

AE-052 ARCH FLOOR PLAN-BLDG 1 FIFTH FLOOR

AE-061 ARCH FLOOR PLAN-BLDG 1 SIXTH FLOOR

AE-071 ARCH FLOOR PLAN-BLDG 1 SEVENTH FLOOR

AE-0B1 ARCH FLOOR PLAN-BLDG 2 BASEMENT

AE-0B1 ARCH FLOOR PLAN-BLDG 4 BASEMENT

AE-0B1 ARCH FLOOR PLAN-BLDG 6 BASEMENT

AE-011 ARCH FLOOR PLAN-BLDG 6 FIRST FLOOR

AE-021 ARCH FLOOR PLAN-BLDG 6 SECOND FLOOR

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 15 - 3 of 13

AE-021 ARCH FLOOR PLAN-BLDG 11 SECOND FLOOR

AK-001 FIRE STOPPING DETAILS

AJ-001 ARCH ENLARGED FLOOR PLANS

AJ-002 ARCH ENLARGED FLOOR PLANS

AJ-003 ARCH ENLARGED FLOOR PLANS

AJ-004 ARCH ENLARGED FLOOR PLANS

AJ-005 ARCH ENLARGED FLOOR PLANS

AJ-006 ARCH ENLARGED FLOOR PLANS

AJ-007 WALL PARTITION TYPES

AJ-008 ARCH ENLARGED FLOOR PLANS

AJ-009 ARCH 3RD FLOOR ROOF ACCESS AND DETAILS

AI-010 DOOR SCHEDULE

AI-011 DOOR DETAILS

AI-012 DOOR HARDWARE SCHEDULE

CIVIL

C10001 GENERAL NOTES

RC0001 EXISTING CONDITIONS PLAN

CS0001 FIBER OPTICS SITE PLAN

CU0100 PRIMARY FIBER OPTICS SITE PLAN

CU0101 PRIMARY FIBER OPTICS PLAN AND PROFILE

CU0102 PRIMARY FIBER OPTICS PLAN AND PROFILE

CU0103 PRIMARY FIBER OPTICS PLAN AND PROFILE

CU0200 SECONDARY FIBER OPTICS SITE PLAN

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 15 - 4 of 13

CU0201 SECONDARY FIBER OPTICS SITE PLAN AND PROFILE

CU0202 RESERVED FOR POWER PLAN AND PROFILE

CU0300 DETAILS

CU0301 DETAILS

STRUCTURAL

SN-001 STRUCTURAL NOTES

SN-002 STRUCTURAL NOTES

SD-100 BUILDING 1 DETAILS

SF-100 BUILDING 2 PLANS

SD-100 BUILDING 2 DETAILS

SF-100 BUILDING 11 PLANS

SD-100 BUILDING 11 DETAILS

MECHANICAL

MG-0001 LEGEND AND ABBREVIATION LIST AND GENERAL NOTES

MG-0002 DETAILS

MG-0003 SCHEDULES

MD-0B1 HVAC DEMOLITION PLAN-BLDG 1 BASEMENT

MD-0B2 HVAC DEMOLITION PLAN-BLDG 1 BASEMENT

MD-0B3 HVAC DEMOLITION PLAN-BLDG 1 BASEMENT

MD-011 HVAC DEMOLITION PLAN-BLDG 1 FIRST FLOOR

MD-012 HVAC DEMOLITION PLAN-BLDG 1 FIRST FLOOR

MD-021 HVAC DEMOLITION PLAN-BLDG 1 SECOND FLOOR

MD-022 HVAC DEMOLITION PLAN-BLDG 1 SECOND FLOOR

MD-031 HVAC DEMOLITION PLAN-BLDG 1 THIRD FLOOR

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 15 - 5 of 13

MD-032 HVAC DEMOLITION PLAN-BLDG 1 THIRD FLOOR

MD-041 HVAC DEMOLITION PLAN-BLDG 1 FOURTH FLOOR

MD-042 HVAC DEMOLITION PLAN-BLDG 1 FOURTH FLOOR

MD-051 HVAC DEMOLITION PLAN-BLDG 1 FIFTH FLOOR

MD-052 HVAC DEMOLITION PLAN-BLDG 1 FIFTH FLOOR

