This document is a Technical Questions and Solicitation Responses Tracking Sheet for the VA Illiana Healthcare System's EHRM Infrastructure Upgrades project in Danville, IL. The tracking sheet contains 91 detailed questions and answers addressing technical specifications, clarifications, and project requirements, covering areas such as electrical systems, telecommunications infrastructure, fire alarm systems, data center upgrades, access controls, and construction logistics. Key details include confirmation of a Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside, bid extension from 7/29/25 to 8/6/25, and specifications for network cabling, conduit installation, and building modifications across multiple campus buildings (14, 19, 22, 58, 60, 64, 98, 101-104, 125, 128-133, 140).

The responses provide technical clarifications on various project elements, including existing system manufacturers, cabling requirements, conduit specifications, laydown areas, parking, work hours, and specific installation details. Notable technical points include using Johnson Controls/Simplex fire alarm systems, installing Category 6a network cables, implementing cold aisle containment systems, and following specific installation guidelines for telecommunications infrastructure. The document also addresses contractor requirements such as BICSI certification for telecommunications contractors, dust control measures, and coordination with VA staff for site surveys and network cutover strategies.

View the file

Other files

File Type Posted
36C77625B0011 0006.pdf PDF
Abstract of Bids OF 1419 - CONSTRUCTION - Signed 8.11.25.pdf PDF
Attachment 21 - Technical Questions - Danville IL 8-5-2025.pdf PDF
36C77625B0011 0005.docx DOCX document
36C77625B0011 0004.pdf PDF
Attachment 21 - Technical Questions - Danville IL 7-30-2025.pdf PDF
Attachment 23 - A-903.pdf PDF
Attachment 3 Construction Wage Rates Vermilion 7.25.25.pdf PDF
Solicitation 36C77625B0011 Amendment 0003 - Danville IL EHRM Construction.pdf PDF
Attachment 21 - Technical Questions - Danville IL 7-28-2025.pdf PDF
Attachment 20 - Stamped Civil Drawings.pdf PDF
Attachment 22 - Electrical Single Line.pdf PDF
Attachment 11 - 02 82 11_Appendix_Asbestos Containing Materials Report Crosswalk.pdf PDF
Attachment 23 - Construction Wage Rates - Vermilion 7-11-25.pdf PDF
Attachment 12 - 58.AE301.pdf PDF
Attachment 14 -101.AE301.pdf PDF
Attachment 13 - 58.AE401.pdf PDF
Amendment - 0002 36C77625B0011.pdf PDF
Attachment 17 - FloorHeightTable.xlsx XLSX spreadsheet
Attachment 16 - FloorHeightTable.pdf PDF
Attachment 15 - 013324 - Electronic Submittals.pdf PDF
Attachment 18 - RFI Log_EHRM Upgrades Danville IL.xls XLS spreadsheet
Attachment 19 - Soil Report Danville IL - 7-15-25.pdf PDF
Amendment - 0001 36C77625B0011.pdf PDF
Attachment 10 Limitations on Subcontracting Construction.pdf PDF
Attachment 8 Drawings Danville IL EHRM IU Construction Volume 3 of 3.pdf PDF
Attachment 6 Drawings Danville IL EHRM IU Construction Volume 1 of 3.pdf PDF
Attachment 1 Specifications Danville IL EHRM IU Construction Volume 1 of 2.pdf PDF
Attachment 4 Site Visit Instructions EHRM IU 550 21 700.docx DOCX document
Attachment 5 Pre Construction Risk Assessment Danville IL EHRM IU.docx DOCX document
Attachment 9 Brand Name Justification Danville IL EHRM IU Construction.pdf PDF
Attachment 3 Construction Wage Rates Vermilion 4 18 25.pdf PDF
Attachment 2 Specifications Danville IL EHRM IU Construction Volume 2 of 2.pdf PDF
36C77625B0011_1.docx DOCX document
Attachment 7 Drawings Danville IL EHRM IU Construction Volume 2 of 3.pdf PDF
36C77625B0011.docx DOCX document
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL QUESTIONS AND

