Attachment 14 Facility Deactivation.docx

DOCX document 21 KB Posted

Attached to
Facility Maintenance Services at Fort McCoy, WI
Solicitation number
W912ES22R0011
Issued by

About this file

This document outlines the tasks required for deactivating various facility types at Fort McCoy, Wisconsin. The tasks include: draining water systems and placing antifreeze in plumbing fixtures; adjusting thermostats and turning off heating systems; disabling fire alarm and security systems; cleaning work areas; and fully draining systems in fully deactivated facilities. Facility types addressed include barracks, dining facilities, laundry facilities, arms vaults, and contingency operation locations. Proper deactivation is required to allow facilities to be shut down safely and securely until they can be reused for their intended purpose.

View the file

Other files

File Type Posted
Amendment 0003 .pdf PDF
Amendment 0002.pdf PDF
Amendment 0002 Site Visit List .pdf PDF
Amendment 0001.pdf PDF
CBA Fort McCoy July 1 2021 - June 30 2024 .pdf PDF
Attachment 9 Available Automation Equipment.xlsx XLSX spreadsheet
Attachment 3.7 Cathodic Protection.xlsx XLSX spreadsheet
Attachment 10 Form TR-WM-118.pdf PDF
Attachment 7 Government Furnished Facilities.xlsx XLSX spreadsheet
Attachment 3.3 Fire Suppression (Wet Pipe).xlsx XLSX spreadsheet
Attachment 3.1 Fire Suppression (Ansul-Chemical).xlsx XLSX spreadsheet
Attachment 6 Historical Workload Service Orders.xlsx XLSX spreadsheet
Attachment 8 Facility Maintenance Repair ATOPSEC Cover Sheet.pdf PDF
Attachment 3.8 Cathodic Protection WWTP.pdf PDF
Attachment 4 Ice Melt Monthly Report.xlsx XLSX spreadsheet
Attachment 3.11 Water Meters Calibration.xlsx XLSX spreadsheet
Attachment 13 Facility Activation.xlsx XLSX spreadsheet
Attachment 1 Performance Requirements Summary.docx DOCX document
Blank Price Schedule - FM Services 15 FEB 2022.xlsx XLSX spreadsheet
Attachment 15 DD Form 254.pdf PDF
Attachment 3.5 Fire Alarm System.docx DOCX document
Attachment 16 Wisconsin HVAC Qualifier Application.pdf PDF
Attachment 18 Water System Valves Lines and Hydrants.pdf PDF
Attachment 10.1 Aboveground Storage Tank Inspection Form 372.xlsx XLSX spreadsheet
Attachment 21 FMF452 Installation Access Pass Request .pdf PDF
Attachment 3.4 Fire Suppression (Dry Pipe).xlsx XLSX spreadsheet
Attachment 20 FMF451 Installation Access NCIC-III Check Request .pdf PDF
Attachment 3.10 Runway Lighting.pdf PDF
Attachment 3.2 Fire Suppression (Kitchen Hood Cleaning).xlsx XLSX spreadsheet
Attachment 2 Fort McCoy Base Data.xlsx XLSX spreadsheet
Solicitation Fort McCoy Fac Maint Services .pdf PDF
Attachment 12 Generator Log.xlsx XLSX spreadsheet
Attachment 3.6 Earth Bond Testing.xlsx XLSX spreadsheet
Attachment 3.9 Elevators and Lifts.xlsx XLSX spreadsheet
Attachment 3.7.1 TR-WM-141 UST Corrosion Protection Test Form.pdf PDF
Attachment 19 POL System Block Book.pdf PDF
Past Performance Questionnaire.pdf PDF
Attachment 6.1 Historical Workload Service Orders.xlsx XLSX spreadsheet
Attachment 11 Facility Standards.docx DOCX document
Attachment 3 PM Task and Frequency Chart.xlsx XLSX spreadsheet
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DPW FACILITY MAINTENANCE & REPAIR CONTRACT

Attachment 14 FACILITY DEACTIVATION

TASK LIST – FORT MCCOY REAL PROPERTY

The following tasks pertain to deactivation of Fort McCoy Facilities. The Contractor is responsible for appropriate measures which will allow the facility and its components to be used for its complete and intended purpose or to conserve energy and to protect facilities and components. The Contractor shall report any deficiencies (in written format) to the Government Work Reception Center. Any work in addition to deactivation will be considered maintenance and repair.