MD-061 HVAC DEMOLITION PLAN-BLDG 1 SIXTH FLOOR

MD-0B1 HVAC DEMOLITION PLAN-BLDG 2 BASEMENT

MD-0B1 HVAC DEMOLITION PLAN-BLDG 4 BASEMENT

MD-011 HVAC DEMOLITION PLAN-BLDG 6 FIRST FLOOR

MD-0B1 HVAC DEMOLITION PLAN-BLDG 11 GROUND FLOOR

MH-0B1 HVAC PLAN-BLDG 1 BASEMENT

MH-0B2 HVAC PLAN-BLDG 1 BASEMENT

MH-0B3 HVAC PLAN-BLDG 1BASEMENT

MH-011 HVAC PLAN-BLDG 1 FIRST FLOOR

MH-012 HVAC PLAN-BLDG 1 FIRST FLOOR

MH-013 HVAC PLAN-BLDG 1 FIRST FLOOR

MH-021 HVAC PLAN-BLDG 1 SECOND FLOOR

MH-022 HVAC PLAN-BLDG 1 SECOND FLOOR

MH-023 HVAC PLAN-BLDG 1 SECOND FLOOR

MH-031 HVAC PLAN-BLDG 1 THIRD FLOOR

MH-032 HVAC PLAN-BLDG 1 THIRD FLOOR

MH-041 HVAC PLAN-BLDG 1 FOURTH FLOOR

MH-042 HVAC PLAN-BLDG 1 FOURTH FLOOR

MH-051 HVAC PLAN-BLDG 1 FIFTH FLOOR

MH-052 HVAC PLAN-BLDG 1 FIFTH FLOOR

MH-061 HVAC PLAN-BLDG 1 SIXTH FLOOR

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 15 - 6 of 13

MH-071 HVAC PLAN-BLDG 1 SEVENTH FLOOR

MH-0B1 HVAC PLAN-BLDG 2 BASEMENT

MH-011 HVAC PLAN-BLDG 2 FIRST FLOOR

MH-0B1 HVAC PLAN-BLDG 4 BASEMENT

MH-011 HVAC PLAN-BLDG 4 FIRST FLOOR

MH-011 HVAC PLAN-BLDG 6 FIRST FLOOR

MH-0B1 HVAC PLAN-BLDG 11 GROUND FLOOR

VOL 2

GENERAL

GI-001 COVER SHEET, VICINITY MAP, AND GENERAL

REQUIREMENTS-VOL 2

GI-002 INDEX OF DRAWINGS-VOL 2

GI-003 ABBREVIATIONS AND GENERAL NOTES

ELECTRICAL & TELECOMMUNICATIONS

EG001 ELECTRICAL LEGEND AND SCHEDULES

EJ-001 ELECTRICAL DETAILS

ES-001 ELECTRICAL SITE PLAN

ED-SB1 ELECTRICAL DEMOLITION-BLDG 1 SUB-BASEMENT

ED-0B1 ELECTRICAL DEMOLITION-BLDG 1 BASEMENT

ED-011 ELECTRICAL DEMOLITION-BLDG 1 FIRST FLOOR

OSCAR G. JOHNSON VA MEDICAL CENTER

ELECTRONIC HEALTH RECORDS

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 15 - 7 of 13

LIST OF DRAWING SHEETS

ED-021 ELECTRICAL DEMOLITION-BLDG 1 SECOND FLOOR

ED-031 ELECTRICAL DEMOLITION-BLDG 1 THIRD FLOOR

ED-041 ELECTRICAL DEMOLITION-BLDG 1 FOURTH FLOOR

ED-051 ELECTRICAL DEMOLITION-BLDG 1 FIFTH FLOOR

ED-061 ELECTRICAL DEMOLITION-BLDG 1 SIXTH FLOOR

ED-071 ELECTRICAL DEMOLITION-BLDG 1 SEVENTH FLOOR

ED-081 ELECTRICAL DEMOLITION-BLDG 1 EIGHTH FLOOR

ED-0B1 ELECTRICAL DEMOLITION-BLDG 2

ED-0B1 ELECTRICAL DEMOLITION-BLDG 4

ED-0B1 ELECTRICAL DEMOLITION-BLDG 6

ED-0B1 ELECTRICAL DEMOLITION BLDG 11 BASEMENT

EP-SB1 ELECTRICAL REMODEL-BLDG 1 SUB BASEMENT

EP-0B1 ELECTRICAL REMODEL-BLDG 1 BASEMENT

EP-011 ELECTRICAL REMODEL-BLDG 1 FIRST FLOOR

