UPDATED_Bid Tab_ID FLAP CANYON MULTI(1).pdf

PDF 697 KB Posted

Attached to
ID FLAP CANYON MULTI(1), Indiana and Orchard Shared Roadway
Solicitation number
69056724B000009
Issued by

About this file

This document is a Tabulation of Bids report for a federal construction contract opportunity for the "ID FLAP CANYON MULTI(1), Indiana and Orchard Shared Roadway" project.

The project has two bid schedules, Schedule A (Base) and Schedule B (Alternate), for which bids were received from two contractors, Construction Solutions Group, LLC and LaRiviere Incorporated. The engineer's estimate for Schedule A was $3,706,045.00, while Construction Solutions Group, LLC bid $4,979,750.20 and LaRiviere Incorporated bid $5,021,295.00. For Schedule B, the engineer's estimate was $4,989,175.00, with Construction Solutions Group, LLC bidding $6,229,039.90 and LaRiviere Incorporated bidding $5,762,775.00. The solicitation number is 69056724B000009, and the federal agency involved is the Department of Transportation Federal Highway Administration. The bid opening date was June 26, 2024, and the contract award date is June 28, 2024.

View the file

Other files

File Type Posted
Bid Tab_ID FLAP CANYON MULTI(1).pdf PDF
BidSum_ID FLAP CANYON MULTI(1).pdf PDF
QA_06-24-2024.pdf PDF
QA_06-20-2024_A.pdf PDF
QA_06-20-2024.pdf PDF
QA_06-18-2024.pdf PDF
Amendment A001.pdf PDF
QA_06-04-2024.pdf PDF
Physical Data.zip ZIP file
ID FLAP Canyon MULTI(1)_XYZ asphalt-MAIN 02.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_XS-APPR 01.pdf PDF
ID FLAP Canyon MULTI(1)_Clearing Limits-APPR 01.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_XYZ asphalt-MAIN 01-A.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_3025A1_Bridge-Inspection-Report.pdf PDF
ID FLAP Canyon MULTI(1)_XYZ base-APPR 01.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_Earthwork-MAIN 01.pdf PDF
ID FLAP Canyon MULTI(1)_GM3623 Final Foundation and Geotechnical Recommendations Memo.pdf PDF
IFB_69056724B000009_ID FLAP CANYON MULTI(1).pdf PDF
ID FLAP Canyon MULTI(1)_XYZ base-MAIN 01-A.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_Staking Notes-MAIN 01-A.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_Earthwork-MAIN 02.pdf PDF
ID FLAP Canyon MULTI(1)_Staking Notes-MAIN 01-B.xlsx XLSX spreadsheet
WFLHD Construction Contract Administration_FY 23 V2.pdf PDF
ID FLAP Canyon MULTI(1)_plans.pdf PDF
ID FLAP Canyon MULTI(1)_Staking Notes-MAIN 02.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_Staking Notes-APPR 01.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_proposed-MAIN 01-02.pdf PDF
ID FLAP Canyon MULTI(1)_XYZ asphalt-MAIN 01-B.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_XYZ base-MAIN 02.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_control-points.xlsx XLSX spreadsheet
ID FLAP Canyon MULTI(1)_Earthwork-approaches.pdf PDF
ID FLAP Canyon MULTI(1)_XS-MAIN 02.pdf PDF
ID FLAP Canyon MULTI(1)_ROW-plans-stamped.dgn.pdf PDF
ID FLAP Canyon MULTI(1)_XS-MAIN 01.pdf PDF
ID FLAP Canyon MULTI(1)_proposed-APPR 01.pdf PDF
ID FLAP Canyon MULTI(1)_XYZ base-MAIN 01-B.xlsx XLSX spreadsheet
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 06/27/24

1 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Contractor Responsive?

Engineer's Estimate

Construction Solutions Group, LLC

LaRiviere Incorporated no

Base Schedule A

$3,706,045.00

$4,979,750.20

$5,021,295.00

Alternate Schedule B

$4,989,175.00

$6,229,039.90

$5,762,775.00

UDPATED

2 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: A

Schedule Type: Base

Solcitation No: 69056724B000009

Division: Western Federal Lands

State: ID County: Canyon

Federal Land: Deer Flat National Wildlife Refuge Opened at: WFLHD Vancouver, WA

Opened by: Robert Kolln

Date: 06/26/24

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Construction Solutions Group, LLC $4,979,750.20 425 Highland Ave St. Louis, MO 63122

LaRiviere Incorporated ( $5,021,295.00 ) no 17564 N Dylan Ctr Rathdrum, ID 83858

Engineer's Estimate $3,706,045.00

UDPATED

Contracting Officer

06/28/2024

3 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0020 15101-0000 MOBILIZATION

