ADDENDUM 5 Attachment C - Revised Drawings Package 1 Day Use Parking Lot Improvements.pdf
PDF 6 MB Posted
- Solicitation number
- S-63400-00016792
- Issued by
- Tillamook County, Oregon
About this file
This document is Addendum 5 to the permit set drawings package for Package 1 (Day Use Parking Lot Improvements) of the Cape Lookout State Park Parkwide Improvements Project, prepared by KPFF Consulting Engineers for the Oregon Parks and Recreation Department. The addendum provides detailed construction notes, specifications, and demolition plans for the day use parking area renovation, including requirements for demolition and disposal of existing asphalt concrete, curbs, sidewalks, and site elements; earthwork and sediment control measures; utility coordination and adjustments for water, storm drain, sanitary sewer, electrical, and telecommunications infrastructure; and materials specifications requiring new materials with minimum compressive strength of 3,300 PSI for concrete and compliance with PVC, ductile iron, reinforced concrete, or high-density polyethylene piping standards. The document specifies critical construction sequencing for the vegetated stormwater facility with required pre-construction meetings and growing medium sample submittal for infiltration testing, mandates that all construction layout be performed by a licensed Oregon surveyor based on provided coordinates and elevations using NAVD 88 vertical datum, and requires strict adherence to 2021 Oregon Standard Specifications for Construction, Oregon Plumbing Specialty Code, and Tillamook County requirements including Oregon Utility Notification Center protocols with minimum 48-business-day advance notice for excavation work.
The demolition and construction plans identify specific removal and salvage operations including storm catch basin removal, pipe capping, curb removal, vegetation clearing, tree removal, and asphalt pile removal, with designated areas for protection of existing trees, electrical vaults, and underground utilities. Key salvage items requiring storage at the project site as directed by the owner include the pay station, EV charging station and signage, park information sign, and picnic table with concrete slab relocation. The contractor is responsible for all permit acquisition through the jurisdiction, traffic control plan development and approval, dust and mud control during demolition, erosion control setup and certification by a registered erosion control inspector prior to work commencement, and maintaining all utilities to structures throughout construction. Separate detailed specifications are provided for crosswalk striping, parallel parking markings, curb cut inlets, utility crossings, yard hydrant installation with backflow prevention and ADA-compliant lockable handles, and water junction valve boxes, with all work requiring coordination with the owner and civil engineer throughout the project duration.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
111 SW Fifth Ave., Suite 2400 Portland, OR 97204 O: 503.227.3251 F: 503.274.4681 www.kpff.com
PERMIT SET
DEMOLITION
1. THE CONTRACTOR SHALL BE RESPONSIBLE FOR DEMOLITION AND DISPOSAL OF EXISTING AC, CURBS, SIDEWALKS AND OTHER SITE ELEMENTS WITHIN THE SITE AREA IDENTIFIED IN THE PLANS.
2. EXCEPT FOR MATERIALS INDICATED TO BE STOCKPILED OR TO REMAIN ON OWNER'S PROPERTY, CLEARED MATERIALS SHALL BECOME CONTRACTOR'S PROPERTY, REMOVED FROM THE SITE, AND DISPOSED OF
PROPERLY.
3. ITEMS INDICATED TO BE SALVAGED SHALL BE CAREFULLY REMOVED AND DELIVERED STORED AT THE
PROJECT SITE AS DIRECTED BY THE OWNER.
4. ALL LANDSCAPING, PAVEMENT, CURBS AND SIDEWALKS, BEYOND THE IDENTIFIED SITE AREA, DAMAGED
DURING THE CONSTRUCTION SHALL BE REPLACED TO THEIR ORIGINAL CONDITION OR BETTER.
5. CONCRETE SIDEWALKS SHOWN FOR DEMOLITION SHALL BE REMOVED TO THE NEAREST EXISTING
CONSTRUCTION JOINT.
6. SAWCUT STRAIGHT MATCHLINES TO CREATE A BUTT JOINT BETWEEN THE EXISTING AND NEW PAVEMENT.
EARTHWORKS
1. CONTRACTOR SHALL PREVENT SEDIMENTS AND SEDIMENT LADEN WATER FROM ENTERING THE STORM
DRAINAGE SYSTEM.
2. TRENCH BEDDING AND BACKFILL SHALL BE AS SHOWN ON THE PIPE BEDDING AND BACKFILL DETAIL, THE
PROJECT SPECIFICATIONS AND AS REQUIRED IN THE SOILS REPORT.
UTILITIES
1. ADJUST ALL INCIDENTAL STRUCTURES, MANHOLES, VALVE BOXES, CATCH BASINS, FRAMES AND COVERS, ETC.
TO FINISHED GRADE.
2. CONTRACTOR SHALL ADJUST ALL EXISTING AND/OR NEW FLEXIBLE UTILITIES (WATER, TV, TELEPHONE, ELEC., ETC.) TO CLEAR ANY EXISTING OR NEW GRAVITY DRAIN UTILITIES (STORM DRAIN, SANITARY SEWER, ETC.) IF
CONFLICT OCCURS.
