Attachment_01C_Price_Breakdown-OFFEROR_COMPLETE.xlsx
XLSX spreadsheet 36 KB Posted
- Attached to
- OPERATION AND MAINTENANCE OF YDP, IDIQ
- Solicitation number
- 140R3026R0012
- Issued by
- Not on record
About this file
This is a Price Breakdown Schedule for an Indefinite Delivery Indefinite Quantity (IDIQ) contract for Operation and Maintenance (O&M) of YDP (Yuma Desalting Plant). The contract is issued by the Department of the Interior Bureau of Reclamation under Solicitation Number 140R2026R0012, covering six ordering periods from February 1, 2027 through August 31, 2032. The contract structure offers multiple tiered service options across each ordering period, including: Routine O&M Services; Routine O&M Services plus O&M for WQIC Research Efforts; Routine O&M Services plus O&M for WQIC Research Efforts plus YDP Maintenance; Routine O&M Services plus O&M for WQIC Research Efforts plus YDP Maintenance plus Operations of the YDP; and variations excluding WQIC Research Efforts. Each primary service tier contains sub-options organized by operational capacity levels (Minimum, 33%, 66%, and Full operation capacity). The contract establishes fixed "Not to Exceed" amounts for Materials and Small Chemical Purchases ranging from $132,000 to $420,000 depending on the service category, Travel and Travel Related Costs capped at $6,000 per ordering period, and an optional Armed Guard Services CLIN for evening and weekend coverage. The first ordering period (February 1, 2027 – January 31, 2028) establishes a baseline contract value of $420,000, with each subsequent twelve-month ordering period maintaining the same value through Ordering Period 5 (February 1, 2031 – January 31, 2032). Ordering Period 6 (February 1, 2032 – August 31, 2032), marked as an optional six-month period, also totals $420,000. The running contract total through all ordering periods reaches $2,520,000. The schedule notes that specific unit prices and total prices for labor-related CLINs will be completed upon award, pending determination of the selected Level of Effort option.
View the file
Other files
Show all 39
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Schedule B
| Solicitation/Contract No. | Document Title | Page 1 of 8 | |
| 140R2026R0012 | YAO O&M Support Services |
| Ordering Period 1 | ||||||
| February 1, 2027 to January 31, 2028 | ||||||
| Contract Line Item Number (CLIN) | Description | Quantity | Unit of Issue | Unit Price | Total Price | |
| A.1 | Routine O&M Services | 12 | Months | $ - 0 | $ - 0 | |
| A.2 | Routine O&M Services, plus O&M for WQIC Research Efforts | |||||
| A.2.1 | Routine O&M & Research Efforts | 12 | Months | $ - 0 | $ - 0 | |
| A.3 | Routine O&M Services, plus O&M for WQIC Research Efforts, | |||||
| plus YDP maintenance | ||||||
| A.3.1 | Minimum Level of Effort | 12 | Months | $ - 0 | $ - 0 | |
| A.3.2 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| A.3.3 | 66% and Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| A.3.4 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| A.4 | Routine O&M Services, plus O&M for WQIC Research Efforts, | |||||
| plus YDP maintenance plus Operations of the YDP | ||||||
| A.4.1 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| A.4.2 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| A.4.3 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| A.5 | Routine O&M Services, plus Maintenance of the YDP, No O&M for WQIC | |||||
| Research Efforts | ||||||
| A.5.1 | Minimum Level of Effort | 12 | Months | $ - 0 | $ - 0 | |
| A.5.2 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| A.5.3 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| A.5.4 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| A.6 | Routine O&M Services, plus Maintenance of the YDP, Plus Operations of the | |||||
| YDP, No O&M for WQIC Research Efforts | ||||||
| A.6.1 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| A.6.2 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| A.6.3 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| A.7 | Variable IDIQ Level of Effort required for O&M services (as issued and funded | $ 5,000.00 | ||||
| on individual task orders, as per Schedule of Fully Burdened Negotiated | ||||||
