This solicitation is for a construction and renovation project at the Jesse Brown VA Medical Center in Chicago, Illinois. The Department of Veterans Affairs Veterans Health Administration Great Lakes Acquisition Center requires a contractor to provide all labor, materials, tools, and supervision necessary to construct and renovate a fully functional Emergency Department Observation Unit. The scope of work includes all tasks detailed in the solicitation. Offerors should price their proposals accordingly and submit responses by the stated deadline.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The Emergency Department Renovation Jesse Brown VAMC, Chicago IL 60612
VA Contract No.: 36C25218D0191 Delivery Order: 36C25219N0275
Project # 573-15-160
For the Department of Veterans Affairs
Great Lakes Acquisition Center (NCO 12) Captain James A. Lovell, FHCC
3001 Green Bay Rd., Bldg. 1, Rm 329 North Chicago, IL 60064-3048
Project Manual Volume 2
DIVISIONS 21-48
100% Construction Documents 5/30/2020
GUIDON-CMTA JV.
lstoy Luke - IL Stamp
PROJECT CONTACTS:
OWNER:
Jesse Brown VA Medical Center Engineering Svc 820 S. Damen Ave Chicago IL 60612
ISSUE DATE: May 30, 2020
Jesse Brown VAMC 06-01-15 VA: 537-15-160 Emergency Department Renovations 100 % Construction Documents Chicago, IL 60612 May 30, 2020
21 13 13 - 1
SECTION 21 13 13
WET-PIPE SPRINKLER SYSTEMS
PART 1 - GENERAL
1.1 DESCRIPTION
A. Design, installation and testing shall be in acc ordance with
NFPA 13.
B. Modification of the existing sprinkler system as indicated on the drawings and as further required by these specifica tions.
1.2 RELATED WORK
A. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, A ND SAMPLES.
B. Section 07 84 00, FIRESTOPPING.
C. Section 09 91 00, PAINTING.
D. Section 22 05 23, GENERAL-DUTY VALVES FOR PLUMBI NG PIPING.
E. Section 28 31 00, FIRE DETECTION AND ALARM.
1.3 DESIGN CRITERIA
A. Design Basis Information: Provide design, materi als, equipment, installation, inspection, and testing of the automa tic sprinkler system in accordance with the requirements of NFPA 13.
1. Perform hydraulic calculations in accordance wit h NFPA 13 utilizing the Area/Density method. Do not restrict design ar ea reductions permitted for using quick response sprinklers throu ghout by the required use of standard response sprinklers in the areas identified in this section.
2. Sprinkler Protection: Sprinkler hazard classific ations shall be in accordance with NFPA 13. The hazard classification examples of uses and conditions identified in the Annex of NFPA 13 s hall be mandatory for areas not listed below. Request clarification f rom the
Government for any hazard classification not identi fied. To determining spacing and sizing, apply the following coverage classifications:
a. Light Hazard Occupancies: Patient care, treatmen t, and customary access areas.
b. Ordinary Hazard Group 1 Occupancies: Laboratorie s, Mechanical
Equipment Rooms, Transformer Rooms, Electrical Swit chgear Rooms, Electric Closets, and Repair Shops.
c. Ordinary Hazard Group 2 Occupancies: Storage roo ms, trash rooms, clean and soiled linen rooms, pharmacy and associat ed storage, 21 13 13 - 2 laundry, kitchens, kitchen storage areas, retail st ores, retail store storage rooms, storage areas, building manage ment storage, boiler plants, energy centers, warehouse spaces, fi le storage areas for the entire area of the space up to 140 sq uare meters
(1500 square feet) and Supply Processing and Distri bution (SPD).
3. Hydraulic Calculations: Calculated demand includ ing hose stream requirements shall fall no less than 10 percent bel ow the available water supply curve.
4. Water Supply: Base water supply on a flow test o f:
a. Location: Stair #5, Damen Building
b. Static pressure: 135 psi
c. Residual pressure: 90 psi
d. Flow: 1,342 gpm
e. Date: May 26, 2020
1.4 SUBMITTALS
A. Submit as one package in accordance with Section 01 33 23, SHOP
DRAWINGS, PRODUCT DATA, AND SAMPLES. Prepare detail ed working drawings that are signed by a NICET Level III or Level IV Sp rinkler Technician or stamped by a Registered Professional Engineer li censed in the field of Fire Protection Engineering. As the Government r eview is for technical adequacy only, the installer remains resp onsible for correcting any conflicts with other trades and buil ding construction that arise during installation. Partial submittals will not be accepted. Material submittals shall be approved pri or to the purchase or delivery to the job site. Suitably bind submitta ls in notebooks or binders and provide an index referencing the approp riate specification section. In addition to the hard copies, provide su bmittal items in
Paragraphs 1.4(A)1 through 1.4(A)5 electronically i n pdf format on a compact disc or as directed by the COR. Submittals shall include, but not be limited to, the following:
1. Qualifications:
a. Provide a copy of the installing contractors fir e sprinkler and state contractor’s license.
b. Provide a copy of the NICET certification for th e NICET Level III or Level IV Sprinkler Technician who prepared and s igned the detailed working drawings unless the drawings are s tamped by a
21 13 13 - 3
Registered Professional Engineer licensed in the fi eld of Fire
Protection Engineering.
c. Provide documentation showing that the installer has been actively and successfully engaged in the installati on of commercial automatic sprinkler systems for the past ten years.
2. Drawings: Submit detailed 1:100 (1/8 inch) scale (minimum) working drawings conforming to the Plans and Calculations c hapter of NFPA
13. Drawings shall include graphical scales that al low the user to determine lengths when the drawings are reduced in size. Include a plan showing the piping to the water supply test lo cation.
3. Manufacturer’s Data Sheets: Provide data sheets for all materials and equipment proposed for use on the system. Inclu de listing information and installation instructions in data s heets. Where data sheets describe items in addition to those proposed to be used for the system, clearly identify the proposed items on the sheet.
