Atch 11- SOMs.xlsx
XLSX spreadsheet 29 KB Posted
- Attached to
- B9992-Doc Stewart Playgrounds [AMENDED INVITATION FOR BID] Federal contract opportunity
- Solicitation number
- FA485522B0005
About this file
This document contains a schedule of materials submittals (SOMS) for a federal contract to repair a playground at Cannon Air Force Base in New Mexico. The contract requires the submission of various plans and documentation to the Air Force at different stages of the project, including an accident prevention plan, quality control plan, environmental and waste management plans, safety data sheets for hazardous materials, as-built drawings, and operation and maintenance manuals. Key due dates include submitting the work clearance request and preliminary construction schedule with the proposal, as well as the project schedule, health and safety plan, and environmental protection plan no later than 14 days prior to starting work. The contractor must also submit hazardous materials worksheets before bringing any such materials on base and monthly during the contract period. All test reports and sealed plans require hard copy submission.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AF FORM 66
| AF FORM 66 SCHEDULE OF MATERIALS SUBMITTALS | PROJECT # | PROJECT TITLE | SOLICITATION/CONTRACT NO. | |
| CZQZ22-0024 | Repair Playground, B9992 | |||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR |
| LINE NUMBER | REFERENCE, ITEM | NUMBER OF COPIES REQUIRED | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | FOLLOW-UP | CONTRACTOR NOTIFIED: Approval Date | CONTRACTOR NOTIFIED: DisApproval Date | CONTRACTOR RE-SUBMITTAL | FINAL APPROVAL | REMARKS |
| 1 | 01 01 00 AF Form 103 - Work Clearance Request | 1 | NLT 14 days prior to work start | |||||||||
| 2 | 01 33 00 Surety Bonds | 1 | 5 days after NTP | |||||||||
| 3 | 01 33 00 Certificates of Insurance | 1 | 5 days after NTP | |||||||||
| 4 | 01 33 00 Project Schedule | 1 | NLT 14 days prior to work start | |||||||||
| 5 | 01 33 00 Health and Safety Plan | 1 | NLT 14 days prior to work start | |||||||||
| 6 | 01 35 26 Accident Prevention Plan | 1 | NLT 14 days prior to work start | |||||||||
| 7 | 01 35 26 Accident Notification | 1 | As incident occurs | |||||||||
| 8 | 01 35 26 Accident Report | 1 | As incident occurs | |||||||||
| 9 | 01 45 00 Quality Control Plan | 1 | NLT 14 days prior to work start | |||||||||
| 10 | 01 57 19 Environmental Protection Plan | 1 | NLT 14 days prior to work start | |||||||||
| 11 | 01 74 19 Waste Management Plan | 1 | NLT 14 days prior to work start | |||||||||
| 12 | 01 74 19 CAFB/MAFR Contractor HAZMAT Worksheet | * | NLT 14 days prior to bringing HAZMAT on base | |||||||||
| 13 | 01 74 19 CAFB/MAFR Contractor Usage HAZMAT Worksheet | ** | NLT the 5th day of each month and at the completion of work | |||||||||
| 14 | 01 74 19 Safety Data Sheet (SDS) | * | NLT 14 days prior to bringing HAZMAT on base | |||||||||
| 15 | As-BuiltPackage (with AutoCAD drawings) | 1 | NLT 7 days after completion of work | |||||||||
| 16 | Base Access Request Form | 1 | NLT 7 days prior to base access | |||||||||
| 17 | Construction Schedule (preliminary - AF3064) | 1 | With proposal | |||||||||
| 18 | O&M Manuals | 1 | NLT 7 days after completion of work | |||||||||
| 19 | Warranty Certification | 1 | NLT 7 days after completion of work |
* Quantity to submit depends on number of HAZMAT items used. Each HAZMAT item requires a separate [CAFB/MAFR Contractor HAZMAT Worksheet] and [Safety Data Sheet].
** Quantity of [CAFB/MAFR Contractor Usage HAZMAT Worksheet] to submit is dependent on the length of the contract.
Note: The contractor is still responsbile for providing the Construction SOMS; this list is for reference only.
Note: All test reports and sealed plans need to be submitted as hard copies.
File details come from the government source that posted it. Updated .