Attachment_06_Reporting__10_pages.pdf

PDF 185 KB Posted

Attached to
OPERATION AND MAINTENANCE OF YDP, IDIQ
Solicitation number
140R3026R0012
Issued by
Not on record

About this file

This attachment specifies the reporting requirements for Solicitation 140R3022R0033 across Administrative, Maintenance, Operations, and Security functions.

Administrative Reporting requires contractors to submit multiple plans and reports via official letters with attachments and e-filed to Government-designated personnel. Key submissions include: Administrative Management Plan (annual within 45 calendar days of contract award, then 30 days after each task year start; monthly updates by exception); Procurement System Plan (annual within 30 days of award, then 30 days after each task year); Drug-Free Workplace Policy (initial within 30 days); Organizational Chart (initial within 30 days); Quality Control Program (annual within 60 days, quarterly updates); Safety Program and Compliance (annual within 10 working days of task year start, quarterly updates); Safety Records and Meetings (immediate reporting after occurrence, Form 7-2077 within 3 working days, monthly plant inspections within 5 working days); Security Compliance (annual within 10 working days, quarterly updates); Environmental Compliance Plan (annual within 15 days, quarterly updates); Labor Hours Tracking (daily within 5 working days, weekly, monthly, and annual reporting); Materials Tracking (monthly within 5 working days, annual within 30 working days); Activities Status Reports (weekly one working day prior to meeting); Equipment Downtime Reports (annual within 10 working days, monthly within 5 working days); Quarterly Reports (detailed outline 30 days prior to quarter end, draft 30 days after, final 45 days after Government comments); and Annual Reports (detailed outline 30 days prior to last quarter end, draft 30 days after, final 30 days after comments).

Maintenance Reporting requires submission of Maintenance Management Plan (annual within 45 days of award, monthly updates by exception), Preventive and Predictive Reporting and Scheduling Plan (annual within 45 days, planned month 10 working days prior, planned week updates by exception), House-keeping and Grounds-keeping (annual within 30 days, monthly updates by exception), Painting and Protective Coating (annual within 30 days, monthly updates), Chemical Corrosion Control and Cleaning Plan (annual within 30 days, monthly updates), Facility Structures Cleaning Plan (annual within 30 days, monthly updates), Defects in Material and Workmanship (within 5 calendar days of discovery), Repairs/Breakdown and Failure Maintenance (annual within 30 days, monthly and weekly plans), Modification Work (annual within 30 days, monthly and weekly plans), Backlog Maintenance (annual within 30 days, monthly and weekly plans), Drawing Plan and Report (annual within 30 days, quarterly, monthly, and past month reports), Welding (90 calendar days after award, then 30 days after each task year), Activities Status Reports (weekly), and Physical Property Inventory and Condition Report (annual within 90 days of award, interim as expressed by COR, 30 days after task year 3).

Operations Reporting includes Operations Management Plan (annual within 45 days of award, monthly updates by exception), Operating and Scheduling Plan (quarterly 10 working days prior to new quarter, planned week updates by exception), House-keeping and Grounds-keeping Plan (annual within 30 days, monthly updates), Hazardous Materials and Waste (monthly within 5 working days), Chemicals (monthly within 5 working days), Activities Status Reports (weekly), Operational Production Records and Data (past month within 5 working days, past week within 1 working day, past work day following each work day), and Chemical Projections and Usage Report (annual by December 31 and October 15, quarterly within 10 working days, monthly updates by exception).

Security Reporting requires a Roster submitted e-filed monthly within 5 working days following each month ending. All submittals are subject to the Contracting Officer Representative (COR) approval, and contractors receive only one 10 calendar day grace period to correct deficient submittals before performance deficiencies are assessed.