| Fixed Unit Labor Rates | ||||||
| A.8 | Materials & Small Chemical Purchases | |||||
| A.8.1 | Necessary for Routine O&M Services | Not to Exceed | $132,000 | |||
| A.8.2 | Necessary for O&M for WQIC Research Efforts | Not to Exceed | $144,000 | |||
| A.8.3 | Necessary for Maintenance of YDP | Not to Exceed | $420,000 | |||
| A.8.4 | Necessary for Operations of YDP | Not to Exceed | $360,000 | |||
| A.9 | Travel and Travel Related Costs | Not to Exceed | $6,000 | |||
| A.10 | Optional CLIN: Armed Guard Services 6 p.m. to 6 a.m., Monday through Friday and from 6 p.m. Friday through 6 a.m. Monday. | 12 | Months | $ - 0 | $ - 0 | |
| A.11 | Phase In Transition | LS | $0 | Contract Manager+Finance/Personnel Admin for 4 weeks + ODC | ||
| A.12 | Phase Out Transition (only to be used if | LS | $0 | Contract Manager+Finance/Personnel Admin for 3 weeks + ODC | ||
| Optional 2nd Performance Period is not | ||||||
| exercised) | ||||||
| Total for Ordering Period 1 Performance Period | $ 420,000.00 | |||||
| As it is unknown at what Level of Effort(s) award will be determined, this field will be completed | ||||||
| upon award or exercise of option. | ||||||
| Running Total through Ordering Period 1 Performance Period | $ 420,000.00 |
| Ordering Period 2 | ||||||
| February 1, 2028 to January 31, 2029 | ||||||
| Contract Line Item Number (CLIN) | Description | Quantity | Unit of Issue | Unit Price | Total Price | |
| B.1 | Routine O&M Services | 12 | Months | $ - 0 | $ - 0 | |
| B.2 | Routine O&M Services, plus O&M for WQIC Research Efforts | |||||
| B.2.1 | Routine O&M & Research Efforts | 12 | Months | $ - 0 | $ - 0 | |
| B.3 | Routine O&M Services, plus O&M for WQIC Research Efforts, | |||||
| plus YDP maintenance | ||||||
| B.3.1 | Minimum Level of Effort | 12 | Months | $ - 0 | $ - 0 | |
| B.3.2 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| B.3.3 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| B.3.4 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| B.4 | Routine O&M Services, plus O&M for WQIC Research Efforts, | |||||
| plus YDP maintenance plus Operations of the YDP | ||||||
| B.4.1 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| B.4.2 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| B.4.3 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| B.5 | Routine O&M Services, plus Maintenance of the YDP, No O&M for WQIC | |||||
| Research Efforts | ||||||
| B.5.1 | Minimum Level of Effort | 12 | Months | $ - 0 | $ - 0 | |
| B.5.2 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| B.5.3 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| B.5.4 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| B.6 | Routine O&M Services, plus Maintenance of the YDP, Plus Operations of the | |||||
| YDP, No O&M for WQIC Research Efforts | ||||||
| B.6.2 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| B.6.3 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| B.5.4 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| B.7 | Variable IDIQ Level of Effort required for O&M services (as issued and funded | |||||
| on individual task orders, as per Schedule of Fully Burdened Negotiated | ||||||
| Fixed Unit Labor Rates | ||||||
| B.8 | Materials & Small Chemical Purchases | |||||
| B.8.1 | Necessary for Routine O&M Services | Not to Exceed | $132,000 | |||
| B.8.2 | Necessary for O&M for WQIC Research Efforts | Not to Exceed | $144,000 | |||
| B.8.3 | Necessary for Maintenance of YDP | Not to Exceed | $420,000 | |||
| B.8.4 | Necessary for Operations of YDP | Not to Exceed | $360,000 | |||
| B.9 | Travel and Travel Related Costs | Not to Exceed | $6,000 | |||
| B.10 | Optional CLIN: Armed Guard Services 6 p.m. to 6 a.m., Monday through Friday and from 6 p.m. Friday through 6 a.m. Monday. | |||||
| 12 | Months | $ - 0 | $ - 0 | |||
| B.11 | Phase Out Transition (only to be used if | LS | $0 | Contract Manager+Finance/Personnel Admin for 3 weeks + ODC | ||
| Optional 2nd Performance Period is not | ||||||
| exercised) | ||||||
| Total for the Ordering Period 2 Performance Period | $ 420,000.00 | |||||
| As it is unknown at what Level of Effort(s) award will be determined, this field will be completed | ||||||
| upon award or exercise of option. | ||||||