4. Calculation Sheets:
a. Submit hydraulic calculation sheets in tabular f orm conforming to the requirements and recommendations of the Plans a nd
Calculations chapter of NFPA 13.
5. Valve Charts: Provide a valve chart that identif ies the location of each control valve. Coordinate nomenclature and id entification of control valves with COR. Where existing nomenclatu re does not exist, the chart shall include no less than the fol lowing: Tag ID
No., Valve Size, Service (control valve, main drain , aux. drain, inspectors test valve, etc.), and Location.
6. Final Document Submittals: Provide as-built draw ings, testing and maintenance instructions in accordance with the req uirements in
Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. In addition, submittals shall include, but not be limi ted to, the following:
a. A complete set of as-built drawings showing the installed system with the specific interconnections between the syst em switches and the fire alarm equipment. Provide a complete s et in the formats as follows. Submit items 2 and 3 below on a compact disc or as directed by the COR.
1) One full size (or size as directed by the COR) p rinted copy.
2) One complete set in electronic pdf format.
21 13 13 - 4
3) One complete set in AutoCAD format or a format a s directed by the COR.
b. Material and Testing Certificate: Upon completio n of the sprinkler system installation or any partial sectio n of the system, including testing and flushing, provide a c opy of a completed Material and Testing Certificate as indic ated in NFPA
13. Certificates shall be provided to document all parts of the installation.
c. Operations and Maintenance Manuals that include step-by-step procedures required for system startup, operation, shutdown, and routine maintenance and testing. The manuals shall include the manufacturer's name, model number, parts list, and tools that should be kept in stock by the owner for routine ma intenance, including the name of a local supplier, simplified wiring and controls diagrams, troubleshooting guide, and recom mended service organization, including address and telephone numbe r, for each item of equipment.
d. One paper copy of the Material and Testing Certi ficates and the
Operations and Maintenance Manuals above shall be p rovided in a binder. In addition, these materials shall be prov ided in pdf format on a compact disc or as directed by the COR.
e. Provide one additional copy of the Operations an d Maintenance
Manual covering the system in a flexible protective cover and mount in an accessible location adjacent to the ris er or as directed by the COR.
1.5 QUALITY ASSURANCE
A. Installer Reliability: The installer shall posse ss a valid State of
Illinois fire sprinkler contractor's license. The i nstaller shall have been actively and successfully engaged in the insta llation of commercial automatic sprinkler systems for the past ten years.
B. Materials and Equipment: All equipment and devic es shall be of a make and type listed by UL or approved by FM, or other n ationally recognized testing laboratory for the specific purpose for whi ch it is used. All materials, devices, and equipment shall be approved by the VA. All materials and equipment shall be free from defect. All materials and equipment shall be new unless specifically indicate d otherwise on the contract drawings.
21 13 13 - 5
1.6 APPLICABLE PUBLICATIONS
A. The publications listed below form a part of thi s specification to the extent referenced. The publications are referenced in the text by the basic designation only. Refer to latest editions of all publications listed below.
B. National Fire Protection Association (NFPA):
13......................Installation of Sprinkler S ystems
25......................Inspection, Testing, and Ma intenance of Water-
Based Fire Protection Systems
101.....................Life Safety Code
170.....................Fire Safety Symbols
C. Underwriters Laboratories, Inc. (UL):
Fire Protection Equipment Directory
D. Factory Mutual Engineering Corporation (FM):
Approval Guide
PART 2 - PRODUCTS
2.1 PIPING & FITTINGS
A. Piping and fittings for sprinkler systems shall be in accordance with
NFPA 13.
1. Plain-end pipe fittings with locking lugs or she ar bolts are not permitted.
2. Piping sizes 50 mm (2 inches) and smaller shall be black steel
Schedule 40 with threaded end connections.
3. Piping sizes 65 mm (2 ½ inches) and larger shall be black steel
Schedule 10 with grooved connections. Grooves in S chedule 10 piping shall be rolled grooved only.
4. Plastic piping shall not be permitted except for drain piping.
5. Flexible sprinkler hose shall be FM Approved and limited to hose with threaded end fittings with a minimum inside di ameter or 1-inch and a maximum length of 6-feet.
2.2 SPRINKLERS
A. All sprinklers shall be FM approved quick respon se except
“institutional” type sprinklers shall be permitted to be UL Listed quick response. “Institutional” type sprinklers in Mental Health and
Behavior Units shall be UL listed or FM approved qu ick response type.
Maximum break away strength shall be certified by t he manufacturer to
21 13 13 - 6 be no more than 39 kPa (85 pounds). Provide FM appr oved quick response sprinklers in all areas.
B. Temperature Ratings: In accordance with NFPA 13 except that sprinklers in elevator shafts and elevator machine rooms shall be no less than intermediate temperature rated and sprinklers in ge nerator rooms shall be no less than high temperature rated.
C. Provide sprinkler guards in accordance with NFPA 13 and when the elevation of the sprinkler head is less than 7 feet 6 inches above finished floor. The sprinkler guard shall be UL lis ted or FM approved for use with the corresponding sprinkler.
2.3 PIPE HANGERS, SUPPORTS AND RESTRAINT OF SYSTEM PIPING
A. Pipe hangers, supports, and restraint of system piping shall be in accordance with NFPA 13.
2.4 WALL, FLOOR AND CEILING PLATES
A. Provide chrome plated steel escutcheon plates.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Installation shall be accomplished by the licens ed contractor. Provide a qualified technician, experienced in the installa tion and operation of the type of system being installed, to supervise the installation and testing of the system.
B. Installation of Piping: Accurately cut pipe to m easurements established by the installer and work into place without spring ing or forcing. In any situation where bending of the pipe is required , use a standard pipe-bending template. Concealed piping in spaces t hat have finished ceilings. Where ceiling mounted equipment exists, s uch as in operating and radiology rooms, install sprinklers so as not t o obstruct the movement or operation of the equipment. Sidewall he ads may need to be utilized. In stairways, locate piping as near to th e ceiling as possible to prevent tampering by unauthorized perso nnel and to provide a minimum headroom clearance of 2250 mm (seven feet six inches). Piping shall not obstruct the minimum means of egress clea rances required by
NFPA 101. Pipe hangers, supports, and restraint of system piping shall be installed accordance with NFPA 13.