3. CONTRACTOR SHALL COORDINATE WITH PRIVATE UTILITY COMPANIES FOR THE INSTALLATION OF OR
ADJUSTMENT TO GAS, ELECTRICAL, POWER AND TELEPHONE SERVICE.
4. BEFORE BACKFILLING ANY SUBGRADE UTILITY IMPROVEMENTS CONTRACTOR SHALL SURVEY AND RECORD
MEASUREMENTS OF EXACT LOCATION AND DEPTH AND SUBMIT TO ENGINEER AND OWNER.
5. ALL WORK TO CONFORM TO THE 2021 OREGON PLUMBING SPECIALTY CODE.
STORM AND SANITARY
1. BEGIN LAYING STORM DRAIN AND SANITARY SEWER PIPE AT THE LOW POINT OF THE SYSTEM, TRUE TO GRADE AND ALIGNMENT INDICATED WITH UNBROKEN CONTINUITY OF INVERT. THE CONTRACTOR SHALL ESTABLISH
LINE AND GRADE FOR THE STORM AND SANITARY SEWER PIPE USING A LASER.
2. ALL ROOF DRAIN AND CATCH BASIN LEADERS SHALL HAVE A MINIMUM SLOPE OF 2 PERCENT UNLESS NOTED
OTHERWISE IN THE PLANS.
WATER
1. ALL WATER AND FIRE PROTECTION PIPE SHALL HAVE A MINIMUM 36-INCH COVER TO THE FINISH GRADE.
2. ALL WATER AND FIRE PRESSURE FITTINGS SHALL BE PROPERLY RESTRAINED WITH THRUST BLOCKS PER
DETAIL.
3. ALL WATER MAIN / SANITARY SEWER CROSSINGS SHALL CONFORM TO THE OREGON STATE HEALTH
DEPARTMENT REGULATIONS, CHAPTER 333.
PAVING
1. SEE LANDSCAPE PLANS FOR SIDEWALK FINISHING AND SCORING PATTERNS.
GENERAL
1. SUBGRADE AND TRENCH BACKFILL SHALL BE COMPACTED TO AT LEAST 95% OF THE MAXIMUM DRY DENSITY AS DETERMINED BY ASTM D-698. FLOODING OR JETTING THE BACKFILLED TRENCHES WITH WATER IS NOT
PERMITTED.
2. SPECIAL INSPECTION REQUIRED FOR ALL COMPACTION TESTING.
3. ADDITIONAL EXCAVATION IS REQUIRED FOR SOFT SOIL AS DIRECTED BY THE STANDARD SPECIFICATIONS AND
THE GEOTECHNICAL REPORT.
1. GENERAL: MATERIALS SHALL BE NEW. THE USE OF MANUFACTURER'S NAMES, MODELS, AND NUMBERS IS INTENDED TO ESTABLISH STYLE, QUALITY, APPEARANCE, AND USEFULNESS. PROPOSED SUBSTITUTIONS WILL
REQUIRE WRITTEN APPROVAL FROM ENGINEER PRIOR TO INSTALLATION.
2. STORM AND SANITARY SEWER PIPING SHALL BE PVC PIPE, DUCTILE IRON PIPE, REINFORCED CONCRETE PIPE (RCP), NON-REINFORCED CONCRETE PIPE (NRCP) OR HIGH DENSITY POLYETHYLENE (HDPE) PIPE CONFORMING TO THE PROJECT SPECIFICATIONS; AS INDICATED IN THE PLANS. PIPES WITH LESS THAN 2' OF
COVER SHALL BE C900/C905 PVC, HDPE OR DUCTILE IRON PIPE.
3. PRIVATE WATER MAINS 3-INCH DIAMETER AND LARGER SHALL CONFORM TO THE PROJECT SPECIFICATIONS.
4. PRIVATE WATER LINES 2-INCH DIAMETER AND SMALLER SHALL CONFORM TO THE PROJECT SPECIFICATIONS.
5. CONCRETE FOR CURBS, SIDEWALK AND DRIVEWAYS SHALL HAVE A MINIMUM COMPRESSIVE STRENGTH OF
3,300 PSI AT 28 DAYS.
ALL WATER MAIN CROSSINGS SHALL CONFORM TO THE OREGON STATE HEALTH DEPARTMENT, CHAPTER 333.
WATER MAINS SHALL CROSS OVER SANITARY SEWERS WITH A 18" MINIMUM CLEARANCE BETWEEN OUTSIDE DIAMETERS OF PIPE WITH ALL PIPE JOINTS EQUIDISTANT FROM CROSSING. HORIZONTAL SEPARATION BETWEEN WATER MAINS AND SANITARY SEWERS IN PARALLEL INSTALLATIONS SHALL BE 10'. MAINTAIN 12" MINIMUM VERTICAL DISTANCE FOR ALL OTHER UTILITY CROSSINGS AND 12" HORIZONTAL PARALLEL DISTANCE. IN CASES WHERE IT IS NOT POSSIBLE TO MAINTAIN THE MINIMUM 10' HORIZONTAL SEPARATION, THE WATER MAIN SHALL BE LAID ON A
SEPARATE SHELF IN THE TRENCH 18" INCHES ABOVE THE SEWER.