SOLICITATION #:
36C77626B0011
RESPONSES TRACKING SHEET
PROJECT TITLE:
EHRM Infrastructure Upgrades - Danville
#
RECEIVED
ANSWERED
CONTRACTOR QUESTION
VA RESPONSE
1
06/30/2025
07/10/2025
262413 – Distribution Switchboards: We will be adding to the existing power distribution and need to match existing. Can the VA please advise the manufacturer of the existing switchboards and panelboards?
Manufacturers vary across campus. See attached single line diagrams for the current info on each building.
2
06/30/2025
07/10/2025
283100 – Fire Alarm & Detection: We are adding to the existing fire alarm system. Can the VA advise the manufacturer of the existing fire alarm? Is there an existing maintenance contract for the fire alarm system? If so, can you please provide the contact information for the maintenance contractor?
AE: Existing fire alarm system is Johnson Controls/Simplex 4100ES.

VA: There is no existing maintenance contractor.

3
06/30/2025
07/10/2025
Please provide clarification as it was mentioned during the pre-bid meeting by Marcus Lehman that the existing network cables to removed and new Category 6a network cables shown to be installed on all building plans for the workstations, wireless access points, phones, and cameras are actually in a separate project. Can you confirm that the bid specifications and drawings submitted are correct with no portion as a separate project?
Scope of work includes the replacement of Unshielded Twisted Pair (UTP) cabling for those devices (Work Area Outlets, Cameras, Wi-Fi Access Points) shown on the drawings. There may be devices not shown on the drawings connected to Telecommunications Rooms (TR) that will NOT have their UTP cables replaced.
4
06/30/2025
07/10/2025
There are motion detectors shown in the new data center, but I am unable to locate anywhere what the design intent is of the devices. Please provide clarification. The symbol is listed below.

This device is a motion detector typically connected to the facility Intrusion Detection System (IDS). As of this writing the Danville VAMC does not have an IDS. These devices shall be connected to a LenelS2 Supervised Input Application Blade I/O board as an input sensor device indicating motion in the space in which it is located. Program the system to log motion events, no alarms are to be programmed at this time.

5
06/30/2025
07/10/2025
Can you provide clarification as to what scope the cold aisle containment system will fall under? I see portions noted under on sheets 104.TN402 and 104.MH105. This is typically a complete system with doors and containment panels made of aluminum and plastic.
Both sheets 104.TN402 and 104.MH105 are to be used together to determine the best system to be used for containment. Contractor to determine the most suitable means and methods for meeting the requirement.
6
06/30/2025
07/10/2025
Are other manufacturers acceptable for the cold aisle doors than Chatsworth products?
Yes
7
06/30/2025
07/10/2025
Please clarify what the “RI” stands for on sheet 101.TD102 for reference. Are these empty boxes just note for future reference?
Treat all RI symbols as a 2 Data 1 Voice WAO.
8
06/30/2025
07/10/2025
There are more access controlled doors shown on sheets 132.TN101 and 133.TN101 than either matrix for access controlled adds list. Are these all existing doors noted for reference only?
The door schedule takes precedence over the plans for these two buildings. Only the TR doors are to be modified for access controls.
9
06/30/2025
07/10/2025
Are the cameras shown on the demo plans for sheets 128.TD101, 129.TD101, and 130.TD101 to removed as all other cable locations noted even though they are not dashed like other locations to be removed?
Disregard the cameras on these sheets. They are not to be re-cabled with new UTP.
10
07/01/2025
07/10/2025
GI002 - Drawing Sheets 58.AE301, 58.AE401 and 101.AE301 are missing from the documents.
Provided
11
07/01/2025
07/10/2025
Is there a location on the campus for a laydown / staging area?
A laydown area on campus will be provided after award. See question 47 and 48 for additional details.
12
07/01/2025
07/10/2025
Spec Section 01 00 00 paragraph 1.6L calls for a 7' temporary fence around staging and work area. Will the VA allow a standard 6' chain link fence?
Follow the specifications.
13
07/01/2025
07/10/2025
Spec Section 01 45 00 paragraph 3.4C. The experience matrix for the CQC personnel list several areas that have very little or no work on this project (i.e. Design Quality Control Manager). Does the contractor need to provide personnel to cover Structural, Civil, Mechanical and design quality control or can the CQC System manager cover these since it is minimal work.
Comply with the Experience Matrix listed in 3.4.C
14
07/01/2025
07/10/2025
Drawing Sheet CK501 Detail 1. Detail calls for 4" concrete or thickness of existing sidewalk. Please confirm we are to bid 4" thick concrete sidewalks or provide the thickness of existing sidewalks.
Assume:

