36C25821R0015_1.docx
DOCX document 104 KB Posted
- Attached to
- Z1DA--Service-Renovate Domestic Water Piping Projects FMS (VA-21-00001742)605-21-1-6043-0001-
- Solicitation number
- 36C25821R0015
About this file
This is a solicitation for construction services to renovate the domestic water piping system at the Jerry L. Pettis Memorial Veterans Medical Center in Loma Linda, California. The solicitation requires contractors to provide all labor, materials, tools, equipment, engineering, supervision, and services to complete the project, which includes removing dead legs, upgrading galvanized steel piping, renovating the chiller plant, and providing hot and cold water insulation. Interested contractors must attend a mandatory site visit. Proposals are due no later than August 28, 2021 by 2:00 PM Pacific Time. The award will be made using the Lowest Priced Technically Acceptable method to a verified Service-Disabled Veteran-Owned Small Business. The period of performance for the base item is 270 calendar days from notice to proceed.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25821R0015
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C25821R0015 X 07-28-2021 605-21-1-6043-0001 605-20-201 Department of Veterans Affairs NCO22-Gilbert Network Contracting 777 E. Missouri Ave Suite 300 Phoenix
AZ
85014 Department of Veterans Affairs Phoenix VA Healthcare System 777 E. Missouri, Suite 300 Phoenix
AZ
85014 Xochi Valdivia 480-466-7927 Project 605-20-201 Renovate Domestic Water Piping Award will be made using Lowest Priced Technically Acceptable solicitation method. This project includes:
Provide all labor, materials, tools, equipment, engineering, supervision, and services to renovate domestic water piping system at the Jerry L. Pettis Memorial Veterans Medical Center (LLVAMC), Loma Linda, California.
The renovation will involve but not be limited to removal of dead legs, upgrade galvanized steel piping, renovate chiller plant, and providing hot and cold-water insulation.
Awardee shall perform work in strict accordance with General Specifications, Statement of Work, Attachments, Schedule, Site Drawings, and terms and conditions set forth within contract documents.
Interested contractors are highly encouraged to attend the site visit walk. Each prime contractor may bring up to 3 individuals (including subcontractors).
RSVP: Submit Company and Individuals Names via email to: Xochipilli.Valdivia@va.gov and Tina.Kennedy@va.gov no later than 0900 AZ Time, 02 August 2021 Subject Line of the email: "SITE WALK ATTENDEES, 36C25821R0015, 605-20-201 YOUR COMPANY NAME" Follow CDC and VHA COVID-19 guidelines at alltime. MASKS ARE REQUIRED in all areas at the Loma Linda VA Medical SITE VISIT CONFERENCE: 06 August 2021, 10:00 am PST. Confirmation emailing will be sent to interested bidders. Meeting area for conference: MD-05D FMS (FMS Conference Room) Check in at front entrance for screening. VA Employee will be in front lobby. Interested contractors should review Instructions for Contractors (Attachment A).
RFI's Due: NLT 10 days before solicitation closing 14 August 2021, 2pm Arizona Time. All RFIs must be submitted in writing. Proposals due NLT 28 August 2021, 2pm PST.
This requirement is 100% set aside for SDVOSB concerns pursuant to Public Law 109-461 (38USC 8127). The SDVOSB is required to perform 15% of the construction work.
Magnitude of project is between $5,000,000 and $10,000,000
Applicable NAICS Code and Size Standard for this acquisition is 236220 / $39.5 Million
Proposal amount shall include Material cost, Labor cost, Overhead, Profit, and Grand Total. This information is required and may be used in the event of possible future modifications.
Proposals will be evaluated on Grand Total amount and Additive Alternatives per VAAR 836.580.
ALL PROPOSALS MUST BE SUBMITTED VIA EMAIL to Xochipilli.Valdivia@va.gov and Tina.Kennedy@va.gov Subject Line of the email: "Solicitation, 36C25821R0015, 605-20-201,YOUR COMPANY'S NAME" Schedule X X 52.211-10 X See Instructions
2PM
MDT
08-27-2021 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
Department of Veterans Affairs NCO22-Gilbert Network Contracting 777 E. Missouri Ave Suite 300 Phoenix
AZ
85014 This is accomplished through the Tungsten Network located at:
http://www.fsc.va.gov/einvoice.asp This is mandatory and the sole method for submitting invoices.