1. SUCCESSFUL CONSTRUCTION OF THE VEGETATED STORMWATER FACILITY DEPEND ON PROPER
CONSTRUCTION SEQUENCING, MATERIALS, INSTALLATION, PROTECTION OF SUBGRADE AND EROSION
CONTROL.
2. CONTRACTOR SHALL SETUP A PRE-CONSTRUCTION MEETING WITH CIVIL ENGINEER TO SPECIFICALLY DISCUSS
THESE ITEMS. CONTACT PAUL SCHMIDTKE WITH KPFF CONSULTING ENGINEERS 503-542-3829.
3. SUBMITTAL REQUIREMENT: SUBMIT (1) 2 GALLON SAMPLE OF GROWING MEDIUM THAT MEETS THE SOIL
SPECIFICATION FOR INFILTRATION TESTING BY KPFF FOR APPROVAL.
1. SURVEY PROVIDED BY KPFF, DATED 9/12/2024. ELEVATIONS ARE BASED ON NAVD 88 VERTICAL DATUM ESTABLISHED PER CONTROL POINT NO. 1 WITH AN ELEVATION OF 31.76' USING THE OREGON REAL-TIME GPS
NETWORK (ORGN)
2. CONSTRUCTION LAYOUT (ALL ACTUAL LINES AND GRADES) SHALL BE STAKED BY A PROFESSIONAL SURVEYOR, REGISTERED IN THE STATE OF OREGON, BASED ON COORDINATES, DIMENSIONS, BEARINGS, AND
ELEVATIONS, AS SHOWN, ON THE PLANS.
3. PROJECT CONTROL SHALL BE FIELD VERIFIED AND CHECKED FOR RELATIVE HORIZONTAL POSITION PRIOR TO
BEGINNING CONSTRUCTION LAYOUT. SEE SHEET C1.2 FOR PROJECT CONTROL INFORMATION.
4. PROJECT CONTROL SHALL BE FIELD VERIFIED AND CHECKED FOR RELATIVE VERTICAL POSITION BASED ON
THE BENCHMARK STATED HEREON, PRIOR TO BEGINNING CONSTRUCTION LAYOUT.
5. WHEN DIMENSIONS AND COORDINATE LOCATIONS ARE REPRESENTED - DIMENSIONS SHALL HOLD OVER COORDINATE LOCATION. NOTIFY THE CIVIL ENGINEER OF RECORD IMMEDIATELY UPON DISCOVERY.
6. CONTRACTOR SHALL PRESERVE AND PROTECT FROM DAMAGE ALL EXISTING MONUMENTATION DURING
CONSTRUCTION. THE CONTRACTOR IS RESPONSIBLE FOR COORDINATING AND PAYING FOR THE
REPLACEMENT OF ANY MONUMENTS DAMAGED OR REMOVED DURING CONSTRUCTION. NEW MONUMENTS
SHALL BE REESTABLISHED BY A LICENSED SURVEYOR.
7. SURVEY MAY NOT BE COMPLETE OR ACCURATE. CONTRACTOR TO VERIFY EXISTING SITE CONDITIONS PRIOR TO CONSTRUCTION. CONTRACTOR SHALL BRING ANY DISCREPANCIES TO THE ATTENTION OF THE ENGINEER
PRIOR TO BEGINNING CONSTRUCTION.
8. CONTRACTOR TO REFERENCE SOILS REPORT BY GRI DATED 5/12/2025 FOR THE SITE SOILS CONDITIONS.
9. ALL CONSTRUCTION AND MATERIALS SHALL CONFORM TO THESE PLANS, THE PROJECT SPECIFICATIONS AND THE APPLICABLE REQUIREMENTS OF THE 2021 OREGON STANDARD SPECIFICATIONS FOR CONSTRUCTION, THE 2021 OREGON PLUMBING SPECIALTY CODE AND REQUIREMENTS OF TILLAMOOK COUNTY.
10. THE COMPLETED INSTALLATION SHALL CONFORM TO ALL APPLICABLE FEDERAL, STATE, AND LOCAL CODES, ORDINANCES AND REGULATIONS. ALL PERMITS, LICENSES AND INSPECTIONS REQUIRED BY THE GOVERNING AUTHORITIES FOR THE EXECUTION AND COMPLETION OF WORK SHALL BE SECURED BY THE CONTRACTOR
PRIOR TO COMMENCING CONSTRUCTION.
