36C25219B0056-0003019.pdf
PDF 931 KB Posted
- Solicitation number
- 36C25219B0056
About this file
36C25219B0056 0003 S06 - GI203 - PROJECT PHASING PLAN-SECOND FLOOR.pdf
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PHASE 5
PHASE 4
PHASE 10
PHASE 8
PHASE 13
WING A WING B WING C WING D
Drawing Title
Approved for Design Concept:
Project Title
Date
Location
Checked By:
Building Number
Project Number
Drawing Number
Drawn By:
Revisions: Date
ARCHITECT/ENGINEERS:
CLEMENT J. ZABLOCKI VAMC
#6 o n e e i g h t h i n c h o n e f o o t 1 t h r e e i n c h e s o n e f o o t o n e a n d o n e h a l f i n c h e s o n e f o o t o n e i n c h o n e f o o t t h r e e q u a r t e r s i n c h o n e f o o t o n e h a l f i n c h o n e f o o t t h r e e e i g h t h s i n c h o n e f o o t o n e q u a r t e r i n c h o n e f o o t
B
A
C
D
E
F
1 2 3 4 5 6 7 9
F
E
D
C
B
A
97 8654321
OFFICE OF
FACILITIES
MANAGEMENT
VA Project Number 695-16-112
FIRE SPRINKLER ENGINEER
RTM CONSULTANTS, INC
6640 Parkdale Place, Suite J, Indianapolis, IN 46254
PHONE: (317) 329-7700
905 N. CAPITOL AVE. SUITE 100 INDIANAPOLIS, IN. 46204
317.800.6388 WWW.GUIDONDESIGN.COM
SUSTAINABLE ARCHITECTURE + ENGINEERING
PROJECT LEAD
Architect, Structural Engineer, Civil Engineer
CLEMENT J. ZABLOCKI VA MEDICAL CENTER
MILWAUKEE, WISCONSIN
C :\U se rs
\k al le n\
D oc um en ts \1
4.
.0
Bl dg .S pr in kl er
R ep la ce m en t 6
-1 6-
2_ ka lle n.
rv t
GI203
FDCMC
PROJECT PHASING PLAN - SECOND FLOOR 14.1020.06BUILDING 6 FIRE
SPRINKLER REPLACEMENT
SCALE: 1/16" = 1'-0"GI203
1 PROJECT PHASING PLAN - SECOND FLOOR
N
CRITICAL PATH METHOD/ PHASING
THE CONSTRUCTION WILL BE PHASED FOR CONTINUED OCCUPANCY OF THE BUILDING. THE BUILDING IS CURRENTLY UNDER FIRE WATCH. IN AN EFFORT TO LIMIT CORING OF FLOORS AND CUTTING OF WALLS TO AVOID UNKNOWN HAZARDOUS MATERIALS EXISTING PIPING PENETRATIONS WILL BE REUSED. FIRE PROTECTION SYSTEMS SERVICES WILL BE DISRUPTED.
PROCEDURES WILL BE INCORPORATED TO MAINTAIN EQUIVALENT LEVELS OF SAFETY WHILE SYSTEMS ARE DOWN. AREAS WHERE THE SPRINKLER SYSTEM IS OUT OF SERVICE WILL BE SEPARATED BY TEMPORARY SMOKE-TIGHT CONSTRUCTION PARTITIONS OF GYPSUM BOARD OR OTHER APPROVED NON- COMBUSTIBLE OR LIMITED-COMBUSTIBLE MATERIAL. PARTITIONS SHALL BE FULL HEIGHT, EXTENDING THROUGH SUSPENDED CEILINGS TO THE FLOOR SLAB OR ROOF DECK ABOVE AND SHALL
BE ONE-HOUR FIRE RATED
IN ORDER TO LIMIT THE AFFECTED AREA, THE SPRINKLER SYSTEM WILL BE REPLACED BY “ZONES”, BY FLOOR AND BUILDING. IN THE FIRST PHASE THE EXISTING INCOMING SERVICE RISERS WILL BE REPLACED AND NEW RISERS WILL BE INSTALLED IN THE STAIRWAY OF EACH WING. AFTER INSTALLATION OF THE NEW RISERS THE EXISTING SPRINKLERS SYSTEMS PROTECTING THE BUILDING WILL BE REMOVED IN THE FOLLOWING ORDER AND REPLACED. EXISTING PENETRATIONS OF WALLS AND FLOORS WILL
BE REUSED TO LIMIT ADDITIONAL DAMAGE TO EXISTING BUILDING.
