J.2-Bid_Form_IFB_Amendment_5.xlsx

XLSX spreadsheet 32 KB Posted

Attached to
USAID Civil Works for Dioxin Remediation at Bien Hoa Airbase Area – Phase 1
Solicitation number
72044021B00001
Issued by

About this file

This document contains an invitation for bids for a construction contract opportunity with the United States Agency for International Development in Vietnam. Key details include that USAID Vietnam is seeking bids for civil works for Phase 1 of dioxin remediation at Bien Hoa Airbase Area, with an estimated total bid value of over $50 million. The solicitation includes construction services across four contract line item numbers. The deadline for bid submission is February 11, 2022, and bids must be submitted electronically. A virtual pre-bid site visit and conference will be held on December 1, 2021. The anticipated award is a single fixed-price contract with an optional period of performance.

View the file

Other files

File Type Posted
J.2-Bid_Form_IFB_Amendment_6.xlsx XLSX spreadsheet
20220216_Amendment_6_IFB_72044021B00001_USAID Civil Works P1 for Dioxin Remediation at BH Airbase.pdf PDF
J.13_Compendium_IFB_Amendment_5.pdf PDF
20220214_Amendment_5_IFB_72044021B00001_USAID Civil Works P1 for Dioxin Remediation at BH Airbase.pdf PDF
20220126_Amendment_4_IFB_72044021B00001_USAID Civil Works P1 for Dioxin Remediation at BH Airbase.pdf PDF
J.2-Bid_Form_IFB_Amendment_4.xlsx XLSX spreadsheet
J.4_10_Treatment_Area_IFB_Amendment+3.pdf PDF
J.2_Bid_Form_IFB_Amendment_3.xlsx XLSX spreadsheet
J.9_40_LTSA_Final_Cover_IFB_Amendment_3.pdf PDF
J.13_Compendium_IFB_Amendment_3.pdf PDF
20220122_Amendment_3_IFB_72044021B00001_USAID Civil Works P1 for Dioxin Remediation at BH Airbase.pdf PDF
J.8_30_Roadways_IFB_Amendment_3.pdf PDF
J.2-Bid_form_IFB Amendment#2.xlsx XLSX spreadsheet
J.8-30_Roadways_Amendment 2.pdf PDF
J.13_Compendium_Amendment 2.pdf PDF
J.3_Civil_Works_Phase_1_Overview_Amendment 2.pdf PDF
J.12_Groundwater_Contours_Amendment 2.pdf PDF
J.11-IM2_LTSA_and_HCTS_Plans_and_Sections_Amendment 2.pdf PDF
J.10-IM1_LCSA_HCSA_and_Staging_Area_Plans_and_Sections_Amendment 2.pdf PDF
20220115 Amendment_2 to IFB_72044021B00001 for USAID Civil Works P1 for Dioxin Remediation at Bien Hoa Airbase Area.pdf PDF
J.5-Decision_Units_Amendment 2.pdf PDF
J.6-20_Dig_and_Haul_SW-07_Amendment 2.pdf PDF
20220115 Revised No. 2 lFB No. 72044021B00001 USAID Civil Works for Dioxin Remediation at Bien Hoa Airbase Area – Phase 1.pdf PDF
20211203 SF30 Amendment_1 to IFB_72044021B00001 for USAID Civil Works P1 for Dioxin Remediation at Bien Hoa Airbase Area.pdf PDF
20211203 Revised No. 1 lFB No. 72044021B00001 USAID Civil Works for Dioxin Remediation at Bien Hoa Airbase Area – Phase 1.pdf PDF
20211201 CW1 Virtual Conference IFB No. 72044021B00001.pdf PDF
20211203 J.1_SF1442-14b IFB_72044021B00001 BH CW1_removed block 17.pdf PDF
20211117 lFB No. 72044021B00001 USAID Civil Works for Dioxin Remediation at Bien Hoa Airbase Area – Phase 1.pdf PDF
J.18-BRANDING IMPLEMENTATION PLAN AND MARKING PLAN.pdf PDF
J.11-IM2_LTSA_and_HCTS_Plans_and_Sections.pdf PDF
J.9-40_LTSA_COVER.pdf PDF
J.3-Civil_Works_Phase_1_Overview.pdf PDF
J.13-Compendium.pdf PDF
J.1_SF1442-14b IFB_72044021B00001 BH CW1.pdf PDF
J.16-Site_wide_EMMP.pdf PDF
J.4-10_Treatment_area.pdf PDF
J.6-20_D_H_SW-07.pdf PDF
J.5-Decision_Units.pdf PDF
J.10-IM1_LCSA_HCSA_and_Staging_Area_Plans_and_Sections.pdf PDF
J.7-20_D_H_NF-04.pdf PDF
J.12-Groundwater Contours.pdf PDF
J.8-30_Roadways.pdf PDF
J.15-Site-wide_HASP_Sign_off_Page.docx DOCX document
J.2-Bid_form.xlsx XLSX spreadsheet
J.17-Site-wide_EMMP_Sign_off_Page.docx DOCX document
J.19-Certification of Key personnel.xlsx XLSX spreadsheet
J.14-Site_wide_HASP.pdf PDF
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid_form