EP-021 ELECTRICAL REMODEL-BLDG 1 SECOND FLOOR

EP-031 ELECTRICAL REMODEL-BLDG 1 THIRD FLOOR

EP-041 ELECTRICAL REMODEL-BLDG 1 FOURTH FLOOR

EP-051 ELECTRICAL REMODEL-BLDG 1 FIFTH FLOOR

EP-061 ELECTRICAL REMODEL-BLDG 1 SIXTH FLOOR

EP-071 ELECTRICAL REMODEL-BLDG 1 SEVENTH FLOOR

EP-081 ELECTRICAL REMODEL-BLDG 1 EIGHT FLOOR

EP—0B1 ELECTRICAL REMODEL-BLDG 2

EP 0B1 ELECTRICAL REMODEL-BLDG 4

EP-0B1 ELECTRICAL REMODEL-BLDG 6

EP-0B1 ELECTRICAL REMODEL-BLDG 11

OSCAR G. JOHNSON VA MEDICAL CENTER

ELECTRONIC HEALTH RECORDS

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 15 - 8 of 13

LIST OF DRAWING SHEETS

TG-001 TELECOMM LEGEND, SCHEDULES, ABBREVIATIONS,

GENERAL NOTES

TS-001 TELECOMMUNICATIONS SITE PLAN

TS-002 TELECOMM DEMOLITION SITE PLAN

TS-003 TELECOMM NEW SITE PLAN

TD-SB1 ELECTRICAL DEMOLITION PLAN-BLDG 1 PARTIAL SUB

BASEMENT

TD-SB2 TELECOMM DEMOLITION PLAN-BLDG 1 PARTIAL SUB

BASEMENT

TD-0B1 TELECOMM DEMOLITION PLAN-BLDG 1 PARTIAL SUB

BASEMENT

TD-0B2 TELECOMM DEMOLITION PLAN-BLDG 1 PARTIAL SUB

BASEMENT

TD-0B3 TELECOMM DEMOLITION PLAN-BLDG 1 PARTIAL

BASEMENT

TD-011 TELECOMM DEMOLITION PLAN-BLDG 1 PARTIAL

FIRST FLOOR

TD-012 TELECOMM DEMOLITION PLAN-BLDG 1 PARTIAL

FIRST FLOOR

TD-013 TELECOMM DEMOLITION PLAN-BLDG 1 PARTIAL

FIRST FLOOR

TD-021 TELECOMM DEMOLITION PLAN-BLDG 1 PARTIAL

SECOND FLOOR

TD-022 TELECOMM DEMOLITION PLAN-BLDG 1 PARTIAL

SECOND FLOOR

TD-031 TELECOMM DEMOLITION PLAN-BLDG 1 PARTIAL

OSCAR G. JOHNSON VA MEDICAL CENTER

ELECTRONIC HEALTH RECORDS

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 15 - 9 of 13

LIST OF DRAWING SHEETS

THIRD FLOOR

TD-032 TELECOMM DEMOLITION PLAN-BLDG 1 PARTIAL

THIRD FLOOR

TD-041 TELECOMM DEMOLITION PLAN-BLDG 1 PARTIAL

FOURTH FLOOR

TD-042 TELECOMM DEMOLITION PLAN-BLDG 1 PARTIAL

FOURTH FLOOR

TD-051 TELECOMM DEMOLITION PLAN-BLDG 1 PARTIAL

FIFTH FLOOR

TD-052 TELECOMM DEMOLITION PLAN-BLDG 1 PARTIAL

FIFTH FLOOR

TD-061 TELECOMM DEMOLITION PLAN-BLDG 1 SIXTH FLOOR

TD-062 TELECOMM DEMOLITION PLAN-BLDG 1 SIXTH FLOOR

TD-071 TELECOMM DEMOLITION PLAN-BLDG 1 SEVENTH FLOOR

TD-081 TELECOMM DEMOLITION PLAN-BLDG 1 EIGHTH FLOOR

TD-0B1 TELECOMM DEMOLITION PLAN-BLDG 2 BASEMENT

TD-011 TELECOMM DEMOLITION PLAN-BLDG 2 FIRST FLOOR

TD-021 TELECOMM DEMOLITION PLAN-BLDG 2 SECOND FLOOR

TD-031 TELECOMM DEMOLITION PLAN-BLDG 2 THIRD FLOOR

TD-0B1 TELECOMM DEMOLITION PLAN-BLDG 4 BASEMENT