C. Welding: Conform to the requirements and recomme ndations of NFPA 13.
D. Drains: Provide drips and drains, including low point drains, in accordance with NFPA 13. Pipe drains to discharge at safe points
21 13 13 - 7 outside of the building or to sight cones attached to drains of adequate size to readily carry the full flow from e ach drain under maximum pressure. Do not provide a direct drain con nection to sewer system or discharge into sinks. Install drips and d rains where necessary and required by NFPA 13. The drain piping shall not be restricted or reduced and shall be of the same diameter as the drain collector.
E. Affix cutout disks, which are created by cutting holes in the walls of pipe for flow switches and non-threaded pipe connec tions to the respective waterflow switch or pipe connection near to the pipe from where they were cut.
F. Provide escutcheon plates for exposed piping pas sing through walls, floors or ceilings.
G. Clearances: For systems requiring seismic protec tion, piping that passes through floors or walls shall have penetrati ons sized 50 mm (2 inches) nominally larger than the penetrating pipe for pipe sizes 25 mm
(1 inch) to 90 mm (3 ½ inches) and 100 mm (4 inches ) nominally larger for penetrating pipe sizes 100 mm (4 inches) and la rger.
H. Sleeves: Provide for pipes passing through mason ry or concrete. Provide space between the pipe and the sleeve in accordance with NFPA 13. Seal this space with a UL Listed through penetration fir e stop material in accordance with Section 07 84 00, FIRESTOPPING. Whe re core drilling is used in lieu of sleeves, also seal space. Seal pene trations of walls, floors and ceilings of other types of construction, in accordance with
Section 07 84 00, FIRESTOPPING.
I. Firestopping shall be provided for all penetrati ons of fire resistance rated construction. Firestopping shall comply with Section 07 84 00, FIRESTOPPING.
J. Repairs: Repair damage to the building or equipm ent resulting from the installation of the sprinkler system by the install er at no additional expense to the Government.
K. Interruption of Service: There shall be no inter ruption of the existing sprinkler protection, water, electric, or fire alar m services without prior permission of the Contracting Officer. Contra ctor shall develop an interim fire protection program where interrupti ons involve occupied spaces. Request in writing at least one week prior to the planned interruption.
21 13 13 - 8
3.2 INSPECTION AND TEST
A. Preliminary Testing: Flush newly installed syste ms prior to performing hydrostatic tests in order to remove any debris whi ch may have been left as well as ensuring piping is unobstructed. Hy drostatically test system, including the fire department connections, as specified in NFPA
13, in the presence of the Contracting Officers Rep resentative (COR) or his designated representative. Test and flush under ground water line prior to performing these hydrostatic tests.
B. Final Inspection and Testing: Subject system to tests in accordance with NFPA 13, and when all necessary corrections ha ve been accomplished, advise COR to schedule a final inspec tion and test.
Connection to the fire alarm system shall have been in service for at least ten days prior to the final inspection, with adjustments made to prevent false alarms. Furnish all instruments, labo r and materials required for the tests and provide the services of the installation foreman or other competent representative of the in staller to perform the tests. Correct deficiencies and retest system a s necessary, prior to the final acceptance. Include the operation of a ll features of the systems under normal operations in test
3.3 INSTRUCTIONS
A. Furnish the services of a competent instructor f or not less than two hours for instructing personnel in the operation an d maintenance of the system, on the dates requested by the COR.
- - - E N D - - -
Jesse Brown VAMC 07-01-16
22 05 11 - 1
SECTION 22 05 11
COMMON WORK RESULTS FOR PLUMBING
PART 1 - GENERAL
1.1 DESCRIPTION
A. The requirements of this Section shall apply to all sections of
Division 22.
B. Definitions:
1. Exposed: Piping and equipment exposed to view in finished rooms.
C. Abbreviations/Acronyms:
1. ABS: Acrylonitrile Butadiene Styrene
2. AC: Alternating Current
3. ACR: Air Conditioning and Refrigeration
4. AI: Analog Input
5. AISI: American Iron and Steel Institute
6. AO: Analog Output
7. AWG: American Wire Gauge
8. BACnet: Building Automation and Control Network
9. BAg: Silver-Copper-Zinc Brazing Alloy
10. BAS: Building Automation System
11. BCuP: Silver-Copper-Phosphorus Brazing Alloy
12. BSG: Borosilicate Glass Pipe
13. CDA: Copper Development Association
14. C: Celsius
15. CLR: Color
16. CO: Carbon Monoxide
17. COR: Contracting Officer’s Representative
18. CPVC: Chlorinated Polyvinyl Chloride
19. CR: Chloroprene
20. CRS: Corrosion Resistant Steel
21. CWP: Cold Working Pressure
22. CxA: Commissioning Agent
23. db(A): Decibels (A weighted)
24. DDC: Direct Digital Control
25. DI: Digital Input
26. DISS: Diameter Index Safety System
27. DO: Digital Output
28. DVD: Digital Video Disc
22 05 11 - 2
29. DN: Diameter Nominal
30. DWV: Drainage, Waste and Vent
31. ECC: Engineering Control Center
32. EPDM: Ethylene Propylene Diene Monomer
33. EPT: Ethylene Propylene Terpolymer
34. ETO: Ethylene Oxide
35. F: Fahrenheit
36. FAR: Federal Acquisition Regulations
37. FD: Floor Drain
38. FED: Federal
39. FG: Fiberglass
40. FNPT: Female National Pipe Thread
41. FPM: Fluoroelastomer Polymer
42. GPM: Gallons Per Minute
43. HDPE: High Density Polyethylene
44. Hg: Mercury
45. HOA: Hands-Off-Automatic
46. HP: Horsepower
