This solicitation package describes requirements for an upgrade emergency power project at a VA medical center. The project involves upgrades to Building 138 and has a budget between $5 million and $10 million. It is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses. Interested SDVOSBs must be registered in VIP and SAM databases. The solicitation will be posted on August 14, 2020 on sam.gov, with bids due approximately 30 days later. The duration shall not exceed 600 calendar days from notice to proceed. The contractor must perform a minimum of 15% self-performance and provide safety and EMR data prior to award. The site visit will be scheduled upon solicitation release. The Northern Indiana VA Medical Center is the contracting agency.

View the file

Other files

File Type Posted
36C25020B0081 0014.docx DOCX document
36C25020B0081 0013.docx DOCX document
EP001S.pdf PDF
36C25020B0081 0012.docx DOCX document
261313 MEDIUM-VOLTAGE CIRCUIT BREAKER SWITCHGEAR seismic.pdf PDF
RFIs - Responses and Answers 20210323.pdf PDF
230541 NOISE AND VIBRATION CONTROL seismic.pdf PDF
231000 FACILITY FUEL SYSTEMS seismic.pdf PDF
211313 Wet-Pipe Sprinkler Systems seismic.pdf PDF
610-16-104 Upgrade Emergency Power Addendum Drawings 2021 0402 sealed_Part6.pdf PDF
260533 Raceway and Boxes seismic.pdf PDF
Revised Bid Schedule.rtf RTF text file
233700 OUTLETS AND INLETS seismic.pdf PDF
238200 Convection Heating and Cooling Units seismic.pdf PDF
610-16-104 Upgrade Emergency Power Addendum Drawings 2021 0402 sealed_Part3.pdf PDF
232113 Hydronic Piping seismic.pdf PDF
238100 DECENTRALIZED UNITARY HVAC EQUIPMENT.pdf PDF
263623 Automatic Transfer Switches seismic.pdf PDF
233100 HVAC DUCTS AND CASINGS seismic.pdf PDF
232300 REFRIGERANT PIPING seismic.pdf PDF
610-16-104 Upgrade Emergency Power Addendum Drawings 2021 0402 sealed_Part2.pdf PDF
230511 COMMON WORK RESULTS FOR HVAC seismic.pdf PDF
232111 BOILER PLANT PIPING SYSTEMS seismic.pdf PDF
092216 NON-STRUCTURAL METAL FRAMING 2.pdf PDF
610-16-104 Upgrade Emergency Power Addendum Drawings 2021 0402 sealed_Part4.pdf PDF
261313 Appendix_Concrete Pad for Metering Cabinet.pdf PDF
000110 Table of Contents seismic.pdf PDF
265100 Interior Lighting seismic.pdf PDF
238413 Self-Contained Steam Humidifiers.pdf PDF
232213 Steam and Condensate Heating Piping seismic.pdf PDF
262313 Generator Paralleling Cont seismic.pdf PDF
262200 Low Voltage Transformers seismic.pdf PDF
610-16-104 Upgrade Emergency Power Addendum Drawings 2021 0402 sealed_Part1.pdf PDF
36C25020B0081 0011.docx DOCX document
074000 Siding Panels seismic.pdf PDF
36C25020B0081 0010.docx DOCX document
36C25020B0081 0009.docx DOCX document
36C25020B0081 0008.docx DOCX document
36C25020B0081 0007.docx DOCX document
36C25020B0081 0006.docx DOCX document
EP201 - POWER - MV SWITCHGEAR ELEVATION.pdf PDF
36C25020B0081 0005.docx DOCX document
EE601 - EMCS - RISER DIAGRAM.pdf PDF
RFI Responses.docx DOCX document
194EP-100 - ELECTRICAL POWER PLAN.pdf PDF
Card Reader Specification 281300.pdf PDF
610-16-104 addendum 04 all drawings 20201201.pdf PDF
610-16-104 Fires Safety CD review and responses 20201201.pdf PDF
Tax Exemption - Indiana (FTW).pdf PDF
36C25020B0081 0004.docx DOCX document
Show 40 more

Latest 50 of 61 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JJ

(4) CONCRETE BRICKS

51mmx203mmx406mm (2"x8"x16")

CONDUIT(S) W ITH BELL

ENDS

(TYP). SIZE, QUANTITY AND

W IRING AS INDICATED ON

PLANS

CLEAN 19mm (3/4")

CRUSHED ROCK

GRADE. FEATHER & TAMP

BACKFILL

TO CREATE FLUSH INSTALLATION

AND POSITIVE DRAINAGE AW AY

FROM BOX

VA

R

IE

S

(1

PULLBOX (SEE SPECIFICATIONS)

LINE SIDES OF EXCAVATION

W ITH 13.6 KG (30 LBS.) FELT

PAPER

(12")

5m m

305mm

UNDERGROUND CONCRETE PULLBOX -

TURF AREAS

NTS

1 3000 LB. CONCRETE.