11. ATTENTION: OREGON LAW REQUIRES YOU TO FOLLOW RULES ADOPTED BY THE OREGON UTILITY NOTIFICATION CENTER. THOSE RULES ARE SET FORTH IN OAR 952-001-0010 THROUGH OAR 952-001-0090. YOU MAY OBTAIN COPIES OF THE RULES BY CALLING THE CENTER. (NOTE: THE TELEPHONE NUMBER FOR THE OREGON UTILITY NOTIFICATION CENTER IS (503) 232-1987). EXCAVATORS MUST NOTIFY ALL PERTINENT COMPANIES OR AGENCIES WITH UNDERGROUND UTILITIES IN THE PROJECT AREA AT LEAST 48 BUSINESS-DAY HOURS, BUT NOT MORE THAN 10 BUSINESS DAYS PRIOR TO COMMENCING AN EXCAVATION, SO UTILITIES MAY
BE ACCURATELY LOCATED.
12. THE LOCATION OF EXISTING UNDERGROUND UTILITIES SHOWN ON THE PLANS ARE FOR INFORMATION ONLY AND ARE NOT GUARANTEED TO BE COMPLETE OR ACCURATE. CONTRACTOR SHALL VERIFY ELEVATIONS, PIPE SIZE, AND MATERIAL TYPES OF ALL UNDERGROUND UTILITIES PRIOR TO COMMENCING WITH CONSTRUCTION AND SHALL BRING ANY DISCREPANCIES TO THE ATTENTION OF KPFF CONSULTING ENGINEERS, 72 HOURS
PRIOR TO START OF CONSTRUCTION TO PREVENT GRADE AND ALIGNMENT CONFLICTS.
13. THE ENGINEER OR OWNER IS NOT RESPONSIBLE FOR THE SAFETY OF THE CONTRACTOR OR THEIR CREW. ALL O.S.H.A. REGULATIONS SHALL BE STRICTLY ADHERED TO IN THE PERFORMANCE OF THE WORK.
14. TEMPORARY AND PERMANENT EROSION CONTROL MEASURES SHALL BE IMPLEMENTED. THE CONTRACTOR SHALL ADHERE TO TILLAMOOK COUNTY REQUIREMENTS FOR MINIMUM EROSION CONTROL MEASURES. THE ESC FACILITIES SHOWN IN THESE PLANS ARE THE MINIMUM REQUIREMENTS FOR ANTICIPATED SITE CONDITIONS. DURING THE CONSTRUCTION PERIOD, ESC FACILITIES SHALL BE UPGRADED AS NEEDED FOR UNEXPECTED STORM EVENTS AND TO ENSURE THAT SEDIMENT AND SEDIMENT LADEN WATER DO NOT LEAVE
THE SITE.
15. THE CONTRACTOR IS RESPONSIBLE FOR MAINTAINING ALL ROADWAYS, KEEPING THEM CLEAN AND FREE OF
CONSTRUCTION MATERIALS AND DEBRIS, AND PROVIDING DUST CONTROL AS REQUIRED.
16. TRAFFIC CONTROL SHALL BE PROVIDED BY THE CONTRACTOR THROUGHOUT CONSTRUCTION. CONTRACTOR SHALL PROVIDE A TRAFFIC CONTROL PLAN TO OPRD FOR REVIEW AND APPROVAL PRIOR TO COMMENCING
CONSTRUCTION.
17. CONTRACTOR SHALL MAINTAIN ALL UTILITIES TO BUILDING AT ALL TIMES DURING CONSTRUCTION. UNLESS
OTHERWISE COORDINATED WITH OWNER.
18. THE CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING AND SCHEDULING ALL WORK WITH THE
OWNER.
GENERAL NOTES CONSTRUCTION NOTES MATERIAL NOTES
SEPARATION STATEMENT
VEGETATED STORMWATER FACILITY NOTE
AC ASPHALT CONCRETE
AD AREA DRAIN
APPROX. APPROXIMATE
B BOLLARD
BLDG BUILDING
BOW BACK OF WALK
BS BOTTOM OF SWALE
BOTTOM OF STAIR
BW BOTTOM OF WALL
CB CATCH BASIN
CL CENTERLINE
CMP CORRUGATED METAL PIPE
CMU CONCRETE MASONRY UNIT
CO CLEANOUT
CONC. CONCRETE
COTG CLEANOUT TO GRADE
CP CONTROL POINT
Δ DELTA
D/W DRIVEWAY
DIA.,Ø DIAMETER
DIP DUCTILE IRON PIPE
E EASTING
EXIST./EX EXISTING
FDC FIRE DEPARTMENT CONNECTION
FF FINISH FLOOR ELEVATION
FG FINISH GRADE
FH FIRE HYDRANT
FL FLOWLINE
FND FOUNDATION
G GUTTER
GB GRADE BREAK
GL GAS LINE
GV GATE VALVE
H HEIGHT
HCP HANDICAP PARKING SPACE