TD-0B1 TELECOMM DEMOLITION PLAN-BLDG 6 BASEMENT

TD-011 TELECOMM DEMOLITION PLAN-BLDG 6 FIRST FLOOR

TD-021 TELECOMM DEMOLITION PLAN-BLDG 6 SECOND FLOOR

TD-011 TELECOMM DEMOLITION PLAN-BLDG 11 GROUND FLOOR

TN-SB1 TELECOMM FLOOR PLAN-BLDG 1 SUB BASEMENT

TN-SB2 TELECOMM FLOOR PLAN-BLDG 1 SUB BASEMENT

OSCAR G. JOHNSON VA MEDICAL CENTER

ELECTRONIC HEALTH RECORDS

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 15 - 10 of 13

LIST OF DRAWING SHEETS

TN-0B1 TELECOMM FLOOR PLAN-COPPER-BLDG 1 PARTIAL

BASEMENT

TN-0B2 TELECOMM FLOOR PLAN-COPPER-BLDG 1 PARTIAL

BASEMENT

TN-0B3 TELECOMM FLOOR PLAN-COPPER-BLDG 1 PARTIAL

BASEMENT

TN-0B4 TELECOMM FLOOR PLAN-FIBER-BLDG 1 PARTIAL

BASEMENT

TN-0B5 TELECOMM FLOOR PLAN-FIBER-BLDG 1 PARTIAL

BASEMENT

TN-0B6 TELECOMM FLOOR PLAN-FIBER-BLDG 1 PARTIAL

BASEMENT

TN-011 TELECOMM FLOOR PLAN-COPPER-BLDG 1 PARTIAL

FIRST FLOOR

TN-012 TELECOMM FLOOR PLAN-COPPER-BLDG 1 PARTIAL

FIRST FLOOR

TN-013 TELECOMM FLOOR PLAN-COPPER-BLDG 1 PARTIAL

FIRST FLOOR

TN-014 TELECOMM FLOOR PLAN-FIBER-BLDG 1 PARTIAL

FIRST FLOOR

TN-015 TELECOMM FLOOR PLAN-FIBER-BLDG 1 PARTIAL

FIRST FLOOR

TN-016 TELECOMM FLOOR PLAN-FIBER-BLDG 1 PARTIAL

FIRST FLOOR

TN-021 TELECOMM FLOOR PLAN-COPPER-BLDG 1 PARTIAL

SECOND FLOOR

TN-022 TELECOMM FLOOR PLAN-COPPER-BLDG 1 PARTIAL

OSCAR G. JOHNSON VA MEDICAL CENTER

ELECTRONIC HEALTH RECORDS

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 15 - 11 of 13

LIST OF DRAWING SHEETS

SECOND FLOOR

TN-023 TELECOMM FLOOR PLAN-FIBER-BLDG 1 PARTIAL

SECOND FLOOR

TN-024 TELECOMM FLOOR PLAN-FIBER-BLDG 1 PARTIAL

SECOND FLOOR

TN-031 TELECOMM FLOOR PLAN-COPPER-BLDG 1 PARTIAL

THIRD FLOOR

TN-032 TELECOMM FLOOR PLAN-COPPER-BLDG 1 PARTIAL

THIRD FLOOR

TN-033 TELECOMM FLOOR PLAN-FIBER-BLDG 1 PARTIAL

THIRD FLOOR

TN-034 TELECOMM FLOOR PLAN-FIBER-BLDG 1 PARTIAL

THIRD FLOOR

TN-041 TELECOMM FLOOR PLAN-COPPER-BLDG 1 PARTIAL

FOURTH FLOOR

TN-042 TELECOMM FLOOR PLAN-COPPER-BLDG 1 PARTIAL

FOURTH FLOOR

TN-043 TELECOMM FLOOR PLAN-FIBER-BLDG 1 PARTIAL

FOURTH FLOOR

TN-044 TELECOMM FLOOR PLAN-FIBER-BLDG 1 PARTIAL

FOURTH FLOOR

TN-051 TELECOMM FLOOR PLAN-COPPER-BLDG 1 PARTIAL

FIFTH FLOOR

TN-052 TELECOMM FLOOR PLAN-COPPER-BLDG 1 PARTIAL

FIFTH FLOOR

TN-053 TELECOMM FLOOR PLAN-FIBER-BLDG 1 PARTIAL

FIFTH FLOOR

OSCAR G. JOHNSON VA MEDICAL CENTER

ELECTRONIC HEALTH RECORDS

