This solicitation requests proposals for a cost-plus-fixed-fee completion contract to provide services under the USAID/Haiti Resilient Environment - North Activity. The purpose of the activity is to increase community, systems, and climate resilience in the Northern Resilience Focus Zone by protecting and restoring ecosystem services using a watershed management approach and fostering sustainable productivity and economic inclusion. The period of performance is five years with a total estimated cost ranging from $21,500,000 to $24,500,000. Offerors are encouraged to submit proposals by January 20, 2022 at 3:00 pm Haiti time. Questions regarding the solicitation are due by December 14, 2021. The solicitation is being conducted through full and open competition and is open to all types of commercial, educational, and non-profit organizations.

View the file

Other files for this federal contract opportunity

Other files attached to USAID/Haiti Resilient Environment - North, newest first.
File Type Posted
1.1.3 Percentage of USAID activity participants with improvement in targeted resilience capacities-PUBLIC.pdf PDF
Haiti Reforestation Project FY18 Annual Progress Report.pdf PDF
USAID_Haiti PMP Indicators - For Public Use - Performance and Context.pdf PDF
Haiti Reforestation Project FY20 Annual Progress Report.pdf PDF
Questions and Answers_72052122R00004.pdf PDF
Asset Indicator PIRS_Envt North.docx DOCX document
72052122R00004_Amendment 0001_Cover Page_final.pdf PDF
Final RFP 72052122R00004 Haiti Resilient Environment North.pdf PDF
Haiti Reforestation Project FY19 Annual Progress Report.pdf PDF
LAC-IEE-22-07 ETD (HA - Haiti Resilient Environment).pdf PDF
USAID Haiti Reforestation Project-Supported Sub-Watershed Management Plan for Les Perches.pdf PDF
USAID Haiti Reforestation Project-Resilience Baseline Study. 2020.pdf PDF
Haiti Politique Nationale de Lutte contre les Changements Climatiques. 2019.pdf PDF
Analyse du Couvert Forestier du Nord et du Nord-Est-USAID 2018.pdf PDF
Mid-Term Evaluation Report for the USAID Reforestation Project-USAID 2021.pdf PDF
Haiti Environmental Vulnerability Report-USAID 2007.pdf PDF
Watershed Management in Action-Lessons learned from Field Projects-FAO 2017.pdf PDF
Charcoal (National Assessment) in Haiti_World Bank Group 2018.pdf PDF
Haiti National Climate Change Policy 2019.pdf PDF
Acces a la terre et securite fonciere-MARNDR.pdf PDF
Paying People to Not Cut Down Trees Pays Off_Study Finds_Inside Climate News.pdf PDF
Revised Haiti Country Programme (En). 2019.pdf PDF
Geographic Data Asset Reporting Requirement.pdf PDF
List of all Standard Foreign Assistance Indicators.pdf PDF
Branding and Marking Template.pdf PDF
USAID Haiti Reforestation Project-Supported Sub-Watershed Management Plan for Bahon.pdf PDF
CIAT-Plan dAmenagement du Nord-Nord-Est-Couloir Cap Ouanaminthe-Decembre 2012.pdf PDF
Handbook for Developing Watershed Plans to Restore and Protect our Waters_EPA 2008.pdf PDF
IDB-Northern Sustainable Mobility Plan 2016.pdf PDF
Plan National dAdaptation-In Focus 2018.pdf PDF
Stimulating Smallholder Woodfuel Production-Lessons from Haitis Thriving Charcoal Market-USAID PROLAND 2021.pdf PDF
Haiti Environment Action Plan for 2021-2030.pdf PDF
Map of Target Watersheds.pdf PDF
Budget Template.xlsx XLSX spreadsheet
Range of FSN Local Compensation Plan.pdf PDF
USAID Haiti 2020-2022 Strategic Framework.pdf PDF
Plan Strategique Decennal 2021-2030-Ministere de lEnvironnement 2021.pdf PDF
Plan dInvestissements Agricoles-Composante Amenagement des Bassins Versants et Foresterie-MARNDR.pdf PDF
Participatory Watershed Management Planning_A Step-by-Step Guide_World Bank 2019.pdf PDF
List of Indicators for Economic Growth and Climate Change.xlsx XLSX spreadsheet
USAID Proland Payment for Ecosystem Services_Case Study.pdf PDF
USAID Haiti Reforestation Project-Supported Sub-Watershed Management Plan for Capotille.pdf PDF
SOL 72052122R00004_Resilient Environment North Activity.pdf PDF
Past Performance Matrix.xlsx XLSX spreadsheet
USAID Haiti Reforestation Project-Supported Sub-Watershed Management Plan for Joli-Trou and Cormier.pdf PDF
USAID Haiti Reforestation Project-Supported Sub-Watershed Management Plan for Gens des Nantes.pdf PDF
Plan dAction National dAdaptation-Haiti.pdf PDF
Political Economic Analysis by the USAID Reforestation Project (French).pdf PDF
Strategic Plan for the Development of Haiti (PSDH).pdf PDF
List of Global Climate Change Standard Indicators.pdf PDF
Show all 50

USAID/Haiti Resilient Environment - North has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

72052122R00004 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

N/A

Not Applicable

720521

00000 USAID/Haiti

12/01/20210001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

12/01/2021

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment to the RFP is to:

1) provide USAID/Haiti's responses to questions received from interested parties;

2) update the RFP in its entirety to reflect changes since the original solicitation;

3) include additional attachments; and

4) extend the deadline for receipt of proposals from January 13, 2022 to January 20, 2022 at 3:00 pm Haiti time.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Matthew Courtad

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

2021-12-17T09:37:04-0500
MATTHEW JOHN COURTAD (affiliate)

File details come from the government source that posted it. Updated .