PHASE 1: INSTALL NEW RISERS FOR WINGS A, B, C AND D IN BASEMENT AND INSTALL NEW DRY PIPE RISERS TO SERVE NEW ATTIC DRY PIPE SYSTEMS IN A AND C WINGS. PROVIDE/INSTALL/PROGRAM/TEST NEW FIRE ALARM DEVICES IN ELEVATOR MACHINE ROOMS (3) AND MODIFY EXISTING FIRE ALARM SYSTEM TO MONITOR NEW FLOW AND TAMPER
SWITCHES.
PHASE 2: REMOVE EXISTING SPRINKLER SYSTEM AND INSTALL NEW SPRINKLER SYSTEM IN WING A BASEMENT.
PHASE 3: REMOVE EXISTING SPRINKLER SYSTEM AND INSTALL NEW SPRINKLER SYSTEM IN WING A FIRST FLOOR.
PHASE 4: REMOVE EXISTING SPRINKLER SYSTEM AND INSTALL NEW SPRINKLER SYSTEM IN WING A SECOND FLOOR AND
ATTIC.
PHASE 5: INSTALL NEW DRY PIPE SPRINKLER SYSTEM TO SERVE SOUTHWING EXTERIOR PORCH AT FIRST AND SECOND
FLOOR LEVELS AND REPLACE EXISTING DRY PIPE SPRINKLER SYSTEM BELOW SOUTHWING PORCH IN WING A PHASE 6: REMOVE EXISTING SPRINKLER SYSTEM AND INSTALL NEW SPRINKLER SYSTEM IN WING C BASEMENT AND
WAREHOUSE
PHASE 7: REMOVE EXISTING SPRINKLER SYSTEM AND INSTALL NEW SPRINKLER SYSTEM IN WING C FIRST FLOOR.
PHASE 8: REMOVE EXISTING SPRINKLER SYSTEM AND INSTALL NEW SPRINKLER SYSTEM IN WING C SECOND FLOOR PHASE 9: REMOVE EXISTING SPRINKLER SYSTEM AND INSTALL NEW SPRINKLER SYSTEM IN WING C THIRD FLOOR AND ATTIC.
PHASE 10: REMOVE EXISTING SPRINKLER SYSTEM AND INSTALL NEW SPRINKLER SYSTEM IN WING B SECOND FLOOR AND
ATTIC.
PHASE 11: REMOVE EXISTING SPRINKLER SYSTEM AND INSTALL NEW SPRINKLER SYSTEM IN WING B FIRST FLOOR.
PHASE 12: REMOVE EXISTING SPRINKLER SYSTEM AND INSTALL NEW SPRINKLER SYSTEM IN WING B BASEMENT.
PHASE 13: REMOVE EXISTING SPRINKLER SYSTEM AND INSTALL NEW SPRINKLER SYSTEM IN WING D SECOND FLOOR AND
ATTIC.
PHASE 14: REMOVE EXISTING SPRINKLER SYSTEM AND INSTALL NEW SPRINKLER SYSTEM IN WING D FIRST FLOOR.
PHASE 15: REMOVE EXISTING SPRINKLER SYSTEM AND INSTALL NEW SPRINKLER SYSTEM IN WING D BASEMENT.
PHASING NOTES:
1. PHASES 1-5 MUST OCCUR FIRST BUT CONTRACTOR MAY ALTER ORDER OF REMAINING PHASES AS NEEDED. ANY CHANGES
TO PHASING SCHEDULE SHALL BE APPROVED BY THE CONTRACTING OFFICER.