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 15 - 12 of 13

LIST OF DRAWING SHEETS

TN-054 TELECOMM FLOOR PLAN-FIBER-BLDG 1 PARTIAL

FIFTH FLOOR

TN-061 TELECOMM FLOOR PLAN-COPPER-BLDG 1 SIXTH FLOOR

TN-062 TELECOMM FLOOR PLAN-COPPER BLDG 1 SIXTH FLOOR

TN-063 TELECOMM FLOOR PLAN-FIBER-BLDG 1 SIXTH FLOOR

TN-064 TELECOMM FLOOR PLAN-FIBER-BLDG 1 SIXTH FLOOR

TN-071 TELECOMM FLOOR PLAN-BLDG SEVENTH FLOOR

TN-081 TELECOMM FLOOR PLAN-BLDG EIGHTH FLOOR

TN-0B1 TELECOMM FLOOR PLAN-BLDG 2 BASEMENT

TN-011 TELECOMM FLOOR PLAN-BLDG 2 FIRST FLOOR

TN-021 TELECOMM FLOOR PLAN-BLDG 2 SECOND FLOOR

TN-031 TELECOMM FLOOR PLAN-BLDG 2 THIRD FLOOR

TN-0B1 TELECOMM FLOOR PLAN-BLDG 4 BASEMENT

TN-0B1 TELECOMM FLOOR PLAN-BLDG 6 BASEMENT

TN-011 TELECOMM FLOOR PLAN-BLDG 6 FIRST FLOOR

TN-021 TELECOMM FLOOR PLAN-BLDG 6 SECOND FLOOR

TN-111 TELECOMM FLOOR PLAN-BLDG 11 GROUND FLOOR

TJ-001 TELECOMM DETAILS

TJ-002 TELECOMM DETAILS

TJ-003 TELECOMM DETAILS

TJ-004 TELECOMM FIBER OPTIC ONE-LINE

TJ-005 TELECOMM EXISTING RACK ELEVATIONS

TJ-006 TELECOMM DETAILS

TJ-007 TELECOMM DETAILS

TJ-008 TELECOMM DETAILS

TJ-009 TELECOMM DETAILS

OSCAR G. JOHNSON VA MEDICAL CENTER

ELECTRONIC HEALTH RECORDS

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

00 01 15 - 13 of 13

LIST OF DRAWING SHEETS

TJ-010 TELECOMM DETAILS

TJ-011 TELECOMM DETAILS

TJ-012 TELECOMM RACK DETAILS

TJ-013 TELECOMM RACK DETAILS

TJ-014 TELECOMM PAGING DEMOLITION

TJ-015 TELECOMM PAGING DETAILS

TY-001 ACCESS CONTROL DOOR DETAILS

FIRE SPRINKLER PLAN

FX-005 NEW AND MODIFIED FIRE SUPPRESSION SYSTEM-

RM 5281

FIRE PROTECTION

FP-00B BUILDING 2 TELECOMM ROOM FIRE SUPPRESSION SYSTEM

FP-00B BUILDING 4 TELECOMM ROOM FIRE SUPPRESSION SYSTEM

FP-001 BUILDING 6 TELECOMM ROOM FIRE SUPPRESSION SYSTEM

FP-002 BUILDING 11 TELECOMM ROOM FIRE SUPPRESSION SYSTEM

FP-005 EXTINGUISHANT PANEL CONNECTIONS

FP-006 DESIGN GUIDELINES

FP-007 FIRE SUPPRESSION DESIGN CALCULATIONS, FACU

BATTERY CALCULATIONS

FP-008 DETAILS

- - - END - - -

OSCAR G. JOHNSON VA MEDICAL CENTER

ELECTRONIC HEALTH RECORDS

MODERNIZATION (EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

01 00 00 - 1 of 30

GENERAL REQUIREMENTS

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1

1.1 SAFETY AND INFECTION CONTROL REQUIREMENTS

A. Refer to Section 01 35 26, SAFETY REQUIREMENTS for safety requirements.

B. Refer to Section 01 81 15 for INFECTION CONTROL AND INTERIUM

