Request For Quotes (RFQ) Fire Extinguisher Maintenance Service
Solicitation number
250244
Issued by
Orange County, California

About this file

This is an Independent Cost Estimate (ICE) document prepared by the Orange County Transportation Authority (OCTA) for fire extinguisher maintenance services. The project involves establishing a blanket contract for fire extinguisher service across all OCTA bases for a two-year term effective July 1, 2026, through June 30, 2028. The scope encompasses fire extinguisher maintenance and servicing on an as-needed basis with no guarantee of usage. The RFQ was issued with a question submission deadline of April 30, 2026, and the Authority committed to responding with written addenda by May 4, 2026. Award will be made to the lowest, responsive, responsible firm on a lump-sum basis, and the successful contractor must bid on all line items to be considered responsive.

The total cost estimate for the two-year contract period is $55,000, allocated across three funding sources: $22,000 from allocation 2162-7612-D2108-2QD, $30,000 from allocation 2168-7612-D2108-2QD, and $3,000 from allocation 0035-7612-OC110-2QD. The estimate was prepared by Ashley Huynh on December 2, 2025, and is based on historical usage data from the current contract with Majestics Fire Inc. (Contract C32615), which this procurement will replace. The contract includes approved equals, and all firms submitting quotes must certify compliance with Ukraine/Russia-related economic sanctions imposed by California and the United States Government.

View the file

Other files

File Type Posted
250244_RFQ_Exhibit_A_SOW.pdf PDF
250244_PP_v2-APPROVED.pdf PDF
250244_PS_v2.pdf PDF
250244_PP_v2.pdf PDF
250244_PP_GMEDITS.pdf PDF
250244_RFQ_Exhibit_A_SOW_gmedits.docx DOCX document
250244_RFQ_Exhibit_D_General_Provisions.pdf PDF
250244_PM_Correspondence.pdf PDF
250244_R001047.pdf PDF
250244_RFQ_Exhibit_C_Insurance.pdf PDF
250244_Insurance_&_Indemnification_Review.pdf PDF
250244_RFQ_Exhibit_B_Price_Summary_Sheet.pdf PDF
250244_Commodity_Code.pdf PDF
250244_SOWV.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INDEPENDENT COST ESTIMATE (ICE)

FA-CAMM-006.docm (09/25/15) Page 1 of 3

INSTRUCTIONS

Complete and submit all three pages to Contracts Administration & Materials Management (CAMM), along with your requisition and scope of work. CAMM will not start the procurement until all three documents have been received.

PART I – GENERAL INFORMATION

Project Description: Fire Extinguisher Service SHADED AREA FOR PROCUREMENT USE ONLY

Assigned Buyer No.:

D/M/WBE%:

Purchase Requisition No.: R001047

New Contract / Procurement

Contract Amendment Current IFAS Printout Contract / PO No.:

(Required for Amendments)

Contract Task Order

Option Term

Date: 12/2/2025

Requestor: Ashley Huynh Contract Analyst Phone Ext.: 5616 Name Title

Signature:

Cost Estimate: $ 55,000.00 (include shipping, handling and taxes, if applicable)

PART II – ESTIMATE GUIDE

Please substantiate the estimate using the following information.

Estimate Type Items to Include Where to Find Supporting Information

Services (Other than A&E)

1. Tasks you want done

2. Types of people needed (i.e., supervisor, administrative assistant, other)

3. Positions required (i.e., Project Manager, Deputy PM, Senior Engineer / Planner, other)

4. Estimated hours by position

5. Salary / billing rates applied

6. Prevailing wage rate category applied

7. Profit / applied fee

8. Direct expenses

9. Completion schedule

1. Current or past contracts for similar services

2. Other properties / departments doing similar work

3. Historical price and cost data

Estimate Guide Continued

FA-CAMM-006.docm (09/25/15) Page 2 of 3

Estimate Type Items to Include Where to Find Supporting Information

Architects, Engineers, Designers

1. Tasks you want done

2. Types of people needed (i.e., engineers, administrative assistant, other)

3. Positions (Project Manager, Deputy PM, Senior Engineer / Planner, other)

4. Estimated hours by position

5. Salary / billing rates applied

6. Profit / applied fee

7. Overhead rate (%)

8. Direct expenses

9. Completion schedule

1. Current or past contracts for similar services

2. Other properties / departments doing similar work

3. Historical price and cost data

Goods/Equipment 1. Product needed

2. Quantity

3. Unit price

4. Markups, overhead, profit

5. Delivery schedule desired

6. Warranty

1. Vendor survey / market survey

2. Current or past contracts for the same or similar product

3. Historical price and cost data

4. Various published indices

Construction 1. Product needed

2. Labor (at a minimum use Davis Bacon)

3. Materials

4. Bonds

5. Insurance

6. Mobilization

7. Equipment

8. Markups, fringes, overheads, profit

9. Completion schedule

1. “Means Book”

2. “Blue Book”

3. Davis Bacon wage rates / prevailing wages

4. Current or past contracts for the same project

5. Historical price and cost data

Additional Information: Establish a blanket contract for two (2) years term for fire extinguishers services, effective 07/01/26, through 06/30/28. This replace contract C32615 for Majestics Fire Inc. The contract is used for fire extinguisher service of all OCTA bases. The cost estimate amount based on past contract historical usage.

Total Amount $55,000 Allocation

2162-7612-D2108-2QD $22,000

2168-7612-D2108-2QD $30,000

0035-7612-OC110-2QD $3,000

FA-CAMM-006.docm (09/25/15) Page 3 of 3

PART III – INDEPENDENT COST ESTIMATE

Using the information provided in Part II, prepare the ICE for your procurement.

Use any or all of the categories listed below.

Prepared By: Ashley Huynh Date: 12/2/2025

Signature:

DESCRIPTION OF COST ELEMENTS

1. DIRECT LABOR

(List of Labor Categories)

Estimated Hours

Rate Per Hour ($)

Estimated Cost ($)

Total Est.

Cost ($)

$ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00 $ $ 0.00

Total Direct Labor: $ 0.00

2. OVERHEAD

Rate (%)

(use decimal input)

Total Labor ($)

Estimated Cost ($)

Total Est.

Cost ($)

% $ 0.00 $ 0.00 $ 0.00

3. MATERIALS/SERVICES (Excluding Information Technology [IT]) Estimated Cost ($)

Total Est.

Cost ($)

Fire Extinguishers Service $ 55,000.00 $ 55,000.00

4. INFORMATION TECHNOLOGY SUPPORT Estimated Cost ($)

Total Est.

Cost ($)

Total IT Support: $ 0.00

5. TRAVEL Estimated Cost ($)

Total Est.

Cost ($)

$ $ 0.00

6. SUBCONTRACTOR(S) / CONSULTANT(S) Estimated Cost ($)

Total Est.

Cost ($)

Total Subcontractor(s) / Consultant(s): $ 0.00

7. OTHER DIRECT COSTS Estimated Cost ($)

Total Est.

Cost ($)

$ $ 0.00

8. TOTAL ESTIMATED COST: $ 55,000.00