2 SCHEDULE 40 PVC DUCT. W IRING AND CONDUITS.

3 MIN. 3" SPACING BETW EEN CONDUITS AND M IN. 3"

ENCASEM ENT (TYPICAL). PROVIDE CONDUIT

SPACERS 6'-0" O.C.

4 RED DYE, RED DUST OR YELLOW M ARKER TAPE ON

COMPACTED FILL.

DETAIL NOTES

'-6

TAM PED

BACKFILL

FINISH GRADE

'-3

C

O V

E R

V A

R

IE

S

VARIES

1 3000 LB. CONCRETE ENCASEM ENT. 3" M IN. FROM

OUTSIDE OF DUCT.

2 SCHEDULE 40 PVC DUCT. W IRING AND CONDUITS.

3 RED DYE, RED DUST OR YELLOW M ARKER TAPE ON

COMPACTED FILL.

DETAIL NOTES

'-6

TAM PED

BACKFILL

FINISH GRADE

'-6

C

O V

E R .

1 3000 LB. CONCRETE.

2 SCHEDULE 40 PVC DUCT. W IRING AND CONDUITS.

3 MIN. 3" SPACING BETW EEN CONDUITS AND M IN. 3"

ENCASEM ENT (TYPICAL). PROVIDE CONDUIT

SPACERS 6'-0" O.C.

4 RED DYE, RED DUST OR YELLOW M ARKER TAPE ON

COMPACTED FILL.

DETAIL NOTES

2'-3"

1"

'-3

C

O V

E R

'-6

TAM PED

BACKFILL

FINISH GRADE

1 3000 LB. CONCRETE.

2 SCHEDULE 40 PVC DUCT. W IRING AND CONDUITS.

3 MIN. 3" SPACING BETW EEN CONDUITS AND M IN. 3"

ENCASEM ENT (TYPICAL). PROVIDE CONDUIT

SPACERS 6'-0" O .C.

4 RED DYE, RED DUST OR YELLOW M ARKER TAPE ON

COMPACTED FILL.

DETAIL NOTES

FINISH GRADE

TAM PED

BACKFILL

1'-6"

'-6

'-3

C

O V

E R

'-6

POW ER MANHOLE DETAILS

NTS

TOP VIEW

SECTION "A-A"

POW ER

SECTION "B-B"

S

LO

P E

SL

OP

E

SLOPE

305x305mm (12"x12")

SUM P

FINISHED

GRADE

GROUND ROD

PER SECTION

26 05 26.

A

A B

B PULLING

IRON

CONC.

ENVELOPE

GROUN

D

ROD

SLEEVE

PULLIN

G

IRON

CABLE STANCHION

PER

SECTION 26 05 41.

305mm (12") SUM P

SUM P FRAM E

COVER

GRADE RINGS AS REQ'D TO MATCH

CIVIL FINISHED GRADE ELEVATION.

CABLE STANCHION

0.764 CUBIC M ETERS (1

CUBIC YARD) 19m m (3/4")

GRAVEL SUMP

GENERAL NOTE:

1. INCLUDE ALUM INUM LADDER (NOT

SHOW N FOR CLARITY)

V A

R

IE

S

(5 '-0")

1930m m (6'-4")

(8") 1524m m 203m m

(8 m m

(6 m m m m

(1

M

IN

m m

(8

1524m m

(5'-0") m m

(8 ")2

5m m (7

'-4

965m m965m m

(3'-2")

1930m m

(6'-4")

(3'-2")

(5 '-6

(3

'-1

(9 '-4

6m m

8m m

5m m

(3") 76m m

(8 '-0

(8 m m (9

'-4

(8 m m

8m m

5m m

(3 '-0 m m915m m (3'-0")

1. COVER SHALL BE LOCKABLE.

52P 52A CPT

PTS

EAST

LOOP

BKR 2

W EST

LOOP

BKR 1

FDR

FDR

FDR

5UTILITY

CTS

OS

BATTERY RACK

BATTERY

CHARGER

EP401

8 E P

BATTERY

SYSTEM

W ORKING

CLEARANCE

NEW MV

SW ITCHGEAR

FUTURE GENERATOR

GENERATOR

A

DCB

TO M H M1A / SW ITCH A

TO M H M1A / SW ITCH A

NEW

CAPACITOR

BANK

2-5" C. 2-4" C.

TO M H 40A TO MH M 40A

INCOMING

PREFERRED

UTILITY M AIN #4 #2 TIE

GEN. 1 #5

#1 ALT. MAIN

INCOMING

ALT.