Not all tasks will be required for every building. Contractor shall perform all tasks which apply for buildings issued on deactivation orders. Contractor shall refer to manufacturer recommendations for additional detail on deactivation of equipment.

NO ANTI-FREEZE/GLYCOL TYPE SOLUTIONS WILL BE USED IN THE POTABLE WATER SUPPLY LINES, FIXTURES, OR EQUIPMENT AT ANY TIME.

NO THERMOSTAT ADJUSTMENTS NECESSARY IN FACILITIES WITH PRESET THERMOSTATS.

1. Wood Framed structures, including barracks, classrooms, administration, and BOQ facilities. Type 1.

a. In buildings with or without backflow preventers, turn off water supply at curb stop.

b. Drain all building water systems and fixtures, including fire sprinkler system when applicable. Ensure no water remains in interior fixtures or piping. Completely drain and turn off power to water heater(s), including tankless water heaters.

c. Place adequate amount of anti-freeze in toilets, urinals, sinks, water fountains, showers and floor drains.

d. Deactivate all building heat, including mechanical room, and turn off gas supply valves.

e. Disable fire alarm zones in the fire alarm control panel (FACP). Leave batteries in fire alarm panels. Reprogram the Sig Com Panel to not look for the voice evacuation panel (VEP). Leave batteries in VEP. FACP and VEP to remain energized to maintain battery charge

f. In barracks buildings, turn off the breaker for the bathroom exhaust fans and close dampers.

g. Disconnect Silent knight freeze alarms or Turn off freeze alarm connected to Sig Com panel

h. Clean work area of spills, debris, and dirt.

2. Permanent Construction Buildings - Block, Brick & Mortar buildings – which are not fully deactivated. Includes Buildings 2674 and 1672. Type 2.

a. Turn off water supply at after the backflow preventer.

b. Turn heat down to 50 degrees F. Prop open doors leading from kitchen into dining room.
c. Ensure freeze alarm is connected to Sig Com and test for functionality. Verify that sensorsare located in any rooms that have water. Test sensors for functionality.
d. Turn off electrical breakers to exterior parking lot or sidewalk lighting (i.e. Building 2674).

e. Turn off interior security lighting breaker.

f. Turn off gas to cooking equipment.

g. Turn off outside stand-alone refrigeration.

h. Clean work area of spills, debris, and dirt.

3. Laundry facility. Type 3.

a. Turn off water supply at after the backflow preventer.

b. Insulate and seal combustion air supply for dryers.

c. Turn heat down to 50 degrees F.

d. Ensure freeze alarm is connected to Sig Com and test for functionality. Verify that sensors are located in any rooms that have water. Test sensors for functionality.

e. Clean work area of spills, debris, and dirt.

f. Drain, and turn off power to water heater(s).

4. Wood framed dining facilities. Type 4.

a. Turn off water supply at after the backflow preventer.

b. Turn heat down to 50 degrees F. Prop open mop closet doors located in kitchens.

c. Deactivate and drain fire sprinkler system. Deactivate the sprinkler system compressor.

d. Ensure freeze alarm is connected to Sig Com and test for functionality. Verify that sensors are located in any rooms that have water. Test sensors for functionality.

e. Clean work area of spills, debris, and dirt.

f. Drain, and turn off power to water heater(s).

5. Permanent Construction Buildings - Block, Brick & Mortar buildings; Metal buildings – which are fully deactivated. Includes Buildings 2643, 2776, 2792, 2793, 2840; Unit Maintenance facilities; and COL Dining Facilities. Type 5.

a. In buildings with or without backflow preventers, turn off water supply at curb stop.

b. Drain all building water systems, including fire sprinkler system when applicable. Ensure no water remains in fixtures or piping. Drain, and turn off power to water heater(s) and eye wash stations. Drain all food service equipment (i.e. coffee urns, ice machines, water/ice dispensers.

c. Place adequate amount of anti-freeze in toilets, urinals, sinks, water fountains, showers and floor drains..

d. Drain air compressor lines when applicable.

e. Deactivate all building heat, including mechanical room, and turn off gas supply valves.

f. Disable fire alarm zones in the fire alarm control panel (FACP). Leave batteries in fire alarm panels. Reprogram the Sig Com Panel to not look for the voice evacuation panel (VEP). Leave batteries in VEP. FACP and VEP to remain energized to maintain battery charge

g. Disconnect Silent knight freeze alarms or Turn off freeze alarm connected to Sig Com panel

h. Shut off outside refrigeration.

i. Clean work area of spills, debris, and dirt.