47. HVE: High Volume Evacuation
48. ID: Inside Diameter
49. IPS: Iron Pipe Size
50. Kg: Kilogram
51. kPa: Kilopascal
52. lb: Pound
53. L/s: Liters Per Second
54. L/min: Liters Per Minute
55. MAWP: Maximum Allowable Working Pressure
56. MAX: Maximum
57. MED: Medical
58. m: Meter
59. MFG: Manufacturer
60. mg: Milligram
61. mg/L: Milligrams per Liter
62. ml: Milliliter
63. mm: Millimeter
64. MIN: Minimum
65. NF: Oil Free Dry (Nitrogen)
22 05 11 - 3
66. NPTF: National Pipe Thread Female
67. NPS: Nominal Pipe Size
68. NPT: Nominal Pipe Thread
69. OD: Outside Diameter
70. OSD: Open Sight Drain
71. OS&Y: Outside Stem and Yoke
72. OXY: Oxygen
73. PBPU: Prefabricated Bedside Patient Units
74. PH: Power of Hydrogen
75. PLC: Programmable Logic Controllers
76. PP: Polypropylene
77. PPM: Parts per Million
78. PSIG: Pounds per Square Inch
79. PTFE: Polytetrafluoroethylene
80. PVC: Polyvinyl Chloride
81. PVDF: Polyvinylidene Fluoride
82. RAD: Radians
83. RO: Reverse Osmosis
84. RPM: Revolutions Per Minute
85. RTRP: Reinforced Thermosetting Resin Pipe
86. SCFM: Standard Cubic Feet Per Minute
87. SDI: Silt Density Index
88. SPEC: Specification
89. SPS: Sterile Processing Services
90. STD: Standard
91. SUS: Saybolt Universal Second
92. SWP: Steam Working Pressure
93. TEFC: Totally Enclosed Fan-Cooled
94. TFE: Tetrafluoroethylene
95. THHN: Thermoplastic High-Heat Resistant Nylon C oated Wire
96. THWN: Thermoplastic Heat & Water Resistant Nylo n Coated Wire
97. T/P: Temperature and Pressure
98. USDA: U.S. Department of Agriculture
99. V: Volt
100. VAC: Vacuum
101. VA: Veterans Administration
102. VAMC: Veterans Administration Medical Center
22 05 11 - 4
103. VAC: Voltage in Alternating Current
104. WAGD: Waste Anesthesia Gas Disposal
105. WOG: Water, Oil, Gas
1.2 RELATED WORK
A. Section 01 00 00, GENERAL REQUIREMENTS.
B. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, A ND SAMPLES.
C. Section 01 74 19, CONSTRUCTION WASTE MANAGEMENT.
D. Section 01 81 13, SUSTAINABLE CONSTRUCTION REQUI REMENTS.
E. Section 07 84 00, FIRESTOPPING.
F. Section 07 92 00, JOINT SEALANTS.
G. Section 09 91 00, PAINTING.
H. Section 22 07 11, PLUMBING INSULATION.
I. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL IN STALLATIONS.
J. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER C ONDUCTORS AND CABLES.
1.3 APPLICABLE PUBLICATIONS
A. The publications listed below shall form a part of this specification to the extent referenced. The publications are refe renced in the text by the basic designation only. Refer to the latest editions of all publications listed below.
B. American Society for Testing and Materials (ASTM ):
A36/A36M................Standard Specification for Carbon Structural
Steel
A57.....................Standard Specification for Steel Bars, Carbon, Merchant Quality, M-Grades
E84.....................Standard Test Method for Su rface Burning
Characteristics of Building Materials
E119....................Standard Test Methods for F ire Tests of
Building Construction and Materials
C. International Code Council, (ICC):
IBC.....................International Building Code
IPC.....................International Plumbing Code
D. Manufacturers Standardization Society (MSS) of t he Valve and Fittings
Industry, Inc:
SP-58...................Pipe Hangers and Supports - Materials, Design, Manufacture, Selection, Application and
Installation
22 05 11 - 5
SP-69-..................Pipe Hangers and Supports - Selection and
Application
E. Military Specifications (MIL):
P-21035B................Paint High Zinc Dust Conten t, Galvanizing
Repair (Metric)
F. National Fire Protection Association (NFPA):
51B.....................Standard for Fire Preventio n During Welding, Cutting and Other Hot Work
70......................National Electrical Code (N EC)
G. NSF International (NSF):
61......................Drinking Water System Compo nents – Health
Effects
372.....................Drinking Water System Compo nents – Lead Content
H. Department of Veterans Affairs (VA):
PG-18-10................Plumbing Design Manual
PG-18-13................Barrier Free Design Guide
1.4 SUBMITTALS
A. Submittals, including number of required copies, shall be submitted in accordance with Section 01 33 23, SHOP DRAWINGS, PR ODUCT DATA, and
SAMPLES.
B. Information and material submitted under this se ction shall be marked
"SUBMITTED UNDER SECTION 22 05 11, COMMON WORK RESULTS FOR PLUMBING",
with applicable paragraph identification.
C. Contractor shall make all necessary field measur ements and investigations to assure that the equipment and ass emblies will meet contract requirements and will fit the space availa ble.
D. If equipment is submitted which differs in arran gement from that shown, provide drawings that show the rearrangement of all associated systems.
Approval will be given only if all features of the equipment and associated systems, including accessibility, are eq uivalent to that required by the contract.
E. Prior to submitting shop drawings for approval, contractor shall certify in writing that manufacturers of all major items of equipment have each reviewed drawings and specifications, and have jointly coordinated and properly integrated their equipment and controls to provide a complete and efficient installation.
22 05 11 - 6
F. Installing Contractor shall provide lists of pre vious installations for selected items of equipment. Contact persons who wi ll serve as references, with telephone numbers and e-mail addre sses shall be submitted with the references.
G. Manufacturer's Literature and Data: Manufacturer ’s literature shall be submitted under the pertinent section rather than u nder this section.