UTILITY

2 - 5"C2 - 4"C

CONCRETE

PAD

FUTURE

GEN 2

2 - 5"

2 - 5"

P: 937-224-0861 www.heapy.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

CONSTRUCTION

DOCUMENTS

Services

Engineering and Facilities Management

U.S. Departm ent of Veterans Affairs

B

C

D

E

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

F F E I n c Engineering and Technical Services 110 Boggs Lane, Suite 170 Cincinnati, OH 45246 513-522-0956

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Marion VA Marion, IN

UPGRADE EMERGENCY

POWER IN BUILDING 138

#610-16-104

PROJECT NO. 2018-05034 FULLY SPRINKLERED

CONSTRUCTION DOCUMENTS

C

B

IM

\M o d e l\

-0

-E le c tr ic a l C e n tr a l_ n e s p ri e g e l.

rv t

/2

/2

:3

:4

A M

EP401

POWER - ENLARGED SITE PLANS

11/23/2020 MSG JHS

SCALE: 1/8" = 1'-0"

UNDERGROUND DUCTS - 2

SCALE: 1/8" = 1'-0"

CONCRETE ENCASED UNDERGROUND DUCT - 1

SCALE: 1/8" = 1'-0"

UNDERGROUND DUCTS - 3

SCALE: 1/8" = 1'-0"

UNDERGROUND DUCTS - 4

SCALE: 1 1/2" = 1'-0"

EXISTING MV CAPACITOR BANK

SCALE: 1 1/2" = 1'-0"

EXISTING MV SWITCHGEAR - EXTERIOR

SCALE: 1 1/2" = 1'-0"

EXISTING MV SWITCHGEAR - INTERIOR

SCALE: 1/8" = 1'-0"

EXISTING MV SW ITCHGEAR - DEMO

SCALE: 1/4" = 1'-0"

GENERATOR BUILDING

1. PROVIDE POW ER TO BLOCK HEATER FROM PANEL P1SG.

COORDINATE BREAKER SIZE W ITH GENERATOR

MANUFACTURER. REFER TO SHEET 194EP-100 FOR

CIRCUITING INFORMATION.

2. PROVIDE POW ER TO BATTERY CHARGER FROM PANEL

P1SG. REFER TO SHEET 194EP-100 FOR CIRCUITING

INFORMATION.

3. MEDIUM VOLTAGE TRANSFORM ER. SEE SINGLE-LINE.

4. MANHOLE.

5. PANEL P1SG LOCATION.

6. ATS. SEE SINGLE-LINE.

PLAN NOTES

DRAWING 55 OF 60Revisions: Date:

