36E77620R0001-0004001.docx

DOCX document Posted

Attached to
650-332 New Mental Health Building - Phase 1 (VA-19-00104660)
Solicitation number
36E77620R0001
Issued by

About this file

This document provides details on an upcoming federal contract opportunity for construction services. The Department of Veterans Affairs intends to solicit bids and award a firm-fixed-price contract to complete work for the construction of a new mental health building project located at the Providence VA Medical Center in Rhode Island. The proposed three-story, freestanding building will provide approximately 15,300 square feet of new mental health program area and require corresponding site and utility work. The solicitation will be set aside for Service-Disabled Veteran-Owned Small Businesses and issued on or around December 20, 2019 as a request for proposal. The period of performance is expected to be approximately 600 calendar days from notice to proceed. The magnitude of construction is estimated between $10-20 million. Questions must be submitted in writing by the stated deadline.

36E77620R0001 0004 S05 - Technical Questions and Answers Providence Continued.docx

View the file

Other files

File Type Posted
36E77620R0001-0007000.docx DOCX document
36E77620R0001-0007001.docx DOCX document
36E77620R0001-0006000.docx DOCX document
36E77620R0001-0005060.docx DOCX document
36E77620R0001-0005061.docx DOCX document
36E77620R0001-0005068.pdf PDF
36E77620R0001-0005064.pdf PDF
36E77620R0001-0005069.pdf PDF
36E77620R0001-0005067.pdf PDF
36E77620R0001-0005062.pdf PDF
36E77620R0001-0005070.pdf PDF
36E77620R0001-0005066.pdf PDF
36E77620R0001-0005065.pdf PDF
36E77620R0001-0005063.pdf PDF
36E77620R0001-0005071.pdf PDF
36E77620R0001-0004000.docx DOCX document
36E77620R0001-0003000.docx DOCX document
36E77620R0001-0003001.docx DOCX document
36E77620R0001-0002000.docx DOCX document
36E77620R0001-0001001.pdf PDF
36E77620R0001-0001000.docx DOCX document
36E77620R0001-008.pdf PDF
36E77620R0001-007.pdf PDF
36E77620R0001-012.pdf PDF
36E77620R0001-016.docx DOCX document
36E77620R0001-001.docx DOCX document
36E77620R0001-004.pdf PDF
36E77620R0001-005.pdf PDF
36E77620R0001-006.pdf PDF
36E77620R0001-010.pdf PDF
36E77620R0001-013.pdf PDF
36E77620R0001-015.docx DOCX document
36E77620R0001-017.pdf PDF
36E77620R0001-002.pdf PDF
36E77620R0001-011.pdf PDF
36E77620R0001-014.pdf PDF
36E77620R0001-009.pdf PDF
36E77620R0001-003.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Technical Questions and Answers Providence Continued

1. On Elevation F1/AE201 there are two type D windows on the lower and first floor between column lines 1 & 2 that do not appear on the floor plans. Are these to be included in the offer?

Yes, all windows shown in the contract documents, including building elevations, should be included in the bid.

2. The door schedule calls for a number of doors and frames to have an STC rating of 45. Two Type 3 frames which are glazed call for this STC rating. The highest STC rating for a laminated single piece of ½” glass is around 40, even with acoustic interlayers. Can the glazing for these frames be clarified?

The STC requirement for doors 028 and 029 into the classrooms may be reduced to STC 40. Glazing thickness, composition and frame requirements to be as required to achieve desired level. IGU glazing composition is acceptable if required.

3. Please provide a specification for electric floor boxes.

Floor Boxes: Cast metal, fully adjustable, rectangular. Also, requirements as noted in specification 26 05 33, including section 2.1.E

4. Telecommunications raceway detail indicates basket type cable tray which is not indicated on the plans. Please confirm whether cable trays are required or not.

Cable tray shall be provided as indicated on Electrical details page. One cable ray should be installed down each corridor.

5. Please confirm any requirements for the tie-ins of smoke dampers or fire dampers with the fire alarm system.

Smoke dampers are required to be tied into the fire alarm system with a relay module to actuate the smoke damper upon initiation by the adjacent duct smoke detector. Fire dampers are not required to be tied into the fire alarm system.