View the file

Other files

File Type Posted
Attachment_01C_Price_Breakdown-OFFEROR_COMPLETE_0002.xlsx XLSX spreadsheet
Attachment_01CC_Schedule_of_Fixed_Hourly_Labor_Rates-OFFEROR_COMPLETE_0002.xlsx XLSX spreadsheet
140R3026R0012-Solicitation_Rev_-1_0002.pdf PDF
Attachment_1_Statement_of_Work_pg_98_0002.pdf PDF
Sol_140R3026R0012_Amd_0002.pdf PDF
Attachment_-_Questions_and_Responses_0002.pdf PDF
140R3026R0012-Solicitation_0001.pdf PDF
Sol_140R3026R0012_Amd_0001.pdf PDF
Attachment_23_-_PPQ.pdf PDF
Attachment_01CC_Schedule_of_Fixed_Hourly_Labor_Rates-OFFEROR_COMPLETE.xlsx XLSX spreadsheet
Attachment_01B_Levels_of_Performance_EXPLANATION__1_page.pdf PDF
Attachment_03_PPICR.xlsx XLSX spreadsheet
Attachment_05_CARMA_Business_Standards__76_pages.pdf PDF
Attachment_10_Forms__12_pages.pdf PDF
Attachment_13_Modification_and_Repair_Backlog.xlsx XLSX spreadsheet
Attachment_22_Sample_YDP_and_PS1_Water_Quality_Reports.xlsx XLSX spreadsheet
Attachment_01D_Personnel_Resource_Matrix__OFFEROR_COMPLETE.xlsx XLSX spreadsheet
Attachment_01A_Basis_for_Contract_Cost__1_page.pdf PDF
Attachment_1_Statement_of_Work_.pdf PDF
Attachment_04_Safety_and_Health_Standards_Glossary__11_pages.pdf PDF
Attachment_11_Emergency_Response_Services__8_pages.pdf PDF
Attachment_15_STORES_Inventory_340_Catalog__1_of_2.xlsx XLSX spreadsheet
Attachment_08_Wage_Determination_2015-5475__Rev__30__10_pages.pdf PDF
Attachment_01B_Levels_of_Performance_OFFEROR_COMPLETE.xlsx XLSX spreadsheet
Attachment_19_Current_AL_Small_Service_Contracts.xlsx XLSX spreadsheet
Attachment_20_Sample_ADEQ_Potable_Water_Inspection_Report__16_pages.pdf PDF
Attachment_17_Sample_CRADA__10_pages.pdf PDF
Attachment_02_Government_Furnished_Equipment__10_pages.pdf PDF
Attachment_01_Performance_Requirements_Summary_(PRS).pdf PDF
Attachment_07_Drawings__6_pages.pdf PDF
Attachment_15_STORES_Inventory_345_Catalog__2_of_2.xlsx XLSX spreadsheet
Sol_140R3026R0012.pdf PDF
Attachment_01C_Price_Breakdown-OFFEROR_COMPLETE.xlsx XLSX spreadsheet
Attachment_21_Sample_FCU_Temperature_Status_Report.xlsx XLSX spreadsheet
Attachment_01E_Service_Contracts_-_Pricing_Summary__OFFEROR_COMPLETE.xlsx XLSX spreadsheet
Attachment_16_Contractor_On-boarding_Off-boarding_Process__23_pages.pdf PDF
Attachment_18_Permits__234_pages.pdf PDF
Attachment_12_Sample_Invoice__6_pages.pdf PDF
Attachment_14_Preventive_and_Predictive_Maintenance_Summary.xlsx XLSX spreadsheet
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation 140R3022R0033 Attachment (6): Reporting: Administrative; Maintenance; Operations; Security

Note 1: Unless otherwise specified, all Submittals, Plans and Reports are subject to the COR’s approval.

Note 2: Unless otherwise specified, the Contractor shall be provided only one 10 calendar day grace period to correct any submittals. Any failure to correct submittals in a manner that gains Government approval will be considered a Deficiency. Any Deficiency will be accessed as per section C.2.5.4.1 (Performance Documentation).

Administrative Reporting

Section C Reference Report Type Method of Report Frequency

C.2.1 Administrative Management Plan

By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – 45 calendar days after contract award and then 30 calendar days after each annual task order (task year) start.

(2) Monthly – Update by Exception, 5 working days prior to planned month.

C.2.3.1 Procurement System Plan By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – 30 calendar days after contract award and then 30 calendar days after each task year start.

(2) Monthly – update by Exception, 5 working days prior to planned month.

C.2.4.2.2 Drug-Free Workplace Policy By Official Letter (with attachment) and E-File to CO

(1) Initial – 30 calendar days after contract award.

(2) Update – Annually based on Reclamation current and evolving policies.

C.2.5.1 Organizational Chart By Official Letter (with attachments) and E-file to Government designated personnel

(1) Initial – 30 calendar days after contract award.

(2) (2) Update by Exception, 5 calendar days prior to implementation.