95% REVIEW 12/17/2019

Addendum 4 11/23/2020

00.00 G000 - COVER SHEET
Sheets
G000 - COVER SHEET
G001 - ABBREVIATIONS AND CODE NOTES
G002 - LIFE SAFETY PLANS
00.02 G001 - ABBREVIATIONS AND CODE NOTES
Sheets
G000 - COVER SHEET
G001 - ABBREVIATIONS AND CODE NOTES
G002 - LIFE SAFETY PLANS
00.03 G002 - LIFE SAFETY PLANS
Sheets
G000 - COVER SHEET
G001 - ABBREVIATIONS AND CODE NOTES
G002 - LIFE SAFETY PLANS
04.04 - C100 - ARCHITECTURAL SITE PLAN
Sheets
C100 - ARCHITECTURAL SITE PLAN
06.14 194SI-001 - STRUCTURAL GENERAL NOTES
Sheets
194SB-101 - FOUNDATION PLAN
194SB-102 - SLAB PLAN
194SB-601 - STRUCTURAL SECTIONS
194SB-602 - STRUCTURAL DETAILS
194SF-101 - STRUCURAL FRAMING PLAN AND ELEVATIONS
194SF-601 - STRUCTURAL FRAMING SECTIONS AND DETAILS
194SI-001 - STRUCTURAL GENERAL NOTES
C100 - ARCHITECTURAL SITE PLAN
06.15 194SB-101 - FOUNDATION PLAN
Sheets
194SB-101 - FOUNDATION PLAN
194SB-102 - SLAB PLAN
194SB-601 - STRUCTURAL SECTIONS
194SB-602 - STRUCTURAL DETAILS
194SF-101 - STRUCURAL FRAMING PLAN AND ELEVATIONS
194SF-601 - STRUCTURAL FRAMING SECTIONS AND DETAILS
194SI-001 - STRUCTURAL GENERAL NOTES
C100 - ARCHITECTURAL SITE PLAN
06.16 194SB-102 - SLAB PLAN
Sheets
194SB-101 - FOUNDATION PLAN
194SB-102 - SLAB PLAN
194SB-601 - STRUCTURAL SECTIONS
194SB-602 - STRUCTURAL DETAILS
194SF-101 - STRUCURAL FRAMING PLAN AND ELEVATIONS
194SF-601 - STRUCTURAL FRAMING SECTIONS AND DETAILS
194SI-001 - STRUCTURAL GENERAL NOTES
C100 - ARCHITECTURAL SITE PLAN
06.17 194SB-601 - STRUCTURAL SECTIONS
Sheets
194SB-101 - FOUNDATION PLAN
194SB-102 - SLAB PLAN
194SB-601 - STRUCTURAL SECTIONS
194SB-602 - STRUCTURAL DETAILS
194SF-101 - STRUCURAL FRAMING PLAN AND ELEVATIONS
194SF-601 - STRUCTURAL FRAMING SECTIONS AND DETAILS
194SI-001 - STRUCTURAL GENERAL NOTES
C100 - ARCHITECTURAL SITE PLAN
06.18 194SB-602 - STRUCTURAL DETAILS
Sheets
194SB-101 - FOUNDATION PLAN
194SB-102 - SLAB PLAN
194SB-601 - STRUCTURAL SECTIONS
194SB-602 - STRUCTURAL DETAILS
194SF-101 - STRUCURAL FRAMING PLAN AND ELEVATIONS
194SF-601 - STRUCTURAL FRAMING SECTIONS AND DETAILS
194SI-001 - STRUCTURAL GENERAL NOTES
C100 - ARCHITECTURAL SITE PLAN
06.19 194SF-101 - STRUCURAL FRAMING PLAN AND ELEVATIONS
Sheets
194SB-101 - FOUNDATION PLAN
194SB-102 - SLAB PLAN
194SB-601 - STRUCTURAL SECTIONS
194SB-602 - STRUCTURAL DETAILS
194SF-101 - STRUCURAL FRAMING PLAN AND ELEVATIONS
194SF-601 - STRUCTURAL FRAMING SECTIONS AND DETAILS
194SI-001 - STRUCTURAL GENERAL NOTES
C100 - ARCHITECTURAL SITE PLAN
06.20 194SF-601 - STRUCTURAL FRAMING SECTIONS AND DETAILS
Sheets
194SB-101 - FOUNDATION PLAN
194SB-102 - SLAB PLAN
194SB-601 - STRUCTURAL SECTIONS
194SB-602 - STRUCTURAL DETAILS
194SF-101 - STRUCURAL FRAMING PLAN AND ELEVATIONS
194SF-601 - STRUCTURAL FRAMING SECTIONS AND DETAILS
194SI-001 - STRUCTURAL GENERAL NOTES
C100 - ARCHITECTURAL SITE PLAN
07.21 175AS-101 - NEW WORK - BUILDING 175 - LEVEL 1
Sheets
138E-002 - BUILDING 138 PANELBOARD SCHEDULES
138E-003 - BUILDING 138 PANELBOARD SCHEDULES
138E-004 - BUILDING 138 - SINGLE LINE DIAGRAM
138E-005 - BUILDING 138 - SINGLE LINE DIAGRAM