| Running Total through Ordering Period 2Performance Period | $ 840,000.00 |
| Ordering Period 3 | ||||||
| February 1, 2029 to January 31, 2030 | ||||||
| Contract Line Item Number (CLIN) | Description | Quantity | Unit of Issue | Unit Price | Total Price | |
| C.1 | Routine O&M Services | 12 | Months | $ - 0 | $ - 0 | |
| C.2 | Routine O&M Services, plus O&M for WQIC Research Efforts | |||||
| C.2.1 | Routine O&M & Research Efforts | 12 | Months | $ - 0 | $ - 0 | |
| C.3 | Routine O&M Services, plus O&M for WQIC Research Efforts, | |||||
| plus YDP maintenance | ||||||
| C.3.1 | Minimum Level of Effort | 12 | Months | $ - 0 | $ - 0 | |
| C.3.2 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| C.3.3 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| C.3.4 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| C.4 | Routine O&M Services, plus O&M for WQIC Research Efforts, | |||||
| plus YDP maintenance plus Operations of the YDP | ||||||
| C.4.1 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| C.4.2 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| C.4.3 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| C.5 | Routine O&M Services, plus Maintenance of the YDP, No O&M for WQIC | |||||
| Research Efforts | ||||||
| C.5.1 | Minimum Level of Effort | 12 | Months | $ - 0 | $ - 0 | |
| C.5.2 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| C.5.3 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| C.5.4 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| C.6 | Routine O&M Services, plus Maintenance of the YDP, Plus Operations of the | |||||
| YDP, No O&M for WQIC Research Efforts | ||||||
| C.6.1 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| C.6.2 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| C.6.3 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| C.7 | Variable IDIQ Level of Effort required for O&M services (as issued and funded | |||||
| on individual task orders, as per Schedule of Fully Burdened Negotiated | ||||||
| Fixed Unit Labor Rates | ||||||
| C.8 | Materials & Small Chemical Purchases | |||||
| C.8.1 | Necessary for Routine O&M Services | Not to Exceed | $132,000 | |||
| C.8.2 | Necessary for O&M for WQIC Research Efforts | Not to Exceed | $144,000 | |||
| C.8.3 | Necessary for Maintenance of YDP | Not to Exceed | $420,000 | |||
| C.8.4 | Necessary for Operations of YDP | Not to Exceed | $360,000 | |||
| C.9 | Travel and Travel Related Costs | Not to Exceed | $6,000 | |||
| C.10 | Optional CLIN: Armed Guard Services 6 p.m. to 6 a.m., Monday through Friday and from 6 p.m. Friday through 6 a.m. Monday. | |||||
| 12 | Months | $ - 0 | $ - 0 | |||
| C.11 | Phase Out Transition (only to be used if | Months | $0 | Contract Manager+Finance/Personnel Admin for 3 weeks + ODC | ||
| Optional 2nd Performance Period is not | ||||||
| exercised) | ||||||
| Total for the Ordering Period 3 Performance Period | $ 420,000.00 | |||||
| As it is unknown at what Level of Effort(s) award will be determined, this field will be completed | ||||||
| upon award or exercise of option. | ||||||
| Running Total through Ordering Period 3 Performance Period | $ 1,260,000.00 |
| Ordering Period 4 | ||||||
| February 1, 2030 to January 31, 2031 | ||||||
| Contract Line Item Number (CLIN) | Description | Quantity | Unit of Issue | Unit Price | Total Price | |
| D.1 | Routine O&M Services | 12 | Months | $ - 0 | $ - 0 | |
| D.2 | Routine O&M Services, plus O&M for WQIC Research Efforts | |||||
| D.2.1 | Routine O&M & Research Efforts | 12 | Months | $ - 0 | $ - 0 | |
| D.3 | Routine O&M Services, plus O&M for WQIC Research Efforts, | |||||
| plus YDP maintenance | ||||||
| D.3.1 | Minimum Level of Effort | 12 | Months | $ - 0 | $ - 0 | |
| D.3.2 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| D.3.3 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| D.3.4 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| D.4 | Routine O&M Services, plus O&M for WQIC Research Efforts, | |||||
| plus YDP maintenance plus Operations of the YDP | ||||||
| D.4.1 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| D.4.2 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| D.4.3 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| D.5 | Routine O&M Services, plus Maintenance of the YDP, No O&M for WQIC | |||||