LIFE SAFETY MEASURES REQUIREMENTS.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Oscar G. Johnson VA OGJVAMC VA project No. 585-21-700 as required by drawings and specifications.

B. Visits to the site by Bidders may be made in accordance with what is listed in the solicitation and at the discretion of the Contracting Officer.

C. Offices of GDM of Oregon (GDM), of DuPont, Washington, as Architect-Engineers of Record, may assist VA with certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by COR or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratories or commissioning authority testing laboratory retained by the General Contractor, the Contractor shall notify the Contracting Officers Representative(COR) in sufficient time to enable testing laboratories or commissioning authority personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

F. Prior to commencing work, general contractor shall provide proof that a qualified "competent person" (CP) per OSHA 29 CFR

OSCAR G. JOHNSON VA MEDICAL CENTER

ELECTRONIC HEALTH RECORDS

MODERNIZATION(EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

01 00 00 - 2 of 30

GENERAL REQUIREMENTS

1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.

G. Training:

1. All employees of general contractor or subcontractors shall have the 10-hour or 30-hour OSHA certified Construction Safety course and/or other relevant competency training, as determined by the VA COR with input from the Infection Control Risk Assessment (ICRA) team.

2. Submit training records of all such employees for approval before the start of work.

H. Terms used in this contract such as Veterans Affairs (VA) and Government; Contracting Officer (CO) or Contracting Officer's Representative (COR) may be used interchangeably, and refer to the same entity.

I. Schedule: To ensure such executions, Contractor shall furnish the Resident Engineer with a Baseline CPM schedule Per Spec Section 01 32 16.15 Project Schedules which indicates phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. No Work shall begin on-site by the Contractor until the CPM schedule has been approved by the Resident Engineer.

J. The Key Personnel assigned by the contractor for the performance of work on this contract shall be acceptable to VA in terms of personal and professional conduct and technical knowledge.