138EP-100 - POWER - BUILDING 138 - BASEMENT PLAN
138EP-101 - POWER - BUILDING 138 - LEVEL 1 PLAN
138EP-102 - POWER - BUILDING 138 - LEVEL 2 PLAN
138EP-103 - POWER - BUILDING 138 - LEVEL 3 PLAN
138EP-104 - POWER - BUILDING 138 - LEVEL 4 PLAN
138EP-105 - POWER - BUILDING 138 - LEVEL 5 PLAN
175AS-101 - NEW WORK - BUILDING 175 - LEVEL 1
175EP-101 - POWER - BUILDING 175 - LEVEL 1 PLAN
175MH-101 - HVAC FLOOR PLAN
E-001 - LEGEND & ABBREVIATIONS
EE001S - EMCS - SITE PLAN
EE100 - EMCS - COMPLEX BASEMENT PLANS
EE101 - EMCS - COMPLEX LEVEL 1 PLANS
EE401 - EMCS - ENLARGED ROOM PLANS
EE601 - EMCS - RISER DIAGRAM
EP001S - POWER - SITE PLAN
EP201 - POWER - MV SWITCHGEAR ELEVATION
EP401 - POWER - ENLARGED SITE PLANS
EP601 - POWER - SITE - SINGLE LINE DIAGRAM
07.22 194AS-100 - FLOOR PLAN
Sheets
194AS-100 - FLOOR PLAN
194AS-101 - ENLARGED FLOOR PLANS
194AS-200 - ELEVATIONS AND SECTIONS
194AS-201 - ELEVATION AND SECTIONS
194AS-300 - WALL SECTIONS
194AS-301 - ENLARGED DETAILS
194AS-302 - MISC. DETAILS
07.23 194AS-101 - ENLARGED FLOOR PLANS
Sheets
194AS-100 - FLOOR PLAN
194AS-101 - ENLARGED FLOOR PLANS
194AS-200 - ELEVATIONS AND SECTIONS
194AS-201 - ELEVATION AND SECTIONS
194AS-300 - WALL SECTIONS
194AS-301 - ENLARGED DETAILS
194AS-302 - MISC. DETAILS
07.24 194AS-200 - ELEVATIONS AND SECTIONS
Sheets
194AS-100 - FLOOR PLAN
194AS-101 - ENLARGED FLOOR PLANS
194AS-200 - ELEVATIONS AND SECTIONS
194AS-201 - ELEVATION AND SECTIONS
194AS-300 - WALL SECTIONS
194AS-301 - ENLARGED DETAILS
194AS-302 - MISC. DETAILS
07.25 194AS-201 - ELEVATION AND SECTIONS
Sheets
194AS-100 - FLOOR PLAN
194AS-101 - ENLARGED FLOOR PLANS
194AS-200 - ELEVATIONS AND SECTIONS
194AS-201 - ELEVATION AND SECTIONS
194AS-300 - WALL SECTIONS
194AS-301 - ENLARGED DETAILS
194AS-302 - MISC. DETAILS
07.26 194AS-300 - WALL SECTIONS
Sheets
194AS-100 - FLOOR PLAN
194AS-101 - ENLARGED FLOOR PLANS
194AS-200 - ELEVATIONS AND SECTIONS
194AS-201 - ELEVATION AND SECTIONS
194AS-300 - WALL SECTIONS
194AS-301 - ENLARGED DETAILS
194AS-302 - MISC. DETAILS
07.27 194AS-302 - MISC- DETAILS
Sheets
194AS-100 - FLOOR PLAN
194AS-101 - ENLARGED FLOOR PLANS
194AS-200 - ELEVATIONS AND SECTIONS
194AS-201 - ELEVATION AND SECTIONS
194AS-300 - WALL SECTIONS
194AS-301 - ENLARGED DETAILS
194AS-302 - MISC. DETAILS
07.28 194AS-301 - ENLARGED DETAILS
Sheets
194AS-100 - FLOOR PLAN
194AS-101 - ENLARGED FLOOR PLANS
194AS-200 - ELEVATIONS AND SECTIONS
194AS-201 - ELEVATION AND SECTIONS
194AS-300 - WALL SECTIONS
194AS-301 - ENLARGED DETAILS
194AS-302 - MISC. DETAILS
10.01 194FP-101 FIRE PROTECTION PLAN
Sheets
194AS-101 - ENLARGED FLOOR PLANS
194AS-302 - MISC. DETAILS
194FP-101 - FIRE PROTECTION PLAN
G000 - COVER SHEET
G001 - ABBREVIATIONS AND CODE NOTES
G002 - LIFE SAFETY PLANS
14.39 R E001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
Sheets
E001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
EE001S - EMCS - SITE PLAN
EE100 - EMCS - COMPLEX BASEMENT PLANS
EE101 - EMCS - COMPLEX LEVEL 1 PLANS
EE401 - EMCS - ENLARGED ROOM PLANS
EE601 - EMCS - RISER DIAGRAM