USAID/VIETNAM CIVIL WORKS FOR DIOXIN REMEDIATION AT THE BIEN HOA AIRBASE AREA – PHASE I
ATTACHMENT J.2 BID FORM (IFB Amendment No. 5)
CLINBid Item No.Bid Item DescriptionUnitsQuantityUnit Price (USD)Total Amount (USD)
100 GENERAL$ -
01.00.01MobilizationLS1$ -$ -
01.00.02Environmental MitigationLS1$ -$ -
01.00.03Health and Safety, Including PPE and Blood MonitoringLS1$ -$ -
01.00.04Traffic ControlLS1$ -$ -
01.00.05DecontaminationLS1$ -$ -
01.00.06Site OfficeLS1$ -$ -
01.00.07Project Management and SupportLS1$ -$ -
01.00.08Bonds or Bank GuaranteesLS1$ -$ -
10 TREATMENT AREA$ -
01.10.01General - Clearing and Removal of VegetationLS1$ -$ -
01.10.02General - Remove amd Stockpile TopsoilLS1$ -$ -
01.10.03General - Excavation, Fill and CompactionLS1$ -$ -
01.10.04PTSA - Non-Woven GeotextileLS1$ -$ -
01.10.05PTSA - Double-Sided Textured HDPE LinerLS1$ -$ -
01.10.06PTSA - Sumps, Piping, Pump Station, Access Points, and All Ancillary ItemsLS1$ -$ -
01.10.07PTSA - Access RampLS1$ -$ -
01.10.08PTSA - Excavate, Fill, and Compact PTSA and Detention Pond BaseLS1$ -$ -
01.10.09PTSA - Fill and Compaction PTSA and Detention Pond BermLS1$ -$ -
01.10.10PTSA - Detention Ponds and Piping, and All Ancillary ItemsLS1$ -$ -
01.10.11Drainage - Install Perimeter Concrete Lined Channel 1000 mm wideLS1$ -$ -
01.10.12Drainage - Install Perimeter Concrete Lined Channel 2000 mm wideLS1$ -$ -
01.10.13Drainage - Improve Existing Earthen Channel 2000 mm wide, DissipationLS1$ -$ -
01.10.14Drainage - 1000 mm by 1000 mm Box Culvert, Headwalls, DissipationLS1$ -$ -
01.10.15Drainage - Double 1000 mm by 1000 mm Box Culvert, Headwalls, DissipationLS1$ -$ -
01.10.16Monitoring WellsEA4$ -$ -
01.10.17Security FenceLS1$ -$ -
01.10.18Northern Control GateEA1$ -$ -
01.10.19Southern Control GateEA1$ -$ -
01.10.20Guard ShacksEA3$ -$ -
01.10.21Site RestorationLS1$ -$ -
20 DIG AND HAUL$ -
01.20.01Dig and Haul - Clear, Chip and Stockpile of VegetationLS1$ -$ -
01.20.02Dig and Haul - Excavation, Dewatering and Drainage, Stockpile, Transport, and Placement and Grade of Soil - Excavation Depth up to 1.5mm343,600$ -$ -
01.20.03Dig and Haul - Excavation, Dewatering and Drainage, Stockpile, Transport, and Placement and Grade of Soil - Excavation Depth >1.5 mm356,000$ -$ -
01.20.04Dig and Haul - Excavation, Dewatering and Drainage, Stockpile, Transport, and Placement and Grade of Sedimentm318,800$ -$ -
01.20.05Dig and Haul - Compaction at LTSAm359,200$ -$ -
01.20.06Dig and Haul - Unloading Low Concentration Material from LCSA; Transport, Placement and Grade LTSAm331,000$ -$ -
01.20.07Dig and Haul - Unloading, High Concentration Material from HCSA and HCTS; Transport, Placement and Grade in PTSAm320,000$ -$ -
01.20.08Monitoring WellsEA3$ -$ -
01.20.09Moveable Barrier FenceLS1$ -$ -