HP HIGH POINT
ID INSIDE DIAMETER
IE INVERT ELEVATION
INV INVERT
IRR. IRRIGATION
LP LIGHT POLE
MH MANHOLE
MIN MINIMUM
N NORTHING
OD OUTSIDE DIAMETER
OF OUTFALL
OVH/OH OVERHEAD
P/L PROPERTY LINE
PC POINT OF CURVATURE
PCC POINT OF COMPOUND CURVATURE
PCR POINT OF CURB RETURN
PED PEDESTRIAN
PIV POST INDICATOR VALVE
PM PARKING METER
POC POINT ON CURVE
PP POWER POLE
PRC POINT OF REVERSE CURVATURE
PT POINT OF TANGENT
PUE PUBLIC UTILITY EASEMENT
PVC POLYVINYL CHLORIDE
PVMT PAVEMENT
PVT PRIVATE
R RIM
RD ROOF DRAIN
ROW RIGHT-OF-WAY
S SLOPE (FT/FT)
SD STORM DRAIN
SDMH STORM DRAIN MANHOLE
SHT SHEET
SS SANITARY SEWER
SSMH SANITARY SEWER MANHOLE
ST STREET
STA STATION
STD STANDARD
S/W SIDEWALK
TC TOP OF CURB
TD TRENCH DRAIN
TG TOP OF GROUND
TP TOP OF PAVEMENT
TRANS. TRANSFORMER
TS TOP OF STAIR
TW TOP OF WALL
TOP OF WALK
TYP TYPICAL
UG UNDERGROUND
UGE UNDERGROUND ELECTRIC
UNO UNLESS NOTED OTHERWISE
W WATER
W/ WITH
WCR WHEEL CHAIR RAMP
WM WATER METER
WV WATER VALVE
ABBREVIATIONS
EXPIRATION DATE:
OREGON
12/31/2027
79775
ADDENDUM 5
6/
/2
A D
D
P S
1. CONTRACTOR MAY STAGE WITHIN EXISTING GRAVEL PARKING AREA.
2. REMOVE ALL SITE COMPONENTS IDENTIFIED IN THE PLANS AND
RECYCLE COMPONENTS AS REQUIRED IN THE SPECIFICATIONS.
3. ALL PERMITS REQUIRED BY THE JHA SHALL BE SECURED BY THE
CONTRACTOR CONTRACTOR.
4. ALL TRADE LICENSES AND PERMITS NECESSARY FOR THE
PROCUREMENT AND COMPLETION OF THE WORK SHALL BE SECURED
BY THE CONTRACTOR PRIOR TO COMMENCING DEMOLITION.
5. PROTECT STRUCTURES, UTILITIES, SIDEWALKS, AND OTHER
FACILITIES IMMEDIATELY ADJACENT TO EXCAVATIONS FROM
DAMAGES CAUSED BY SETTLEMENT, LATERAL MOVEMENT,
UNDERMINING, WASHOUT AND OTHER HAZARDS.
6. SAWCUT STRAIGHT LINES IN SIDEWALK, AS NECESSARY AT THE
NEAREST JOINT.
7. CONTRACTOR IS RESPONSIBLE TO CONTROL DUST AND MUD DURING
THE DEMOLITION PERIOD, AND DURING TRANSPORTATION OF
DEMOLITION DEBRIS. ALL STREET SURFACES OUTSIDE THE
CONSTRUCTION ZONE MUST BE KEPT CLEAN.
8. ALL EXPOSED PORTIONS OF UNDERGROUND UTILITIES TO BE
ABANDONED SHALL BE PLUGGED PER DETAIL 4/C5.5.
9. EROSION CONTROL SHALL BE SET UP IN PLACE AND APPROVED BY A
REGISTERED CERTIFIED EROSION CONTROL INSPECTOR PRIOR TO
COMMENCEMENT OF WORK.
20 SAWCUT EXISTING ASPHALT OR CONCRETE PAVEMENT.
21 REMOVE STORM CATCH BASIN.
22 CUT AND CAP STORM LINE AT CATCH BASIN CONNECTION. ABANDON
LINE IN PLACE.
23 EXCAVATE ASPHALT PAVEMENT AND CRUSHED ROCK SUBGRADE.
24 REMOVE CURB
25 REMOVE GATE AND POSTS
26 REMOVE ALL CURB, ASPHALT AND CONCRETE PAVEMENT
27 CLEAR AND GRUBB VEGETATION
28 CUT AND CAP PIPE OUTSIDE OF WETLAND BOUNDARY. REMOVE
CHANNEL AND ABANDON SECTION OF PIPE IN THE WETLAND.
29 REMOVE TREE AND STUMP
30 CUT WOODEN SIGN POST AND ABANDON IN WETLAND.
31 REMOVE ASPHALT PILE
40 PROTECT TREE.
41 PROTECT ELECTRICAL VAULT.
42 PROTECT UNDERGROUND UTILITIES.
60 SALVAGE PAY STATION AND STORE IN LOCATION AS DIRECTED BY
OWNER.
61 SALVAGE EV CHARGING STATION AND SIGNAGE AND STORE IN
LOCATION AS DIRECTED BY OWNER.