EP001S - POWER - SITE PLAN
EP201 - POWER - MV SWITCHGEAR ELEVATION
EP401 - POWER - ENLARGED SITE PLANS
EP601 - POWER - SITE - SINGLE LINE DIAGRAM
14.41 138E-003 - BUILDING 138 PANELBOARD SCHEDULES
Sheets
138E-002 - BUILDING 138 PANELBOARD SCHEDULES
138E-003 - BUILDING 138 PANELBOARD SCHEDULES
138E-004 - BUILDING 138 - SINGLE LINE DIAGRAM
138E-005 - BUILDING 138 - SINGLE LINE DIAGRAM
138EP-100 - POWER - BUILDING 138 - BASEMENT PLAN
138EP-101 - POWER - BUILDING 138 - LEVEL 1 PLAN
138EP-102 - POWER - BUILDING 138 - LEVEL 2 PLAN
138EP-103 - POWER - BUILDING 138 - LEVEL 3 PLAN
138EP-104 - POWER - BUILDING 138 - LEVEL 4 PLAN
138EP-105 - POWER - BUILDING 138 - LEVEL 5 PLAN
175AS-101 - NEW WORK - BUILDING 175 - LEVEL 1
175EP-101 - POWER - BUILDING 175 - LEVEL 1 PLAN
175MH-101 - HVAC FLOOR PLAN
E-001 - LEGEND & ABBREVIATIONS
EE001S - EMCS - SITE PLAN
EE100 - EMCS - COMPLEX BASEMENT PLANS
EE101 - EMCS - COMPLEX LEVEL 1 PLANS
EE401 - EMCS - ENLARGED ROOM PLANS
EE601 - EMCS - RISER DIAGRAM
EP001S - POWER - SITE PLAN
EP201 - POWER - MV SWITCHGEAR ELEVATION
EP401 - POWER - ENLARGED SITE PLANS
EP601 - POWER - SITE - SINGLE LINE DIAGRAM
14.42 138E-004 - BUILDING 138 - SINGLE LINE DIAGRAM
Sheets
138E-002 - BUILDING 138 PANELBOARD SCHEDULES
138E-003 - BUILDING 138 PANELBOARD SCHEDULES
138E-004 - BUILDING 138 - SINGLE LINE DIAGRAM
138E-005 - BUILDING 138 - SINGLE LINE DIAGRAM
138EP-100 - POWER - BUILDING 138 - BASEMENT PLAN
138EP-101 - POWER - BUILDING 138 - LEVEL 1 PLAN
138EP-102 - POWER - BUILDING 138 - LEVEL 2 PLAN
138EP-103 - POWER - BUILDING 138 - LEVEL 3 PLAN
138EP-104 - POWER - BUILDING 138 - LEVEL 4 PLAN
138EP-105 - POWER - BUILDING 138 - LEVEL 5 PLAN
175AS-101 - NEW WORK - BUILDING 175 - LEVEL 1
175EP-101 - POWER - BUILDING 175 - LEVEL 1 PLAN
175MH-101 - HVAC FLOOR PLAN
E-001 - LEGEND & ABBREVIATIONS
EE001S - EMCS - SITE PLAN
EE100 - EMCS - COMPLEX BASEMENT PLANS
EE101 - EMCS - COMPLEX LEVEL 1 PLANS
EE401 - EMCS - ENLARGED ROOM PLANS
EE601 - EMCS - RISER DIAGRAM
EP001S - POWER - SITE PLAN
EP201 - POWER - MV SWITCHGEAR ELEVATION
EP401 - POWER - ENLARGED SITE PLANS
EP601 - POWER - SITE - SINGLE LINE DIAGRAM
14.43 138E-005 - BUILDING 138 - SINGLE LINE DIAGRAM
Sheets
138E-002 - BUILDING 138 PANELBOARD SCHEDULES
138E-003 - BUILDING 138 PANELBOARD SCHEDULES
138E-004 - BUILDING 138 - SINGLE LINE DIAGRAM
138E-005 - BUILDING 138 - SINGLE LINE DIAGRAM
138EP-100 - POWER - BUILDING 138 - BASEMENT PLAN
138EP-101 - POWER - BUILDING 138 - LEVEL 1 PLAN
138EP-102 - POWER - BUILDING 138 - LEVEL 2 PLAN
138EP-103 - POWER - BUILDING 138 - LEVEL 3 PLAN
138EP-104 - POWER - BUILDING 138 - LEVEL 4 PLAN
138EP-105 - POWER - BUILDING 138 - LEVEL 5 PLAN
175AS-101 - NEW WORK - BUILDING 175 - LEVEL 1
175EP-101 - POWER - BUILDING 175 - LEVEL 1 PLAN
175MH-101 - HVAC FLOOR PLAN
E-001 - LEGEND & ABBREVIATIONS
EE001S - EMCS - SITE PLAN
EE100 - EMCS - COMPLEX BASEMENT PLANS
EE101 - EMCS - COMPLEX LEVEL 1 PLANS
EE401 - EMCS - ENLARGED ROOM PLANS
EE601 - EMCS - RISER DIAGRAM
EP001S - POWER - SITE PLAN