X Tina M. Kennedy
VA-VHA-2020-F1EDF803
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| SECTION B - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK | 5 |
| SECTION A - SUPPLIES OR SERVICES AND PRICE/COSTS | 8 |
| A.1 PRICE/COST SCHEDULE | 9 |
| ITEM INFORMATION | 9 |
| A.2 DELIVERY SCHEDULE | 9 |
| SECTION C - CONTRACT CLAUSES | 11 |
| C.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 11 |
| C.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) | 11 |
| C.3 52.219-14 LIMITATIONS ON SUBCONTRACTING (MAR 2020) | 11 |
| C.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (NOV 2020) | 12 |
| C.5 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020) | 14 |
| C.6 52.223-21 FOAMS (JUN 2016) | 15 |
| C.7 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (JAN 2021) ALTERNATE I (JAN 2021) | 15 |
| C.8 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) ALTERNATE I (MAY 2014) | 20 |
| C.9 SUPPLEMENTAL INSURANCE REQUIREMENTS | 21 |
| C.10 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 24 |
| C.11 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018) | 24 |
| C.12 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION) | 25 |
| C.13 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 27 |
| C.14 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008) | 27 |
| C.15 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 27 |
| C.16 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018) | 28 |
| C.17 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018) | 28 |
| C.18 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 30 |
| C.19 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 31 |
| C.20 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019) | 32 |
| C.21 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019) | 32 |
| C.22 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020) | 32 |
| C.23 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) | 33 |
| C.24 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019) | 33 |
| C.25 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) | 35 |
| SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS | 36 |
| SECTION E - SOLICITATION PROVISIONS | 37 |
| E.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 37 |
| E.2 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020) (JUL 2020) (DEVIATION) | 37 |
| E.3 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (OCT 2020) | 40 |
| E.4 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 42 |
| E.5 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (FEB 2021) | 43 |
| E.6 52.216-1 TYPE OF CONTRACT (APR 1984) | 45 |
| E.7 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 45 |
| E.8 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 45 |
| E.9 52.233-2 SERVICE OF PROTEST (SEP 2006) | 46 |
| E.10 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 46 |
| E.11 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018) | 47 |
SECTION B - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
REQUEST FOR proposal for construction services (Renovate DOMESTIC WATER PIPING) Project No. 605-20-201
SCOPE OF WORK
General Requirement: Experienced contractor with demonstrated VA Directive 1061 Legionella mitigation experience and extensive water piping experience. Provide all labor, materials, tools, equipment, engineering, supervision, and services to renovate domestic water piping system at the Jerry L. Pettis Memorial Veterans Medical Center (LLVAMC), Loma Linda, California.
Project Scope: The renovation will involve but not be limited to removal of dead legs, upgrade galvanized steel piping, renovate chiller plant, and providing hot and cold-water insulation.
GENERAL REQUIREMENTS
General Construction services: The contractor will furnish all materials, equipment, supervision, and personnel necessary to accomplish the project as indicated on the contractual documents. The project will involve but not be limited to trades required for the complete renovation of areas indicated on the drawings.
The project Architect/Engineer hired by the VA has prepared drawings and specifications which are part of this SOW and are to be used for the completion of this project.
All employees of the general contractor and subcontractors shall comply with the VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
Prior to commencing work, the general contractor shall provide proof that an OSHA certified “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.
Key Personnel and Minimum Experience/Certification Required: General Contractors Superintendent. 8 years’ plumbing experience with legionella mitigation / renovation experience.
Prior to the commencement of work, the general contractor shall conduct a site walk with the VA COTR, VA Interior Designer, VA Safety Manager and VA Infection Control Agent.
The general contractor shall establish and maintain a fire protection program in accordance with 29 CFR 1926.
The general contractor shall implement the requirements of the VA Infection Control Risk Assessment (ICRA) team, including the establishment and maintenance of a dust control program.