1. Electric motor data and variable speed drive dat a shall be submitted with the driven equipment.
2. Equipment and materials identification.
3. Firestopping materials.
4. Hangers, inserts, supports and bracing. Provide load calculations for variable spring and constant support hangers.
5. Wall, floor, and ceiling plates.
H. Submittals and shop drawings for interdependent items, containing applicable descriptive information, shall be furnis hed together and complete in a group. Coordinate and properly integr ate materials and equipment in each group to provide a completely com patible and efficient installation. Final review and approvals will be made only by groups.
I. Coordination Drawings: Complete consolidated and coordinated layout drawings shall be submitted for all new systems, an d for existing systems that are in the same areas. The drawings sh all include plan views, elevations and sections of all systems and s hall be on a scale of not less than 1:32 (3/8 inch equal to one foot). Clearly identify and dimension the proposed locations of the princip al items of equipment. The drawings shall clearly show the prop osed location and adequate clearance for all equipment, controls, pip ing, pumps, valves and other items. All valves, trap primer valves, wa ter hammer arrestors, strainers, and equipment requiring servi ce shall be provided with an access door sized for the complete removal of plumbing device, component, or equipment. Equipment foundations shal l not be installed until equipment or piping layout drawings have been approved. Detailed layout drawings shall be provided for all piping sy stems. In addition, details of the following shall be provided.
1. Mechanical equipment rooms.
2. Interstitial space.
3. Hangers, inserts, supports, and bracing.
22 05 11 - 7
4. Pipe sleeves.
5. Equipment penetrations of floors, walls, ceiling s, or roofs.
J. Maintenance Data and Operating Instructions:
1. Maintenance and operating manuals in accordance with Section 01 00
00, GENERAL REQUIREMENTS, Article, INSTRUCTIONS, fo r systems and equipment. Include complete list indicating all com ponents of the systems with diagrams of the internal wiring for ea ch item of equipment.
2. Include listing of recommended replacement parts for keeping in stock supply, including sources of supply, for equi pment shall be provided. The listing shall include belts for equip ment: Belt manufacturer, model number, size and style, and dis tinguished whether of multiple belt sets.
1.5 QUALITY ASSURANCE
A. Products Criteria:
1. Standard Products: Material and equipment shall be the standard products of a manufacturer regularly engaged in the manufacture, supply and servicing of the specified products for at least 5 years.
However, digital electronics devices, software and systems such as controls, instruments, computer work station, shall be the current generation of technology and basic design that has a proven satisfactory service record of at least 5 years.
2. Equipment Service: There shall be permanent serv ice organizations, authorized and trained by manufacturers of the equi pment supplied, located within 160 km (100 miles) of the project. T hese organizations shall come to the site and provide ac ceptable service to restore operations within four hours of receipt of notification by phone, e-mail or fax in event of an emergency, s uch as the shut-down of equipment; or within 24 hours in a non-emer gency. Names, mail and e-mail addresses and phone numbers of serv ice organizations providing service under these conditions for (as ap plicable to the project): pumps, compressors, water heaters, critic al instrumentation, computer workstation and programmi ng shall be submitted for project record and inserted into the operations and maintenance manual.
22 05 11 - 8
3. All items furnished shall be free from defects t hat would adversely affect the performance, maintainability and appeara nce of individual components and overall assembly.
4. The products and execution of work specified in Division 22 shall conform to the referenced codes and standards as re quired by the specifications. Local codes and amendments enforced by the local code official shall be enforced, if required by loc al authorities such as the natural gas supplier. If the local code s are more stringent, then the local code shall apply. Any con flicts shall be brought to the attention of the Contracting Officer s Representative
(COR).
5. Multiple Units: When two or more units of materi als or equipment of the same type or class are required, these units sh all be products of one manufacturer.
6. Assembled Units: Manufacturers of equipment asse mblies, which use components made by others, assume complete responsi bility for the final assembled product.
7. Nameplates: Nameplate bearing manufacturer's nam e or identifiable trademark shall be securely affixed in a conspicuou s place on equipment, or name or trademark cast integrally wit h equipment, stamped or otherwise permanently marked on each ite m of equipment.
8. Asbestos products or equipment or materials cont aining asbestos shall not be used.
9. Bio-Based Materials: For products designated by the USDA’s Bio-
Preferred Program, provide products that meet or ex ceed USDA recommendations for bio-based content, so long as p roducts meet all performance requirements in this specifications sec tion. For more information regarding the product categories covere d by the Bio-
Preferred Program, visit http://www.biopreferred.gov .
B. Welding: Before any welding is performed, contra ctor shall submit a certificate certifying that welders comply with the following requirements:
1. Qualify welding processes and operators for pipi ng according to ASME
"Boiler and Pressure Vessel Code", Section IX, "Wel ding and Brazing
Qualifications".
2. Comply with provisions of ASME B31 series "Code for Pressure
Piping".
22 05 11 - 9
3. Certify that each welder and welding operator ha s passed American
Welding Society (AWS) qualification tests for the w elding processes involved, and that certification is current.
4. All welds shall be stamped according to the prov isions of the
American Welding Society.
C. Manufacturer's Recommendations: Where installati on procedures or any part thereof are required to be in accordance with the recommendations of the manufacturer of the material being installed , printed copies of these recommendations shall be furnished to the COR prior to installation. Installation of the item will not be allowed to proceed until the recommendations are received. Failure to furnish these recommendations can be cause for rejection of the m aterial.
D. Execution (Installation, Construction) Quality:
1. All items shall be applied and installed in acco rdance with manufacturer's written instructions. Conflicts betw een the manufacturer's instructions and the contract docume nts shall be referred to the COR for resolution. Printed copies or electronic files of manufacturer’s installation instructions s hall be provided to the COR at least 10 working days prior to commen cing installation of any item.
