QA_06-18-2024.pdf
PDF 98 KB Posted
- Solicitation number
- 69056724B000009
About this file
This document contains a series of questions and answers related to a federal contract opportunity for the ID FLAP CANYON MULTI(1), Indiana and Orchard Shared Roadway project. The key details are:
The contract opportunity is an Invitation for Bidders (IFB) issued by the Department of Transportation Federal Highway Administration. It includes two bid schedules, with only one schedule to be awarded. The IFB, plans, physical data, and construction contract administration documents are provided as attachments.
The questions cover topics such as the contracting officer's representative, dewatering requirements, installation of the box culvert during irrigation season, and pay items for SWPPP management. The government provides responses clarifying the requirements, referencing relevant sections of the specifications. The government also indicates they will not evaluate proposed design changes before contract award.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No.ID FLAP CANYON MULTI(1)
Project: Indiana and Orchard Shared Roadway
# General Technical Question Answer Date
1 X I am looking for the contact information of the COR on the project Indiana and Orchard
Shared Roadway.
The Government has not appointed a COR at this time. 6/4/24
2 X What is the intention of the dewatering item? We are assuming this item is for dewatering for the demo/install of the Box Culvert.
see subsection 602.03 and Subsection 209.06 of the FP‐14 6/18/24
3 X Please confirm if the contractor is to plan to install the box culvert while irrigation water is off (October‐April) or if the intent is to bypass the canal and install the culvert while irrigation water is on.
see Sub‐section 108.01(b) of the SCR's. 6/18/24
4 X Typically, there is an item for filing the SWPPP, inspections, etc… On this contract there are only items for install of BMP’s. Is there a pay item where the management of the
SWPPP is intended to fall under?
No. See FP‐14 Subsection 109.05, Scope of Payment 6/18/24
5 X For the concrete box culvert, would a cast‐in place method be accepted instead of precast?
The Government will not be evaluating proposed design changes before contract award. Please submit bids according to the solicitation documents.
6/18/24
Check General or Technical