62 SALVAGE SIGN AND STORE IN LOCATION AS DIRECTED BY OWNER.
63 SALVAGE PARK INFORMATION SIGN AND STORE IN LOCATION AS
DIRECTED BY OWNER.
64 REMOVE PICNIC TABLE AND CONCRETE SLAB. RELOCATE AS
DIRECTED BY OWNER.
SHEET NOTES
X DEMOLITION KEY NOTES
X PROTECTION KEY NOTES
X SALVAGE KEY NOTES
TRAN
E
HB
W
STOP
EV CH
AR
GI
NG
PAY
STATION
NO
PARKING
DO NOT
ENTER
PICNIC
SHELTER
OREGON
COAST TRAIL
HCP
TRAIL
MAP
HCP
HCP HCP
HCP HCP
HCP
CABIN
PARKING
ONLY
REGISTERED
GUESTS ONLY
CABIN
PARKING
ONLY
CABIN
PARKING
ONLY
CABIN
PARKING
ONLY
HCP
F
BB
BBQ
BBQ
BBQ
BBQ
''S
D
12''SD
PICNIC SHELTER
GATE
DU
M
PS
TE
R
DENSE
VEGETATION
C
12" CONC
IE = 24.71'
18" CONC
IE = 31.83'
E E
E
E
E E
E E
E
E
E
E E
E
E
E
EV
EC
JB
JB
JB
WETLAND
E1
WETLAND
E2
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD][SD]
[E]
62 62
40TYP
24 24
REMOVE OR ABANDON UTILITY LINE IN
PLACE
SAWCUT LINE
DEMOLITION/WORK LIMITS (SHOWN OFFSET
FOR CLARITY)
PROPERTY LINE
SHEET LEGEND
HARDSCAPE DEMOLITION LIMITS. SEE
KEYNOTE 26
SCALE
1 INCH = 20 FEET
20 400
111 SW Fifth Ave., Suite 2400 Portland, OR 97204 O: 503.227.3251 F: 503.274.4681 www.kpff.com
KEY MAP
PERMIT SET
MATCHLINE SEE SHEET C2.2
M
AT
CH
LI
N E
SE
E
SH
EE
T C2
.3
EXPIRATION DATE:
OREGON
12/31/2027
79775
6/
/2
A D
D
P
SADDENDUM 5
MULTICORELINK:2200270-15-DEMO-C2.2
MULTICORELINK:2200270-15-DEMO-C2.2
MULTICORELINK:2200270-15-DEMO-C2.2
DAY USE
AREA
BROKEN
ASPHALT
PILE
E
E
E
E
E
E
E
E
E
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[W
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[S M
[SM]
[SM]
[SM]
[SM]
[SM]
[SM]
[SM]
[SM]
[SM]
[SM]
[SM]
[SM]
[SM]
[E
[E
[E
REMOVE OR ABANDON UTILITY LINE IN
PLACE
SAWCUT LINE
DEMOLITION/WORK LIMITS (SHOWN OFFSET
FOR CLARITY)
PROPERTY LINE
SHEET LEGEND
HARDSCAPE DEMOLITION LIMITS. SEE
KEYNOTE 26
1. CONTRACTOR MAY STAGE WITHIN EXISTING GRAVEL PARKING AREA.
2. REMOVE ALL SITE COMPONENTS IDENTIFIED IN THE PLANS AND
RECYCLE COMPONENTS AS REQUIRED IN THE SPECIFICATIONS.
3. ALL PERMITS REQUIRED BY THE JHA SHALL BE SECURED BY THE
CONTRACTOR CONTRACTOR.
4. ALL TRADE LICENSES AND PERMITS NECESSARY FOR THE
PROCUREMENT AND COMPLETION OF THE WORK SHALL BE SECURED
BY THE CONTRACTOR PRIOR TO COMMENCING DEMOLITION.
5. PROTECT STRUCTURES, UTILITIES, SIDEWALKS, AND OTHER
FACILITIES IMMEDIATELY ADJACENT TO EXCAVATIONS FROM
DAMAGES CAUSED BY SETTLEMENT, LATERAL MOVEMENT,
UNDERMINING, WASHOUT AND OTHER HAZARDS.
6. SAWCUT STRAIGHT LINES IN SIDEWALK, AS NECESSARY AT THE
NEAREST JOINT.
7. CONTRACTOR IS RESPONSIBLE TO CONTROL DUST AND MUD DURING
THE DEMOLITION PERIOD, AND DURING TRANSPORTATION OF
DEMOLITION DEBRIS. ALL STREET SURFACES OUTSIDE THE
CONSTRUCTION ZONE MUST BE KEPT CLEAN.
8. ALL EXPOSED PORTIONS OF UNDERGROUND UTILITIES TO BE
ABANDONED SHALL BE PLUGGED PER DETAIL 4/C5.5.
9. EROSION CONTROL SHALL BE SET UP IN PLACE AND APPROVED BY A
REGISTERED CERTIFIED EROSION CONTROL INSPECTOR PRIOR TO
COMMENCEMENT OF WORK.