2. All items that require access, such as for opera ting, cleaning, servicing, maintenance, and calibration, shall be e asily and safely accessible by persons standing at floor level, or s tanding on permanent platforms, without the use of portable la dders. Examples of these items include, but are not limited to: all types of valves, filters and strainers, transmitters, and control de vices. Prior to commencing installation work, refer conflicts betwe en this requirement and contract documents to COR for resol ution.
3. Complete layout drawings shall be required by Pa ragraph, SUBMITTALS.
Construction work shall not start on any system unt il the layout drawings have been approved by VA.
4. Installer Qualifications: Installer shall be lic ensed and shall provide evidence of the successful completion of at least five projects of equal or greater size and complexity. P rovide tradesmen skilled in the appropriate trade.
22 05 11 - 10
5. If an installation is unsatisfactory to the COR, the Contractor shall correct the installation at no additional cos t or additional time to the Government.
E. Guaranty: Warranty of Construction, FAR clause 5 2.246-21.
F. Plumbing Systems: IPC, International Plumbing Co de. Unless otherwise required herein, perform plumbing work in accordanc e with the latest version of the IPC. For IPC codes referenced in the contract documents, advisory provisions shall be considered mandatory, the word “should” shall be interpreted as “shall”. Reference to the “ code official” or
“owner” shall be interpreted to mean the COR.
G. Cleanliness of Piping and Equipment Systems:
1. Care shall be exercised in the storage and handl ing of equipment and piping material to be incorporated in the work. Deb ris arising from cutting, threading and welding of piping shall be r emoved.
2. Piping systems shall be flushed, blown or pigged as necessary to deliver clean systems.
3. The interior of all tanks shall be cleaned prior to delivery and beneficial use by the Government. All piping shall be tested in accordance with the specifications and the Internat ional Plumbing
Code (IPC). All filters, strainers, fixture faucets shall be flushed of debris prior to final acceptance.
4. Contractor shall be fully responsible for all co sts, damage, and delay arising from failure to provide clean systems .
1.6 DELIVERY, STORAGE AND HANDLING
A. Protection of Equipment:
1. Equipment and material placed on the job site sh all remain in the custody of the Contractor until phased acceptance, whether or not the Government has reimbursed the Contractor for th e equipment and material. The Contractor is solely responsible for the protection of such equipment and material against any damage.
2. Damaged equipment shall be replaced with an iden tical unit as determined and directed by the COR. Such replacemen t shall be at no additional cost or additional time to the Governmen t.
3. Interiors of new equipment and piping systems sh all be protected against entry of foreign matter. Both inside and ou tside shall be cleaned before painting or placing equipment in ope ration.
22 05 11 - 11
4. Existing equipment and piping being worked on by the Contractor shall be under the custody and responsibility of th e Contractor and shall be protected as required for new work.
1.7 AS-BUILT DOCUMENTATION.
A. Submit manufacturer’s literature and data update d to include submittal review comments and any equipment substitutions.
B. Submit operation and maintenance data updated to include submittal review comments, substitutions and construction rev isions shall be inserted into a three ring binder. All aspects of s ystem operation and maintenance procedures, including piping isometrics , wiring diagrams of all circuits, a written description of system desig n, control logic, and sequence of operation shall be included in the operation and maintenance manual. The operations and maintenance manual shall include troubleshooting techniques and procedures for emerg ency situations.
Notes on all special systems or devices such as dam per and door closure interlocks shall be included. A List of recommended spare parts
(manufacturer, model number, and quantity) shall be furnished.
Information explaining any special knowledge or too ls the owner will be required to employ shall be inserted into the As-Bu ilt documentation.
C. The installing contractor shall maintain as-buil t drawings of each completed phase for verification; and, shall provid e the complete set at the time of final systems certification testing. As-built drawings are to be provided, and a copy of them on Auto-Cad version 2019 provided on compact disk or DVD. Should the install ing contractor engage the testing company to provide as-built or a ny portion thereof, it shall not be deemed a conflict of interest or br each of the ‘third party testing company’ requirement.
D. Certification documentation shall be provided pr ior to submitting the request for final inspection. The documentation sha ll include all test results, the names of individuals performing work f or the testing agency on this project, detailed procedures followe d for all tests, and a certification that all results of tests were with in limits specified.
PART 2 - PRODUCTS
2.1 MATERIALS FOR VARIOUS SERVICES
A. Solder or flux containing lead shall not be used with copper pipe.
B. Material or equipment containing a weighted aver age of greater than
0.25 percent lead shall not be used in any potable water system
22 05 11 - 12 intended for human consumption, and shall be certif ied in accordance with NSF 61 or NSF 372.
C. In-line devices such as water meters, building v alves, check valves, stops, valves, fittings, tanks and backflow prevent ers shall comply with NSF 61 and NSF 372.
D. End point devices such as drinking fountains, la vatory faucets, kitchen and bar faucets, ice makers supply stops, and end-p oint control valves used to dispense drinking water must meet requireme nts of NSF 61 and
NSF 372.
2.2 FACTORY-ASSEMBLED PRODUCTS
A. Standardization of components shall be maximized to reduce spare part requirements.
B. Manufacturers of equipment assemblies that inclu de components made by others shall assume complete responsibility for fin al assembled unit.
1. All components of an assembled unit need not be products of same manufacturer.
2. Constituent parts that are alike shall be produc ts of a single manufacturer.
3. Components shall be compatible with each other a nd with the total assembly for intended service.
4. Contractor shall guarantee performance of assemb lies of components, and shall repair or replace elements of the assembl ies as required to deliver specified performance of the complete as sembly at no additional cost or time to the Government.
C. Components of equipment shall bear manufacturer' s name and trademark, model number, serial number and performance data on a name plate securely affixed in a conspicuous place, or cast in tegral with, stamped or otherwise permanently marked upon the components of the equipment.
D. Major items of equipment, which serve the same f unction, shall be the same make and model.
2.3 COMPATIBILITY OF RELATED EQUIPMENT
A. Equipment and materials installed shall be compa tible in all respects with other items being furnished and with existing items so that the result will be a complete and fully operational sys tem that conforms to contract requirements.
