Project C - Spec C 833 Drainage Structure

View the file

Other files

File Type Posted
Amend 8 Roads. SF 30.pdf PDF
Amend 8 Evaluation Factors.pdf PDF
Amend 7 Roads. SF 30.pdf PDF
map vulcan water source.pdf PDF
Amend 6 Roads. SF 30.pdf PDF
Amend 6 Project B Schedule.pdf PDF
Picture 2113250.pdf PDF
Past Performance Survey.pdf PDF
Picture 2113200 A.pdf PDF
Project C Section 881.pdf PDF
Pictures 2113250 2113200.pdf PDF
Picture 2113400.pdf PDF
Picture 2113015a..pdf PDF
Project C 813_pbsc.pdf PDF
Project C 836.pdf PDF
Earth Mound Typical Drawing.pdf PDF
Pictures 2113200.pdf PDF
WA1 03202009.pdf PDF
Amend 5 Roads.pdf PDF
PreBid Conference Amend 5.pdf PDF
Amend 4 Attachment.pdf PDF
EXAMPLE C.pdf PDF
Wage_ Deter_ 1977_0209_37 05292008.pdf PDF
Amend 4 Roads.pdf PDF
Amend 3 Roads.pdf PDF
Est Quantity 3.pdf PDF
typrd Model 6.pdf PDF
vulcan worklist 12.pdf PDF
Project B Vulcan.pdf PDF
Title Model 1.pdf PDF
Est Qty 5.pdf PDF
Vicinity Map Model 2.pdf PDF
EstQty 4.pdf PDF
vulcan_worklist 16.pdf PDF
Type II gate detail model 10.pdf PDF
culvert details model 7 pdf.pdf PDF
vulcan_worklist 13.pdf PDF
vulcan_worklist 11.pdf PDF
!Vulcan Specs Project B.pdf PDF
Drainage Details Model 8.pdf PDF
AT7&8.pdf PDF
cmplist Model 9.pdf PDF
vulcan_worklist 14.pdf PDF
vulcan_worklist 15.pdf PDF
Amend 2 Roads.pdf PDF
Project A Growden Energy Dissipater.pdf PDF
growden_energy_dis_plans.pdf PDF
Vicnity Map.pdf PDF
sf24_f.pdf PDF
Amend 1 Roads.pdf PDF
Show 40 more

Latest 50 of 60 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project C Spec 833 RFP AG-05G1-S-09-0010

IDIQ Road Work for the Colville National Forest Page 1 of 4

833 - DRAINAGE STRUCTURE INSTALLATION OR REMOVAL (08/21/07) 1

833 DRAINAGE STRUCTURE INSTALLATION OR REMOVAL (8/07)

833.01 Service Required

Install or remove drainage structures including culverts, water-bars, drivable drain dips (they need to be armored), and cross ditches.

833.02 Performance Standard

Drainage structure installation is complete when culverts, water-bars, drivable drain dips (with armoring) and cross ditches have been installed to the lines and grades specified, and drainage structure removal is complete when designated culverts, water-bars and cross ditches have been removed and culverts have been properly disposed of.

833.03 Location of Work

As specified on roads listed on the ROAD LISTING, SHOWN ON THE PLANS, or as ordered by the Contracting Officer.

833.04 Measurement

Measurement under this Section will be made by the total number of units for each item listed in the SCHEDULE OF ITEMS completed and accepted.

A. Mile: Work activity will be measured along the centerline of the road regardless of the number of lanes.

B. Linear Foot: Work activities by the linear foot will be measured using standard survey methods rounded to the nearest one (1) foot. Culvert bands are incidental to the installation.

833 - DRAINAGE STRUCTURE INSTALLATION OR REMOVAL (08/21/07) 2

833.05 Payment

A. The accepted quantities will be paid at the contract price per unit of measurement for the Section 833 pay items listed in the schedule of items. Payment will be full compensation for the work prescribed in this Section.

Pay Item Description Pay Unit

833(1) ______ Inch corrugated metal pipe, ______ Inch thickness for steel, ______ Inch thickness for aluminum or ______ Inch thickness for Plastic Linear Foot

833(2) Culvert Removal Each 833(3) Water-bar Installation Each 833(4) Water-bar Installation Mile 833(5) Water-bar Removal Each 833(6) Water-bar Removal Mile 833(7) Cross Ditch Installation Each 833(8) Cross Ditch Installation Mile 833(9) Cross Ditch Removal Each 833(10) Cross Ditch Removal Mile 833(11) Drivable Drain Dip Installation Each 833(12) Drivable Drain Dip Installation Mile

833 - DRAINAGE STRUCTURE INSTALLATION OR REMOVAL (08/21/07) 3

833.06 Acceptable Quality Levels

Major Minor Allowable Defects Required Action Description

Defect Defect Major Minor Major Minor

Culvert is smaller than the designated diameter shown on the drawings.

Culvert is larger than the designated diameter shown on the drawings. 0 N/A

Remove culvert and replace with designated size

Accept if culvert fits the geometry of the road but pay at designated size otherwise replace

Culvert size Culvert is shorter than the designated length shown on the drawings.

Culvert is longer than the designated length shown on the drawings.

0 0

Replace or add section to fit geometry of road.

Remove excess culvert and treat cut end, or harden fill slope to prevent erosion and pay for ordered length

Grade and alignment of culvert

More than 10% deviation from original lines and grades.

10% or less deviation from original lines and grades.

0 X per unit

Remove and replace culvert

Repair if greater than X minor defects *

Sag or depression in road after placement of culvert and backfill material

Greater than 2 inch depression in traveled way

2 inch or less depression in traveled way 0 X per unit

Furnish, place and compact designated material to repair depression.

Repair if greater than X minor defects *

Removed culvert or pieces left on National

Forest System Lands

Culverts or pieces of culvert left on National

Forest System Lands N/A 0 N/A

Remove from National Forest System Lands

N/A

Water-bars and cross ditches

More than 10% deviation from original lines and grades.

10% or less deviation from original lines and grades.

0 X per unit

Rework Rework if greater than X minor defects *

Drivable drain dip

More than 10% deviation from specified lines and grades

10% or less deviation from specified lines and grades 0 1 per unit

Rework

Rework if minor defects interfere with proper drainage

Sedimentation

Operations cause or allow sediment to leave site.

N/A 0 N/A

Cease operations until sediment is controlled

N/A

833 - DRAINAGE STRUCTURE INSTALLATION OR REMOVAL (08/21/07) 4

Work Area Management

Not following approved safety plan which may include signs, flaggers, and other temporary traffic control measures

Not following approved safety plan which may include signs, flaggers, and other temporary traffic control measures

0 0

Suspend work until in compliance

Suspend work until in compliance

* Forests have the option to choose a pay reduction in lieu of rework. However, each Forest must establish a threshold where rework is required and define pay reductions for each defect.

Intent and use: User to establish threshold for the acceptable level of quality.