This document is a utility coordination plan for a temporary trailer site at the Mather VA Medical Center in Mather, California. The plan provides detailed specifications for electrical, sanitary/sewer, domestic water, and fiber/telecom utility connections required to support temporary outpatient pharmacy trailers and related facilities during a renovation project (Project Number 19-103, Drawing Number 612A4-19-016).

The electrical requirements include providing power from Building 107 to the temporary trailers via overhead service as soon as possible, utilizing two temporary power poles with a 300 kVA transformer rated at 10,000 AIC short circuit capacity. Sanitary infrastructure requires installation of a holding basin for human effluent with a new 4-inch PVC sanitary line routed from the temporary building at a minimum 2% slope. Domestic water service calls for a 2-inch connection from the existing building system with a backflow preventer and point-of-use hot water generation at each sink location. Fiber/telecom infrastructure requires connecting to existing fiber from the vault north of the trailer location and routing new fiber to OIT Room B650. All work must be coordinated with ongoing hospital operations to minimize disruption, with the contractor required to field verify exact utility locations and depths, provide trenching where necessary, and restore all disturbed areas to their original condition. The document is dated May 19, 2026, and marked as 100% Bid Documents.

View the file

Other files

File Type Posted
36C26126C0064 Award Notice.docx DOCX document
36C26126R0036 0005.docx DOCX document
36C26126R0036 0004.docx DOCX document
9- Site Visit log.jpeg JPEG file
8- VHA ICRA_612A4-19-016 Bid.pdf PDF
5- EQUIPMENT AND FURNITURE SCHEDULE_TEMPORARY TRAILER.xlsx XLSX spreadsheet
2- 087100 Door Hardware.docx DOCX document
1- RFI answers - 36C26126R0036 - Pharmacy - 612A4-19-016.xlsx XLSX spreadsheet
6- Utilty Map- Canteen Parking Lot.pdf PDF
7- B650 As builts 2014.pdf PDF
3- 281300-Physical access control SYStem.doc DOC document
36C26126R0036 0003.docx DOCX document
4- Pre-Inspection Submittals Checklist to Bidders.xlsx XLSX spreadsheet
36C26126R0036 0002.docx DOCX document
36C26126R0036 0001.docx DOCX document
11. Sheets I-001, I-101, and I-401.pdf PDF
Brand Name Justification.pdf PDF
Past Performance Questionnaire.docx DOCX document
13. 070150.19 PrepReRoof.docx DOCX document
9. NorCal Finish Standards 2025.pdf PDF
6. Sheet ES101 - ELECTRICAL SITE PLAN_SEALED_signed.pdf PDF
2. 010000 - General Requirements - CAEdits.docx DOCX document
0. Adendum to 19-103 Specs 100percent BD 20231108 -sumary of changes-.doc DOC document
S02 RFI FORM.docx DOCX document
VAAR 852.219-75.docx DOCX document
12. VA Provided Vault door cut sheet.pdf PDF
10. Spec Section 09 06 00 Schedof Finishes.docx DOCX document
36C26126R0036_2.docx DOCX document
14. 087100 Door Hardware.docx DOCX document
7. Sheet G-006_-signed.pdf PDF
5. 013323 Shop Drawings-CA Edits.docx DOCX document
4. 013216.15 Project Sched. Small - CA Edits.docx DOCX document
3. 015000.01 Temporary Facilities and Controls - Pharmacy Trailer_CHANGES.docx DOCX document
1. 000110 TOC.docx DOCX document
SAFETY - ENVIRONMENTAL RECORD AND EXPERIENCE MODIFICATION RATE.docx DOCX document
DIVISIONAL COST BREAK-OUT.docx DOCX document
19-103 SubReg 100percent BD 20231013 .pdf PDF
19-103 Specs 100percent BD 20231108 .pdf PDF
19-103 DWGs 100 BD 20231012 .pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CANTEEN PARKING

TEMPORARY

OUTPATIENT

PHARMACY (3

TRAILERS LINKED

TOGETHER)

TEMPORARY WAITING

OUTPATIENT PHARMACY

(2 TRAILERS LINKED

TOGETHER)

PHARMACY

VAULT

BLDG 649

BLDG 647

BLDG 650

HOSPITAL W

AY

TEMP FIBER

SEE NOTES

F1-5

TEMP DOMESTIC

2" WATER SEE

NOTES P1-4

SANITARY

HOLDING BASIN

TEMP 4" PVC

SANITARY PIPING

SEE S1-4

TEMP ELECTRICAL LINE

SEE NOTES E1-8

ISO VAVLE

BACKFLOW PREVENTER

Engineers Architects

Revisions: Date

Drawing Title

Approved: Project Director

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/2

/2

:2

:5

P

M

G - 007

UTILITY COORDINATION FOR TEMP

TRAILER PLAN

7 7EFJ

RENOVATION OF

OUTPATIENT PHARMACY

AND HVAC

MATHER VAMC

10535 HOSPITAL WAY,

MATHER,CA, 95655 MAY 19, 2026

100% BID DOCUMENTS

612A4-19-01619-103

JAV

Scale: 1/16" = 1'-0"

UTILITY COORDINATION FOR TEMP TRAILER SITE PLAN

GENERAL / COORDINATION

G-1 ALL UTILITY ROUTES SHOWN ARE DIAGRAMMATIC.