01.20.10Brick Fencing Type 1m180$ -$ -
01.20.11Brick Fencing Type 2m150$ -$ -
01.20.12Guard ShacksEA5$ -$ -
01.20.13Site Restoration - Backfilling and Compaction of Borrow Materialsm384,500$ -$ -
01.20.14Site Restoration - Topsoilm280,000$ -$ -
01.20.15Site Restoration - Soddingm280,000$ -$ -
30 ROADWAYS$ -
01.30.01Access Road to Treatment areaLS1$ -$ -
01.30.02Reconstruct SW-07 Road SectionLS1$ -$ -
01.30.03Dig and Haul - Bypass RoadLS1$ -$ -
40 PROTECT, MAINTAIN, AND HANDOVER PROJECT ASSETS$ -
01.40.01Maintainance of Installed Project Work - High Concentration Storage Area, High Concentration Temporary Storage, and Low Concentration Storage AreaLS1$ -$ -
01.40.02Maintenance of Installed Project Work - Long Term Storage Area Including Drainage, LTSA Site Office, and all Associated FacilitiesLS1$ -$ -
01.40.03Operation and Maintenance of Treatment Area Components Including the PTSA, PTSA Detention Ponds, Drainage, Fencing, Guard Shacks, Access Roads, and all Associated WorkLS1$ -$ -
01.40.04Grass cutting, and tree trimming alongside roadways, ditches, existing steel fencingLS1$ -$ -
01.40.05LTSA - Non-Woven Geotextile at baseLS1$ -$ -
01.40.06LTSA - Final CoverLS1$ -$ -
01.40.07Monitoring WellsLS1$ -$ -
50 STORAGE AND STAGING AREA DEMOLITION$ -
01.50.01LCSA and IM1 CLIN 2 Area Demolition and Site RestorationLS1$ -$ -
01.50.02HCSA Demolition and Site RestorationLS1$ -$ -
01.50.03HCTS Demolition and Site RestorationLS1$ -$ -
01.50.04IM1 Staging Area DemolitionLS1$ -$ -
CLIN 1 SUBTOTAL$ -
200 GENERAL$ -
02.00.01DemobilizationLS1$ -$ -
CLIN 2 SUBTOTAL$ -
320 DIG AND HAUL$ -
03.20.01Dig and Haul - Excavation, Dewatering and Drainage, Stockpile, Transport, and Placement and Grade of Soil - Excavation Depth up to 1.5mm325,700$ -$ -
03.20.02Dig and Haul - Excavation, Dewatering and Drainage, Stockpile, Transport, and Placement and Grade of Soil - Excavation Depth >1.5 mm331,500$ -$ -
03.20.03Dig and Haul - Excavation, Dewatering and Drainage, Stockpile, Transport, and Placement and Grade of Sedimentm311,300$ -$ -
03.20.04Dig and Haul - Compaction at LTSAm327,600$ -$ -
03.20.05Hauling Treated Material to Stockpilem350,000$ -$ -
03.20.06Monitoring WellsEA5$ -$ -
03.20.07Site Restoration - Backfilling and Compaction of Borrow Materialsm357,200$ -$ -
03.20.08Dig and Haul and Site Restoration - Unloading, Transport, Backfill and Compaction of Treated Materialm350,000$ -$ -
03.20.09Site Restoration - Topsoilm232,000$ -$ -
03.20.10Site Restoration - Soddingm232,000$ -$ -
03.20.11Temporary Steel Sheet Fencem1,500$ -$ -
03.20.12On and Off-Base GatesEA6$ -$ -
03.20.13Repair Existing Mornitoring WellsEA4$ -$ -
30 ROADWAYS$ -
03.30.01Construction of Masonry Ditchm16,080$ -$ -
03.30.02Asphalt Concrete C12.5, 5 cm Thickm230,000$ -$ -
