About this file

This document contains questions and answers regarding a solicitation for renovating domestic water piping projects at a Veterans Affairs medical center. The solicitation requires contractors to submit price proposals not exceeding 20 pages by August 28, 2021. It clarifies that basement access for materials is available through a removable floor panel near the boiler room, and contractors are responsible for verifying piping lengths and accessing all areas of the basement. The scope of work does not include replacing the existing building management system, but contractors must connect new equipment to the current Andover/Schneider Electric BMS network. Reviewers should follow the instructions and past performance questionnaire in the solicitation, not a prior pre-solicitation notice.

View the file

Other files

File Type Posted
36C25821R0015 0006.docx DOCX document
Questions - RFI last Questions.pdf PDF
36C25821R0015 0005.docx DOCX document
CLC_RCP-A-131-2019-11-18.pdf PDF
CLC2_RCP-AE1-16-2019-11-18.pdf PDF
Second Set of Questions.pdf PDF
36C25821R0015 0004.docx DOCX document
Site Walk Sign In Sheet.pdf PDF
36C25821R0015 0003.docx DOCX document
Volume II Building 1 Loma Linda Final.pdf PDF
36C25821R0015 0002.docx DOCX document
36C25821R0015 0001.pdf PDF
S02 DWG FINAL SUBMITTAL-VOL2 Part C 22 Dec 20.pdf PDF
S02 DWG FINAL SUBMITTAL-VOL2 Part B 22 Dec 20.pdf PDF
S02 DWG FINAL SUBMITTAL-VOL1 PART A 22 Dec 20.pdf PDF
S02 DWG FINAL SUBMITTAL-VOL1 PART B 22 Dec 20.pdf PDF
S02 DWG FINAL SUBMITTAL-VOL2 Part A 22 Dec 20.pdf PDF
Attachment J Legionella 1061 Directive.pdf PDF
Attachment F AWWA C651-14 Disinfecting Water Mains.pdf PDF
Attachment H Loma Linda HCS Infection Prevention Guide.pdf PDF
Attachment C Self Performance Calculations.docx DOCX document
Attachment B Bid Breakout Form.docx DOCX document
S20 SPEC FINAL SUBMITTAL 22 Dec 20.pdf PDF
Attachment I 1061 D 2021-02-16.pdf PDF
Attachment E Davis Bacon Wage 06.25.21.docx DOCX document
Attachment A Instructions for Contractors 07.27.docx DOCX document
Attachment G Part 8 ICRA for Loma Linda Renovate Domestic Piping.doc DOC document
Attachment D Past Performance Survey 07.27.docx DOCX document
36C25821R0015_1.docx DOCX document
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Page Limit on Price Proposal: Solicitation puts a 5-page limit on price proposal but requires:

1 page – Cover Sheet 1 page – Table of Contents 2 page – SF1442 2 page – Price schedule 1 page – Attach B, continuation page for Box 17, bid price break out 1 page – VETS 100 report 3 page – Safety % EMR letters 1 page – Attach C, Self perform calcs 4 - page bid bond Minimum of 16 pages required, not counting if signed amendment cover sheets are also to be included... to fit in a 5 page limitation. Can the Page restriction on the price proposal be expanded?

The volume page limit for Price was changed from Five (5) to Twenty (20).

2. During the site walk, recently replaced/installed 20’ copper piping was observed. Can the VA provide details on how 20’ lengths of material were brought into the basement?

Boiler Room 1D-16 there is a removable floor panel that can be removed for basement access. This will be up to the contractor to provide a forklift and manpower to remove and reinstall the floor panel. All materials for the basement can be lowered through this area. There is a fire sprinkler that will have to be moved before the panel is removed and reinstalled after the panel is set back in place and sealed with appropriate materials. Half of the basement is accessible for 20’ sections of piping. Contractor will be responsible for verifying the piping lengths for the other half of the hospital basement.

3. During the site walk, comments were made that there is “no work inside walls”. Can the VA clarify?

AE Response: The question did not indicate which wall. Refer to the contract documents. The point of connection and the scope of work is specified on plans.

4. Do the existing Siemens panels in service bays get removed and replaced with Andover/Schneider Electric panels, or is that scope a separate project / future?

AE Response: Replacing the existing BMS system is not in the scope of work. Connect the new chlorine analyzer control panels to the existing BMS network. Contractor to modify the current BMS system to receive new equipment per contract documents as required. COR Response: Current systems is Andover provided by Schneider Electric.

5. The (PPQ) Past Performance Questionnaire included in the pre-solicitation notice is different from the PPQ included as Attachment D and specifically called out in instructions to bidders. Confirm the Solicitation PPQ form supersedes the Pre-Solicitation PPQ form.

Follow instructions from the Solicitation NOT Pre-Solicitation. Review the solicitation Attachment A Instructions to Contractors Factor 2 – Past Performance Attachment D.