The general contractor shall implement all measures and requirements of the Radiation Control Plan, including but not limited to proper radiation barriers, energy output of the unit, workload, distance, occupancy of surrounding areas and existing structural materials.
Upon completion of the site walk. The general contractor will be issued a Work Permit, ILSM and IC implementation permit.
Contractor will provide all documentation per Specifications and validated by the submittal registry to the COTR prior to work.
Building utility shutdowns require a 21-day minimum notification from the general contractor and must be coordinated with the VA COR and facility shop supervisors. General contractor to minimize the interruption to hospital operations. This may require performing utility shutdowns after-hours and/or weekends.
CONSTRUCTION COST
Per contracted amount, See Contract documents.
ENVIRONMENTAL/OCCUPATIONAL SAFETY AND HEALTH (EOSH)
EXPECTATION: All General Contractor submissions for project shall contain language that addresses all applicable EOSH requirements.
Regulatory Compliance – EOSH requirements for work performed at the above location can be found in:
Volume 29 of the Code of Federal Regulations, Part 1910 – Occupational Safety for General Industry
Volume 29 of the Code of Federal Regulations, Part 1926 – Occupational Safety for The Construction Industry
Volume 40 of the Code of Federal Regulations – Protection of The Environment
Volume 49 of the Code of Federal Regulations, Part 397 – Transportation of Hazardous Materials
Specifications is as provided in this solicitation.
SITE SURVEY
EXPECTATION: Contractor will make site visits as necessary to survey existing conditions.
Make site visits as required to determine existing as-built conditions affecting this project. May include power metering, air flow testing, utility Survey, etc.)
Provide any civil, structural, architectural, electrical, and mechanical investigative work including exterior site work, of both existing and designed systems necessary to ensure the accuracy of the design.
Prepare any measured drawings of existing systems of facility required to ensure the accuracy of the design.
NOTE: Information including drawings and other documentation provided to the general contractor is used as reference only. All additional references and specifications are available in VHA’s Technical Information Library at address http://www.cfm.va.gov. AutoCAD background drawings will be provided by the VA upon request.
The general contractor shall field verify all dimensions and submit shop drawings for approval by contracting officer. Coordinate site visits with the COTR.
CONTRACT DURATION
Construction Contract Duration please reference schedule.
36C25821R0015
Page 1 of Page 1 of
SECTION A - SUPPLIES OR SERVICES AND PRICE/COSTS
36C25821R0015
Page 1 of Page 1 of
DESCRIPTION OF WORK: Provide all labor, materials, tools, equipment, engineering, supervision, and services to renovate domestic water piping system at the Jerry L. Pettis Memorial Veterans Medical Center (LLVAMC), Loma Linda, California. The renovation will involve but not be limited to removal of dead legs, upgrade galvanized steel piping, renovate chiller plant, and providing hot and cold-water insulation. Awardee shall perform work in strict accordance with General Specifications, Statement of Work, Attachments, Schedule, Site Drawings, and terms and conditions set forth within contract documents.
BASIS OF AWARD: A single award will be made on Line Item No. 1, but in the event there is insufficient funds available, a single award will be made on Line Item No. II, Line Item No. III, or Line Item No. IV, in that order, based on available funding. The line items are listed in descending order of importance. Offerors shall provide a total contract price on each line item listed. The project’s period of performance is reflected in each bid line item.
STATEMENT OF BID ITEM(S):
A. ITEM I: Renovate Domestic Water Piping: Work includes general construction, alterations, necessary removal of existing structures and construction and certain other items. Offeror to use offered price for the work and not the deducted amount in the “Total Bid Item Price”.
Completion Time: 270 Calendar Days. Total Bid Item 1 Price $____________
B. ITEM II: DEDUCTIVE ALTERNATE NO.1: All work associated with ITEM – I, minus Chlorine Analyzer Systems (CAS-1 & CAS-2), at Eight (8) Service bays on all Four (4) Floors for a total of Thirty-Two (32) locations.
