This document is a specification section (01 33 24) detailing Electronic Submittal Procedures for a construction project. The section mandates the use of a web-based service for transmitting and tracking construction submittals electronically, with the primary goal of expediting the construction process by reducing paperwork and improving information flow.

Key requirements include using a web-based service (pre-approved option is Submittal Exchange) that provides web-based tracking, automated email notifications, document status tracking, and organized submittal storage. The contractor is responsible for all costs associated with the service, must have necessary hardware and software (including PDF review tools like Adobe Acrobat), and must prepare submittals in PDF format with a minimum 300 dpi resolution. Physical samples and color charts are excluded from the electronic submittal process. The contractor must submit a complete set of submittals on CD to the owner at project completion, and all submittals must be transmitted simultaneously to the Architect and Owner.

View the file

Other files

File Type Posted
Abstract of Bids OF 1419 - CONSTRUCTION - Signed 8.11.25.pdf PDF
36C77625B0011 0006.pdf PDF
Attachment 21 - Technical Questions - Danville IL 8-5-2025.pdf PDF
36C77625B0011 0005.docx DOCX document
Attachment 21 - Technical Questions - Danville IL 7-30-2025.pdf PDF
36C77625B0011 0004.pdf PDF
Attachment 23 - A-903.pdf PDF
Attachment 21 - Technical Questions - Danville IL 7-28-2025.pdf PDF
Solicitation 36C77625B0011 Amendment 0003 - Danville IL EHRM Construction.pdf PDF
Attachment 3 Construction Wage Rates Vermilion 7.25.25.pdf PDF
Attachment 20 - Stamped Civil Drawings.pdf PDF
Attachment 17 - FloorHeightTable.xlsx XLSX spreadsheet
Attachment 16 - FloorHeightTable.pdf PDF
Attachment 14 -101.AE301.pdf PDF
Attachment 12 - 58.AE301.pdf PDF
Amendment - 0002 36C77625B0011.pdf PDF
Attachment 22 - Electrical Single Line.pdf PDF
Attachment 13 - 58.AE401.pdf PDF
Attachment 11 - 02 82 11_Appendix_Asbestos Containing Materials Report Crosswalk.pdf PDF
Attachment 23 - Construction Wage Rates - Vermilion 7-11-25.pdf PDF
Attachment 21 - Technical Questions - Danville IL 7-15-2025.docx DOCX document
Attachment 19 - Soil Report Danville IL - 7-15-25.pdf PDF
Attachment 18 - RFI Log_EHRM Upgrades Danville IL.xls XLS spreadsheet
Amendment - 0001 36C77625B0011.pdf PDF
Attachment 6 Drawings Danville IL EHRM IU Construction Volume 1 of 3.pdf PDF
Attachment 5 Pre Construction Risk Assessment Danville IL EHRM IU.docx DOCX document
Attachment 9 Brand Name Justification Danville IL EHRM IU Construction.pdf PDF
Attachment 8 Drawings Danville IL EHRM IU Construction Volume 3 of 3.pdf PDF
Attachment 4 Site Visit Instructions EHRM IU 550 21 700.docx DOCX document
Attachment 3 Construction Wage Rates Vermilion 4 18 25.pdf PDF
Attachment 2 Specifications Danville IL EHRM IU Construction Volume 2 of 2.pdf PDF
36C77625B0011_1.docx DOCX document
Attachment 10 Limitations on Subcontracting Construction.pdf PDF
Attachment 7 Drawings Danville IL EHRM IU Construction Volume 2 of 3.pdf PDF
Attachment 1 Specifications Danville IL EHRM IU Construction Volume 1 of 2.pdf PDF
36C77625B0011.docx DOCX document
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

04-01-20

01 33 24 -1

SECTION 01 33 24

ELECTRONIC SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 DESCRIPTION:

A. This section specifies requirements for provision and use of an electronic, web-based service for submittal and tracking of construction submittals for the Project.

1.2 REFERENCED DOCUMENTS:

A. Additional submittal requirements: Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

1.3 SUMMARY:

A. The intent of electronic submittals is to expedite the construction process by reducing paperwork, improving information flow, and decreasing turnaround time.

B. Shop drawing and product data submittals shall be transmitted to Architect in electronic (PDF) format using a web-based service designed specifically for transmitting and tracking submittals between construction team members.

C. The electronic submittal process is not intended for color samples, color charts, or physical material samples.

1.4 GENERAL DESCRIPTION OF PROCEDURES:

A. Submittal Preparation - Contractor may use any or all of the following options:

1. Subcontractors and Suppliers provide electronic (PDF) submittals to Contractor via the selected web-based service.

2. Subcontractors and Suppliers provide paper submittals to General Contractor who electronically scans and converts to PDF format.

3. Subcontractors and Suppliers provide paper submittals to Scanning Service which electronically scans and converts to PDF format.

B. Contractor shall review, comment, and apply electronic stamp certifying that the submittal (as noted) complies with the requirements of the Contract Documents including verification of manufacturer / product, dimensions, and coordination of information with other parts of the work.

C. Contractor shall transmit each submittal to Architect and Owner (simultaneously) using the selected web-based service.

1. Architect / Engineer review comments will be made available on the selected web-based service. Contractor shall receive email notice of completed review.

01 33 24 -2

D. Distribution of reviewed submittals to subcontractors and suppliers is the responsibility of the Contractor.

1.5 REQUIREMENTS AND RESPONSIBILITIES:

A. The selected web-based service for submittal and tracking of construction submittals must provide:

1. Web-based tracking and approval system.

2. Automated email notice for new submittals and reminders for submittals approaching the review deadline.

3. Tracking and exchange of ITC/RFI/CO’s and other similar documents as well as product and equipment submittals.

4. Means for tracking of the status such documents including whether they have been approved and released by the Owner.

5. Organized storage of submittals that is accessible for review by the designated construction team members at any time.

6. Submit a complete set of submittals on CD to the Owner at the end of the Project. Include all submittals included product submittals, shop drawings, ITC/RFI/CO’s and other similar submittals.

B. Contractor responsibilities:

1. The cost of services shall be paid in full by the Contractor.

Contractor shall include the full cost of the service and all related costs in their proposal.

2. Training in the use of the service by the team members shall be at the option of the Contractor and, if chosen, shall be paid by the Contractor

3. Contractor shall have or obtain required hardware and software:

Internet Service and Equipment Requirements:

4. Email address and Internet access at Contractor’s main office.

5. Adobe Acrobat (www.adobe.com), Bluebeam PDF Revu (www.bluebeam.com), or other similar PDF review software for applying electronic stamps and comments.

6. Contractor shall prepare or have prepared all required submittals in the PDF format required.

(1) PDF files must be readable. As a general rule, a resolution of 300 dpi should be used.

(2) If the Architect can download more readable product data directly from the manufacturer’s website than was submitted by the Contractor, the Architect shall reserve the right to reject the submittal.

7. Other responsibilities for submittals shall be as described in Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

(1) Color samples, color charts, or physical material samples shall be submitted as described in Section 01 33 23.

1.6 ACCEPTABLE SERVICES:

A. Service must by pre-approved by the Owner.

http://www.adobe.com/ http://www.bluebeam.com/

01 33 24 -3

B. The Contractor may submit any service meeting these requirements for approval.

C. The following services have been pre-approved:

1. Submittal Exchange: 1-800-714-0024; www.submittalexchange.com.