Sidewalks: 6” concrete / 4” base Parking lots: 4” asphalt / 8” base Roads: 8” asphalt / 12” base

15
07/01/2025
07/10/2025
Drawing Sheet CK501 Detail 5, 6 & 7. Please provide the thickness of the existing asphalt and granular base so we can provide the correct thickness of patch.
Actual thickness are unknown. Contractor to bid based on the following assumptions:

Assume:

Sidewalks: 6” concrete / 4” base Parking lots: 4” asphalt / 8” base Roads: 8” asphalt / 12” base

16
07/01/2025
07/10/2025
Drawing Sheet CS105. Please provide the thickness of gravel required for the replacement. Is filter fabric required underneath
12" of gravel and a fabric separator shall be used
17
07/01/2025
07/10/2025
Building 19 - Architectural Drawings and Technology Drawings have different layouts. A drawings have the entrance on the West side of the Building and the T drawings show the fiber entrance on the East side. The room number is the same. The civil drawings show the service coming into the West side of the building. Please confirm the fiber entrance is on the West side and the technology drawings have been flipped.
Confirmed
18
07/01/2025
07/10/2025
19.AE102 Note A52 calls to return the window to the existing conditions. Please advise what is required.
Remove the mounting brackets, fill any screw holes, remove sealing tape and insulation, provide touch up painting as needed and close the single hung metal window in which the AC unit is mounted.
19
07/01/2025
07/10/2025
Drawing Sheet 104.AC102 room 128 shows a drywall ceiling. The room finish schedule calls for AT-2. Which is correct.
Drywall
20
07/01/2025
07/10/2025
Drawing Sheet 130.AE101 calls for new 45 min. Wood Door. Door schedule calls for Hollow Metal. Which Is correct? Bldg 131, 132 & 133 similar.

Hollow Metal

21
07/01/2025
07/10/2025
Drawing Sheet AG001 Fireproofing General Notes 3 & 4 calls to repair fireproofing / caulking of items uncovered during the work. Can an allowance be provided for this scope of work since it is an unknown condition.
Areas needing repairs that are not associated with this project will be considered an unforeseen site condition.
22
07/01/2025
07/10/2025
Drawing Sheet 14 TN102 Mentions (2) 2" conduits going to the second floor. Drawing Sheet 14 TN103 says they are to be 4" conduits. Which is correct?
4” Conduits
23
07/01/2025
07/10/2025
Drawing Sheet 60 TN101 Keynote #2 Refers to drawing TN003. This sheet is not included.
Reference TN002 for continuation of conduit system.
24
07/01/2025
07/10/2025
Drawing Sheet 102TD105 refers to details 1 and 3 on 102 TN402 these details are labeled incorrectly.
Reference 1 102TN402 -> F2 102TN402