Construction Solutions Group, LLC Lump Sum $879,500.00 LaRiviere Incorporated Lump Sum $150,000.00 Engineer's Estimate ALL LPSM Lump Sum $340,000.00

A0040 15201-0000 CONSTRUCTION SURVEY AND STAKING

Construction Solutions Group, LLC Lump Sum $292,500.00 LaRiviere Incorporated Lump Sum $30,000.00 Engineer's Estimate ALL LPSM Lump Sum $63,000.00

A0060 15301-0000 CONTRACTOR QUALITY CONTROL

Construction Solutions Group, LLC Lump Sum $210,000.00 LaRiviere Incorporated Lump Sum $30,000.00 Engineer's Estimate ALL LPSM Lump Sum $63,000.00

A0080 15401-0000 CONTRACTOR TESTING

Construction Solutions Group, LLC Lump Sum $77,500.00 LaRiviere Incorporated Lump Sum $115,000.00 Engineer's Estimate ALL LPSM Lump Sum $63,000.00

A0100 15501-0000 CONSTRUCTION SCHEDULE

Construction Solutions Group, LLC Lump Sum $79,480.00 LaRiviere Incorporated Lump Sum $6,500.00 Engineer's Estimate ALL LPSM Lump Sum $16,000.00

A0120 15705-0100 SOIL EROSION CONTROL, SILT FENCE

Construction Solutions Group, LLC $2.64 $2,376.00 LaRiviere Incorporated $6.00 $5,400.00 Engineer's Estimate 900 LNFT $6.00 $5,400.00

A0140 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

Construction Solutions Group, LLC $3.03 $39,390.00 LaRiviere Incorporated $8.00 $104,000.00 Engineer's Estimate 13,000 LNFT $5.00 $65,000.00

4 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0160 15706-0200 SOIL EROSION CONTROL, CHECK DAM (FIBER ROLL)

Construction Solutions Group, LLC $64.90 $1,298.00 LaRiviere Incorporated $300.00 $6,000.00 Engineer's Estimate 20 EACH $155.00 $3,100.00

A0180 15706-1100 SOIL EROSION CONTROL, INLET PROTECTION TYPE A

Construction Solutions Group, LLC $129.80 $1,168.20 LaRiviere Incorporated $175.00 $1,575.00 Engineer's Estimate 9 EACH $640.00 $5,760.00

A0200 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION EXIT

Construction Solutions Group, LLC $18,700.00 $18,700.00 LaRiviere Incorporated $2,500.00 $2,500.00 Engineer's Estimate 1 EACH $2,600.00 $2,600.00

A0220 15802-0000 WATERING FOR DUST CONTROL

Construction Solutions Group, LLC Lump Sum $94,000.00 LaRiviere Incorporated Lump Sum $40,000.00 Engineer's Estimate ALL LPSM Lump Sum $20,000.00

A0240 20101-0000 CLEARING AND GRUBBING

Construction Solutions Group, LLC $9,900.00 $69,300.00 LaRiviere Incorporated $9,000.00 $63,000.00 Engineer's Estimate 7.0 ACRE $9,000.00 $63,000.00

A0260 20301-0400 REMOVAL OF BRIDGE

Construction Solutions Group, LLC $127,500.00 $127,500.00 LaRiviere Incorporated $100,000.00 $100,000.00 Engineer's Estimate 1 EACH $65,000.00 $65,000.00

A0300 20302-0700 REMOVAL OF FENCE

Construction Solutions Group, LLC $5.78 $40,460.00 LaRiviere Incorporated $10.00 $70,000.00 Engineer's Estimate 7,000 LNFT $3.00 $21,000.00

5 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0320 20315-0000 SAWCUTTING PAVEMENT

Construction Solutions Group, LLC $2.20 $53,240.00 LaRiviere Incorporated $3.00 $72,600.00 Engineer's Estimate 24,200 LNFT $2.00 $48,400.00

A0340 20401-0000 ROADWAY EXCAVATION

Construction Solutions Group, LLC $49.50 $346,500.00 LaRiviere Incorporated $26.00 $182,000.00 Engineer's Estimate 7,000 CUYD $30.00 $210,000.00

A0360 20701-0400 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE D

Construction Solutions Group, LLC $4.13 $10,738.00 LaRiviere Incorporated $4.00 $10,400.00 Engineer's Estimate 2,600 SQYD $4.00 $10,400.00

A0380 20820-0000 DEWATERING

Construction Solutions Group, LLC Lump Sum $61,000.00 LaRiviere Incorporated Lump Sum $60,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

A0400 30202-2000 ROADWAY AGGREGATE, METHOD 2

Construction Solutions Group, LLC $49.50 $569,250.00 LaRiviere Incorporated $42.00 $483,000.00 Engineer's Estimate 11,500 TON $40.00 $460,000.00