(Proposed price it the amount after taking the deducted amount out of the proposal, not the amount of the deducted price – The cost for the work)
Completion Time: 250 Calendar Days. Total Bid Item II Price $_____________
C. ITEM III: DEDUCTIVE ALTERNATE NO.2: All work associated with ITEM – II, minus Water Flow Meters, at Eight (8) Service bays on all Four (4) Floors for a total of Thirty-Two (32) locations.
(Proposed price it the amount after taking the deducted amount out of the proposal, not the amount of the deducted price – The cost for the work)
Completion Time: 240 Calendar Days. Total Bid Item III Price $_____________
D. ITEM IV: DEDUCTIVE ALTERNATE NO.3: All work associated with ITEM – III, minus Cold Water Heat Exchanger (HXT-1).
(Proposed price it the amount after taking the deducted amount out of the proposal, not the amount of the deducted price – The cost for the work)
Completion Time: 230 Calendar Days. Total Bid Item IV Price $_____________
A.1 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1.00 |
| JB |
| __________________ |
| __________________ |
Renovate Domestic Water Piping: Work includes general construction, alterations, necessary removal of existing structures and construction and certain other items.
Offeror to use offered price for the work and not the deducted amount in the “Total Bid Item Price”.
| 1.00 |
| JB |
| __________________ |
| __________________ |
DEDUCTIVE ALTERNATE NO.1: All work associated with ITEM – I, minus Chlorine Analyzer Systems (CAS-1 & CAS-2), at Eight (8) Service bays on all Four (4) Floors for a total of Thirty-Two (32) locations.
(Proposed price it the amount after taking the deducted amount out of the proposal, not the amount of the deducted price – The cost for the work)
| 1.00 |
| JB |
| __________________ |
| __________________ |
DEDUCTIVE ALTERNATE NO.2: All work associated with ITEM – II, minus Water Flow Meters, at Eight (8) Service bays on all Four (4) Floors for a total of Thirty-Two (32) locations
(Proposed price it the amount after taking the deducted amount out of the proposal, not the amount of the deducted price – The cost for the work)
| 1.00 |
| JB |
| __________________ |
| __________________ |
DEDUCTIVE ALTERNATE NO.3: All work associated with ITEM – III, minus Cold Water Heat Exchanger (HXT-1).
(Proposed price it the amount after taking the deducted amount out of the proposal, not the amount of the deducted price – The cost for the work)
| GRAND TOTAL |
| __________________ |
A.2 DELIVERY SCHEDULE
| ITEM NUMBER |
| QUANTITY |
| DELIVERY DATE |
| 0001 |
| SHIP TO: |
| Department of Veterans Affairs |
Loma Linda VAMC 11201 Benton Street Loma Linda, CA 92357
USA
| 1.00 |
| 270 Calendar Days |
| INSTRUCTIONS: |
| From date of notice to proceed. |
| 0002 |
| SHIP TO: |
| Department of Veterans Affairs |
Loma Linda VAMC 11201 Benton Street Loma Linda, CA 92357
USA
| 1.00 |
| 250 Calendar Days |
| INSTRUCTIONS: |
| From date of notice to proceed. |
| 0003 |
| SHIP TO: |
| Department of Veterans Affairs |
Loma Linda VAMC 11201 Benton Street Loma Linda, CA 92357
USA
| 1.00 |
| 240 Calendar Days |
| INSTRUCTIONS: |
| From date of notice to proceed. |
| 0004 |
| SHIP TO: |
| Department of Veterans Affairs |
Loma Linda VAMC 11201 Benton Street Loma Linda, CA 92357
USA
| 1.00 |
| 230 Calendar Days |
| INSTRUCTIONS: |
| From date of notice to proceed. |
Page 1 of Page 1 of Page 1 of Page 1 of
SECTION C - CONTRACT CLAUSES
C.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/
(End of Clause) C.2 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than Schedule days after receipt of notice to proceed. The time stated for completion shall include final cleanup of the premises.
The completion date is based on the assumption that the successful offeror will receive the notice to proceed by 30 days after award. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
(End of Clause)
C.3 52.219-14 LIMITATIONS ON SUBCONTRACTING (MAR 2020)
(a) This clause does not apply to the unrestricted portion of a partial set-aside.