20 SAWCUT EXISTING ASPHALT OR CONCRETE PAVEMENT.
21 REMOVE STORM CATCH BASIN.
22 CUT AND CAP STORM LINE AT CATCH BASIN CONNECTION. ABANDON
LINE IN PLACE.
23 EXCAVATE ASPHALT PAVEMENT AND CRUSHED ROCK SUBGRADE.
24 REMOVE CURB
25 REMOVE GATE AND POSTS
26 REMOVE ALL CURB, ASPHALT AND CONCRETE PAVEMENT
27 CLEAR AND GRUBB VEGETATION
28 CUT AND CAP PIPE OUTSIDE OF WETLAND BOUNDARY. REMOVE
CHANNEL AND ABANDON SECTION OF PIPE IN THE WETLAND.
29 REMOVE TREE AND STUMP
30 CUT WOODEN SIGN POST AND ABANDON IN WETLAND.
31 REMOVE ASPHALT PILE
40 PROTECT TREE.
41 PROTECT ELECTRICAL VAULT.
42 PROTECT UNDERGROUND UTILITIES.
60 SALVAGE PAY STATION AND STORE IN LOCATION AS DIRECTED BY
OWNER.
61 SALVAGE EV CHARGING STATION AND SIGNAGE AND STORE IN
LOCATION AS DIRECTED BY OWNER.
62 SALVAGE SIGN AND STORE IN LOCATION AS DIRECTED BY OWNER.
63 SALVAGE PARK INFORMATION SIGN AND STORE IN LOCATION AS
DIRECTED BY OWNER.
64 REMOVE PICNIC TABLE AND CONCRETE SLAB. RELOCATE AS
DIRECTED BY OWNER.
SHEET NOTES
X DEMOLITION KEY NOTES
X PROTECTION KEY NOTES
X SALVAGE KEY NOTES
SCALE
1 INCH = 20 FEET
20 400
111 SW Fifth Ave., Suite 2400 Portland, OR 97204 O: 503.227.3251 F: 503.274.4681 www.kpff.com
KEY MAP
PERMIT SET
MATCHLINE SEE SHEET C2.1
EXPIRATION DATE:
OREGON
12/31/2027
79775
6/
/2
A D
D
P
SADDENDUM 5
MULTICORELINK:2200270-15-DEMO-C2.1
MULTICORELINK:2200270-15-DEMO-C2.1
MULTICORELINK:2200270-15-DEMO-C2.1
SCALE: NTS3 CROSSWALK STRIPING - THERMOPLASTIC
3' TYP.
8'
2' WIDE
WHITE BARS
2'
VARIES
2' MIN
6"
SECTION 'A'
12"
18"
12"
12" 6"
PLAN
6"
PLANTER WALL
PAVEMENT
CONCRETE CURB
R=6", TYP.
R=1"PAVEMENT
1"
18"
TP
'-0
8'-0"
1'-0"
2'- 4"
4" WIDE
WHITE STRIPE
SCALE: NTS1 PARALLEL PARKING STRIPING - PAINTED
1'-0"
2'- 4"
CURBLINE
SCALE: NTS2 CURB CUT INLET TO PLANTER
SCALE: NTS4 CONCRETE CRADLE
D+1'-0"
0'-6"0'-6"
>1 '-0
4000 PSI CONCRETE
Ø 16 REINFORCING BARS @ 8" O.C.
PIPE
PIPE
D/
D
1"
PLANTER WALL
RIP-RAP SHALL BE
4"-2" BALLAST AGGREGATE
1'
DE
EP
2'
W
ID
E
24"
EXTEND RIPRAP TO
TOE OF SLOPE
12"
5 L.F.-
*"DIP
*3"
MIN.
IE=*
NOTE 2
PROPOSED *
SD45° MJ BEND
TYP.
45° MJ BEND
TYP.
2 L.F.-*" DIP
58" TIE ROD
NOTE 1
SCALE: NTS5 TYPICAL UTILITY CROSSING
NOTES:
1. DIP MJ SPOOL. * L.F.-* DIP CONTRACTOR TO VERIFY LENGTH OF * DIP NECESSARY TO MEET
WATERLINE CLEARANCE TYP.
2. CONC. ANCHOR BLOCK W/ TIE BOLTS, DUCT LUGS OR STEEL PLATE AS APPROVED
NOTE 2SCALE: NTS6 YARD HYDRANT
36"
3/4" SHARKBITE BRASS PUSH MALE
ADAPTER ELBOW (SHARKBITE X MALE MIP)
3/4" MALE THREADED BRASS BALL VALVE (LOW LEAD)
WITH FEMALE UNIONS (LOW LEAD) ON EACH SIDE,
WITH STAINLESS STEEL T-HANDLE.
3/4" QUARTER BEND BRASS
FITTING (COMPRESSION
CTS X MIP) MULLER
H15531N OR EQUAL.
NEW 3/4" WATER
SUPPLY LINE.