C.2.5.3 Quality Control Program

(QCP)

By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – Planned, 60 calendar days after contract award and then 30 calendar days after each task year start.

(2) Quarterly – update by Exception, 10 working days prior to planned month.

C.2.6.1 Safety Program and Compliance

By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – 10 working days after each task year start.

(2) Quarterly – update by Exception, 10 working days prior to planned month.

Note 1: Unless otherwise specified, all Submittals, Plans and Reports are subject to the COR’s approval.

Note 2: Unless otherwise specified, the Contractor shall be provided only one 10 calendar day grace period to correct any submittals. Any failure to correct submittals in a manner that gains Government approval will be considered a Deficiency. Any Deficiency will be accessed as per section C.2.5.4.1 (Performance Documentation).

Administrative Reporting

Section C Reference Report Type Method of Report Frequency

C.2.6.1.2 and C.2.6.1.5

Safety Records and Safety Meetings

By Official Letter (with attachments) and e-file to Government designated personnel

(1) Immediately after occurrence.

(2) Contractor’s Report of Recordable Injury/Illness, (Form 7-

2077) - 3 working days after occurrence.

(3) Weekly safety contractor meeting (Tool Box) inclusion in monthly report.

(4) Monthly Plant Inspections & Reporting - 5 working days following month ending.

(5) Monthly Summary of Occupational Injuries/Illness

Experience (Form 7-2218) Reporting - 5 working days following month ending.

(6) Annual Reporting – 10 working days after each task year start.

C.2.6.2 Security Compliance By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – 10 working days after each task year start.

(2) Quarterly – update by Exception, 10 working days prior to planned month.

C.2.6.2.4 Theft, Damage, Lost, Missing, and Vandalism

By Official Letter (with attachments) and E-file to Government designated personnel per occurrence

(1) Verbal notification within 1 hour after discovery, written documentation the following workday.

C.2.7 Environmental Compliance Plan

By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – 15 calendar days after each task year start.

(2) Quarterly – update by Exception, 10 working days prior to planned month.

C.2.7.2 Environmental Records By Official Letter (with attachments) and E-file to Government designated personnel

(1) Immediately after occurrence.

(2) Monthly Plant Inspections & Reporting - 5 working days following month ending.

(3) Compliance Reporting - As required by BOR, permitting &

Note 1: Unless otherwise specified, all Submittals, Plans and Reports are subject to the COR’s approval.

Note 2: Unless otherwise specified, the Contractor shall be provided only one 10 calendar day grace period to correct any submittals. Any failure to correct submittals in a manner that gains Government approval will be considered a Deficiency. Any Deficiency will be accessed as per section C.2.5.4.1 (Performance Documentation).

Administrative Reporting

Section C Reference Report Type Method of Report Frequency regulatory agencies.

(4) Annual – and then 30 calendar days after each task year start.

(1)

C.2.8.6.6.5 Labor Hours Tracking E-file to Government designated personnel (All reports)

(1) Daily – no more than 5 working days after occurrence.

(2) Weekly Reporting – 1 working day following week ending.

(3) Monthly Reporting – 5 working days following month ending.

(4) Annual Reporting – 30 working days following year end.

C.2.8.6.6.6 Materials Tracking E-file to Government designated personnel (All reports)

(1) Monthly – 5 working days following month end.

(2) Annual – 30 working days following year end.

C.2.9.2 Activities Status Report By E-file to Government designated personnel prior to meeting

(1) Weekly – One working day prior to weekly meeting.

C.2.9.2 Equipment Downtime Report By Official Letter (with attachments) and (Annual & Monthly), E-file to Government designated personnel (All reports)

(1) Annual – 10 working days after each task year start.

(2) Monthly – 5 working days following month ending.

(3)

C.2.9.3.3 Quarterly Report By Official Letter (with attachments) and E-file to Government designated personnel

(1) Quarterly – Detailed Outline, 30 calendar days prior to the end of the quarter.

(2) Quarterly – Planned Draft, 30 calendar days after the end of the quarter.

(3) Quarterly – Planned Final, 45 calendar days after Government comments.

Note 1: Unless otherwise specified, all Submittals, Plans and Reports are subject to the COR’s approval.

