DB RFP – STATION FORT MYERS REBUILD
U S C G F o r t M y e r s , F l o r i d a |
SPACE CRITERIA SHEET
Multi-Mission Building - Station Update to pages
67, 68 & 69
Fort Myers, Florida Date: 12/02/2020
SPACE NAME Work Bay (Boat Work Bay)
SPACE
TYPE
Marine Maintenance
ACTIVITY Boat Maintenance of Trailerable Boats
ADJACENCIES
ROOM NO.
Min Ceiling Ht. 21’-0” (clear)
Program Area 1,830
Contractor Qty Item Qty Item
Furnished;
Contractor Installed
S-1A Eye Level Hgt Cab S-1C Eye Level Hgt Cab S-1D Eye Level Hgt Cab S-1E Eye Level Hgt Cab S-1F Eye Level Hgt Cab S-3A Bench Level Hgt Cab S-3B Bench Level Hgt Cab S-3C Bench Level Hgt Cab S-3D Bench Level Hgt Cab S-3E Bench Level Hgt Cab S-4 Mobile Utility Cart S-5 Shop Workbench Top S-8 Shop Stool
S-13 Drill Press S-14 Hydraulic Press S-15 Grinder S-16 Large Vice S-17 Pedestal Grinder S-18 Blast Cabinet S-24 Pallet Rack S-27 Flammable Storage Cab S-28 Corrosive Storage Cab S-29 Hazmat Storage Cab S-31 Solvent Cleaner F-8 Recycling Bins
Government Furnished;
Contractor Installed
Finishes Ceiling Open to Structure, painted. Ceiling height: 21’-0” clear to underside of any element. Height to include SPC-LE boat height of 14’-5” (on trailer), 1’ of ground clearance, 5’ clearance to underside of structure, lighting, fire sprinklers, overhead crane, HVAC components, whichever is lower.
Boat Work Bay to be designed with structural elements and other building elements deterring the roosting of birds. Bird netting not allowed.
Floor Provide high reflectance index epoxy coating at concrete floor slab.
Provide grit in floor to prevent slipping. Floor design load 250psf minimum. Slope floor as required to central trench drain (removable grating) that feeds to 24”x48”x24” deep sump. Sump is not connected to the sewer system and must be manually evacuated for offsite disposal.
Walls Shall be CMU or concrete, sealed or painted.
Door 16’H x 16’W clear opening roll-up exterior door. Provide (2) 3’W x 7’H egress doors with vision panels. Provide (1) door located near/adjacent to roll-up door and other at the opposite end of bay. Doors/frames to be FRP. Doors to have SS kickplates extending from bottom to 24"AFF (min.).
Sound Ceiling
Attenuation Floor
Walls
Security
Multi-Mission Building - Station Update to pages
67, 68 & 69
Fort Myers, Florida Date: 12/02/2020
SPACE NAME Work Bay (Boat Work Bay)
SPACE
TYPE
Marine Maintenance
ACTIVITY Boat Maintenance of Trailerable Boats
ADJACENCIES
ROOM NO.
Min Ceiling Ht. 21’-0” (clear)
Program Area 1,830
Utility Mech.
Rollup door switch shutting off HVAC when the door is open. No refrigerant air conditioning in the boat maintenance bay. Circulation fans to be provided to control stratified air.
Services
Plumb.
Provide four compressed air tool drops in bays, two drops on the exterior of the boat bays adjacent hose bibbs including valve, filter, and accessories, two compressed air hose reels, two hose bibbs on exterior walls, and one hose bibb within the boat bay.
Elect.
Power: Provide one receptacle for every 25 ft of wall space at the floor line. When 25 ft or less of wall at the floor line exists in a room, provide a minimum of two receptacles. Provide receptacle within 25 ft of mechanical equipment on the interior and exterior of buildings. Provide dedicated circuits for equipment in special use room.
Lighting: Suspended linear direct LED luminaire / indirect LED luminaire.
Provide 50 foot-candles (fc) at 2’-6” AFF. Provide manual controls with bi-level dimming capabilities to independently control general lighting, manual on with step dimming capability with at least one step to between 30% and 70% of lighting power. General lighting in day lighted areas separately controlled through multilevel photo control, step dimming or continuous dimming to reduce light output when daylight is available, with at least two steps, one to 35% lighting power, and one between 50% and 70% of lighting power. Provide two portable drop down LED luminaires per maintenance bay.
Comm.
Fire Life Safety
Other
Notes:
1.
2.
Multi-Mission Building - Station Fort Myers, Florida Date: 7/22/2020
SPACE NAME Work Bay (Boat Work Bay)
SPACE
TYPE
Marine Maintenance
Program Area 1830
ROOM OUTFITTING PLAN:
Notes:
1. FF+E Indicator: Refer to space data sheet and section 01800.15.0.
2.