(b) Applicability. This clause applies only to—
(1) Contracts that have been set aside for small business concerns or 8(a) participants;
(2) Part or parts of a multiple-award contract that have been set aside for small business concerns or 8(a) participants;
(3) Orders set aside for small business concerns or 8(a) participants under multiple-award contracts as described in 8.405-5 and 16.505(b)(2)(i)(F);
(4) Orders issued directly to small business concerns or 8(a) participants under multiple-award contracts as described in 19.504(c)(1)(ii).
(c) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees that in performance of the contract in the case of a contract for—
(1) Services (except construction). At least 50 percent of the cost of contract performance incurred for personnel shall be expended for employees of the concern.
(2) Supplies (other than procurement from a nonmanufacturer of such supplies). The concern shall perform work for at least 50 percent of the cost of manufacturing the supplies, not including the cost of materials.
(3) General construction. The concern will perform at least 15 percent of the cost of the contract, not including the cost of materials, with its own employees.
(4) Construction by special trade contractors. The concern will perform at least 25 percent of the cost of the contract, not including the cost of materials, with its own employees.
(d) The Contractor shall comply with the limitations on subcontracting as follows:
(1) For contracts, in accordance with paragraph (b)(1) and (2) of this clause— [Contracting Officer check as appropriate.] _ By the end of the base term of the contract and then by the end of each subsequent option period; or _ By the end of the performance period for each order issued under the contract.
(2) For orders, in accordance with paragraphs (b)(3) and (4) of this clause, by the end of the performance period for the order.
(End of Clause)
C.4 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (NOV 2020)
(a) Definitions. As used in this clause— Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern—
(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (d) of this clause. Such a concern is ‘‘not dominant in its field of operation’’ when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.
(2) Affiliates, as used in this definition, means business concerns, one of whom directly or indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.
(b) If the Contractor represented that it was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (f) of this clause or, if applicable, paragraph (h) of this clause, upon occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts—
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c) If the Contractor represented that it was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (f) of this clause or, if applicable, paragraph (h) of this clause, when the Contracting Officer explicitly requires it for an order issued under a multiple-award contract.
(d) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code(s) assigned to this contract. The small business size standard corresponding to this NAICS code(s) can be found at https://www.sba.gov/document/support--table-size-standards.
(e) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.
(f) Except as provided in paragraph (h) of this clause, the Contractor shall make the representation(s) required by paragraph (b) and (c) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause, or with its offer for an order (see paragraph (c) of this clause), that the data have been validated or updated, and provide the date of the validation or update.
(g) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (f) or (h) of this clause.
(h) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
(1) The Contractor represents that it [ ] is, [ ] is not a small business concern under NAICS Code 236220 assigned to contract number .
(2) [Complete only if the Contractor represented itself as a small business concern in paragraph (h)(1) of this clause.] The Contractor represents that it [ ] is, [ ] is not, a small disadvantaged business concern as defined in 13 CFR 124.1002.
(3) [Complete only if the Contractor represented itself as a small business concern in paragraph (h)(1) of this clause.] The Contractor represents that it [ ] is, [ ] is not a women-owned small business concern.
(4) Women-owned small business (WOSB) concern eligible under the WOSB Program. [Complete only if the Contractor represented itself as a women-owned small business concern in paragraph (h)(3) of this clause.] The Contractor represents that—
(i) It [ ] is, [ ] is not a WOSB concern eligible under the WOSB Program, has provided all the required documents to the WOSB Repository, and no change in circumstances or adverse decisions have been issued that affects its eligibility; and
(ii) It [ ] is, [ ] is not a joint venture that complies with the requirements of 13 CFR part 127, and the representation in paragraph (h)(4)(i) of this clause is accurate for each WOSB concern eligible under the WOSB Program participating in the joint venture. [The Contractor shall enter the name or names of the WOSB concern eligible under the WOSB Program and other small businesses that are participating in the joint venture: _____.] Each WOSB concern eligible under the WOSB Program participating in the joint venture shall submit a separate signed copy of the WOSB representation.