6. Arms Vaults. Type 6.

a. Deactivate building heat and turn off gas supply valves.

b. Disable fire alarm zones in the fire alarm control panel (FACP). Leave batteries in fire alarm panels. Reprogram the Sig Com Panel to not look for the voice evacuation panel (VEP). Leave batteries in VEP. FACP and VEP to remain energized to maintain battery charge

c. Deactivate the intrusion detection system. Notify DES prior to disconnect.

d. Clean work area of spills, debris, and dirt.

7. COL Shower Trailers. Type 7.

a. In buildings with or without backflow preventers, turn off water supply at curb stop.

b. Drain water systems. Ensure no water remains in fixtures or piping. Drain and turn off power to water heater(s).

c. Place adequate amount of anti-freeze in toilets, urinals, sinks, water fountains, showers and floor drains.

d. Deactivate all building heat, including mechanical room, and turn off gas supply valves.

e. Disable fire alarm zones in the fire alarm control panel (FACP). Leave batteries in fire alarm panels. Reprogram the Sig Com Panel to not look for the voice evacuation panel (VEP). Leave batteries in VEP. FACP and VEP to remain energized to maintain battery charge

f. Disconnect Silent knight freeze alarms or Turn off freeze alarm connected to Sig Com panel

g. Clean work area of spills, debris, and dirt.

8. Building 204. Type 8.

a. In buildings with or without backflow preventers, turn off water supply at curb stop.

b. Drain all building water systems, including fire sprinkler system, to the mechanical rooms. Ensure no water remains in fixtures or piping outside the mechanical room.

c. Place adequate amount of anti-freeze in toilets, urinals, sinks, water fountains, showers and floor drains.

d. Turn off/disconnect compressors. Drain compressor tanks and tanks not located in mechanical rooms.

e. Deactivate all building heat, excluding mechanical rooms, and turn off gas supply valves for areas other than mechanical rooms. Set mechanical room heat to 50 degrees F.

f. Disable fire alarm zones in the fire alarm control panel (FACP). Leave batteries in fire alarm panels. Reprogram the Sig Com Panel to not look for the voice evacuation panel (VEP). Leave batteries in VEP. FACP and VEP to remain energized to maintain battery charge

g. Disconnect freeze alarm sensors in unheated areas. Ensure freeze alarm in mechanical room is connected to Sig Com and test for functionality.

h. Clean work area of spills, debris, and dirt.

9. Contingency Operation Locations (COL)

a. Turn off water supply at valve on exterior of the COL.

b. Drain water systems. Ensure no water remains in fixtures or piping. Drain and turn off power to water heater(s).

c. Place adequate amount of anti-freeze in toilets, urinals, sinks, water fountains, showers and floor drains.

d. Disable fire alarm zones in the fire alarm control panel (FACP) of any facility not covered by previous deactivation. Leave batteries in fire alarm panels. Reprogram the Sig Com Panel to not look for the voice evacuation panel (VEP). Leave batteries in VEP. FACP and VEP to remain energized to maintain battery charge

e. Disconnect Silent knight freeze alarms or Turn off freeze alarm connected to Sig Com panel

f. Clean work area of spills, debris, and dirt.

10. TBB Justice, Independence, Range 8

a. Turn off electric power, Range 8 and Independence.

b. Turn on hose bibb to relieve system pressure.

c. Remove pressure tank, disconnect supply and drain piping.

d. Remove water meter.

e. Disconnect water supply piping from UV unit and drain all system piping.

f. Disconnect UV solenoid valve from water supply piping, drain all piping and solenoid valve.

File details come from the government source that posted it. Updated .