About this file
This is a specification document for exterior lighting work as part of project 25-388, a CBI HVAC and Lighting Upgrade (GovTribe ID: 265600). The document outlines the requirements for furnishing and installing exterior luminaires, poles, and associated accessories. The scope includes complete luminaire systems with lamps, sockets, ballasts, reflectors, lenses, housings, conduit, boxes, wiring, connectors, hardware, poles, foundations, and all other components necessary for a complete operating system. Installation must comply with manufacturer instructions and industry standards including NECA/IESNA 501, NFPA 70, IEEE C2, and UL 1598 requirements. Luminaires must be sourced from approved manufacturers including Acuity Brands, Alloy LED, Cooper Lighting, Electro-Matic Visual, Hubbell Lighting, and Philips Lighting North America Corporation. All poles must be steel with square straight configuration, installed on concrete foundations at heights indicated in drawings, and equipped with handholes, anchor bolts, leveling nuts or shims, anchor base covers, and weatherproof GFI receptacles where specified.
Installation requirements include coordination with utilities and existing infrastructure to resolve conflicts prior to proceeding, verification of field measurements and outlet box locations, and proper positioning of luminaires plumb and square with building lines. Poles must be installed plumb using leveling nuts or shims, with anchor bolt nuts torqued to manufacturer specifications. All luminaires, metal accessories, poles, and foundation reinforcement must be bonded to branch circuit equipment grounding conductors. Separate 12 AWG copper service conductors must be installed from each luminaire to the handhole for connection to branch circuit conductors. Upon completion, all surfaces must be cleaned to remove dirt, fingerprints, paint, or foreign material to restore finishes to original factory condition, and installed luminaires must be protected from subsequent construction operations.
View the file
Other files
Show all 42
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
25-388 CBI HVAC and Lighting Upgrade 265600 - 1 Exterior Lighting
SECTION 265600
EXTERIOR LIGHTING
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Exterior luminaires.
B. Poles and accessories.
C. Luminaire accessories.
1.02 RELATED REQUIREMENTS
A. Section 260526 - Grounding and Bonding for Electrical Systems.
B. Section 260529 - Hangers and Supports for Electrical Systems.
C. Section 260533.16 - Boxes for Electrical Systems.
D. Section 262726 - Wiring Devices: Receptacles for installation in poles.
E. Section 262813 - Fuses.
F. Section 265100 - Interior Lighting.
1.03 REFERENCE STANDARDS
A. IEEE C2 - National Electrical Safety Code(R) (NESC(R)); 2023.
B. NECA 1 - Standard for Good Workmanship in Electrical Construction; 2023.
C. NECA/IESNA 501 - Standard for Installing Exterior Lighting Systems; 2000 (Reaffirmed 2006).
D. NFPA 70 - National Electrical Code; Most Recent Edition Adopted by Authority Having
Jurisdiction, Including All Applicable Amendments and Supplements.
E. UL 1598 - Luminaires; Current Edition, Including All Revisions.
1.04 ADMINISTRATIVE REQUIREMENTS
A. Coordination:
1. Coordinate placement of poles and associated foundations with utilities, curbs, sidewalks, trees, walls, fences, striping, etc. installed under other sections or by others. Coordinate elevation to obtain specified foundation height.
2. Notify Architect of any conflicts or deviations from Contract Documents to obtain direction prior to proceeding with work.
1.05 SUBMITTALS
A. See Section 013000 - Administrative Requirements, for submittal procedures.
B. Shop Drawings:
C. Product Data: Provide manufacturer's standard catalog pages and data sheets including detailed information on luminaire construction, dimensions, ratings, finishes, mounting requirements, listings, service conditions, photometric performance, weight, effective projected area (EPA), and installed accessories; include model number nomenclature clearly marked with all proposed features.