A0420 30302-1000 DITCH RECONDITIONING

Construction Solutions Group, LLC $27.50 $16,500.00 LaRiviere Incorporated $17.00 $10,200.00 Engineer's Estimate 600 LNFT $13.00 $7,800.00

A0440 40301-0000 ASPHALT CONCRETE PAVEMENT

Construction Solutions Group, LLC $231.00 $693,000.00 LaRiviere Incorporated $350.00 $1,050,000.00 Engineer's Estimate 3,000 TON $165.00 $495,000.00

6 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0460 41201-0000 TACK COAT

Construction Solutions Group, LLC $3,850.00 $21,175.00 LaRiviere Incorporated $1,500.00 $8,250.00 Engineer's Estimate 5.5 TON $1,100.00 $6,050.00

A0480 60210-0400 END SECTION FOR 12-INCH PIPE CULVERT

Construction Solutions Group, LLC $1,023.00 $10,230.00 LaRiviere Incorporated $500.00 $5,000.00 Engineer's Estimate 10 EACH $450.00 $4,500.00

A0500 60220-0000 PRECAST REINFORCED CONCRETE BOX CULVERT (20 FEET SPAN, 7.6 FEET RISE 3-SIDED)

Construction Solutions Group, LLC $6,325.00 $316,250.00 LaRiviere Incorporated $7,000.00 $350,000.00 Engineer's Estimate 50 LNFT $11,500.00 $575,000.00

A0520 60406-0000 INLET ADJUSTMENT

Construction Solutions Group, LLC $4,400.00 $8,800.00 LaRiviere Incorporated $1,200.00 $2,400.00 Engineer's Estimate 2 EACH $1,500.00 $3,000.00

A0540 60704-0000 CLEANING CULVERT IN PLACE

Construction Solutions Group, LLC $522.50 $4,180.00 LaRiviere Incorporated $900.00 $7,200.00 Engineer's Estimate 8 EACH $2,000.00 $16,000.00

A0560 61108-1000 ADJUST WATER VALVE

Construction Solutions Group, LLC $660.00 $3,300.00 LaRiviere Incorporated $700.00 $3,500.00 Engineer's Estimate 5 EACH $950.00 $4,750.00

A0580 61901-0553 FENCE, BARB-LESS WIRE, 4 STRAND

Construction Solutions Group, LLC $17.60 $59,840.00 LaRiviere Incorporated $45.00 $153,000.00 Engineer's Estimate 3,400 LNFT $8.00 $27,200.00

7 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0585 61901-1300 FENCE, CHAIN LINK (TEMPORARY)

Construction Solutions Group, LLC $17.60 $1,760.00 LaRiviere Incorporated $0.00 $0.00 Engineer's Estimate 100 LNFT $40.00 $4,000.00

A0590 61902-2700 GATE, CHAIN LINK (TEMPORARY)

Construction Solutions Group, LLC $1,760.00 $1,760.00 LaRiviere Incorporated $0.00 $0.00 Engineer's Estimate 1 EACH $4,000.00 $4,000.00

A0595 61920-2000 REMOVE AND RESET GATE

Construction Solutions Group, LLC $2,062.50 $2,062.50 LaRiviere Incorporated $0.00 $0.00 Engineer's Estimate 1 EACH $1,750.00 $1,750.00

A0596 61921-1000 REMOVE AND RESET FENCE

Construction Solutions Group, LLC $56.10 $5,610.00 LaRiviere Incorporated $0.00 $0.00 Engineer's Estimate 100 LNFT $85.00 $8,500.00

A0600 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY

Construction Solutions Group, LLC $170.50 $4,092.00 LaRiviere Incorporated $200.00 $4,800.00 Engineer's Estimate 24 HOUR $200.00 $4,800.00

A0620 62201-0600 BACKHOE LOADER, 8 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 30-INCH WIDTH

Construction Solutions Group, LLC $159.50 $3,828.00 LaRiviere Incorporated $300.00 $7,200.00 Engineer's Estimate 24 HOUR $185.00 $4,440.00

A0640 62201-3400 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY WITH THUMB ATTACHMENT

Construction Solutions Group, LLC $225.50 $5,412.00 LaRiviere Incorporated $300.00 $7,200.00 Engineer's Estimate 24 HOUR $250.00 $6,000.00

UDPATED

rebekah.webb Cross-Out rebekah.webb Cross-Out rebekah.webb Cross-Out rebekah.webb Cross-Out rebekah.webb Cross-Out

8 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0660 62301-0000 GENERAL LABOR

Construction Solutions Group, LLC $99.00 $2,376.00 LaRiviere Incorporated $125.00 $3,000.00 Engineer's Estimate 24 HOUR $100.00 $2,400.00

