WORK SUMMARY SHEET TOTAL SHEETS
ROAD 2114400R ROAD 2114500R Seg 1
MP WORK ITEMS MP
0.00 Jct 2114000 0.00 Jct 2114000
Begin establishing clearing limits Begin establishing clearing limits Begin clearing and grubbing Begin clearing and grubbing Begin constructing 12' roadbed Begin constructing 12' roadbed Construct T-intersection 0.13 Begin 2' CWL Haul and place 16CY of unclassified borrow for T-intersection Construct OSD with 8' LOD Haul excess material from berm removal on the 2114000R segment 2 0.16 End 2' CWL Haul remainder of material from designated borrow source 0.20 Construct DD
0.04 Begin 4' CWL 0.50 Construct DD
0.07 End 4' CWL 0.57 Begin 2' CWR
0.13 Construct DD 0.60 End 2' CWR
0.47 Begin 2' CWR 0.69 Construct DD
0.50 End 2' CWR 0.78 Construct DD
0.54 Construct DD 0.81 Jct 2114510R Left
0.61 Construct OSD 1.01 Construct OSD with 15' LOD
0.72 Construct DD 1.11 Construct DD
0.82 Construct OSD 1.41 Construct DD
0.91 Construct TOL and TAR 1.47 Construct DD
0.92 End establishing clearing limits 1.50 Begin placing 6" of aggregate
End clearing and grubbing 1.52 Construct OSD End constructing 12' roadbed 1.54 End placing 6" of aggregate EOP 1.72 Construct DD
1.95 Construct OSD
2.09 Construct OSD
2.18 End establishing clearing limits
End clearing and grubbing End constructing 12' roadbed EOP Segment 1
15 16