CONTRACTOR SHALL FIELD VERIFY EXACT LOCATIONS

AND DEPTHS OF EXISTING UTILITIES PRIOR TO

CONSTRUCTION.

G-2 COORDINATE ALL WORK WITH ONGOING HOSPITAL

OPERATIONS TO MINIMIZE DISRUPTION.

G-3 PROVIDE RESTORATION OF ALL DISTURBED AREAS

TO ORIGINAL CONDITION.

ELECTRICAL POWER (OVER HEAD AS SOON AS POSSIBLE)

E-1 PROVIDE POWER FROM BUILDING 107 DISTRIBUTION

PANEL TO TEMPORARY TRAILER (SEE ELECTRICAL PLANS

FOR CONTINUATION).

E-2 INSTALL AT-GRADE CONDUIT FROM TRAILER TO FIRST

TRANSITION POINT PER ELECTRICAL PLANS.

E-3 PROVIDE ELECTRICAL TRENCHING ACROSS SITE

WHERE REQUIRED TO ROUTE FEEDERS (LIMIT

DISTURBANCE AREA).

E-4 CONNECT TO PROPOSED TEMPORARY POWER POLE

(POLE #1) PER ELECTRICAL PLANS.

E-5 PROVIDE OVERHEAD SERVICE FROM TEMPORARY

POWER POLE (POLE #1) TO SECOND TEMPORARY POWER

POLE (POLE #2).

E-6 EXTEND OVERHEAD SERVICE FROM POLE #2 TO

TEMPORARY LAB (TRAILER).

E-7 TEMPORARY LAB SHALL BE SERVED BY 300 kVA

TRANSFORMER WITH 10,000 AIC SHORT CIRCUIT RATING

(VERIFY FINAL WITH ELECTRICAL ENGINEER).

E-8 ONTRACTOR TO COORDINATE ALL CLEARANCES,

POLE LOCATIONS, AND UTILITY REQUIREMENTS WITH VA

AND LOCAL AUTHORITIES.

SANITARY / SEWER

S-1 INSTALL HOLDING BASIN FOR HUMAN EFFLUENT PER

PLUMBING PLANS.

S-2 CONNECT NEW 4-INCH PVC SDR-26 SANITARY LINE

FROM TEMPORARY BUILDING TO HOLDING BASIN.

S-3 PROVIDE MINIMUM SLOPE OF 2% FOR ALL SANITARY

PIPING.

S-4 COORDINATE EXACT LOCATION OF HOLDING BASIN

WITH SITE AND MAINTAIN REQUIRED CLEARANCES FROM

UTILITIES AND STRUCTURES.

DOMESTIC WATER

P-1 PROVIDE 2-INCH DOMESTIC WATER SERVICE

CONNECTION FROM EXISTING BUILDING SYSTEM (MATCH

EXISTING LABORATORY STANDARD PER VA DETAIL

612-907).

P-2 PROVIDE BACKFLOW PREVENTER AT POINT OF

CONNECTION IN ACCORDANCE WITH VA AND LOCAL CODE

REQUIREMENTS.

P-3 ROUTE DOMESTIC WATER LINE FROM BUILDING

CONNECTION TO TEMPORARY TRAILER. CONTRACTOR TO

VERIFY EXACT CONNECTION POINT AND CAPACITY.

P-4 PROVIDE POINT-OF-USE HOT WATER GENERATION

(INSTANTANEOUS WATER HEATERS OR MIXING DEVICES)

AT EACH SINK LOCATION WITHIN TRAILER.

FIBER / TELECOM

F-1 CONNECT TO EXISTING FIBER FROM EXISTING VAULT

LOCATED NORTH OF TRAILER LOCATION (SEE – FIBER

OPTIC ROUTE ‘F’ PLAN). TRENCHING REQ'd).

F-2 ROUTE NEW FIBER UTILIZING EXISTING PATHWAY

(FIBER OPTIC ROUTE ‘F’) SOUTH OF BUILDING T8,

FOLLOWING EXISTING UNDERGROUND/DUCT BANK

ALIGNMENT.

F-3 EXTEND FIBER CONTINUOUSLY TO OIT ROOM B650

(ROOM 1E272). COORDINATE EXACT ENTRY POINT AND

TERMINATION WITH VA OIT.

F-4 CONTRACTOR TO VERIFY EXISTING PATHWAY

CAPACITY AND CONDITION PRIOR TO INSTALLATION.

PROVIDE NEW CONDUIT WHERE THE EXISTING PATHWAY

IS NOT VIABLE.

F-5 PROVIDE TELECOM HAND HOLD FOR SERVICE CABLE

FOR FUTURE USE AND CONVENIENCE ACCESS POINT.

3 Progress Issuance 4 Date 4 mnorris Text Box

UTILITY COORDINATION/

DIAGRAMMATIC FOR COORDINATION PURPOSES/

CONTRACTOR SHALL VERIFY ALL EXISTING CONDITIONS AND FINAL INSTALLATION REQUIREMENTS mnorris Ellipse

VHAMACMalonA Rectangle

VHAMACMalonA Callout Panel QHD1001A

VHAMACMalonA Text Box

VHAMACMalonA Image

Sheets
G - 007 - UTILITY COORDINATION FOR TEMP TRAILER PLAN

File details come from the government source that posted it. Updated .