A0680 62401-0300 FURNISHING AND PLACING TOPSOIL, 4-INCH DEPTH

Construction Solutions Group, LLC $16.50 $6,600.00 LaRiviere Incorporated $21.00 $8,400.00 Engineer's Estimate 400 SQYD $12.50 $5,000.00

A0700 62502-0000 TURF ESTABLISHMENT

Construction Solutions Group, LLC $4.13 $1,652.00 LaRiviere Incorporated $9.00 $3,600.00 Engineer's Estimate 400 SQYD $11.50 $4,600.00

A0720 63308-3000 OBJECT MARKER, TYPE 3

Construction Solutions Group, LLC $550.00 $2,200.00 LaRiviere Incorporated $450.00 $1,800.00 Engineer's Estimate 4 EACH $400.00 $1,600.00

A0740 63316-1000 REMOVE AND RESET SIGN

Construction Solutions Group, LLC $352.00 $15,840.00 LaRiviere Incorporated $300.00 $13,500.00 Engineer's Estimate 45 EACH $450.00 $20,250.00

A0760 63316-2000 REMOVE AND RESET DELINEATOR

Construction Solutions Group, LLC $115.50 $231.00 LaRiviere Incorporated $250.00 $500.00 Engineer's Estimate 2 EACH $150.00 $300.00

A0780 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (YELLOW)

Construction Solutions Group, LLC $0.28 $5,964.00 LaRiviere Incorporated $9.00 $191,700.00 Engineer's Estimate 21,300 LNFT $0.20 $4,260.00

9 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0800 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (WHITE)

Construction Solutions Group, LLC $0.28 $14,056.00 LaRiviere Incorporated $9.00 $451,800.00 Engineer's Estimate 50,200 LNFT $0.20 $10,040.00

A0820 63401-0400 PAVEMENT MARKINGS, TYPE B, BROKEN (YELLOW)

Construction Solutions Group, LLC $0.28 $1,120.00 LaRiviere Incorporated $9.00 $36,000.00 Engineer's Estimate 4,000 LNFT $0.20 $800.00

A0840 63403-0900 PAVEMENT MARKINGS, TYPE I

Construction Solutions Group, LLC $3.85 $308.00 LaRiviere Incorporated $100.00 $8,000.00 Engineer's Estimate 80 SQFT $7.00 $560.00

A0860 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3 (8 FEET WIDE)

Construction Solutions Group, LLC $115.50 $1,155.00 LaRiviere Incorporated $1,500.00 $15,000.00 Engineer's Estimate 10 EACH $200.00 $2,000.00

A0880 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM

Construction Solutions Group, LLC $23.10 $3,003.00 LaRiviere Incorporated $30.00 $3,900.00 Engineer's Estimate 130 EACH $25.00 $3,250.00

A0900 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B

Construction Solutions Group, LLC $16.50 $165.00 LaRiviere Incorporated $22,000.00 $220,000.00 Engineer's Estimate 10 EACH $65.00 $650.00

A0920 63502-1700 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE C

Construction Solutions Group, LLC $16.50 $115.50 LaRiviere Incorporated $22,000.00 $154,000.00 Engineer's Estimate 7 EACH $80.00 $560.00

10 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0940 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN

Construction Solutions Group, LLC $27,500.00 $55,000.00 LaRiviere Incorporated $13,500.00 $27,000.00 Engineer's Estimate 2 EACH $9,000.00 $18,000.00

A0960 63503-0700 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS

Construction Solutions Group, LLC $2.20 $2,420.00 LaRiviere Incorporated $4.00 $4,400.00 Engineer's Estimate 1,100 LNFT $3.00 $3,300.00

A0980 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

Construction Solutions Group, LLC $23.10 $10,395.00 LaRiviere Incorporated $9.00 $4,050.00 Engineer's Estimate 450.0 SQFT $12.00 $5,400.00

A1000 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER

Construction Solutions Group, LLC $58.30 $326,480.00 LaRiviere Incorporated $100.00 $560,000.00 Engineer's Estimate 5,600 HOUR $85.00 $476,000.00

A1020 63507-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR

Construction Solutions Group, LLC $588.50 $82,390.00 LaRiviere Incorporated $600.00 $84,000.00 Engineer's Estimate 140 DAY $1,300.00 $182,000.00

A1040 63507-0700 TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR

Construction Solutions Group, LLC $638.00 $102,080.00 LaRiviere Incorporated $125.00 $20,000.00 Engineer's Estimate 160 DAY $1,100.00 $176,000.00

A1060 63701-0000 FIELD OFFICE

Construction Solutions Group, LLC $132,000.00 $132,000.00 LaRiviere Incorporated $25,000.00 $25,000.00 Engineer's Estimate 1 EACH $19,500.00 $19,500.00