22 05 11 - 13
2.4 EQUIPMENT AND MATERIALS IDENTIFICATION
A. Interior (Indoor) Equipment: Engraved nameplates , with letters not less than 7 mm (3/16 inch) high of brass with black-fill ed letters, or rigid black plastic with white letters specified in Secti on 09 91 00, PAINTING shall be permanently fastened to the equip ment. Unit components such as water heaters, tanks, coils, fil ters, etc. shall be identified.
B. Control Items: All temperature, pressure, and co ntrollers shall be labeled and the component’s function identified. Id entify and label each item as they appear on the control diagrams.
C. Valve Tags and Lists:
1. Plumbing: All valves shall be provided with valv e tags and listed on a valve list (Fixture stops not included).
2. Valve tags: Engraved black filled numbers and le tters not less than
15 mm (1/2 inch) high for number designation, and n ot less than 8 mm
(1/4 inch) for service designation on 19 gage, 40 m m (1-1/2 inches) round brass disc, attached with brass "S" hook or b rass chain.
3. Valve lists: Valve lists shall be created using a word processing program and printed on plastic coated cards. The pl astic coated valve list card(s), sized 215 mm (8-1/2 inches) by 275 mm (11 inches) shall show valve tag number, valve function and area of control for each service or system. The valve list shall be in a punched 3-ring binder notebook. An additional copy of the valve list shall be mounted in picture frames for mounting to a wall. COR shall instruct contractor where frames shall be mounted.
4. A detailed plan for each floor of the building i ndicating the location and valve number for each valve shall be p rovided in the
3-ring binder notebook. Each valve location shall b e identified with a color coded sticker or thumb tack in ceiling or a ccess door.
2.5 FIRESTOPPING
A. Section 07 84 00, FIRESTOPPING specifies an effe ctive barrier against the spread of fire, smoke and gases where penetrati ons occur for piping. Refer to Section 22 07 11, PLUMBING INSULAT ION, for pipe insulation.
2.6 GALVANIZED REPAIR COMPOUND
A. Mil. Spec. DOD-P-21035B, paint.
22 05 11 - 14
2.7 PIPE AND EQUIPMENT SUPPORTS AND RESTRAINTS
A. In lieu of the paragraph which follows, suspende d equipment support and restraints may be designed and installed in accorda nce with the
International Building Code (IBC) Submittals based on the International
Building Code (IBC) requirements, or the following paragraphs of this
Section shall be stamped and signed by a profession al engineer registered in the state where the project is locate d. The Support system of suspended equipment over 227 kg (500 poun ds) shall be submitted for approval of the COR in all cases. See the above specifications for lateral force design requirement s.
B. Type Numbers Specified: For materials, design, m anufacture, selection, application, and installation refer to MSS SP-58. F or selection and application refer to MSS SP-69. Refer to Section 05 50 00, METAL
FABRICATIONS, for miscellaneous metal support mater ials and prime coat painting.
C. For Attachment to Concrete Construction:
1. Concrete insert: Type 18, MSS SP-58.
2. Self-drilling expansion shields and machine bolt expansion anchors:
Permitted in concrete not less than 100 mm (4 inche s) thick when approved by the COR for each job condition.
3. Power-driven fasteners: Permitted in existing co ncrete or masonry not less than 100 mm (4 inches) thick when approved by the COR for each job condition.
D. For Attachment to Steel Construction: MSS SP-58.
1. Welded attachment: Type 22.
2. Beam clamps: Types 20, 21, 28 or 29. Type 23 C-c lamp may be used for individual copper tubing up to 23 mm (7/8 inch) out side diameter.
E. For Attachment to Wood Construction: Wood screws or lag bolts.
F. Hanger Rods: Hot-rolled steel, ASTM A36/A36M or ASTM A575 for allowable load listed in MSS SP-58. For piping, provide adjus tment means for controlling level or slope. Types 13 or 15 turn-buc kles shall provide
40 mm (1-1/2 inches) minimum of adjustment and inco rporate locknuts.
All-thread rods are acceptable.
G. Multiple (Trapeze) Hangers: Galvanized, cold for med, lipped steel channel horizontal member, not less than 43 mm by 4 3 mm (1-5/8 inches by 1-5/8 inches), 2.7 mm (No. 12 gage), designed to accept special spring held, hardened steel nuts.
22 05 11 - 15
1. Allowable hanger load: Manufacturers rating less 91kg (200 pounds).
2. Guide individual pipes on the horizontal member of every other trapeze hanger with 8 mm (1/4 inch) U-bolt fabricat ed from steel rod. Provide Type 40 insulation shield, secured by two 15 mm (1/2 inch) galvanized steel bands, or insulated calcium silicate shield for insulated piping at each hanger.
H. Pipe Hangers and Supports: (MSS SP-58), use hang ers sized to encircle insulation on insulated piping. Refer to Section 22 07 11, PLUMBING
INSULATION for insulation thickness. To protect ins ulation, provide
Type 39 saddles for roller type supports or insulat ed calcium silicate shields. Provide Type 40 insulation shield or insul ated calcium silicate shield at all other types of supports and hangers including those for insulated piping.
1. General Types (MSS SP-58):
a. Standard clevis hanger: Type 1; provide locknut.
b. Riser clamps: Type 8.
c. Wall brackets: Types 31, 32 or 33.
d. Roller supports: Type 41, 43, 44 and 46.
e. Saddle support: Type 36, 37 or 38.
f. Turnbuckle: Types 13 or 15.
g. U-bolt clamp: Type 24.
h. Copper Tube:
1) Hangers, clamps and other support material in co ntact with tubing shall be painted with copper colored epoxy p aint, copper-coated, plastic coated or taped with isolati on tape to prevent electrolysis.
2) For vertical runs use epoxy painted, copper-coat ed or plastic coated riser clamps.
3) For supporting tube to strut: Provide epoxy pain ted pipe straps for copper tube or plastic inserted vibratio n isolation clamps.