1.06 QUALITY ASSURANCE
A. Comply with requirements of NFPA 70.
1.07 DELIVERY, STORAGE, AND HANDLING
A. Receive, handle, and store products according to NECA/IESNA 501 and manufacturer's written instructions.
B. Keep products in original manufacturer's packaging and protect from damage until ready for installation.
PART 2 PRODUCTS
Upgrade 265600 - 2 Exterior Lighting
2.01 LUMINAIRE TYPES
A. Furnish products as indicated in luminaire schedule included on the drawings.
2.02 LUMINAIRES
A. Manufacturers:
1. Acuity Brands, Inc: www.acuitybrands.com/#sle.
2. Alloy LED; www.alloyled.com/#sle.
3. Cooper Lighting, a division of Cooper Industries: www.cooperindustries.com/#sle.
4. Electro-Matic Visual, Inc; www.empvisual.com/#sle.
5. Hubbell Lighting, Inc: www.hubbelllighting.com/#sle.
6. Philips Lighting North America Corporation; www.lightingproducts.philips.com/#sle.
B. Provide products that comply with requirements of NFPA 70.
C. Provide products that are listed and labeled as complying with UL 1598, where applicable.
D. Provide products listed, classified, and labeled as suitable for the purpose intended.
E. Unless otherwise indicated, provide complete luminaires including lamp(s) and all sockets, ballasts, reflectors, lenses, housings and other components required to position, energize and protect the lamp and distribute the light.
F. Unless specifically indicated to be excluded, provide all required conduit, boxes, wiring, connectors, hardware, poles, foundations, supports, trims, accessories, etc. as necessary for a complete operating system.
G. Provide products suitable to withstand normal handling, installation, and service without any damage, distortion, corrosion, fading, discoloring, etc.
2.03 POLES
A. Manufacturers:
1. Acuity Brands, Inc: www.acuitybrands.com/#sle.
B. All Poles:
1. Provide poles and associated support components suitable for the luminaire(s) and associated supports and accessories to be installed.
2. Material: Steel, unless otherwise indicated.
3. Shape: Square straight, unless otherwise indicated.
4. Finish: Match luminaire finish, unless otherwise indicated.
5. Mounting: Install on concrete foundation, height as indicated on the drawings, unless otherwise indicated.
6. Unless otherwise indicated, provide with the following features/accessories:
a. Handhole.
b. Anchor bolts with leveling nuts or leveling shims.
c. Anchor base cover.
d. Provision for pole-mounted weatherproof GFI receptacle where indicated.
C. Metal Poles: Provide ground lug, accessible from handhole or transformer base.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that field measurements are as indicated.
B. Verify that outlet boxes are installed in proper locations and at proper mounting heights and are properly sized to accommodate conductors in accordance with NFPA 70.
C. Verify that suitable support frames are installed where required.
D. Verify that branch circuit wiring installation is completed, tested, and ready for connection to luminaires.
E. Verify that conditions are satisfactory for installation prior to starting work.
Upgrade 265600 - 3 Exterior Lighting
3.02 INSTALLATION
A. Coordinate locations of outlet boxes provided under Section 260533.16 as required for installation of luminaires provided under this section.
B. Install products in accordance with manufacturer's instructions.
C. Install luminaires in accordance with NECA/IESNA 501.
D. Provide required support and attachment in accordance with Section 260529.
E. Install luminaires plumb and square and aligned with building lines and with adjacent luminaires.
F. Pole-Mounted Luminaires:
1. Maintain the following minimum clearances:
a. Comply with IEEE C2.
b. Comply with utility company requirements.
2. Foundation-Mounted Poles:
a. Install foundations plumb.
b. Install poles plumb, using leveling nuts or shims as required to adjust to plumb.
c. Tighten anchor bolt nuts to manufacturer's recommended torque.
3. Grounding:
a. Bond luminaires, metal accessories, metal poles, and foundation reinforcement to branch circuit equipment grounding conductor.
4. Install separate service conductors, 12 AWG copper, from each luminaire down to handhole for connection to branch circuit conductors.
G. Install accessories furnished with each luminaire.
H. Bond products and metal accessories to branch circuit equipment grounding conductor.
I. Install lamps in each luminaire.
3.03 ADJUSTING
A. Aim and position adjustable luminaires to achieve desired illumination as indicated or as directed by Architect. Secure locking fittings in place.
3.04 CLEANING
A. Clean surfaces according to NECA/IESNA 501 and manufacturer's instructions to remove dirt, fingerprints, paint, or other foreign material and restore finishes to match original factory finish.
3.05 PROTECTION
A. Protect installed luminaires from subsequent construction operations.
END OF SECTION