11 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1080 64502-0000 LOCATE UTILITIES (POTHOLING)

Construction Solutions Group, LLC $412.50 $10,312.50 LaRiviere Incorporated $500.00 $12,500.00 Engineer's Estimate 25 EACH $750.00 $18,750.00

A1100 64620-0400 REMOVE AND RESET MAILBOX

Construction Solutions Group, LLC $632.50 $18,975.00 LaRiviere Incorporated $450.00 $13,500.00 Engineer's Estimate 30 EACH $550.00 $16,500.00

A1120 64704-1600 MITIGATION, STREAMBED CHANNEL RECONSTRUCTION

Construction Solutions Group, LLC $247.50 $53,212.50 LaRiviere Incorporated $88.00 $18,920.00 Engineer's Estimate 215 CUYD $125.00 $26,875.00

Total Schedule - All Items

Construction Solutions Group, LLC $4,979,750.20 LaRiviere Incorporated $5,021,295.00 Engineer's Estimate $3,706,045.00

12 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: B

Schedule Type: Alternate

Solcitation No: 69056724B000009

Division: Western Federal Lands

State: ID County: Canyon

Federal Land: Deer Flat National Wildlife Refuge Opened at: WFLHD Vancouver, WA

Opened by: Robert Kolln

Date: 06/26/24

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

LaRiviere Incorporated ( $5,762,775.00 ) no 17564 N Dylan Ctr Rathdrum, ID 83858

Construction Solutions Group, LLC $6,229,039.90 425 Highland Ave St. Louis, MO 63122

Engineer's Estimate $4,989,175.00

UDPATED

Contracting Officer 06/28/2024

13 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: B

Schedule Type: Alternate

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

B0020 15101-0000 MOBILIZATION

LaRiviere Incorporated Lump Sum $225,000.00 Construction Solutions Group, LLC Lump Sum $829,000.00 Engineer's Estimate ALL LPSM Lump Sum $450,000.00

B0040 15201-0000 CONSTRUCTION SURVEY AND STAKING

LaRiviere Incorporated Lump Sum $18,000.00 Construction Solutions Group, LLC Lump Sum $347,500.00 Engineer's Estimate ALL LPSM Lump Sum $85,000.00

B0060 15301-0000 CONTRACTOR QUALITY CONTROL

LaRiviere Incorporated Lump Sum $60,000.00 Construction Solutions Group, LLC Lump Sum $260,000.00 Engineer's Estimate ALL LPSM Lump Sum $85,000.00

B0080 15401-0000 CONTRACTOR TESTING

LaRiviere Incorporated Lump Sum $64,000.00 Construction Solutions Group, LLC Lump Sum $77,500.00 Engineer's Estimate ALL LPSM Lump Sum $85,000.00

B0100 15501-0000 CONSTRUCTION SCHEDULE

LaRiviere Incorporated Lump Sum $17,000.00 Construction Solutions Group, LLC Lump Sum $79,480.00 Engineer's Estimate ALL LPSM Lump Sum $22,000.00

B0120 15705-0100 SOIL EROSION CONTROL, SILT FENCE

LaRiviere Incorporated $6.00 $5,400.00 Construction Solutions Group, LLC $2.64 $2,376.00 Engineer's Estimate 900 LNFT $6.00 $5,400.00

B0140 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

LaRiviere Incorporated $6.00 $138,000.00 Construction Solutions Group, LLC $3.03 $69,690.00 Engineer's Estimate 23,000 LNFT $5.00 $115,000.00

14 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: B

Schedule Type: Alternate

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

B0160 15706-0200 SOIL EROSION CONTROL, CHECK DAM (FIBER ROLL)

LaRiviere Incorporated $1,200.00 $60,000.00 Construction Solutions Group, LLC $64.90 $3,245.00 Engineer's Estimate 50 EACH $155.00 $7,750.00

B0180 15706-1100 SOIL EROSION CONTROL, INLET PROTECTION TYPE A

LaRiviere Incorporated $500.00 $5,000.00 Construction Solutions Group, LLC $129.80 $1,298.00 Engineer's Estimate 10 EACH $640.00 $6,400.00

B0200 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION EXIT

LaRiviere Incorporated $1,500.00 $3,000.00 Construction Solutions Group, LLC $18,700.00 $37,400.00 Engineer's Estimate 2 EACH $2,600.00 $5,200.00

B0220 15802-0000 WATERING FOR DUST CONTROL

LaRiviere Incorporated Lump Sum $33,000.00 Construction Solutions Group, LLC Lump Sum $49,500.00 Engineer's Estimate ALL LPSM Lump Sum $30,000.00