4) Insulated Lines: Provide pre-insulated calcium s ilicate shields sized for copper tube.
2. Plumbing Piping (Other Than General Types):
a. Horizontal piping: Type 1, 5, 7, 9, and 10.
b. Chrome plated piping: Chrome plated supports.
22 05 11 - 16
c. Hangers and supports in pipe chase: Prefabricate d system ABS self-extinguishing material, not subject to electro lytic action, to hold piping, prevent vibration and compensate fo r all static and operational conditions.
d. Blocking, stays and bracing: Angle iron or prefo rmed metal channel shapes, 1.3 mm (18 gage) minimum.
J. Pre-insulated Calcium Silicate Shields:
1. Provide 360 degree water resistant high density 965 kPa (140 psig) compressive strength calcium silicate shields encas ed in galvanized metal.
2. Pre-insulated calcium silicate shields to be ins talled at the point of support during erection.
3. Shield thickness shall match the pipe insulation .
4. The type of shield is selected by the temperatur e of the pipe, the load it must carry, and the type of support it will be used with.
a. Shields for supporting cold water shall have ins ulation that extends a minimum of 25 mm (1 inch) past the sheet metal.
b. The insulated calcium silicate shield shall supp ort the maximum allowable water filled span as indicated in MSS SP- 69. To support the load, the shields shall have one or more of the following features: structural inserts 4138 kPa (600 psig) co mpressive strength, an extra bottom metal shield, or formed s tructural steel (ASTM A36/A36M) wear plates welded to the bot tom sheet metal jacket.
5. Shields may be used on steel clevis hanger type supports, trapeze hangers, roller supports or flat surfaces.
2.8 PIPE PENETRATIONS
A. Pipe penetration sleeves shall be installed for all pipe other than rectangular blocked out floor openings for risers i n mechanical bays.
B. Pipe penetration sleeve materials shall comply w ith all firestopping requirements for each penetration.
C. To prevent accidental liquid spills from passing to a lower level, provide the following:
1. For sleeves: Extend sleeve 25 mm (1 inch) above finished floor and provide sealant for watertight joint.
2. For blocked out floor openings: Provide 40 mm (1 -1/2 inch) angle set in silicone adhesive around opening.
22 05 11 - 17
3. For drilled penetrations: Provide 40 mm (1-1/2 i nch) angle ring or square set in silicone adhesive around penetration.
D. Penetrations are not allowed through beams or ri bs, but may be installed in concrete beam flanges, with structural engineer prior approval. Any deviation from these requirements mus t receive prior approval of COR.
E. Sheet metal, plastic, or moisture resistant fibe r sleeves shall be provided for pipe passing through floors, interior walls, and partitions, unless brass or steel pipe sleeves are specifically called for below.
F. Cast iron or zinc coated pipe sleeves shall be p rovided for pipe passing through exterior walls below grade. The spa ce between the sleeve and pipe shall be made watertight with a mod ular or link rubber seal. The link seal shall be applied at both ends o f the sleeve.
G. Galvanized steel or an alternate black iron pipe with asphalt coating sleeves shall be for pipe passing through concrete beam flanges, except where brass pipe sleeves are called for. A galvaniz ed steel sleeve shall be provided for pipe passing through floor of mechanical rooms, laundry work rooms. Except in mechanical rooms, sle eves shall be connected with a floor plate.
H. Brass Pipe Sleeves shall be provided for pipe pa ssing through quarry tile, terrazzo or ceramic tile floors. The sleeve s hall be connected with a floor plate.
I. Sleeve clearance through floors, walls, partitio ns, and beam flanges shall be 25 mm (1 inch) greater in diameter than ex ternal diameter of pipe. Sleeve for pipe with insulation shall be larg e enough to accommodate the insulation plus 25 mm (1 inch) in d iameter. Interior openings shall be caulked tight with firestopping m aterial and sealant to prevent the spread of fire, smoke, water and gas es.
J. Sealant and Adhesives: Shall be as specified in Section 07 92 00, JOINT
SEALANTS. Bio-based materials shall be utilized whe n possible.
2.9 TOOLS AND LUBRICANTS
A. Furnish, and turn over to the COR, special tools not readily available commercially, that are required for disassembly or adjustment of equipment and machinery furnished.
B. Grease Guns with Attachments for Applicable Fitt ings: One for each type of grease required for each motor or other equipmen t.
22 05 11 - 18
C. Tool Containers: metal, permanently identified f or intended service and mounted, or located, where directed by the COR.
D. Lubricants: A minimum of 0.95 L (1 quart) of oil , and 0.45 kg (1 pound) of grease, of equipment manufacturer's recommended grade and type, in unopened containers and properly identified as to u se for each different application. Bio-based materials shall be utilized when possible.
2.10 WALL, FLOOR AND CEILING PLATES
A. Material and Type: Chrome plated brass or chrome plated steel, one piece or split type with concealed hinge, with set screw for fastening to pipe, or sleeve. Use plates that fit tight aroun d pipes, cover openings around pipes and cover the entire pipe sle eve projection.
B. Thickness: Not less than 2.4 mm (3/32 inch) for floor plates. For wall and ceiling plates, not less than 0.64 mm (0.025 in ch) for up to 75 mm
(3 inch) pipe, 0.89 mm (0.035 inch) for larger pipe .
C. Locations: Use where pipe penetrates floors, wal ls and ceilings in exposed locations, in finished areas only. Wall pla tes shall be used where insulation ends on exposed water supply pipe drop from overhead.
A watertight joint shall be provided in spaces wher e brass or steel pipe sleeves are specified.
2.11 ASBESTOS
A. Materials containing asbestos are not permitted.
PART 3 - EXECUTION
3.1 ARRANGEMENT AND INSTALLATION OF EQUIPMENT AND PIPING
A. Location of piping, sleeves, inserts, hangers, a nd equipment, access provisions shall be coordinated with the work of al l trades.