Reference 3 102TN402 -> F8 102TN402

25
07/01/2025
07/10/2025
Drawing Sheet 102TD104 refers to detail 2 on 102 TN402 this detail is labeled incorrectly
Reference 2 102TN402 -> F5 102TN402
26
07/01/2025
07/10/2025
Drawing Sheet 125TD101 refers to detail C13 on 125 TN401 this detail is labeled incorrectly
Reference C13 125TN401 -> F2 125TN401
27
07/01/2025
07/10/2025
Drawing Sheet 132 TD101 refers to detail C15 on 132 TN401 this detail is labeled incorrectly
Reference C15 132TD101 –> F2 132TN401
28
07/01/2025
07/10/2025
Drawing Sheet 133 TD101 refers to detail C15 on 133 TN401 this detail is labeled incorrectly.
Reference C15 133TN401 -> F2 133TN401
29
07/01/2025
07/10/2025
Drawing 58 TN102 keynote #2 refers to TN201 This page is not included.
Keynote 2 on 58 TN102 shall reference sheet TN102 for continuation.
30
07/01/2025
07/10/2025
The drawings ask to include an allowance for 10 additional 2-port CAT 6A information outlets on 43 different pages. Is it your intention for us to include an allowance for 430 extra outlets?
Yes
31
07/01/2025
07/10/2025
Drawing Sheet 14 TN101 calls for (2) 4" conduits to go through (2) 2" sleeves. Which is correct the conduit size or the sleeve size?
4” conduits
32
07/01/2025
07/10/2025
Drawing Sheet 58.MD101 states "Mop sink to be relocated…". Where is this sink to be relocated to?
The mop sink is to be relocated to the plan North East corner of the expanded HAC room.
33
07/01/2025
07/10/2025
Will surface mounted conduit be allowed for date drops in rooms with block walls?
Yes. Specification 27 05 33 covers surface mounted metal raceway.
34
07/01/2025
07/15/2025
Please provide additional time for this procurement. EHRM projects of this size and complexity have had significantly longer procurement durations which benefit the VA by giving sufficient time for the contractors resulting in more accurate pricing.
Yes. Bids are extended from 7.29.25 to 8.6.25 @ 1pm CST. See amendment for details.
35
07/01/2025
07/15/2025
Please provide additional time for RFIs. Subcontractors are still reviewing the contract documents for protentional RFI’s that will affect pricing.
Yes. Bids are extended from 7.29.25 to 8.6.25 @ 1pm CST. See amendment for details.
36
07/01/2025
07/10/2025
Please confirm if contaminated soils are encounter, a change order will be issued to the contractor to properly haul and dispose of contaminated soils.
This would be regarded as an unforeseen site condition.
37
07/01/2025
07/10/2025
Please confirm the superintendent shall not have any shared duties as a QCM, SSHO or any other roles on the project.
The superintendent cannot also be the SSHO. See question 39.
38
07/01/2025
07/10/2025
Please confirm the SSHO shall not have any shared duties as a QCM, superintendent or any other role on the project.
Confirmed
39
07/01/2025
07/10/2025
Please confirm the QCM shall not have any shared duties as the SSHO, superintendent or any other role on the project.
No. See specification 01 45 00 3.4.B for CQC System Manager role.

The SSHO must not have any other duties, see question 38.

40
07/01/2025
07/10/2025
Please confirm the cable installer must have on staff a Registered Communication Distribution Designer (RCDD) certified by Building Industry Consulting Service International (BICSI).
Follow the specifications.
41
07/01/2025
07/10/2025
With regards to the Communications Project Manager, can this role be filled by a subcontractor’s staff?
Yes
42
07/01/2025
07/10/2025
Please confirm if the VA can and will be flexible on the site phasing plan provided in this procurement.
AE: Alternate phasing of the installation of the OSP fiber duct bank system at no additional cost or time that provides the same levels of reliability and compliance will be reviewed after the award. Contractors shall not assume the existing infrastructure can support alternative phasing.

VA: Please refer to Spec Section 01 00 00 1.6 J for some supplemental language to VCI’s response above.