B0240 20101-0000 CLEARING AND GRUBBING

LaRiviere Incorporated $5,000.00 $53,500.00 Construction Solutions Group, LLC $9,900.00 $105,930.00 Engineer's Estimate 10.7 ACRE $9,000.00 $96,300.00

B0260 20301-0400 REMOVAL OF BRIDGE

LaRiviere Incorporated $70,000.00 $70,000.00 Construction Solutions Group, LLC $127,500.00 $127,500.00 Engineer's Estimate 1 EACH $65,000.00 $65,000.00

B0300 20302-0700 REMOVAL OF FENCE

LaRiviere Incorporated $9.00 $71,100.00 Construction Solutions Group, LLC $5.78 $45,662.00 Engineer's Estimate 7,900 LNFT $3.00 $23,700.00

15 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: B

Schedule Type: Alternate

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

B0320 20315-0000 SAWCUTTING PAVEMENT

LaRiviere Incorporated $4.00 $156,000.00 Construction Solutions Group, LLC $2.20 $85,800.00 Engineer's Estimate 39,000 LNFT $2.00 $78,000.00

B0340 20401-0000 ROADWAY EXCAVATION

LaRiviere Incorporated $24.00 $264,000.00 Construction Solutions Group, LLC $49.50 $544,500.00 Engineer's Estimate 11,000 CUYD $30.00 $330,000.00

B0360 20701-0400 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE D

LaRiviere Incorporated $6.00 $15,600.00 Construction Solutions Group, LLC $4.13 $10,738.00 Engineer's Estimate 2,600 SQYD $4.00 $10,400.00

B0380 20820-0000 DEWATERING

LaRiviere Incorporated Lump Sum $50,000.00 Construction Solutions Group, LLC Lump Sum $61,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

B0400 30202-2000 ROADWAY AGGREGATE, METHOD 2

LaRiviere Incorporated $42.00 $756,000.00 Construction Solutions Group, LLC $49.50 $891,000.00 Engineer's Estimate 18,000 TON $40.00 $720,000.00

B0420 30302-1000 DITCH RECONDITIONING

LaRiviere Incorporated $21.00 $14,700.00 Construction Solutions Group, LLC $27.50 $19,250.00 Engineer's Estimate 700 LNFT $13.00 $9,100.00

B0440 40301-0000 ASPHALT CONCRETE PAVEMENT

LaRiviere Incorporated $300.00 $1,350,000.00 Construction Solutions Group, LLC $231.00 $1,039,500.00 Engineer's Estimate 4,500 TON $165.00 $742,500.00

16 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: B

Schedule Type: Alternate

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

B0460 41201-0000 TACK COAT

LaRiviere Incorporated $1,500.00 $12,000.00 Construction Solutions Group, LLC $3,850.00 $30,800.00 Engineer's Estimate 8.0 TON $1,100.00 $8,800.00

B0480 41801-1000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 1

LaRiviere Incorporated $125.00 $2,125.00 Construction Solutions Group, LLC $198.00 $3,366.00 Engineer's Estimate 17.0 SQYD $420.00 $7,140.00

B0500 41801-2000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 2

LaRiviere Incorporated $300.00 $51,300.00 Construction Solutions Group, LLC $77.00 $13,167.00 Engineer's Estimate 171.0 SQYD $250.00 $42,750.00

B0520 60210-0400 END SECTION FOR 12-INCH PIPE CULVERT

LaRiviere Incorporated $1,500.00 $18,000.00 Construction Solutions Group, LLC $1,023.00 $12,276.00 Engineer's Estimate 12 EACH $450.00 $5,400.00

B0540 60210-0600 END SECTION FOR 18-INCH PIPE CULVERT

LaRiviere Incorporated $1,200.00 $2,400.00 Construction Solutions Group, LLC $1,155.00 $2,310.00 Engineer's Estimate 2 EACH $550.00 $1,100.00

B0560 60220-0000 PRECAST REINFORCED CONCRETE BOX CULVERT (20 FEET SPAN, 7.6 FEET RISE 3-SIDED)

LaRiviere Incorporated $8,000.00 $400,000.00 Construction Solutions Group, LLC $6,325.00 $316,250.00 Engineer's Estimate 50 LNFT $11,500.00 $575,000.00

B0580 60405-0000 MANHOLE ADJUSTMENT (WATER)

LaRiviere Incorporated $1,200.00 $3,600.00 Construction Solutions Group, LLC $1,980.00 $5,940.00 Engineer's Estimate 3 EACH $4,300.00 $12,900.00

17 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: B

Schedule Type: Alternate

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

B0600 60406-0000 INLET ADJUSTMENT

LaRiviere Incorporated $1,700.00 $3,400.00 Construction Solutions Group, LLC $4,400.00 $8,800.00 Engineer's Estimate 2 EACH $1,500.00 $3,000.00

