This document contains a specification table of contents and details for a federal construction contract opportunity with the Department of Veterans Affairs. The specification table of contents outlines the division and section structure for renovation of the Emergency Department Observation Unit at the Jesse Brown VA Medical Center in Chicago, Illinois, including demolition, concrete, masonry, metals, wood and plastics, thermal and moisture protection, openings, finishes, specialties, equipment, furnishings, special construction, conveyance equipment, fire suppression, plumbing, HVAC, electrical, communications, electronic safety and security, earthwork, exterior improvements, and utilities work. The related federal contract opportunity is solicitation number 36C25220B0023 for the emergency department observation unit renovation project at the medical center, requiring a contractor to provide all tools, materials, components, labor and supervision for construction and renovation of a fully functional observation unit, as detailed in the scope of work.

View the file

Other files

File Type Posted
AE Responses 537-15-160 Consolidated RFI Amendment 6.xlsx XLSX spreadsheet
36C25220B0023 0006.docx DOCX document
537-15-160 SOW - Mod2.docx DOCX document
IFB Bid opening invitation changed to 10SEP.pdf PDF
36C25220B0023 0005.docx DOCX document
AE Responses 537-15-160 Consolidated RFI Amendment 4.pdf PDF
085113 - Psychiatric windows.docx DOCX document
081710 - Integrated Door Assemblies.docx DOCX document
36C25220B0023 0004.docx DOCX document
087100 - Door Hardware.docx DOCX document
Basement sketch Question 64.png PNG image
024100 - Demolition.pdf PDF
SIGNED Brand Name J and A.pdf PDF
36C25220B0023 0003.docx DOCX document
262416 - Panels.pdf PDF
264313 - Surge Protective Devices.pdf PDF
537-15-160 Consolidated RFI-ADD1.pdf PDF
Bid opening change to 10 AUG Meeting Invitation.pdf PDF
260573 - OCP Device Coordination Study.pdf PDF
C03 36C25220B0023 0002.docx DOCX document
EJ200 - Addendum 1 Elec - 07.23.20.pdf PDF
RFI-001_Guidon Addendum 1.pdf PDF
537-15-160 SOW - Mod1.pdf PDF
ED201 - Addendum 1 Elec - 07.23.20.pdf PDF
36C25220B0023 A0001.docx DOCX document
ATCH 2 537-15-160 sign in sheets 8-9 jul 2020.pdf PDF
ATCH 1 537-15-160 Construction Bid Opening Meeting.pdf PDF
537-15-160 Construction Drawings 1 of 4.pdf PDF
537-15-160 Construction Drawings 3 of 4.pdf PDF
537-15-160 Construction Drawings 2 of 4.pdf PDF
S02 36C25220B0023_2_7-1-2020.docx DOCX document
537-15-160 Construction Drawings 4 of 4.pdf PDF
537-15-160 Project Manual Vol2.pdf PDF
537-15-160 Project Manual Vol1.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Jesse Brown VAMC VA: 537-15-160 Emergency Department Renovations Chicago, IL 60612

10-01-17 100% Construction Documents

May 30, 2020

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

DIVISION 00 - SPECIAL SECTIONS DATE

00 01 00 Table of Contents 10-17 00 01 15 List of Drawing Sheets 07-15

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 12-18 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 04-13 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 02-17 01 35 33 Infection Control Requirements 06-19 01 35 33.01 Construction Safety Procedures Appendix A 01 35 33.02 Construction Safety Procedures Appendix B 01 35 33.03 Construction Safety Procedures Appendix C 01 35 33.04 Construction Safety Procedures Appendix D 01 35 33.05 Construction Safety Procedures Appendix E 01 35 33.06 Construction Safety Procedures Appendix F 01 42 19 Reference Standards 05-16 01 45 00 Quality Control 03-19 01 45 29 Testing Laboratory Services 11-18 01 45 35 Special Inspections 03-19 01 57 19 Temporary Environmental Controls 01-11 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 09-13 01 81 13 Sustainable Construction Requirements 10-17

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 08-17

DIVISION 03 – CONCRETE NOT USED

DIVISION 04 – MASONRY NOT USED

04 20 00 Unit Masonry 08-17 04 72 00 Cast Stone Masonry 06-14

DIVISION 05 – METALS

05 12 00 Structural Steel Framing 11-18 05 43 00 Slotted Channel Framing

Chicago, IL 60612

10-01-17

00 01 10-2

05 50 00 Metal Fabrications 08-18

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 10-17

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13 Thermal Insulation 10-17 07 53 23 Ethylene-Propylene-Diene-Monomer 07 60 00 Flashing and Sheet Flashing 07 81 00 Applied Fireproofing 10-17 07 84 00 Firestopping 02-16 07 92 00 Joint Sealants 10-17 07 95 13 Expansion Joint Assemblies 02-16

