WFLHD Construction Contract Administration_FY 23 V2.pdf

PDF 162 KB Posted

Attached to
ID FLAP CANYON MULTI(1), Indiana and Orchard Shared Roadway
Solicitation number
69056724B000009
Issued by

About this file

This document is the Federal Highway Administration's (FHWA) procedures for definitizing equitable adjustments for change orders under construction contracts, as required by FAR 36.211. It provides data on the agency's past performance regarding the time required to definitize such change orders over the prior 3 fiscal years. The data shows that in FY 2021-2023, the majority of change order proposals were definitized within 90-180 days, with a small number taking over 1 year. There are no agency-specific additional policies or procedures beyond those outlined.

The related federal contract opportunity is a solicitation (Solicitation Number: 69056724B000009) for the ID FLAP CANYON MULTI(1), Indiana and Orchard Shared Roadway project. The solicitation includes two bid schedules, with only one schedule to be awarded. The full Invitation for Bidders (IFB), plans, physical data, and the Construction Contract Administration Document per FAR 36.211 are provided as attachments.

View the file

Other files

File Type Posted
UPDATED_Bid Tab_ID FLAP CANYON MULTI(1).pdf PDF
Bid Tab_ID FLAP CANYON MULTI(1).pdf PDF
BidSum_ID FLAP CANYON MULTI(1).pdf PDF
QA_06-24-2024.pdf PDF
QA_06-20-2024_A.pdf PDF
QA_06-20-2024.pdf PDF
QA_06-18-2024.pdf PDF
Amendment A001.pdf PDF
QA_06-04-2024.pdf PDF
Physical Data.zip ZIP file
ID FLAP Canyon MULTI(1)_XYZ asphalt-MAIN 02.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_XS-APPR 01.pdf PDF
ID FLAP Canyon MULTI(1)_Clearing Limits-APPR 01.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_XYZ asphalt-MAIN 01-A.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_3025A1_Bridge-Inspection-Report.pdf PDF
ID FLAP Canyon MULTI(1)_XYZ base-APPR 01.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_Earthwork-MAIN 01.pdf PDF
ID FLAP Canyon MULTI(1)_GM3623 Final Foundation and Geotechnical Recommendations Memo.pdf PDF
IFB_69056724B000009_ID FLAP CANYON MULTI(1).pdf PDF
ID FLAP Canyon MULTI(1)_XYZ base-MAIN 01-A.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_Staking Notes-MAIN 01-A.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_Earthwork-MAIN 02.pdf PDF
ID FLAP Canyon MULTI(1)_Staking Notes-MAIN 01-B.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_plans.pdf PDF
ID FLAP Canyon MULTI(1)_Staking Notes-MAIN 02.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_Staking Notes-APPR 01.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_proposed-MAIN 01-02.pdf PDF
ID FLAP Canyon MULTI(1)_XYZ asphalt-MAIN 01-B.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_XYZ base-MAIN 02.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_control-points.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_Earthwork-approaches.pdf PDF
ID FLAP Canyon MULTI(1)_XS-MAIN 02.pdf PDF
ID FLAP Canyon MULTI(1)_ROW-plans-stamped.dgn.pdf PDF
ID FLAP Canyon MULTI(1)_XS-MAIN 01.pdf PDF
ID FLAP Canyon MULTI(1)_proposed-APPR 01.pdf PDF
ID FLAP Canyon MULTI(1)_XYZ base-MAIN 01-B.xlsx XLSX spreadsheet
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WFLHD Construction Contract Administration

FAR 36.211 requires a description of the Federal Highway Administration’s (FHWA) procedures that apply to definitization of equitable adjustments for change orders under construction contracts. It also requires that FWHA furnish data on the agency’s past performance, for the prior 3 fiscal years, regarding the time required to definitize equitable adjustments for change orders under construction contracts.

Change orders as defined in FAR 2.101 are changes to the contract work pursuant to FAR 52.243-4, Changes.

There are no agency-specific additional policies and procedures that exist at this time.

The table below contains data regarding the definitization of equitable adjustments for change orders under construction contracts by fiscal year (FY).

Time to definitize after receipt of an adequate change order definitization proposal under construction contracts

Number of change order proposals definitized under construction contracts

FY 2021 FY 2022 FY 2023

0 to 30 days 1 1 0 31 to 60 days 1 0 3 61 to 90 days 0 0 3 91 to 180 days 5 1 4 181 to 365 days 0 0 3 366 or more days 2 0 0 After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance

0 0 0 https://www.acquisition.gov/far/part-52#FAR_52_243_4

File details come from the government source that posted it. Updated .