B0620 60704-0000 CLEANING CULVERT IN PLACE

LaRiviere Incorporated $1,500.00 $18,000.00 Construction Solutions Group, LLC $341.00 $4,092.00 Engineer's Estimate 12 EACH $2,000.00 $24,000.00

B0640 61108-1000 ADJUST WATER VALVE

LaRiviere Incorporated $600.00 $4,800.00 Construction Solutions Group, LLC $880.00 $7,040.00 Engineer's Estimate 8 EACH $950.00 $7,600.00

B0660 61901-0553 FENCE, BARB-LESS WIRE, 4 STRAND

LaRiviere Incorporated $25.00 $85,000.00 Construction Solutions Group, LLC $17.60 $59,840.00 Engineer's Estimate 3,400 LNFT $8.00 $27,200.00

B0665 61901-1300 FENCE, CHAIN LINK (TEMPORARY)

LaRiviere Incorporated $0.00 $0.00 Construction Solutions Group, LLC $17.60 $1,760.00 Engineer's Estimate 100 LNFT $40.00 $4,000.00

B0670 61902-2700 GATE, CHAIN LINK (TEMPORARY)

LaRiviere Incorporated $0.00 $0.00 Construction Solutions Group, LLC $1,760.00 $1,760.00 Engineer's Estimate 1 EACH $4,000.00 $4,000.00

B0675 61920-2000 REMOVE AND RESET GATE

LaRiviere Incorporated $0.00 $0.00 Construction Solutions Group, LLC $2,062.50 $2,062.50 Engineer's Estimate 1 EACH $1,750.00 $1,750.00

UDPATED

rebekah.webb Cross-Out rebekah.webb Cross-Out

18 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: B

Schedule Type: Alternate

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

B0676 61921-1000 REMOVE AND RESET FENCE

LaRiviere Incorporated $0.00 $0.00 Construction Solutions Group, LLC $56.10 $5,610.00 Engineer's Estimate 100 LNFT $85.00 $8,500.00

B0680 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY

LaRiviere Incorporated $200.00 $8,000.00 Construction Solutions Group, LLC $170.50 $6,820.00 Engineer's Estimate 40 HOUR $200.00 $8,000.00

B0700 62201-0600 BACKHOE LOADER, 8 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 30-INCH WIDTH

LaRiviere Incorporated $300.00 $12,000.00 Construction Solutions Group, LLC $159.50 $6,380.00 Engineer's Estimate 40 HOUR $185.00 $7,400.00

B0720 62201-3400 HYDRAULIC EXCAVATOR, 1 CUBIC YARD MINIMUM CAPACITY WITH THUMB ATTACHMENT

LaRiviere Incorporated $300.00 $12,000.00 Construction Solutions Group, LLC $231.00 $9,240.00 Engineer's Estimate 40 HOUR $250.00 $10,000.00

B0740 62301-0000 GENERAL LABOR

LaRiviere Incorporated $125.00 $5,000.00 Construction Solutions Group, LLC $99.00 $3,960.00 Engineer's Estimate 40 HOUR $100.00 $4,000.00

B0760 62401-0300 FURNISHING AND PLACING TOPSOIL, 4-INCH DEPTH

LaRiviere Incorporated $30.00 $12,000.00 Construction Solutions Group, LLC $16.50 $6,600.00 Engineer's Estimate 400 SQYD $12.50 $5,000.00

B0780 62502-0000 TURF ESTABLISHMENT

LaRiviere Incorporated $7.00 $2,800.00 Construction Solutions Group, LLC $4.13 $1,652.00 Engineer's Estimate 400 SQYD $11.50 $4,600.00

UDPATED

19 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: B

Schedule Type: Alternate

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

B0800 63308-3000 OBJECT MARKER, TYPE 3

LaRiviere Incorporated $100.00 $400.00 Construction Solutions Group, LLC $550.00 $2,200.00 Engineer's Estimate 4 EACH $400.00 $1,600.00

B0820 63316-1000 REMOVE AND RESET SIGN

LaRiviere Incorporated $200.00 $11,000.00 Construction Solutions Group, LLC $352.00 $19,360.00 Engineer's Estimate 55 EACH $450.00 $24,750.00

B0840 63316-2000 REMOVE AND RESET DELINEATOR

LaRiviere Incorporated $500.00 $1,000.00 Construction Solutions Group, LLC $115.50 $231.00 Engineer's Estimate 2 EACH $150.00 $300.00

B0860 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (YELLOW)

LaRiviere Incorporated $3.00 $88,500.00 Construction Solutions Group, LLC $0.28 $8,260.00 Engineer's Estimate 29,500 LNFT $0.20 $5,900.00