| Research Efforts | ||||||
| D.5.1 | Minimum Level of Effort | 12 | Months | $ - 0 | $ - 0 | |
| D.5.2 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| D.5.3 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| D.5.4 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| D.6 | Routine O&M Services, plus Maintenance of the YDP, Plus Operations of the | |||||
| YDP, No O&M for WQIC Research Efforts | ||||||
| D.6.1 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| D.6.2 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| D.6.3 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| D.7 | Variable IDIQ Level of Effort required for O&M services (as issued and funded | |||||
| on individual task orders, as per Schedule of Fully Burdened Negotiated | ||||||
| Fixed Unit Labor Rates | ||||||
| D.8 | Materials & Small Chemical Purchases | |||||
| D.8.1 | Necessary for Routine O&M Services | Not to Exceed | $132,000 | |||
| D.8.2 | Necessary for O&M for WQIC Research Efforts | Not to Exceed | $144,000 | |||
| D.8.3 | Necessary for Maintenance of YDP | Not to Exceed | $420,000 | |||
| D.8.4 | Necessary for Operations of YDP | Not to Exceed | $360,000 | |||
| D.9 | Travel and Travel Related Costs | Not to Exceed | $6,000 | |||
| D.10 | Optional CLIN: Armed Guard Services 6 p.m. to 6 a.m., Monday through Friday and from 6 p.m. Friday through 6 a.m. Monday. | |||||
| 12 | Months | $ - 0 | $ - 0 | |||
| D.11 | Phase Out Transition (only to be used if | LS | $0 | Contract Manager+Finance/Personnel Admin for 3 weeks + ODC | ||
| Optional 2nd Performance Period is not | ||||||
| exercised) | ||||||
| Total for the Ordering Period 4 Performance Period | $ 420,000.00 | |||||
| As it is unknown at what Level of Effort(s) award will be determined, this field will be completed | ||||||
| upon award or exercise of option. | ||||||
| Running Total through Ordering Period 4 Performance Period | $ 1,680,000.00 |
| Ordering Period 5 | ||||||
| February 1, 2031 to January 31, 2032 | ||||||
| Contract Line Item Number (CLIN) | Description | Quantity | Unit of Issue | Unit Price | Total Price | |
| E.1 | Routine O&M Services | 12 | Months | $ - 0 | $ - 0 | |
| E.2 | Routine O&M Services, plus O&M for WQIC Research Efforts | |||||
| E.2.1 | Routine O&M & Research Efforts | 12 | Months | $ - 0 | $ - 0 | |
| E.3 | Routine O&M Services, plus O&M for WQIC Research Efforts, | |||||
| plus YDP maintenance | ||||||
| E.3.1 | Minimum Level of Effort | 12 | Months | $ - 0 | $ - 0 | |
| E.3.2 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| E.3.3 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| E.3.4 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| E.4 | Routine O&M Services, plus O&M for WQIC Research Efforts, | |||||
| plus YDP maintenance plus Operations of the YDP | ||||||
| E.4.1 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| E.4.2 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| E.4.3 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| E.5 | Routine O&M Services, plus Maintenance of the YDP, No O&M for WQIC | |||||
| Research Efforts | ||||||
| E.5.1 | Minimum Level of Effort | 12 | Months | $ - 0 | $ - 0 | |
| E.5.2 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| E.5.3 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| E.5.4 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| E.6 | Routine O&M Services, plus Maintenance of the YDP, Plus Operations of the | |||||
| YDP, No O&M for WQIC Research Efforts | ||||||
| E.6.1 | 33% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| E.6.2 | 66% operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| E.6.3 | Full operation capacity | 12 | Months | $ - 0 | $ - 0 | |
| Level of Effort | ||||||
| E.7 | Variable IDIQ Level of Effort required for O&M services (as issued and funded | |||||
| on individual task orders, as per Schedule of Fully Burdened Negotiated | ||||||
| Fixed Unit Labor Rates | ||||||
| E.8 | Materials & Small Chemical Purchases | |||||
| E.8.1 | Necessary for Routine O&M Services | Not to Exceed | $132,000 | |||
| E.8.2 | Necessary for O&M for WQIC Research Efforts | Not to Exceed | $144,000 | |||