EP201 - POWER - MV SWITCHGEAR ELEVATION
EP401 - POWER - ENLARGED SITE PLANS
EP601 - POWER - SITE - SINGLE LINE DIAGRAM
14.45 138EP-101 - POWER - BUILDING 138 - LEVEL 1 PLAN
Sheets
138E-002 - BUILDING 138 PANELBOARD SCHEDULES
138E-003 - BUILDING 138 PANELBOARD SCHEDULES
138E-004 - BUILDING 138 - SINGLE LINE DIAGRAM
138E-005 - BUILDING 138 - SINGLE LINE DIAGRAM
138EP-100 - POWER - BUILDING 138 - BASEMENT PLAN
138EP-101 - POWER - BUILDING 138 - LEVEL 1 PLAN
138EP-102 - POWER - BUILDING 138 - LEVEL 2 PLAN
138EP-103 - POWER - BUILDING 138 - LEVEL 3 PLAN
138EP-104 - POWER - BUILDING 138 - LEVEL 4 PLAN
138EP-105 - POWER - BUILDING 138 - LEVEL 5 PLAN
175AS-101 - NEW WORK - BUILDING 175 - LEVEL 1
175EP-101 - POWER - BUILDING 175 - LEVEL 1 PLAN
175MH-101 - HVAC FLOOR PLAN
E-001 - LEGEND & ABBREVIATIONS
EE001S - EMCS - SITE PLAN
EE100 - EMCS - COMPLEX BASEMENT PLANS
EE101 - EMCS - COMPLEX LEVEL 1 PLANS
EE401 - EMCS - ENLARGED ROOM PLANS
EE601 - EMCS - RISER DIAGRAM
EP001S - POWER - SITE PLAN
EP201 - POWER - MV SWITCHGEAR ELEVATION
EP401 - POWER - ENLARGED SITE PLANS
EP601 - POWER - SITE - SINGLE LINE DIAGRAM
14.46 138EP-102 - POWER - BUILDING 138 - LEVEL 2 PLAN
Sheets
138EP-102 - POWER - BUILDING 138 - LEVEL 2 PLAN
14.47 138EP-103 - POWER - BUILDING 138 - LEVEL 3 PLAN
Sheets
138EP-103 - POWER - BUILDING 138 - LEVEL 3 PLAN
14.48 138EP-104 - POWER - BUILDING 138 - LEVEL 4 PLAN
Sheets
138E-002 - BUILDING 138 PANELBOARD SCHEDULES
138E-003 - BUILDING 138 PANELBOARD SCHEDULES
138E-004 - BUILDING 138 - SINGLE LINE DIAGRAM
138E-005 - BUILDING 138 - SINGLE LINE DIAGRAM
138EP-100 - POWER - BUILDING 138 - BASEMENT PLAN
138EP-101 - POWER - BUILDING 138 - LEVEL 1 PLAN
138EP-102 - POWER - BUILDING 138 - LEVEL 2 PLAN
138EP-103 - POWER - BUILDING 138 - LEVEL 3 PLAN
138EP-104 - POWER - BUILDING 138 - LEVEL 4 PLAN
138EP-105 - POWER - BUILDING 138 - LEVEL 5 PLAN
175AS-101 - NEW WORK - BUILDING 175 - LEVEL 1
175EP-101 - POWER - BUILDING 175 - LEVEL 1 PLAN
175MH-101 - HVAC FLOOR PLAN
E-001 - LEGEND & ABBREVIATIONS
EE001S - EMCS - SITE PLAN
EE100 - EMCS - COMPLEX BASEMENT PLANS
EE101 - EMCS - COMPLEX LEVEL 1 PLANS
EE401 - EMCS - ENLARGED ROOM PLANS
EE601 - EMCS - RISER DIAGRAM
EP001S - POWER - SITE PLAN
EP201 - POWER - MV SWITCHGEAR ELEVATION
EP401 - POWER - ENLARGED SITE PLANS
EP601 - POWER - SITE - SINGLE LINE DIAGRAM
14.49 138EP-105 - POWER - BUILDING 138 - LEVEL 5 PLAN
Sheets
138EP-105 - POWER - BUILDING 138 - LEVEL 5 PLAN
14.50 175EP-101 - POWER - BUILDING 175 - LEVEL 1 PLAN
Sheets
138E-002 - BUILDING 138 PANELBOARD SCHEDULES
138E-003 - BUILDING 138 PANELBOARD SCHEDULES
138E-004 - BUILDING 138 - SINGLE LINE DIAGRAM
138E-005 - BUILDING 138 - SINGLE LINE DIAGRAM
138EP-100 - POWER - BUILDING 138 - BASEMENT PLAN
138EP-101 - POWER - BUILDING 138 - LEVEL 1 PLAN
138EP-102 - POWER - BUILDING 138 - LEVEL 2 PLAN
138EP-103 - POWER - BUILDING 138 - LEVEL 3 PLAN
138EP-104 - POWER - BUILDING 138 - LEVEL 4 PLAN
138EP-105 - POWER - BUILDING 138 - LEVEL 5 PLAN
175AS-101 - NEW WORK - BUILDING 175 - LEVEL 1
