AMENDMENT 0005 PRICE COST SCHEDULE.docx
DOCX document 18 KB Posted
- Solicitation number
- 36C77624R0087
About this file
This document is an amendment to the price/cost schedule for a federal contract opportunity to construct a new outpatient clinic for the Department of Veterans Affairs. The amendment includes five deduct alternates that describe potential reductions to the base bid scope of work, such as removing canopies, patios, and landscaping elements. The solicitation number is 36C77624R0087, and the contract is for the construction of a replacement outpatient clinic at the US Coast Guard Air Station for the Providence VA Medical Center. The base bid includes construction of the new clinic facility, with the deduct alternates providing options to reduce the overall scope and cost. No additional details on the response or award dates, set-asides, or incumbent information are provided in this document.
View the file
Other files
Show all 46
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT 0005 PRICE/COST SCHEDULE
ITEM INFORMATION June 20, 2024
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1.00 |
| JB |
| __________________ |
| __________________ |
ITEM I, GENERAL CONSTRUCTION:/BASE BID / Work includes Construction of new outpatient clinic located off Connery Ave on a greenfield site. Contract Period: Base POP Begin:
POP End:
| 1.00 |
| JB |
| __________________ |
| __________________ |
Deduct Alternate No. 1: Base Bid except delete canopies at staff entry, delete staff patio, delete pavers at main entrance and replace with concrete, provide manual operation folding partition between Rooms 112 and 113 in lieu of specified automatic operation folding partition, delete screen wall around MEP equipment.
| 1.00 |
| JB |
| __________________ |
| __________________ |
Deduct Alternate No. 02: Base Bid except delete “skylight” feature from Team Work Area 147. To be replaced with (10) standard troffer lights, asphalt shingle roof in lieu of Standing Seam.
| 1.00 |
| JB |
| __________________ |
| __________________ |
Deduct Alternate No. 03: Base Bid except fiber cement exterior wall in lieu of phenolic panel, replace brick wainscotting at exterior with 8x16 ground face CMU block and CMU sills, replace all manufactured casework with stick built millwork. All layouts, sizes and finishes to match contract documents.
| 1.00 |
| JB |
| __________________ |
| __________________ |
Deduct Alternate No. 04: Base Bid except asphalt sidewalks in lieu of concrete sidewalks, delete patient lift from Room 143. Patient lift to be owner provided and installed. Account for coordination with owner’s vendor. Delete trees and shrubs from landscaping, to be completed by owner at a later date. Landscaping limited to grass in all areas. Modular millwork to be removed from scope and to be provided and installed by owner. Delete folding partition between rooms 112 and 113. Delete curbing from all parking areas.
| GRAND TOTAL |
| __________________ |