(5) Economically disadvantaged women-owned small business (EDWOSB) concern. [Complete only if the Contractor represented itself as a women-owned small business concern eligible under the WOSB Program in (h)(4) of this clause.] The Contractor represents that—
(i) It [ ] is, [ ] is not an EDWOSB concern eligible under the WOSB Program, has provided all the required documents to the WOSB Repository, and no change in circumstances or adverse decisions have been issued that affects its eligibility; and
(ii) It [ ] is, [ ] is not a joint venture that complies with the requirements of 13 CFR part 127, and the representation in paragraph (h)(5)(i) of this clause is accurate for each EDWOSB concern participating in the joint venture. [The Contractor shall enter the name or names of the EDWOSB concern and other small businesses that are participating in the joint venture: _____.] Each EDWOSB concern participating in the joint venture shall submit a separate signed copy of the EDWOSB representation.
(6) [Complete only if the Contractor represented itself as a small business concern in paragraph (h)(1) of this clause.] The Contractor represents that it [ ] is, [ ] is not a veteran-owned small business concern.
(7) [Complete only if the Contractor represented itself as a veteran-owned small business concern in paragraph (h)(6) of this clause.] The Contractor represents that it [ ] is, [ ] is not a service-disabled veteran-owned small business concern.
(8) [Complete only if the Contractor represented itself as a small business concern in paragraph (h)(1) of this clause.] The Contractor represents that—
(i) It [ ] is, [ ] is not a HUBZone small business concern listed, on the date of this representation, on the List of Qualified HUBZone Small Business Concerns maintained by the Small Business Administration, and no material changes in ownership and control, principal office, or HUBZone employee percentage have occurred since it was certified in accordance with 13 CFR part 126; and
(ii) It [ ] is, [ ] is not a HUBZone joint venture that complies with the requirements of 13 CFR part 126, and the representation in paragraph (h)(8)(i) of this clause is accurate for each HUBZone small business concern participating in the HUBZone joint venture. [The Contractor shall enter the names of each of the HUBZone small business concerns participating in the HUBZone joint venture: _____.] Each HUBZone small business concern participating in the HUBZone joint venture shall submit a separate signed copy of the HUBZone representation.
[Contractor to sign and date and insert authorized signer's name and title.] (End of Clause)
C.5 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)
(a) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-741.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified individuals on the basis of disability, and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.
(b) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of the threshold specified in Federal Acquisition Regulation (FAR) 22.1408(a) on the date of subcontract award, unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs of the U.S. Department of Labor, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
(End of Clause)
C.6 52.223-21 FOAMS (JUN 2016)
(a) Definitions. As used in this clause— Global warming potential means how much a given mass of a chemical contributes to global warming over a given time period compared to the same mass of carbon dioxide. Carbon dioxide's global warming potential is defined as 1.0.
High global warming potential hydrofluorocarbons means any hydrofluorocarbons in a particular end use for which EPA's Significant New Alternatives Policy (SNAP) program has identified other acceptable alternatives that have lower global warming potential. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables of alternatives available at http://www.epa.gov/snap/.
Hydrofluorocarbons means compounds that contain only hydrogen, fluorine, and carbon.
(b) Unless otherwise specified in the contract, the Contractor shall reduce its use, release, and emissions of high global warming potential hydrofluorocarbons and refrigerant blends containing hydrofluorocarbons, when feasible, from foam blowing agents, under this contract. When determining feasibility of using a particular alternative, the Contractor shall consider environmental, technical, and economic factors such as—
(1) In-use emission rates, energy efficiency, and safety;
(2) Ability to meet performance requirements; and
(3) Commercial availability at a reasonable cost.
(c) The Contractor shall refer to EPA's SNAP program to identify alternatives. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables available at http://www.epa.gov/snap/.
(End of Clause) C.7 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (JAN 2021) ALTERNATE I (JAN 2021)
(a) Definitions. As used in this clause— Bahrainian, Mexican, or Omani construction material means a construction material that—
(1) Is wholly the growth, product, or manufacture of Bahrain, Mexico or Oman; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in Bahrain, Mexico, or Oman into a new and different construction material distinct from the materials from which it was transformed.