Note 2: Unless otherwise specified, the Contractor shall be provided only one 10 calendar day grace period to correct any submittals. Any failure to correct submittals in a manner that gains Government approval will be considered a Deficiency. Any Deficiency will be accessed as per section C.2.5.4.1 (Performance Documentation).

Administrative Reporting

Section C Reference Report Type Method of Report Frequency

C.2.9.3.4 Annual Report By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – Detailed Outline, 30 calendar days prior to the end of the last quarter.

(2) Annual – Planned Draft, 30 calendar days after the end of the last quarter.

(3) Annual – Planned Final, 30 calendar days after Government comments.

C.2.9.4 Additional Reports By Official Letter (with attachments) and E-file to Government designated personnel

(1) 30 calendar days after COR’s established performance period of the technical work unless otherwise expressed by the COR.

Note 1: Unless otherwise specified, all Submittals, Plans and Reports are subject to the COR’s approval.

Note 2: Unless otherwise specified, the Contractor shall be provided only one 10 calendar day grace period to correct any submittals. Any failure to correct submittals in a manner that gains Government approval will be considered a Deficiency. Any Deficiency will be accessed as per section C.2.5.4.1 (Performance Documentation).

Maintenance Reporting

Section C Reference Report Type Method of Report Frequency C.3.1 Maintenance Management

Plan By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – 45 calendar days after contract award and then 30 calendar days after each task year start.

(2) Monthly – Update by Exception, 5 working days prior to the month.

C.3.3.1.1.1 Preventive and Predictive Reporting and Scheduling Plan

By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – 45 calendar days after contract award and then 30 calendar days after each task year start.

(2) Planned Month – 10 working days prior to each planned month.

(3) Planned Week – Update by exception, 1 work day prior to each week.

(4) C.3.3.1.1.2

House-keeping and Grounds-keeping

By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – 30 calendar days after contract award and then 30 calendar days after each task year start.

(2) Planned Month - Update by exception, 5 working days prior to each month

C.3.3.1.1.3 Painting and Protective Coating

By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – 30 calendar days after contract award and then 30 calendar days after each task year start.

(2) Planned Month - Update by exception, 5 working days prior to each month.

C.3.3.1.1.4 Chemical Corrosion Control and Cleaning Plan

By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – 30 calendar days after contract award and then 30 calendar days after each task year start.

(2) Planned Month – Update by exception, 5 working days prior to each month.

C.3.3.1.1.5 Facility Structures Cleaning Plan

By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – 30 calendar days after contract award and then 30 calendar days after each task year start.

(2) Planned Month – Update by exception, 5 working days prior to each month.

C.3.3.1.2 Defects in Material and Workmanship Covered by Manufacturer Warranty

By E-file to Government designated personnel

(1) 5 calendar days after discovery of any observed or noted defects in material and workmanship.

C.3.3.2 Repairs (Breakdown and Failure Maintenance)

By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – 30 calendar days after contract award and then 30 calendar days after each task year start.

(2) Planned Month – 5 working days prior to each month.

(3) Planned Week – By exception, 1 day prior to each

Note 1: Unless otherwise specified, all Submittals, Plans and Reports are subject to the COR’s approval.

Note 2: Unless otherwise specified, the Contractor shall be provided only one 10 calendar day grace period to correct any submittals. Any failure to correct submittals in a manner that gains Government approval will be considered a Deficiency. Any Deficiency will be accessed as per section C.2.5.4.1 (Performance Documentation).

Maintenance Reporting

Section C Reference Report Type Method of Report Frequency week.

(4)

Maintenance Reporting

Section C Reference Report Type Method of Report Frequency

C.3.3.3 Modification Work By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – 30 calendar days after contract award and then 30 calendar days after each task year start.

(2) Planned Month – 5 working days prior to each month.

(3) Planned Week – By exception, 1 day prior to each week.

(4)

C.3.3.4 Backlog Maintenance By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – Backlog, 30 calendar days after contract award and then 30 calendar days after each task year start.

(2) Planned Month – 5 working days prior to each month.

(3) Planned Week – By exception, 1 day prior to each week.

(4)

C.3.4 Drawing Plan and Report By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – 30 calendar days after contract award and then 30 calendar days after each task year start.

(2) Plan Quarter – 10 working days prior to each month.

(3) Plan Month - Update by exception, 5 working days prior to each month.

(4) Past Month - 5 working days following each month.