Should the assignment to this contract of any person by the contractor be deemed to conflict with the interests of VA, or in the event performance is deemed to be unsatisfactory at any time during the life of the contract, the Contracting Officer may notify the contractor and request the person be removed from the assignment. The reason for removal will be documented and a request to receive key personnel replacement within three (3) business days of the notification will be made. Replacement of key personnel qualifications shall be equal to or greater than those of the key personnel being replaced. Employment and staffing difficulties will not be justification for failure to meet established schedules. The contractor is required to submit a resume with qualifications for the proposed replacement which shall be approved by the COR and CO prior to the replacement starting work.

1.3 STATEMENT OF BID ITEM(S)

A. See solicitation for specific information.

OSCAR G. JOHNSON VA MEDICAL CENTER

ELECTRONIC HEALTH RECORDS

MODERNIZATION(EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

01 00 00 - 3 of 30

GENERAL REQUIREMENTS

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the COR so that security escort or arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the COR.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the COR.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the COR for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation.

3. The General Contractor shall provide temporary lock cylinders for use by the contractors during the construction period.

MODERNIZATION(EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

01 00 00 - 4 of 30

GENERAL REQUIREMENTS

a. Lock cores shall be compatible with existing door hardware.

b. Existing lock cores are 6 pin cores with VA keyway.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the COR upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of COR.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify COR and VA Police immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access.

Access shall be restricted to picking up and dropping off materials and supplies by the Loading Dock. Coordinate

MODERNIZATION(EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

01 00 00 - 5 of 30 parking at VA Medical Center with Police and COTR in south parking lot. Parking will be limited due to additional construction projects that will be on-going throughout the VA grounds. Parking may be required off campus. Dumpster for debris shall be located in the south gravel contractor parking area.

F. Personal Conduct:

1. Every person who enters the OGJVAMC’s grounds is expected to conduct themselves in a professional responsible manner without the need to enumerate every expected or prohibited behavior.

2. Weapons, ammunition, explosives, and alcoholic beverages are prohibited on the OGJVAMC’s grounds.

3. There shall be no solicitations or sales of any kind on the OGJVAMC’s grounds.

4. VA reserves the right to refuse to permit employment on the Work or require dismissal from the Work of any subcontractor who, by reason of previous unsatisfactory work on Department of Veterans Affairs project or for any other reason, is considered by the COR to be incompetent or otherwise objectionable.

5. See VA Acquisition Regulation (VAAR) 852.236-80 for additional stipulation.

1.6 OPERATIONS AND STORAGE AREAS

A. The Contractor shall confine all operations (including storage of materials) on OGJAMC premises to areas authorized or approved by the COR. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the COR and shall be built with labor and materials furnished by the Contractor without expense to the Government.

The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the COR, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the COR, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the COR.

When materials are transported in prosecuting the work, vehicles

MODERNIZATION(EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

01 00 00 - 6 of 30 shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. See FAR 52.236-10 for additional stipulations.

E. Working space and space available for storing materials shall be as shown on the drawings.

F. Workers are subject to rules of OGJVAMC applicable to their conduct.

G. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

H. Execute work so as to interfere as little as possible with normal functioning of OGJVAMC as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.

1. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by the COR where required by limited working space.

2. Do not store materials and equipment in other than assigned areas.

3. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than 2 work days.

a. Provide unobstructed access to OGJVAMC areas required to remain in operation.

4. All Work in corridors and other occupied spaces shall be completed after normal working hours and shall be coordinated with the COR.

I. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed

MODERNIZATION(EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

01 00 00 - 7 of 30 by COR. All such actions shall be coordinated with the COR and the Utility Company involved.

J. Phasing:

1. The OGJVAMC must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the Contractor's responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety plan to be used during the work, and a schedule defining the duration of the work with milestone subtasks.

2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR 2 weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to the COR and Contractor.