43
07/01/2025
07/10/2025
Please confirm that the contractor is to supply all materials testing for the project.
Follow the specifications.
44
07/01/2025
07/10/2025
Please confirm that all firestopping must be either installed by an FM global approved contractor, or a UL qualified firestop contractor certified.
Follow the specifications.
45
07/01/2025
07/10/2025
Please confirm that the contractor is to include the services of a third party independent firestopping inspector in their bid.
Follow the specifications.
46
07/01/2025
07/10/2025
Please confirm that firestopping installers accredited by a firestopping product manufacturer will not be approved by the VA unless they meet the FM global or UL qualifications referenced in section 07 84 00.
Follow the specifications.
47
07/01/2025
07/10/2025
Please confirm that the VA will provide the contractor with a laydown area for dumpsters, toilets, storage, and trailers. We understand there is not much room onsite however without this area there will be an impact to cost and efficiency.
A laydown area on campus will be provided after award. See question 47 and 48 for additional details. Toilets are covered under spec section 01 00 00 1.20.
48
07/01/2025
07/10/2025
Please provide a site plan showing the contractor trailer and laydown area(s).
This VA has multiple locations and sizes of areas that we have used as lay down areas. The exact location will be decided with the awardee and will be dependent on areas available at the time of need.
49
07/01/2025
07/10/2025
Please confirm that contractor parking will be provided on site. This directly impacts pricing.
Open parking is available throughout campus parking lots. See attached parking map. However, VA may make specific parking restrictions once the contractor’s number of daily vehicles is known and/or if the quantity of contractor vehicles is over-populating a certain lot. In those cases, VA may redirect contractor parking to a different lot on campus.
50
07/01/2025
07/15/2025
Please confirm if this project is tax exempt. If so, will the VA provide the documentation to the prime contractor after award?
See clause 52.229-3 and special note regarding 52.229-3 of solicitation.
51
07/01/2025
07/10/2025
Please confirm the contractor will be required to submit post award the requested information that the telecommunications contractor shall be a BICSI licensed Contractor with a minimum of five (5) years’ experience installing and servicing systems of similar scope and complexity. The Contractor shall provide four (4) current references from clients with systems of similar scope and complexity which became operational in the past three (3) years. At least three (3) of the references shall be utilizing the same system components, in a similar configuration as the proposed system. The references must include a current point of contact, company or agency name, address, telephone number, complete system description, date of completion, and approximate cost of the project.
Follow the specifications.
52
07/01/2025
07/10/2025
Please confirm that the telecommunications contractor must submit copies of system manufacturer certification for all technicians. The Contractor shall provide proof project superintendent with BICSI Certified Commercial Installer Level 1, Level 2, or Technician to provide oversight of the project.
Follow the specifications.
53
07/01/2025
07/15/2025
Please confirm this project must meet the buy American act requirements.
See clause 52.225-12 of solicitation.
54
07/01/2025
07/10/2025
Please confirm level 4 finish for all finished gypsum board including patches.
Confirmed. Patches must match surrounding walls.
55
07/01/2025
07/10/2025
Please confirm painting unless otherwise noted is to be (3) coats (prime, body, and finish) and will be from "seam to seam" or to a change of materials where walls are patched and refinished.
Entire wall must be repainted where a patch is used.
56
07/01/2025
07/10/2025
Please confirm work in common hallways requires use of the control cube method i.e. cart with plastic covering and sealed connection to work site with hepa vacuum for vacuuming prior to exit.
Follow ICRA specification 01 01 10.
57
07/01/2025
07/10/2025
Can the data cables be allowed to be fished in where pathways are not large enough?
All above ceiling pathways shall be either in conduit, innerduct, cable trays or J Hooks. In-Wall UTP must be in conduit (No ‘ring and string’).
58
07/01/2025
07/10/2025
Does the VA have extra network equipment (switch gear, routers, UPS's) to keep the network connected during construction and cut over?
The VA OIT will provide extra network switches for Data Center and TR / WAO cutover using a ‘leap frog’ switch move method utilizing the new fiber. The VA may, at their choosing, decide to do a ‘forklift’ switch move cutover method if the WAO port count is not too large for the outage period. Contractor to provide UPS as indicated on drawings.
59
07/01/2025
07/10/2025
Are we required to use plenum rated cabling for all areas? Can we use riser rated cabling in non plenum spaces?
See specification 27 13 23 2.1.E and 27 15 13 2.1.G.
60
07/01/2025
07/10/2025
Will flexible metal conduit be allowed?
See specification 27 05 33 2.1.5 & .6
61
07/01/2025
07/10/2025
Please confirm, that all existing conduit stubs for data communications are 3/4".
See note 14 on sheet TN001.
62
07/01/2025
07/10/2025
Please confirm existing locations where 1/2" conduits need to be replaced.
See note 14 on sheet TN001.
63
07/01/2025
07/10/2025
If existing pathways cannot be used, Contractors would need to assume a quantity to remove and replace. Please provide a quantity of pathways the contractor should use for pricing purposes.
Existing pathways can be re-used when they can be cleared of existing cables (Reliant on phasing). New pathways are expected due to phasing and separation distance requirements.
64
07/01/2025
07/10/2025
Please confirm the VA will be working and scheduling with the subsystem vendors on scheduling network outages.
Contractor shall create all utility outage (including network) schedules per the specifications and submit outage requests for VA to coordination with the service lines.
65
07/01/2025
07/10/2025
Is there a current roof warranty for each building? If so, please confirm who has the roofing warranty and provide point of contact.
Roof access and modification for this project should be limited to the tramways and a small roof section on B58. These roofs are not currently under warranty. Contractor to coordinate with COR if other roof access/modification becomes required. Information will be investigated and provided on a case by case basis.
66
07/01/2025
07/10/2025
Please provide floor to finish heights and floor to structure heights for all buildings.
See attached floor height table.
67
07/01/2025
07/10/2025
Is the contractor required to provide the licensing for the new Security Cameras? Or will the VA be providing that?
Contractor to provide license to be transferred to the VA.
68
07/01/2025
07/10/2025
Please confirm allowance for additional data drops are provided on a per-page basis and an overall project allowance should not be factored into our bids.
Additional data drops are total for the project.
69
07/01/2025
07/15/2025
Please confirm that this project is a competitive Service-Disabled Veteran-Owned Small Business Set-Aside project and that any bonding provided by a contractor must be through a SDVOSB or SBA/VA APPROVED Mentor-Protege partnership under the SBA/VA Mentor-Protégé program in which the partnership has been approved prior to the bid date.
This project is set aside for SDVOSBs. The bonding requirements must be met for this project per the applicable clauses, provisions, and instructions to offerors.
70
07/01/2025
07/15/2025
Please confirm that a large business not part of an SBA/VA APPROVED Mentor-Protégé team under the VA Mentor-Protégé program cannot provide a Payment & Performance bond for a SDVOSB.
This project is set aside for SDVOSBs. The bonding requirements must be met for this project per the applicable clauses, provisions, and instructions to offerors.
71
07/01/2025
07/15/2025
Please confirm that a large business not part of an SBA/VA APPROVED Mentor-Protégé team under the VA Mentor-Protégé program cannot provide a bid guarantee for a SDVOSB.
This project is set aside for SDVOSBs. The bonding requirements must be met for this project per the applicable clauses, provisions, and instructions to offerors.
72
07/01/2025
07/10/2025
Please confirm contractor must provide a dust-tight 1-hour rated temporary construction wall with locking door to isolate the area of work when altering rated walls in the facility.
Follow ICRA Specification 01 01 10.
73
07/01/2025
07/10/2025
Please provide a current soils report for the campus.
AE: No geotechnical investigations were performed for design.