C.3.5 Welding By Official Letter (with attachments) and E-file to Government designated personnel

(1) 90 calendar days after contract award and then 30 calendar days after each task year start.

C.3.12.1 Activities Status Report By E-file to Government designated personnel prior to meeting

(1) Weekly – One working day prior to planned meeting.

Note 1: Unless otherwise specified, all Submittals, Plans and Reports are subject to the COR’s approval.

Note 2: Unless otherwise specified, the Contractor shall be provided only one 10 calendar day grace period to correct any submittals. Any failure to correct submittals in a manner that gains Government approval will be considered a Deficiency. Any Deficiency will be accessed as per section C.2.5.4.1 (Performance Documentation).

Maintenance Reporting

Section C Reference Report Type Method of Report Frequency

C.3.12.2 Physical Property Inventory and Condition Report

By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – Planned, 90 calendar days after contract award.

(2) Interim – As expressed by the COR.

(3) 30 calendar days after task year 3.

C.3.13 Additional Reports By Official Letter (with attachments) and E-file to Government designated personnel

(1) 30 calendar days after COR’s established performance

Note 1: Unless otherwise specified, all Submittals, Plans and Reports are subject to the COR’s approval.

Note 2: Unless otherwise specified, the Contractor shall be provided only one 10 calendar day grace period to correct any submittals. Any failure to correct submittals in a manner that gains Government approval will be considered a Deficiency. Any Deficiency will be accessed as per section C.2.5.4.1 (Performance Documentation).

Operations Reporting

Reference Report Type Method of Report Frequency

C.4.1 Operations Management Plan

By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – 45 calendar days after contract award and then 30 calendar days after each task year start.

(2) Monthly – Update by Exception, 5 working days prior to the month.

C.4.2 Operating and Scheduling Plan

By Official Letter (with attachments) and E-file to Government designated personnel

(1) Quarterly – 10 working days prior to the new quarter.

(2) Planned Week – Update by Exception, 1 working day prior to the planned week.

(3)

C.4.8 House-keeping and Grounds-keeping Plan

By Official Letter (with attachments) and E-file to Government designated personnel

(1) Annual – 30 calendar days after contract award and then 30 calendar days after each task year start.

(2) Planned Month – Update by exception, 5 working days prior to each month.

C.4.10.1 Hazardous Materials and Waste

E-file to Government designated personnel

(1) Monthly – 5 working days after the end of each month.

C.4.11 Chemicals E-file to Government designated personnel

(1) Monthly – 5 working days after the end of each month.

C.4.12.1 Activities Status Report By E-file to Government designated personnel prior to meeting

(1) Weekly – One working day prior to planned meeting.

C.4.12.2 Operational Production Records and Data Reporting

E-file to Government designated personnel

(1) Past Month – 5 working days following each month ending.

(2) Past Week – 1 working day after each week ending.

(3) Past work day – Following each work day.

Note 1: Unless otherwise specified, all Submittals, Plans and Reports are subject to the COR’s approval.

Note 2: Unless otherwise specified, the Contractor shall be provided only one 10 calendar day grace period to correct any submittals. Any failure to correct submittals in a manner that gains Government approval will be considered a Deficiency. Any Deficiency will be accessed as per section C.2.5.4.1 (Performance Documentation).

Operations Reporting

Section C Reference Report Type Method of Report Frequency

C.4.12.3 Chemical Projections and Usage Report

By Official Letter (with attachments) and (Annual and Monthly), E-file to Government designated personnel

(1) Annual – Initial by December 31st and October 15 of each task year.

(2) Past Quarter – 10 working days after each quarter.

(3) Monthly (Update by exception) – 5 working days following each month ending.

C.4.13 Additional Reports By Official Letter (with attachments) and E-file to Government designated personnel

(1) 30 calendar days after COR’s established performance

Note 1: Unless otherwise specified, all Submittals, Plans and Reports are subject to the COR’s approval.

Note 2: Unless otherwise specified, the Contractor shall be provided only one 10 calendar day grace period to correct any submittals. Any failure to correct submittals in a manner that gains Government approval will be considered a Deficiency. Any Deficiency will be accessed as per section C.2.5.4.1 (Performance Documentation).

Security Reporting

Reference Report Type Method of Report Frequency

C.7.6.6 Roster E-file to Government designated personnel

(1) Monthly – 5 working days following each month ending.

File details come from the government source that posted it. Updated .