3. Contractor shall prepare the Project Schedule to reflect the following construction sequencing to maintain hospital functions to the maximum extent practicable:

• All Utility work (electrical distribution, UPS, etc.)

shall be completed first.

• Work within B105 and 5281 may start along with the utility work at the beginning of the project. All work shall be completed with the new racks, switches, and mechanical installation prior to fiber distributions to the Telecommunication Rooms (TR’s).

• TR’s in new locations (not existing TR’s being expanded) can be started at the beginning of the project.

• Existing TR’s that are being expanded shall not start until the utility work, B105 and 5281 mentioned above are complete.

• Only four (4) separate locations (TR’s/B105/5281) that will require OIT escorts can be worked on at the same time.

MODERNIZATION(EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

01 00 00 - 8 of 30 o Contractor shall provide a request, in writing, to the COR for VA staff escorts no less than 3 days prior to scheduled work.

• Existing TR shall remain active until replacement TR is complete and activated. No more than one (1) activation of a completed TR shall happen at a time.

K. All buildings on the campus will be occupied during performance of work.

1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the OGJVAMCs operations will not be hindered. Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment.

These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting, etc., to facilitate patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that OGJVAMC operations will continue during the construction period.

L. When a portion of a building is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 18 degrees C (65 degrees F) at all times, except as otherwise specified.

a. Server rooms shall be maintained between 72-81 degrees F, <60% relative humidity, non-condensing, at all times that server equipment is operating.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.

M. Utilities Services: Maintain existing utility services for OGJVAMC at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, MODERNIZATION(EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

01 00 00 - 9 of 30 steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by the COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of the COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, and the COR and the OGJVAMC Director’s prior knowledge and written approval.

2. Contractor shall submit a request to interrupt any such services to the COR, in writing, 14 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of OGJVAMC. Interruption time approved by OGJVAMC may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of the COR. Such approval will be confirmed in writing as soon as practical.

N. All services to be abandoned such as wires, cables, raceways, ducts, pipes, and the like and their hangers or supports, are to be removed entirely back to the point of connection to the active utility (i.e. piping and ductwork back to active mains, electrical wires and cables back to active circuitry, and all empty raceways). If items are noted to be abandoned in place, they are to be sealed, capped, or plugged.

O. To minimize interference of construction activities with flow of OGJVAMC traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross

MODERNIZATION(EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

01 00 00 - 10 of 30 existing roads, at least one lane must be open to traffic at all times with approval.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

P. Coordinate the work for this contract with other construction operations as directed by the COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE

OF ROADWAYS.

Q. See Far 52.236-10 for future stipulations.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR, of areas of building(s) in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the COR. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected area(s) of building.

2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and the COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of the COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and

"CHANGES" (FAR 52.243-4).

C. Re-Survey: Thirty calendar before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They

MODERNIZATION(EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

01 00 00 - 11 of 30 shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed or used as work access paths they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed the COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from OGJVAMC.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT

MODERNIZATION(EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

01 00 00 - 12 of 30 required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,

UTILITIES, AND IMPROVEMENTS

A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the COR.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the COR may have the necessary work performed and charge the cost to the Contractor.

C. Refer to Section 01 57 19 for additional requirements on protecting existing site improvements, vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge Elimination System (NPDES) permit is required for this project. The Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate OGJVAMC) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the Contractor's method of operations and operations planning and the Contractor

MODERNIZATION(EHRM)

INFRASTRUCTURE UPGRADES

VA Project No. 585-21-700

01 00 00 - 13 of 30 is responsible for employing best management practices. The affected activities often include, but are not limited to the following:

1. Designating areas for equipment maintenance and repair;

2. Providing waste receptacles at convenient locations and provide regular collection of wastes;

3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;

4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and

5. Providing adequately maintained sanitary facilities.

E. Refer to FAR 52.236-9 for additional stipulations.

1.10…

This is the start of the file's text. The full file is on GovTribe.