FURNISH & INSTALL
(2) 3/8" INSERT ON
COMPRESSION
FITTINGS (MCDONALD
6133T) OR EQUAL.
VALVE BOX AND COVER
SEE DETAIL 7
SIDEWALK
BOX CENTERED
ON VALVE
FINISH GRADE
SECTION
4"
MIN.
12" MIN.
DRAIN
ROCK
30"
MIN.
NOTES:
1. TYPICAL PIPE CONFIGURATION SHOWN, SEE PLAN FOR ACTUAL CONFIGURATION. CONFIRM VAULT LOCATION WITH OWNER.
2. VAULT SHALL BE HDPE WITH POLYMER CONCRETE (H-20 LOADING MIN) COVER BY OLDCASTLE. CARSON OLDCASTLE MODEL MSBCF-1118-18XL OR APPROVED EQUAL.
3. INSTALL VALVES 3" MIN. CLR FROM VAULT WALL AND TEES.
NOTE 2
PLAN (INSIDE VAULT)
VALVE, TYP.
(BALL OR GATE VALVE
DEPENDING ON SIZE)
FLOW
SCALE: NTS7 WATER JUNCTION VALVE BOX
CXT RESTROOM
NOTES:
1. SANITARY TYPE YARD HYDRANT SHALL BE APPROVED BY OPRD PRIOR TO ORDERING.
2. YARD HYDRANTS SHALL BE CERTIFIED TO ASSE 1057 SANITARY YARD HYDRANT STANDARD.
3. YARD HYDRANTS SHALL BE SUPPLIED WITH A BACKFLOW PREVENTER AND ADA TURN HANDLE HOSE BIB. THE
INLET OF THE HYDRANT SHALL BE 3/4 FIP AND THE OUTLET SHALL BE 3/4 HOSE THREAD.
4. ALL MOVING PARTS ARE TO BE REPLACEABLE FROM THE SURFACE WITHOUT THE NEED TO EXCAVATE HYDRANT.
5. YARD HYDRANT SHALL OPERATE AT A MINIMUM OPERATING PRESSURE OF 20 PSI AND A MAX. OF 100 PSI.
6. YARD HYDRANT SHALL HAVE LOCKABLE HANDLE. PROVIDE SUBMITTAL TO OPRD FOR REVIEW AND APPROVAL.
7. COMPOSITE LUMBER COLOR TO BE COORDINATED WITH OWNER PRIOR TO CONSTRUCTION STARTING.
DETAIL A
4"X6"
COMPOSITE
LUMBER
2"X6"
COMPOSITE
LUMBER
LAG SCREW
EVERY 14" (TYP)
1.5" DEEP, 2" WIDE CUT
OUT FOR 3/4" PIPE
BRACING
3/4" PIPE
LOW LEAD HOSE BIB WITH ADA COMPLIANT AND LOCKABLE
HANDLE. ARROWHEAD BRASS MODEL 353BVLF WITH ARROWHEAD
BRASS MODEL 58ABP BRASS VACUUM BREAKER, OR EQUAL.
PROVIDE ALL HARDWARE TO MOUNT TO PEDESTAL. ORIENT
TOWARD CAMPING STALL
2"X6" COMPOSITE LUMBER
6"X6" HDPE SQUARE CAP
3/4" GALVANIZED 90° BEND
15/16" X 1/4" X 1/8" THICK
TEFLON WASHER
BRACE PIPE TO POST
EVERY 24"
3/4" GALVANIZED PIPE
4"X6" COMPOSITE LUMBER3/4" GALVANIZED NIPPLE
PRE DRILL & COUNTERSINK
1/4" GALVANIZED HEX HEAD
LAG SCREW (TYP) 48
SEE DETAIL A FOR
SECTION CUT OF
COMPOSITE LUMBER
AND PIPE ATTACHMENT
3/4" COMPRESSION BY
MALE PIPE THREAD W/ A
FEMALE PIPE THREAD
COUPLER
3/4" PEX WATER LINE
6"
111 SW Fifth Ave., Suite 2400 Portland, OR 97204 O: 503.227.3251 F: 503.274.4681 www.kpff.com
PERMIT SET
EXPIRATION DATE:
OREGON
12/31/2027
79775
5/
/2
A D
D
P S
6/
/2
A D
D
P
SADDENDUM 5
file:///L:/DETAILS/paving/201-A.DWG file:///L:/DETAILS/paving/201-A.DWG file:///L:/DETAILS/paving/201-A.DWG file:///L:/DETAILS/paving/201-A.DWG file:///L:/DETAILS/paving/201-A.DWG
| C0.1 CIVIL NOTES |
| C0.1 CIVIL NOTES |
| C2.1 DEMOLITION PLAN |
| C2.1 DEMOLITION PLAN |
| C2.2 DEMOLITION PLAN |
| C2.2 DEMOLITION PLAN |
| C6.3 DETAILS |
| C6.3 DETAILS |
File details come from the government source that posted it. Updated .