BidSum_ID FLAP CANYON MULTI(1).pdf
PDF 101 KB Posted
- Solicitation number
- 69056724B000009
About this file
This document is a Bid Opening Summary for Solicitation No. 69056724B000009 related to the "ID FLAP CANYON MULTI(1), Indiana and Orchard Shared Roadway" project.
The summary indicates that two bids were received for this project, which is divided into two bid schedules. The low bidder for Schedule A was Construction Solutions Group, LLC with a bid of $4,979,750.20, and the low bidder for Schedule B was LaRiviere Incorporated with a bid of $5,763,275.00. The Engineer's Estimate for the overall project was $3,706,045.00 for Schedule A and $4,989,175.00 for Schedule B.
The federal contract opportunity is an Invitation for Bidders (IFB) issued by the Department of Transportation Federal Highway Administration. The IFB, Plans, Physical Data, and Construction Contract Administration Document are available as attachments. Only one schedule will be awarded under this solicitation.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID OPENING SUMMARY
Solicitation No. 69056724B000009 Bid Opening Date 06/26/2024 Time 2:00 p.m.
Project Name/Number: ID FLAP CANYON MULTI(1), Indiana and Orchard Shared Roadway
OFFER RECEIVED
REC'D
BY
CONTRACTOR
DATE
TIME
Schedule A Schedule B
1.
06/25/2024 Mod 06/26/2024
3:07pm Mod 10:53am
RW
Mod
RW
Construction Solutions Group, LLC
$4,979,750.20 $6,229,039.90
2.
06/26/2024 1:59pm RW LaRiviere Incorporated
$5,022,045.00 $5,763,275.00
3.
4.
5.
6.
7.
8.
9.
10.
Engineer’s Estimate
$3,706,045.00 $4,989,175.00
LOW BIDDER'S
PHONE NUMBER: Schedule A- Construction Solutions Group: 314-596-7213 Schedule B- LaRiviere Incorporated: 208-683-2646
Attendance: 14 WFLHD staff; 1 public attendee
Bid Opening Officer: Robert Kolln Assistant: Rebekah Webb
File details come from the government source that posted it. Updated .