03.30.03Asphalt Concrete C12.5 Levellingm31,200$ -$ -
03.30.04Asphalt Concrete C19, 7 cm Thickm230,000$ -$ -
03.30.05Asphalt Concrete C19 Levellingm31,200$ -$ -
03.30.06Tack Coat 0.5 L/ 1m2 in Densitym260,000$ -$ -
03.30.07Prime Coat 1 L/ 1m2 in Densitym230,000$ -$ -
03.30.08Fiberglass Mesh 100/100 kN/mm230,000$ -$ -
03.30.09Aggregate Base Course Dmax 25m35,000$ -$ -
03.30.10Aggregate Base Course Dmax 37.5m35,500$ -$ -
03.30.11Fill Compacted to 98%m315,000$ -$ -
03.30.12Fill Compacted to 95%m315,000$ -$ -
03.30.13Neoweb Reinforced Slopem2200$ -$ -
03.30.14Cement Concrete Patchingm220,000$ -$ -
03.30.15Crushed Stonem320$ -$ -
03.30.16Remove, Transport and Disposal of Road Structurem320,000$ -$ -
CLIN 3 SUBTOTAL
60 TOTAL DAY WORKS$ 3,000,000
03.60.01Total Day Works - The CONTRACTOR is not entitled to any part of the Day Work item, either partially or fully, unless specifically authorized by USAID--$ 3,000,000$3,000,000
CLIN 3 SUBTOTAL$ 3,000,000
BASE BID (CLIN 1 + CLIN 2 + CLIN 3)$ 3,000,000
400 GENERAL$ -
04.00.01Environmental MitigationLS1$ -$ -
04.00.02Health and Safety, Including PPE and Blood MonitoringLS1$ -$ -
04.00.03Traffic ControlLS1$ -$ -
04.00.04DecontaminationLS1$ -$ -
04.00.05Site Office Operation and MaintenanceLS1$ -$ -
04.00.06Project Management and SupportLS1$ -$ -
04.00.07Bonds or Bank GuaranteesLS1$ -$ -
20 DIG AND HAUL$ -
04.20.01Dig and Haul - Clear, Chip and Stockpile of VegetationLS1$ -$ -
04.20.02Dig and Haul - Excavation, Dewatering and Drainage, Stockpile, Transport, and Placement and Grade of Soil - Excavation Depth up to 1.5mm318,400$ -$ -
04.20.03Dig and Haul - Excavation, Dewatering and Drainage, Stockpile, Transport, and Placement and Grade of Soil - Excavation Depth >1.5 mm338,000$ -$ -
04.20.04Dig and Haul - Excavation, Dewatering and Drainage, Stockpile, Transport, and Placement and Grade of Sedimentm315,000$ -$ -
04.20.05Dig and Haul - Compaction at LTSAm323,300$ -$ -
04.20.06Moveable Barrier FenceLS1$ -$ -
04.20.07Site Restoration - Backfilling and Compaction of Borrow Materialsm347,600$ -$ -
04.20.08Guard ShacksEA6$ -$ -
04.20.09Site Restoration - Topsoilm246,800$ -$ -
04.20.10Site Restoration - Soddingm246,800$ -$ -
40 PROTECT, MAINTAIN, AND HANDOVER PROJECT ASSETS$ -
04.40.01Operation and Maintenance of Treatment Area Components Including the PTSA, PTSA Detention Ponds, Drainage, Fencing, Guard Shacks, Access Roads, and all Associated WorkLS1$ -$ -
04.40.02Grass cutting, and tree trimming alongside roadways, ditches, existing steel fencingLS1$ -$ -
04.40.03LTSA - Non-Woven Geotextile at baseLS1$ -$ -
04.40.04LTSA - Final CoverLS1$ -$ -
04.40.05Monitoring WellsLS1$ -$ -
CLIN 4 (OPTION PERIOD) SUBTOTAL$ -
TOTAL BID (BASE BID + CLIN 4)$ 3,000,000

File details come from the government source that posted it. Updated .