B0880 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID (WHITE)

LaRiviere Incorporated $3.00 $238,500.00 Construction Solutions Group, LLC $0.28 $22,260.00 Engineer's Estimate 79,500 LNFT $0.20 $15,900.00

B0900 63401-0400 PAVEMENT MARKINGS, TYPE B, BROKEN (YELLOW)

LaRiviere Incorporated $2.00 $19,000.00 Construction Solutions Group, LLC $0.28 $2,660.00 Engineer's Estimate 9,500 LNFT $0.20 $1,900.00

B0920 63403-0900 PAVEMENT MARKINGS, TYPE I

LaRiviere Incorporated $2.00 $400.00 Construction Solutions Group, LLC $3.85 $770.00 Engineer's Estimate 200 SQFT $7.00 $1,400.00

20 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: B

Schedule Type: Alternate

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

B0940 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3 (8 FEET WIDE)

LaRiviere Incorporated $1,500.00 $15,000.00 Construction Solutions Group, LLC $115.50 $1,155.00 Engineer's Estimate 10 EACH $200.00 $2,000.00

B0960 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM

LaRiviere Incorporated $90.00 $11,700.00 Construction Solutions Group, LLC $23.10 $3,003.00 Engineer's Estimate 130 EACH $25.00 $3,250.00

B0980 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B

LaRiviere Incorporated $11,200.00 $112,000.00 Construction Solutions Group, LLC $18.70 $187.00 Engineer's Estimate 10 EACH $65.00 $650.00

B1000 63502-1700 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE C

LaRiviere Incorporated $11,200.00 $78,400.00 Construction Solutions Group, LLC $18.70 $130.90 Engineer's Estimate 7 EACH $80.00 $560.00

B1020 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN

LaRiviere Incorporated $15,000.00 $30,000.00 Construction Solutions Group, LLC $27,500.00 $55,000.00 Engineer's Estimate 2 EACH $9,000.00 $18,000.00

B1040 63503-0700 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS

LaRiviere Incorporated $1.50 $1,650.00 Construction Solutions Group, LLC $2.31 $2,541.00 Engineer's Estimate 1,100 LNFT $3.00 $3,300.00

B1060 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

LaRiviere Incorporated $21.00 $9,450.00 Construction Solutions Group, LLC $23.10 $10,395.00 Engineer's Estimate 450.0 SQFT $12.00 $5,400.00

21 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: B

Schedule Type: Alternate

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

B1080 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER

LaRiviere Incorporated $125.00 $900,000.00 Construction Solutions Group, LLC $59.40 $427,680.00 Engineer's Estimate 7,200 HOUR $85.00 $612,000.00

B1100 63507-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR

LaRiviere Incorporated $300.00 $54,000.00 Construction Solutions Group, LLC $577.50 $103,950.00 Engineer's Estimate 180 DAY $1,300.00 $234,000.00

B1120 63507-0700 TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR

LaRiviere Incorporated $150.00 $30,000.00 Construction Solutions Group, LLC $638.00 $127,600.00 Engineer's Estimate 200 DAY $1,100.00 $220,000.00

B1140 63701-0000 FIELD OFFICE

LaRiviere Incorporated $10,000.00 $10,000.00 Construction Solutions Group, LLC $158,400.00 $158,400.00 Engineer's Estimate 1 EACH $19,500.00 $19,500.00

B1160 64502-0000 LOCATE UTILITIES (POTHOLING)

LaRiviere Incorporated $1,500.00 $37,500.00 Construction Solutions Group, LLC $412.50 $10,312.50 Engineer's Estimate 25 EACH $750.00 $18,750.00

B1180 64620-0400 REMOVE AND RESET MAILBOX

LaRiviere Incorporated $500.00 $17,500.00 Construction Solutions Group, LLC $632.50 $22,137.50 Engineer's Estimate 35 EACH $550.00 $19,250.00

B1200 64704-1600 MITIGATION, STREAMBED CHANNEL RECONSTRUCTION

LaRiviere Incorporated $70.00 $15,050.00 Construction Solutions Group, LLC $247.50 $53,212.50 Engineer's Estimate 215 CUYD $125.00 $26,875.00

22 out of 22

Project No: ID FLAP Canyon MULTI(1)

Project Name: Indiana and Orchard Shared Roadway

Schedule: B

Schedule Type: Alternate

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Total Schedule - All Items

LaRiviere Incorporated $5,762,775.00 Construction Solutions Group, LLC $6,229,039.90 Engineer's Estimate $4,989,175.00

2024-06-28T09:16:34-0700
DEAN ALAN UMATHUM
2024-06-28T09:14:52-0700
DEAN ALAN UMATHUM

File details come from the government source that posted it. Updated .