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 08-16 08 14 00 Interior Wood Doors 02-16 08 17 10 Integrated Door Assemblies 02-16 08 31 13 Access Doors and Frames 02-16 08 33 00 Coiling Doors and Grilles 09-18 08 42 43 Intensive Care Units/Critical Care Unit(ICU/CCU)

Entrances

08 71 00 Door Hardware 05-19 08 71 13 Automatic Door Operators 02-16 08 80 00 Glazing 10-15 08 90 00 Louvers and Vents 05-15

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 02-15 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 06-18 09 30 13 Ceramic/Porcelain Tiling 09-15 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 02-16 09 65 16 Resilient Sheet Flooring 05-18 09 91 00 Painting 01-16

DIVISION 10 – SPECIALTIES

10 21 23 Cubicle Curtain Tracks 05-15 10 25 13 Patient Bed Service Walls 01-20 10 26 00 Wall and Door Protection 10-15 10 28 00 Toilet, Bath, and Laundry Accessories 02-16 10 44 13 Fire Extinguisher Cabinets 08-18

DIVISION 11 – EQUIPMENT NOT USED

Chicago, IL 60612

10-01-17

00 01 10-3

DIVISION 12 – FURNISHINGS

12 32 00 Manufactured Wood Casework 09-15 12 36 00 Countertops 12-18

DIVISION 13 - SPECIAL CONSTRUCTION NOT USED

DIVISION 14– CONVEYING EQUIPEMENT NOT USED

DIVISION 21- FIRE SUPPRESSION

21 13 13 Wet-Pipe Sprinkler Systems 06-15

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 07-16 22 07 11 Plumbing Insulation 09-15 22 11 00 Facility Water Distribution 09-15 22 13 00 Facility Sanitary and Vent Piping 09-15 22 40 00 Plumbing Fixtures 09-15 22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 09-15 22 63 00 Gas Systems for Laboratory and Healthcare Facilities 09-15

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

08-17 23 05 11 Common Work Results for HVAC 08-17 23 05 12 General Motor Requirements for HVAC and Steam

Generation Equipment 08-17

23 05 41 Noise and Vibration Control for HVAC Piping and Equipment

02-15

23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15 23 07 11 HVAC and Boiler Plant Insulation 02-15 23 09 23 Direct-Digital Control System for HVAC 09-11 23 21 13 Hydronic Piping 08-17 23 31 00 HVAC Ducts and Casings 03-13 23 34 00 HVAC Fans 02-15 23 36 00 Air Terminal Units 02-15 23 37 00 Air Outlets and Inlets 02-15 23 40 00 HVAC Air Cleaning Devices 02-12 23 82 16 Air Coils 04-11

DIVISION 25 – INTEGRATED AUTOMATION NOT USED

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 01-16

Chicago, IL 60612

10-01-17

00 01 10-4

26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 05 73 Overcurrent Protective Device Coordination Study 10-17 26 09 23 Lighting Controls 01-18 26 24 16 Panelboard 01-18 26 27 26 Wiring Devices 01-18 26 43 13 Surge Protective Devices 01-17 26 51 00 Interior Lighting 01-18

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19 27 05 26 Grounding and Bonding for Communications Systems 06-15 27 05 33 Raceways and Boxes for Communications Systems 10-18 27 10 00 Control, Communication and Signal Wiring 06-15 27 15 00 Communications Structured Cabling 01-16 27 52 23 Nurse Call and Code Blue Systems 10-18

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00 Common Work Results for Electronic Safety and Security 04-18 28 05 13 Conductors and Cables for Electronic Safety and

Security 10-18

28 05 26 Grounding and Bonding for Electronic Safety and Security

09-11

28 05 28.33 Conduits and Backboxes for Electronic Safety and Security

09-11

28 31 00 Fire Detection and Alarm 10-11

DIVISION 31 – EARTHWORK NOT USED

DIVISION 32 – EXTERIOR IMPROVEMENTS NOT USED

DIVISION 33 – UTILITIES NOT USED

DIVISION 34 – TRANSPORTATION NOT USED

DIVISION 48 – Electrical Power Generation NOT USED

File details come from the government source that posted it. Updated .