VA: There is no current soil report available for the entire campus. See attached Soil Report Danville IL – 7-15-25 from 2010 targeting the west side of campus for general soil info and expectations.

74
07/01/2025
07/10/2025
Please confirm if all buildings work can only be performed outside of normal working hours?
Some work will have to be performed outside of normal working hours; see spec section 01 00 00 I, J, K. Some work can be done during normal working hours such as work that does not disrupt normal operation of the facility and complies with all safety related measures for occupied buildings. See table on drawing GI007 for generalized day/night work per building. Type of work, ILSM, noise generation, etc will all be consideration
75
07/01/2025
07/10/2025
Please confirm the TR room build outs can take place during normal working hours?
TR construction can typically take place during normal business hours. Noise producing activities (Core drilling) may need to be done after hours depending on the building / area.

VA: see table on drawing GI007 for generalized day/night work per building.

76
07/01/2025
07/10/2025
Please confirm if work in the corridors should be performed outside of normal working hours?
Some work will have to be performed outside of normal working hours; see spec section 01 00 00 I, J, K. Some work can be done during normal working hours such as work that does not disrupt normal operation of the facility and complies with all safety related measures for occupied buildings.
77
07/01/2025
07/10/2025
Please define off hours, we assume off hours to be second shift work but need confirmation.
Generalized normal working hours are defined in Spec Section 01 00 00 I. Any hour not “normal working hours” or on an “established holiday” would be considered off hours. The table on drawing GI007 will give a generalized day/night work allowance per building.
78
07/01/2025
07/10/2025
Section 01 00 00 general requirements “alterations includes that the GC will provide a thorough survey of areas in which work is to be done with the COR and VA representative in attendance”. Please confirm that the VA staff will schedule and have the time to do these surveys without delaying the contractor as these thorough surveys are extremely time-consuming.
AE: The VA will be engaging with a 3rd party Construction Manager for this project.