Caribbean Basin country construction material means a construction material that—
(1) Is wholly the growth, product, or manufacture of a Caribbean Basin country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a Caribbean Basin country into a new and different construction material distinct from the materials from which it was transformed.
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is—
(i) A commercial item (as defined in paragraph (1) of the definition at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
Component means an article, material, or supply incorporated directly into a construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Designated country means any of the following countries:
(1) A World Trade Organization Government Procurement Agreement (WTO GPA) country (Armenia, Aruba, Australia, Austria, Belgium, Bulgaria, Canada, Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Moldova, Montenegro, Netherlands, New Zealand, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Taiwan, Ukraine, or United Kingdom);
(2) A Free Trade Agreement (FTA) country (Australia, Bahrain, Canada, Chile, Colombia, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Korea (Republic of), Mexico, Morocco, Nicaragua, Oman, Panama, Peru, or Singapore);
(3) A least developed country (Afghanistan, Angola, Bangladesh, Benin, Bhutan, Burkina Faso, Burundi, Cambodia, Central African Republic, Chad, Comoros, Democratic Republic of Congo, Djibouti, Equatorial Guinea, Eritrea, Ethiopia, Gambia, Guinea, Guinea-Bissau, Haiti, Kiribati, Laos, Lesotho, Liberia, Madagascar, Malawi, Mali, Mauritania, Mozambique, Nepal, Niger, Rwanda, Samoa, Sao Tome and Principe, Senegal, Sierra Leone, Solomon Islands, Somalia, South Sudan, Tanzania, Timor-Leste, Togo, Tuvalu, Uganda, Vanuatu, Yemen, or Zambia); or
(4) A Caribbean Basin country (Antigua and Barbuda, Aruba, Bahamas, Barbados, Belize, Bonaire, British Virgin Islands, Curacao, Dominica, Grenada, Guyana, Haiti, Jamaica, Montserrat, Saba, St. Kitts and Nevis, St. Lucia, St. Vincent and the Grenadines, Sint Eustatius, Sint Maarten, or Trinidad and Tobago).
Designated country construction material means a construction material that is a WTO GPA country construction material, an FTA country construction material, a least developed country construction material, or a Caribbean Basin country construction material.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both—
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if—
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of ‘‘cost of components’’.
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Free Trade Agreement country construction material means a construction material that—
(1) Is wholly the growth, product, or manufacture of a Free Trade Agreement (FTA) country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a FTA country into a new and different construction material distinct from the materials from which it was transformed.
Least developed country construction material means a construction material that—
(1) Is wholly the growth, product, or manufacture of a least developed country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a least developed country into a new and different construction material distinct from the materials from which it was transformed.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
United States means the 50 States, the District of Columbia, and outlying areas.
WTO GPA country construction material means a construction material that—
(1) Is wholly the growth, product, or manufacture of a WTO GPA country; or
(2) In the case of a construction material that consists in whole or in part of materials from another country, has been substantially transformed in a WTO GPA country into a new and different construction material distinct from the materials from which it was transformed.
(b) Construction materials.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction material, excluding COTS fasteners. (See FAR 12.505(a)(2)). In addition, the Contracting Officer has determined that the WTO GPA and all the Free Trade Agreements except the Bahrain FTA, NAFTA, and the Oman FTA apply to this acquisition. Therefore, the Buy American statute restrictions are waived for designated country construction materials other than Bahrainian, Mexican, or Omani construction materials.
(2) The Contractor shall use only domestic or designated country construction material other than Bahrainian, Mexican, or Omani construction material in performing this contract, except as provided in paragraphs (b)(3) and (b)(4) of this clause.
(3) The requirement in paragraph (b)(2) of this clause does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
N/A
(4) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(3) of this clause if the Government determines that—
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the restrictions of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(4) of this clause shall include adequate information for Government evaluation of the request, including—
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting…
This is the start of the file's text. The full file is on GovTribe.