2. ALL WORK SHALL BE CONDUCTED OFF HOURS AND ON WEEKENDS. SOME AREAS REQUIRE MONITORED ACCESS.
3. CONTRACTOR SHALL REMOVE ALL DEBRIS GENERATED DAILY AND SHALL CLEAN WORK AREA EACH DAY PRIOR TO LEAVING
THE JOBSITE.
4. EXISTING SPRINKLER SYSTEM SHALL BE REMOVED IN ITS ENTIRETY PRIOR TO THE INSTALLATION OF NEW SPRINKLERS AND PIPING IN EACH PHASE. PHASES SERVING OCCUPIED FLOORS OF WINGS A AND C MAY BE DIVIDED INTO TWO SEPARATE AREAS TO MINIMIZE TIME EACH AREA IS UNPROTECTED. CONTRACTOR SHALL PROVIDE CONNECTIONS AS REQUIRED TO
MAINTAIN CONTINUITY OF SPRINKLER COVERAGE FOR SPACES IN ADJACENT PHASES.
5. FLOOR AND WING UNDER CONSTRUCTION WILL BE PERMITTED TO BE WITHOUT SPRINKLER PROTECTION DURING
CONSTRUCTION. EXISTING HANGARS AND WALL PENETRATIONS MAY BE REUSED.
CONSTRUCTION WILL BE PHASED AS NECESSARY TO ENSURE THAT OBSTRUCTION OF EXITS IS MINIMIZED OR AVOIDED. IF EXITS ARE OBSTRUCTED DURING CONSTRUCTION, ALTERNATE EXIT ROUTES DURING EACH PHASE OF CONSTRUCTION WILL BE PROVIDED AND IDENTIFIED ON THE CONSTRUCTION DRAWINGS. FIRE PROTECTION SYSTEMS SERVICES WILL BE DISRUPTED.
PROCEDURES WILL BE INCORPORATED TO MAINTAIN EQUIVALENT LEVELS OF SAFETY WHILE SYSTEMS ARE DOWN. AREAS WHERE THE SPRINKLER SYSTEM IS OUT OF SERVICE WILL BE SEPARATED BY TEMPORARY SMOKE-TIGHT CONSTRUCTION PARTITIONS OF GYPSUM BOARD OR OTHER APPROVED NON- COMBUSTIBLE OR LIMITED-COMBUSTIBLE MATERIAL. PARTITIONS SHALL BE FULL HEIGHT, EXTENDING TO SUSPENDED CEILINGS OR TO THE FLOOR SLAB OR ROOF DECK ABOVE.
MAXIMUM TIME AND AREAS THAT MAY BE OUT OF SERVICE PER PHASE AS FOLLOWS:
PHASE: DURATION: APPROXIMATE COVERAGE AREA:
PHASE:1 6 WEEKS STAIRWELLS (NOT SHOWN ON DRAWING)
PHASE:2 3 WEEKS 10,950 FT2
PHASE:3 3 WEEKS 11,700 FT2
PHASE:4 3 WEEKS 27,550 FT2
PHASE:5 NO RESTRICTION 10,250 FT2
PHASE:6 3 WEEKS 15,350 FT2
PHASE:7 3 WEEKS 16,100 FT2
PHASE:8 3 WEEKS 8,750 FT2
PHASE:9 3 WEEKS 16,700 FT2
PHASE:10 2 WEEKS 5,150 FT2
PHASE:11 2 WEEKS 10,350 FT2
PHASE:12 2 WEEKS 4,900 FT2
PHASE:13 2 WEEKS 10,300 FT2
PHASE:14 2 WEEKS 5,150 FT2
PHASE:15 2 WEEKS 5,150 FT2
BID DOCUMENTS
COR : MATTHEW OSGOOD
5/20/2019
P M
ACCOMPANYING 36C25219B0056 0003
File details come from the government source that posted it.