| E.8.3 | Necessary for Maintenance of YDP | Not to Exceed | $420,000 | |||
| E.8.4 | Necessary for Operations of YDP | Not to Exceed | $360,000 | |||
| E.9 | Travel and Travel Related Costs | Not to Exceed | $6,000 | |||
| E.10 | Optional CLIN: Armed Guard Services 6 p.m. to 6 a.m., Monday through Friday and from 6 p.m. Friday through 6 a.m. Monday. | |||||
| 12 | Months | $ - 0 | $ - 0 | |||
| E.11 | Phase Out Transition (only to be used if | LS | $0 | Contract Manager+Finance/Personnel Admin for 3 weeks + ODC | ||
| Optional 2nd Performance Period is not | ||||||
| exercised) | ||||||
| Total for the Ordering Period 5 Performance Period | $ 420,000.00 | |||||
| As it is unknown at what Level of Effort(s) award will be determined, this field will be completed | ||||||
| upon award or exercise of option. | ||||||
| Running Total through Ordering Period 5 Performance Period | $ 2,100,000.00 |
| 52.217-8 Option Ordering Period 6 | |||||
| February 1, 2032 to August 31, 2032 | |||||
| Contract Line Item Number (CLIN) | Description | Quantity | Unit of Issue | Unit Price | Total Price |
| F.1 | Routine O&M Services | 6 | Months | $ - 0 | $ - 0 |
| F.2 | Routine O&M Services, plus O&M for WQIC Research Efforts | ||||
| F.2.1 | Routine O&M & Research Efforts | 6 | Months | $ - 0 | $ - 0 |
| F.3 | Routine O&M Services, plus O&M for WQIC Research Efforts, | ||||
| plus YDP maintenance | |||||
| F.3.1 | Minimum Level of Effort | 6 | Months | $ - 0 | $ - 0 |
| F.3.2 | 33% operation capacity | 6 | Months | $ - 0 | $ - 0 |
| Level of Effort | |||||
| F.3.3 | 66% operation capacity | 6 | Months | $ - 0 | $ - 0 |
| Level of Effort | |||||
| F.3.4 | Full operation capacity | 6 | Months | $ - 0 | $ - 0 |
| Level of Effort | |||||
| F.4 | Routine O&M Services, plus O&M for WQIC Research Efforts, | ||||
| plus YDP maintenance plus Operations of the YDP | |||||
| F.4.1 | 33% operation capacity | 6 | Months | $ - 0 | $ - 0 |
| Level of Effort | |||||
| F.4.2 | 66% operation capacity | 6 | Months | $ - 0 | $ - 0 |
| Level of Effort | |||||
| F.4.3 | Full operation capacity | 6 | Months | $ - 0 | $ - 0 |
| Level of Effort | |||||
| F.5 | Routine O&M Services, plus Maintenance of the YDP, No O&M for WQIC | ||||
| Research Efforts | |||||
| F.5.1 | Minimum Level of Effort | 6 | Months | $ - 0 | $ - 0 |
| F.5.2 | 33% operation capacity | 6 | Months | $ - 0 | $ - 0 |
| Level of Effort | |||||
| F.5.3 | 66% operation capacity | 6 | Months | $ - 0 | $ - 0 |
| Level of Effort | |||||
| F.5.4 | Full operation capacity | 6 | Months | $ - 0 | $ - 0 |
| Level of Effort | |||||
| F.6 | Routine O&M Services, plus Maintenance of the YDP, Plus Operations of the | ||||
| YDP, No O&M for WQIC Research Efforts | |||||
| F.6.1 | 33% operation capacity | 6 | Months | $ - 0 | $ - 0 |
| Level of Effort | |||||
| F.6.2 | 66% operation capacity | 6 | Months | $ - 0 | $ - 0 |
| Level of Effort | |||||
| F.6.3 | Full operation capacity | 6 | Months | $ - 0 | $ - 0 |
| Level of Effort | |||||
| F.7 | Variable IDIQ Level of Effort required for O&M services (as issued and funded | ||||
| on individual task orders, as per Schedule of Fully Burdened Negotiated | |||||
| Fixed Unit Labor Rates | |||||
| F.8 | Materials & Small Chemical Purchases | ||||
| F.8.1 | Necessary for Routine O&M Services | Not to Exceed | $132,000 | ||
| F.8.2 | Necessary for O&M for WQIC Research Efforts | Not to Exceed | $144,000 | ||
| F.8.3 | Necessary for Maintenance of YDP | Not to Exceed | $420,000 | ||
| F.8.4 | Necessary for Operations of YDP | Not to Exceed | $360,000 | ||
| F.9 | Travel and Travel Related Costs | Not to Exceed | $6,000 | ||
| F.10 | Optional CLIN: Armed Guard Services 6 p.m. to 6 a.m., Monday through Friday and from 6 p.m. Friday through 6 a.m. Monday. | ||||
| 12 | Months | $ - 0 | $ - 0 | ||
| F.11 | Phase Out Transition (only to be used if | LS | $0 | ||
| Optional 2nd Performance Period is not | |||||
| exercised) | |||||
| Total for the Ordering Period 6 Performance Period | $ 420,000.00 | ||||
| As it is unknown at what Level of Effort(s) award will be determined, this field will be completed | |||||
| upon award or exercise of option. | |||||
| Running Total through Ordering Period 6 Performance Period | $ 2,520,000.00 |