175EP-101 - POWER - BUILDING 175 - LEVEL 1 PLAN
175MH-101 - HVAC FLOOR PLAN
E-001 - LEGEND & ABBREVIATIONS
EE001S - EMCS - SITE PLAN
EE100 - EMCS - COMPLEX BASEMENT PLANS
EE101 - EMCS - COMPLEX LEVEL 1 PLANS
EE401 - EMCS - ENLARGED ROOM PLANS
EE601 - EMCS - RISER DIAGRAM
EP001S - POWER - SITE PLAN
EP201 - POWER - MV SWITCHGEAR ELEVATION
EP401 - POWER - ENLARGED SITE PLANS
EP601 - POWER - SITE - SINGLE LINE DIAGRAM
14.51 EE001S - EMCS - SITE PLAN h
Sheets
EE001S - EMCS - SITE PLAN
EE100 - EMCS - COMPLEX BASEMENT PLANS
EE101 - EMCS - COMPLEX LEVEL 1 PLANS
EE401 - EMCS - ENLARGED ROOM PLANS
EP001S - POWER - SITE PLAN
EP201 - POWER - MV SWITCHGEAR ELEVATION
EP401 - POWER - ENLARGED SITE PLANS
EP601 - POWER - SITE - SINGLE LINE DIAGRAM
14.55 EE401 - EMCS - ENLARGED ROOM PLANS A10
Sheets
EE401 - EMCS - ENLARGED ROOM PLANS
EP201 - POWER - MV SWITCHGEAR ELEVATION
EP601 - POWER - SITE - SINGLE LINE DIAGRAM
14.58 EP201 - POWER - MV SWITCHGEAR ELEVATION A10
Sheets
EE401 - EMCS - ENLARGED ROOM PLANS
EP201 - POWER - MV SWITCHGEAR ELEVATION
EP601 - POWER - SITE - SINGLE LINE DIAGRAM
14.59 EP401 - POWER - ENLARGED SITE PLANS h
Sheets
EE001S - EMCS - SITE PLAN
EE100 - EMCS - COMPLEX BASEMENT PLANS
EE101 - EMCS - COMPLEX LEVEL 1 PLANS
EE401 - EMCS - ENLARGED ROOM PLANS
EP001S - POWER - SITE PLAN
EP201 - POWER - MV SWITCHGEAR ELEVATION
EP401 - POWER - ENLARGED SITE PLANS
EP601 - POWER - SITE - SINGLE LINE DIAGRAM
14.60 EP601 - POWER - SITE - SINGLE LINE DIAGRAM A10
Sheets
EP601 - POWER - SITE - SINGLE LINE DIAGRAM
14.61 194EL-100 - ELECTRICAL LIGHTING PLAN
Sheets
194EL-100 - ELECTRICAL LIGHTING PLAN
194EP-100 - ELECTRICAL POWER PLAN
194EY-100 - ELECTRICAL SITE COMMUNICATION PLAN
EP002S - BUILDING 175 & 138 CONDUIT SITE PLAN
14.62_194EP-100 - ELECTRICAL POWER PLAN
Sheets
194EP-100 - ELECTRICAL POWER PLAN
14.63 194EY-100 - ELECTRICAL SITE COMMUNICATION PLAN
Sheets
194EP-100 - ELECTRICAL POWER PLAN
194EY-100 - ELECTRICAL SITE COMMUNICATION PLAN
14.64 194LP-100 - ELECTRICAL LIGHTNING PROTECTION PLAN
Sheets
194AS-100 - FLOOR PLAN
194AS-101 - ENLARGED FLOOR PLANS
194AS-200 - ELEVATIONS AND SECTIONS
194AS-201 - ELEVATION AND SECTIONS
194AS-300 - WALL SECTIONS
194AS-301 - ENLARGED DETAILS
194AS-302 - MISC. DETAILS
194EL-100 - ELECTRICAL LIGHTING PLAN
194EP-100 - ELECTRICAL POWER PLAN
194EY-100 - ELECTRICAL SITE COMMUNICATION PLAN
194LP-100 - ELECTRICAL LIGHTNING PROTECTION PLAN
194MH-101 - MECHANICAL PLANS AND SECTIONS
194MH-102 - MECHANICAL PLANS AND SECTIONS
194MH-501 - MECHANICAL DETAILS
194MH-601 - MECHANICAL SCHEDULES I
194MH-602 - MECHANICAL SCHEDULES II
194MH-603 - HVAC INSTRUMENTATION AND CONTROLS - SWITCHGEAR ROOM
194MH-604 - FUEL PIPING DIAGRAM AND INSTRUMENTATION
194SB-101 - FOUNDATION PLAN
194SB-102 - SLAB PLAN
194SB-601 - STRUCTURAL SECTIONS
194SB-602 - STRUCTURAL DETAILS
194SF-101 - STRUCURAL FRAMING PLAN AND ELEVATIONS
194SF-601 - STRUCTURAL FRAMING SECTIONS AND DETAILS
194SI-001 - STRUCTURAL GENERAL NOTES
G002 - LIFE SAFETY PLANS
MH-001 - MECHANICAL LEGEND

14.65 175-E172 Bldg 172 Electric annotated A10