VA: The VA’s current staffing model for the duration of the subject EHRM project includes a COR, an alternate COR and two 3rd party full-time contracted construction managers. The staffing model is subject to change as personnel availability and project needs develop.

79
07/01/2025
07/10/2025
Please confirm the contractor is to assume no use of basket (cable) trays in the corridors for both new fiber line and data cables.
Re-use of existing trays may be possible on a case-by-case basis but should not be assumed.
80
07/01/2025
07/10/2025
Can the QC manager serve as the photographer for the demonstration and training recordings? The term “Commercial Photographer” is vague, has no licensing requirements or any other information required.
Yes
81
07/01/2025
07/10/2025
Please confirm contractor to provide (3) maxcell 3-pocket fabric innerducts (mxe86383) in each 4" conduit for the site duct banks.
On sheet TN502 add to detail E7 Note 5: Provide 3ea 3x3" Maxcell Innerduct (Or Equal) for each 4" conduit
82
07/01/2025
Reflected ceiling plans have not been provided for corridor areas, please identify ceiling types in corridors.
Assume ACT unless otherwise noted.
83
07/01/2025
Please confirm the General Contractor is to have two separate and direct contract with the DDC Contractor and the Systems Integrator.
The DDC, PACS, SSTV, Fire Alarm and other low voltage systems are extensions of existing systems. Contractor is expected to be able to extend, connect to and expand these systems without issues from the respective manufacturers.
84
07/01/2025
If system integration is required for this contract, please provide a set of specs for this scope of work.
The DDC, PACS, SSTV, Fire Alarm and other low voltage systems are extensions of existing systems. Contractor is expected to extend, connect to and expand these systems with new devices without issues from the respective manufacturers.

The DDC system and Fire Alarm systems are to be connected to with new ‘sub systems’: FM200, EPSMS / EPO, and Data Center Cooling Management. The facility DDC and Fire Alarm Systems will be used for reporting status of these sub system panels.

There is no expectation that a wholistic ‘Systems Integration’ effort is needed.

85
07/01/2025
Please confirm no advanced utility metering system is required for this scope of work.
Confirmed
86
07/01/2025
Please confirm the DDC Contractor is not a sole source vendor for the campus and this project.
See 23 09 23 for DDC requirements. The ‘DDC Contractor’ is not required to be a sole source.
87
07/01/2025
07/10/2025
Please confirm if Kahuah can be used on this project.
VA: See Attached Spec 01 33 24 – Electronic Submittals.

Our current pre-approved list of web-based services for submittal and tracking of construction submittals contains only “Submittal Exchange” but others may be submitted for approval. We are currently testing Kahuah and believe it does not adequately meet spec 01 33 24 1.5 A 4. Contractor may demonstrate compliance of their submitted service. Any additional/supplemental software/application required to meet the specification requirements will be at the contractor’s expense.

88
07/03/2025
07/10/2025
02 82 11, part 1-B it says that the there is an attached “Danville EHRM Hazardous Materials Crosswalk” document. This document can not be found in the attachment. Please confirm the information that this spec section is referencing is the drawings provided in Volume 3 of the Drawings.
Provided
89
07/06/2025
07/10/2025
Please provide 101.AE301 drawing sheet. It is listed in the table of contents but not included in the original bid documents set
Provided
90
07/06/2025
07/10/2025
Please provide 58.AE301 drawing sheet. It is listed in the table of contents but not included in the original bid documents set
Provided
91
7/10/2025
07/10/2025
ICRA requirements on drawing GI007 differ from those listed in the Specification section 01 01 10, which is correct?
The specification supersedes. Follow the specification.